Kaliwa Low Dam

Last updated

The Kaliwa Low Dam, proposed by the Philippine Government in 2012, was one of several bulk water supply projects on the upper portion of the Kaliwa River Watershed that have been proposed but ultimately shelved by the Philippine Government since the 1970s. [1]

Contents

The proposed Kaliwa Low Dam design had a 600 million-liters-a-day (MLD) capacity, and the water supply tunnel has a 2,400-MLD capacity. Had it been built, the Kaliwa Low Dam was expected to ease the demand on the Angat Dam, Manila's sole water storage facility. [2] It was the main component of the New Centennial Water Source-Kaliwa Dam Project in Tanay, Rizal, which also called for the construction of a water supply tunnel and various attendant infrastructure. [1]

The project had originally been proposed as a bigger, integrated system that included a plan for a second dam, named Laiban dam further upstream. But the government decided on a proposal that would have built the system in stages, and only stage one, involving Kaliwa Low Dam and the water supply tunnel, was approved under the administration of Benigno Aquino III. [3] When the project did not move forward by the time Aquino administration ended, the succeeding Duterte administration decided not to pursue the Japanese-proposed Kaliwa Low Dam plan in 2019, deciding to instead pursue a bigger, China-funded dam project. [4] [5]


Earlier projects at the Laiban Watershed

Various plans for the construction of a dam in Tanay, Rizal, have been proposed since the 1970s, when the Marcos government first decided that the location was a more viable location for a dam than the Marikina River. However, protests against the construction of the dam, called Laiban because Barangay Laiban was chosen as the exact project site, very quickly led to protests from various groups. Foremost among these were Indigenous peoples from Central and Southern Luzon, notably the local Remontado Dumagat people, whose ancestral lands would specifically be affected. [6] [7] Environmental and activist groups later also raised concerns. As a result, construction of the dam has been approved, deferred, stopped, and restarted a number of times in the decades since. [8]

Project approval process

Original proposal, including Laiban Dam and Power Plant

The roots of the current "New Centennial Water Source Project" can be traced to the Water Security Legacy (WSL) Roadmap proposed by the Metropolitan Waterworks and Sewerage System (MWSS) in 2012–2016. Based on this document, the MWSS developed plans for "the development of a dam at the Kaliwa River (Laiban Dam), and/or a smaller dam downstream (Kaliwa Low Dam) to maximize water supply, ensure short - and long - term redundancy, and optimize power generation capacities," and in February 2013, the Public Private Partnership Center released a document "sounding out" interested parties. [9]

In that initial market sounding, this proposal was already thought likely to comprise: [9]

  1. ) Laiban Dam and/or Kaliwa Low Dam;
  2. ) Head works and its appurtenant facilities;
  3. ) Conveyance structure from the diversion point to the water treatment facility(s);
  4. ) Water treatment facility(s); and
  5. ) Hydropower facility(s).

In report by Philippine Daily Inquirer reporter Niña Calleja in that same month, MWSS senior deputy administrator Nathaniel Santos indicated that the main difference of the NCWSP from previous plans was that it would involve the construction of two smaller dams at the Kaliwa watershed instead of just the one. A main dam (Laiban Dam) would be built at the upper Kaliwa River in Barangay Laiban, and another regulating dam (Kaliwa Low Dam) further downstream. [10]

When the National Economic and Development Authority (NEDA) Investment Coordination Committee (ICC) had their October 4, 2013, Joint Cabinet Committee and Technical Board Meeting, however, they suggested that the MWSS to develop the project in stages, allowing for construction on the Kaliwa Low Dam to begin sooner, and for the Laiban Dam components of the project to be funded under a different financial mechanism. [3] [11]

Project financing

The original integrated project had been proposed by the MWSS under a build-operate-transfer (BOT) financing scheme. When the Joint Cabinet Committee and Technical Board Meeting of the National Economic and Development Authority (NEDA) Investment Coordination Committee (ICC) discussed the project on 4 October 2013, however, they recommended that the MWSS resubmit its proposal with only the Kaliwa Low Dam and water supply tunnel components, and that it be funded using the MWSS' funds or though overseas development assistance. [11]

Approval of Kaliwa Low Dam proposal

The project, with its revised scope, was approved at the May 29, 2014, meeting of the NEDA Board, which is chaired by President Benigno Aquino III. [12]

On July 28, 2014, President Aquino cited Kaliwa dam in his 5th State of the Nation Address as one of the infrastructure projects approved by his administration as part of its drought prevention efforts. [13]

In 2015, two consortia were pre-qualified to bid for the undertaking of the Kaliwa Dam project [14] — the SMC-K Water Consortium, which is a partnership between San Miguel Holdings Corp. and Korea Water Resources Corp.; and the Abeima-Datem Consortium, which is a partnership between Albeinsa Infraestructura Medio Ambiento S.A and Datem Inc. [14]

Government shift to Chinese proposal

In 2019, under the administration of President Rodrigo Duterte, the government revealed that it would not continue with the project under a public–private partnership agreement as proposed during the Aquino administration, but would instead pursue the project using Official Development Assistance loan from China. [5]

Some lawyers noted that the interest rate of the Chinese deal was 2%, while the Japanese deal that was sidelined by the government only had a 1.25% interest. [15] The Japanese have since renewed their call for the Philippine government to reconsider their proposal. [16] [17]

Social and environmental concerns

Social issues

Ancestral lands belonging to Indigenous Dumagats and Remontados will be affected by the Kaliwa Dam project. [18] The coalition Sectors Opposed to the Kaliwa Dam (STOP Kaliwa Dam) estimate that 1,000 households from Barangay Daraitan in Tanay, Rizal, and 500 households in Pagsangahan, General Nakar, Quezon, will be inundated by the construction. [19] The Samahan ng mga Katutubong Agta/Dumagat (Organization of Indigenous Agta/Dumagat) estimate that the project would displace 10,000 members of the Dumagat tribe. [20] Protesters have maintained that Indigenous communities that will be affected by the project were not consulted. [20] [21] [22] Philippine law requires that such projects acquire free, prior, and informed consent (FPIC) from Indigenous communities. [23]

Environmental issues

Sierra Madre is one of the most biodiverse areas in the Philippines and the largest remaining rainforest in the country. [24] An estimated 12,147 hectares of residual forests, home to 172 recorded plant or flora species will be affected by the dam construction. [24]

The project site is part of the Kaliwa Watershed Forest Reserve, which is supposedly protected by virtue of Proclamation No. 573 on June 22, 1968. [25] Proclamation 1636 declared a portion of the area a National Park and Wildlife Sanctuary. [19]

Environmental groups have protested the project, as the dam will destroy a great portion of the Sierra Madre range. The dam will ultimately destroy numerous habitats of many endangered species living in the mountains once construction begins. [26] Among the thousands of plant and animal life whose home will be destroyed by the project is the critically endangered Philippine eagle. [24] [25] Other species that will be affected by the project are the endangered north Philippine hawk-eagle, the Philippine brown deer, the Philippine warty pig, and the vulnerable northern rufous hornbill. [24]

See also

Related Research Articles

<span class="mw-page-title-main">History of the Philippines (1986–present)</span>

This article covers the history of the current Philippine republican state following the 1986 People Power Revolution, known as the Fifth Philippine Republic.

Water privatization in Metro Manila began when the then President of the Philippines, Fidel Ramos, instructed the government in 1994 to solve what he called the water crisis in Manila by engaging with the private sector. In 1997, two concession contracts for the Eastern and Western halves of Metro Manila were awarded after an open competition. The concessions represent the largest population served by private operators in the developing world. Both winning companies, Maynilad Water Services in West Manila and especially Manila Water in East Manila, submitted bids with extremely low water tariffs. The tariffs proved to be too low to finance the investments needed to improve performance, especially after the East Asian financial crisis and the devaluation of the Philippine Peso.

<span class="mw-page-title-main">Angat Dam</span> Dam in Bulacan, Philippines

Angat Dam is a concrete water reservoir embankment hydroelectric dam that supplies Metro Manila and nearby provinces with water. It was a part of the Angat-Ipo-La Mesa water system. The reservoir supplies about 90 percent of raw water requirements for Metro Manila through the facilities of the Metropolitan Waterworks and Sewerage System and it irrigates about 28,000 hectares of farmland in the provinces of Bulacan and Pampanga.

<span class="mw-page-title-main">Metropolitan Waterworks and Sewerage System</span>

The Metropolitan Waterworks and Sewerage System, formerly known as the National Waterworks and Sewerage System Authority (NAWASA), is the government agency that is in charge of water privatization in Metro Manila and nearby provinces of Cavite and Rizal in the Philippines. It split the water concession into an east and a west concession with Manila Water being awarded one contract and Maynilad Water Services being awarded the other.

The Laguna Lakeshore Expressway Dike is a proposed expressway in the Philippines that will start from the coastal area of Laguna de Bay from Taguig in Metro Manila to Calamba and Los Baños in Laguna.

<span class="mw-page-title-main">Wawa Dam</span> Dam in Rodriguez, Rizal

Wawa Dam is a gravity dam constructed over the Marikina River in the municipality of Rodriguez in Rizal province, Philippines. The slightly arched dam is situated in the 360-metre (1,180 ft) high Montalban Gorge or Wawa Gorge, a water gap in the Sierra Madre Mountains, east of Manila.

Several bulk water supply projects on the upper portion of the Kaliwa River Watershed have been proposed by the Philippine Government since the 1970s, with the intent of relieving Metro Manila of its overdependence on the water supplied by Angat Dam. Most of these have focused on a particular site in Barangay Laiban in Tanay, Rizal, on the upper portion of the Kaliwa River Watershed to which the Laiban Dam belongs, and the projects have thus often been referred to as Laiban dam or Kaliwa dam, although multiple projects have been referred to using either name.

<span class="mw-page-title-main">Sierra Madre (Philippines)</span> Mountain range in the Philippines

The Sierra Madre is the longest mountain range in the Philippines. Spanning over 540 kilometers (340 mi), it runs from the province of Cagayan down to the province of Quezon, forming a north–south direction on the eastern portion of Luzon, the largest island of the archipelago. It is bordered by the Pacific Ocean to the east, Cagayan Valley to the northwest, Central Luzon to the midwest, and Calabarzon to the southwest. Some communities east of the mountain range, along the coast, are less developed and so remote that they could only be accessed by taking a plane or a boat.

<span class="mw-page-title-main">Angat Watershed Forest Reserve</span>

The Angat Watershed Forest Reserve is a conservation area that protects the drainage basin in the southern Sierra Madre range north of Metro Manila in the Philippines where surface water empties into the Angat River and its distributaries. It is spread over an area of 62,309 hectares in the eastern portion of Bulacan and northern Rizal province at an altitude of between 490 and 1,206 metres. The conservation area also extends to the provinces of Nueva Ecija and Quezon and is centered on an artificial lake created by the Angat Dam which, together with the Ipo Dam located 7.5 kilometres (4.7 mi) downstream, supply 97% of the water requirement of Metro Manila via an aqueduct system to the La Mesa Dam and Reservoir and the Balara Filtration Plant in Quezon City. The Angat Dam and Reservoir is also a major source of hydroelectricity for Metro Manila and surrounding provinces, contributing some 200 megawatts to the Luzon grid. The watershed is a popular birdwatching site and is a biodiversity hotspot containing most of the remaining closed-canopy forests in Central Luzon.

<span class="mw-page-title-main">Pantabangan–Carranglan Watershed Forest Reserve</span> Nature reserve in the Philippines

The Pantabangan–Carranglan Watershed Forest Reserve is a conservation area located in the upper reaches of the Pampanga River in Nueva Ecija, Philippines, and borders the Sierra Madre and Caraballo Mountains in Aurora and Nueva Vizcaya. It encompasses 84,500 hectares of the drainage basin surrounding the Pantabangan Lake, an impoundment of the Pampanga River by the Pantabangan Dam. The multi-purpose dam is situated at the confluence of Pampanga River's two headwaters, namely the Pantabangan and Carranglan Rivers in the municipality of Pantabangan. It stretches above the dam site for 21 kilometres (13 mi) to where Carranglan River originates in the Caraballo on the north, and for 18 kilometres (11 mi) to where Pantabangan River originates in the Sierra Madre on the east. It is considered a critical watershed for the agricultural economy and hydroelectric power generation in the region of Central Luzon.

The Metro Manila Subway, formerly known as the Mega Manila Subway (MMS), is an under-construction underground rapid transit line in Metro Manila, Philippines. The 36-kilometer (22 mi) line, which will run north–south between Valenzuela, Quezon City, Pasig, Taguig, Parañaque and Pasay, consists of 15 stations between the East Valenzuela and Bicutan stations. It will become the country's second direct airport rail link after the North–South Commuter Railway, with a branch line to Ninoy Aquino International Airport.

<span class="mw-page-title-main">Sangley Point Airport</span> Domestic airport serving Manila, Philippines

Sangley Point Airport, also referred to as Cavite Airport, is a domestic airport at Sangley Point, Cavite City in the Philippines primarily serving general aviation and turbo-propped airliners in the general vicinity of South Luzon and the Greater Manila Area.

New Manila International Airport, also known as Bulacan International Airport, is an international airport under construction on the coastal areas of Bulakan, Bulacan, 35 km (22 mi) north of the capital Manila. The project was proposed by the San Miguel Corporation (SMC) and is set to help decongest Ninoy Aquino International Airport (NAIA), the main gateway to the capital for air travelers.

<span class="mw-page-title-main">North–South Commuter Railway</span> Future commuter railway line in the Philippines

The North–South Commuter Railway (NSCR), also known as the Clark–Calamba Railway, is a 147-kilometer (91-mile) urban rail transit system under construction in the island of Luzon, Philippines. Running from New Clark City in Capas to Calamba, Laguna with 36 stations and four services, the railway was designed to improve connectivity within the Greater Manila Area and will be integrated with the railway network in the region.

The water crisis in Metro Manila, Philippines is the ongoing crisis that affected most of the households with a water interruption. The crisis usually occurs in dry season from March to May. The water suppliers, Manila Water and Maynilad, held responsibility for the crisis.

<span class="mw-page-title-main">Build! Build! Build!</span> Infrastructure program of Rodrigo Duterte

The Build! Build! Build! Infrastructure Program (BBB) was the infrastructure program of the administration of Rodrigo Duterte, the 16th president of the Philippines. A key component of his socioeconomic policy, the program aimed to reduce poverty, encourage economic growth and reduce congestion in Metro Manila, and address the country's infrastructure gap. Launched on April 18, 2017, the program also included the continuation of 44 infrastructure projects under previous administrations.

The Umiray–Angat Transbasin Project (UATP) is an expansion project of the Metropolitan Waterworks and Sewerage System (MWSS) for the supply of the Angat Dam reservoir. The 13-kilometer-long (8.1 mi) 4.30-meter (14.1 ft) diameter tunnel-aqueduct system diverts waters from the Umiray River east of the Angat Basin. 20–30% of the water that is consumed in Metro Manila and its outlying regions is supplied by the Umiray Basin.

Indigenous people’s resistance against the Marcos dictatorship varied from case to case among the various indigenous peoples of the Philippines. The most documented cases are the various resistance movements towards the Marcos administration’s appropriation of indigenous lands, particularly in the case of the Chico River Dam Project and the Manila Water Supply III project on the Kaliwa River watershed, and the birth of the various separatist groups and their coalescing into the Moro conflict in the wake of news about the Jabidah Massacre.

The Build Better More (BBM) is the infrastructure program of the Marcos administration (2022–2028). It superseded the Build! Build! Build! infrastructure program of the Duterte administration (2016–2022). The following Infrastructure Flagship Projects (IFP)s were identified by the National Economic and Development Authority (NEDA).

References

  1. 1 2 "China will make Philippines dam a reality, after four decades of protest". South China Morning Post. 2018-12-09. Retrieved 2018-12-10.
  2. Smith, Sandy (June 23, 2014). "New Starts: Closing 6 Blocks in D.C., Planning K.C. Streetcars From Afar, Manila's New Water Supply". nextcity.org. Next City . Retrieved June 30, 2014.
  3. 1 2 Añonuevo, Euan Paulo C. (June 11, 2014), Laiban Dam Project next on MWSS' PPP list, InterAksyon.com
  4. "Why borrow from China? Japanese dam is free, safe" . Retrieved 2019-08-20.
  5. 1 2 "Gov't targets construction of China-funded Kaliwa Dam by July". CNN. March 18, 2019. Archived from the original on 19 July 2019. Retrieved 19 July 2019.
  6. Mallari, Delfin T. Jr. (July 12, 2013). "Sierra Madre tribe asks Congress to stop Laiban dam". Philippine Daily Inquirer . Makati City: Philippine Daily Inquirer, Inc. Retrieved July 2, 2014.
  7. "Tribes oppose dams for MM folk's water". Inquirer News. 5 May 2013.
  8. "Laiban Dam Project Chronology of Events" (PDF). Philippine Center for Investigative Journalism. July 2009. Archived from the original (PDF) on 2013-08-20. Retrieved July 1, 2014.
  9. 1 2 Market Sounding for the New Centennial Water Source Project (NCWP) (PDF), Public-Private Partnership Center, February 2013, retrieved January 30, 2014
  10. Calleja, Niña (February 25, 2013). "P85B MWSS project: Same river in Tanay but different plan: Gov't to undertake project to head off possible water shortage in NCR". Philippine Daily Inquirer . Makati: Philippine Daily Inquirer, Inc. Retrieved July 1, 2014.
  11. 1 2 New Centennial Water Supply Source Project, For Policy Decision by NEDA ICC Cabinet Committee, Metropolitan Waterworks and Sewerage System, December 3, 2013, archived from the original on May 28, 2014, retrieved June 30, 2014
  12. "NEDA approves nine projects worth P62 billion - Solar News". www.solarnews.ph. Archived from the original on 2014-05-31.
  13. "SONA Fact Check: Dike, dam pose environmental threats". 30 July 2014.
  14. 1 2 "Integrated PPP vs Hybrid PPP: The case of Kaliwa Dam". BusinessWorld . 7 November 2018.
  15. "Diokno questions several provisions in P12.2-B loan agreement for Kaliwa Dam project". Manila Bulletin. 25 March 2019. Archived from the original on 21 April 2019. Retrieved 21 April 2019.
  16. Raymundo, Jr., Perfecto (18 March 2019). "Japanese firm renews proposal on Kaliwa Dam project". Philippine News Agency. Retrieved 2 July 2022.
  17. "EXECUTIVE SUMMARY FOR THE PUBLIC (ESP) New Centennial Water Source (NCWS) - Kaliwa Dam Project" (PDF). Environmental Management Bureau. Philippines. 2014. Retrieved 2 July 2022.
  18. Luci-Atienza, Charissa; Cahiles-Magkilat, Bernie (March 20, 2019). "Weirs, instead of dams, for our water problem". Manila Bulletin News. Retrieved 22 April 2019.
  19. 1 2 "Coalition rejects China-funded Kaliwa Dam project". Philstar. April 2, 2019. Retrieved 22 April 2019.
  20. 1 2 Vergara, Robert (March 21, 2019). "Dumagat leader laments alleged lack of tribe consent for Kaliwa dam: 'Binabraso nila kami'". CNN. Archived from the original on 19 July 2019. Retrieved 19 July 2019.
  21. "The big sacrifice". Philippine Daily Inquirer. April 17, 2019. Retrieved 19 July 2019.
  22. Punongbayan, J. C. (July 18, 2019). "[ANALYSIS] The poor quality of economic growth under Duterte". Rappler. Retrieved 19 July 2019.
  23. Ramos, Mariejo S. (April 11, 2019). "Kaliwa Dam opponets[sic] cite lack of indigenous people's consent". Inquirer. Retrieved 19 July 2019.
  24. 1 2 3 4 "Kaliwa Dam will destroy Sierra Madre biodiversity". Philstar. November 29, 2018. Retrieved 22 April 2019.
  25. 1 2 Madarang, Catalina Ricci S. (14 March 2019). "Why China-funded Kaliwa Dam, a possible alternate water source, is heavily opposed". Interaksyon. Retrieved 22 April 2019.
  26. Archived at Ghostarchive and the Wayback Machine : Brigada: Ano-ano ang magiging epekto ng Kaliwa Dam Project? [Brigada: What will be the impact of the Left Dam Project?]. YouTube (in Filipino).