Karenge Drinking Water Supply System

Last updated

Karenge Drinking Water Supply System
Rwanda adm location map.svg
Red pog.svg
Location of Karenge Drinking Water Supply System
Desalination plant
LocationKarenge, Lake Mugesera, Rwamagana District
Coordinates 02°13′08″S30°27′50″E / 2.21889°S 30.46389°E / -2.21889; 30.46389
Estimated output15,000 cubic meters (15,000,000 L) of water daily
Extended output48,000 cubic meters (48,000,000 L) of water daily
CostUS$163.4 million
Technology Filtration, Sedimentation, Chlorination
Percent of water supply Kigali City & Rwamagana District
Operation date31 December 2024 (Expected)

Karenge Drinking Water Supply System (KDWSS), also Karenge Water Supply System is a water intake, purification, and distribution system in Rwanda. The system supplies water to parts of the capital city of Kigali and the neighboring Rwamagana District. [1]

Contents

Location

The water treatment and distribution facility is located in the lakeside community of Karenge, Rwamagana District, in the Eastern Province of Rwanda, on the shores of Lake Mugesera, approximately 50 kilometres (31 mi), by road, southeast of the city of Kigali, the national capital. [1]

Overview

KDWSS was established in 1975 with processing capacity of 3,840 cubic metres (135,608 cu ft) every day. In 1985, that capacity was increased to 7,200 cubic metres (254,266 cu ft) daily. In 2008, daily output was increased to 12,000 cubic metres (423,776 cu ft). As of October 2020, the system produced 15,000 cubic metres (529,720 cu ft) of drinkable water every day, of which 12,000 cubic metres (423,776 cu ft) (80 percent) was piped to Kigali and 3,000 cubic metres (105,944 cu ft) (20 percent) was distributed within Rwamagana District. [2] [3]

Expansion

In 2020 the government of Rwanda, through its subsidiary, Water and Sanitation Corporation (WASAC Limited), resolved to increase the processing capacity of this plant to 48,000 cubic metres (1,695,104 cu ft) daily. [1] [2] [3] The expansion involves: [1]

Construction and funding

The cost of expansion is budgeted at $164.3 million. Construction financing is provided by the entities listed below: [1]

Karenge Water System Expansion Funding
RankDevelopment PartnerContribution in USDPercentageNotes
1 OPEC Fund for International Development (OFID)
21.0 million
12.8
Loan [1]
2 Abu Dhabi Fund for Development (ADFD)Loan [1]
3 Saudi Fund for Development (SFD)Loan [1]
4 Arab Bank for Economic Development in Africa (BADEA)Loan [1]
5Exim Bank of Hungary
52.0
31.6
Loan [4]
Total
164.3 million
100.00

Other considerations

The expanded plant is part of the plans by the Rwandan authorities to have 100 percent universal potable water supply by December 2024. [1] [2] [4]

See also

Related Research Articles

<span class="mw-page-title-main">Water supply</span> Provision of water by public utilities, commercial organisations or others

Water supply is the provision of water by public utilities, commercial organisations, community endeavors or by individuals, usually via a system of pumps and pipes. Public water supply systems are crucial to properly functioning societies. These systems are what supply drinking water to populations around the globe. Aspects of service quality include continuity of supply, water quality and water pressure. The institutional responsibility for water supply is arranged differently in different countries and regions. It usually includes issues surrounding policy and regulation, service provision and standardization.

Water supply and sanitation in Hong Kong is characterized by water import, reservoirs, and treatment infrastructure. Though multiple measures were made throughout its history, providing an adequate water supply for Hong Kong has met with numerous challenges because the region has few natural lakes and rivers, inadequate groundwater sources, a high population density, and extreme seasonable variations in rainfall. Thus nearly 80 percent of water demand is met by importing water from mainland China, based on a longstanding contract. In addition, freshwater demand is curtailed by the use of seawater for toilet flushing, using a separate distribution system. Hong Kong also uses reservoirs and water treatment plants to maintain its source of clean water.

<span class="mw-page-title-main">Split Rock Dam</span> Dam in North West Slopes, New South Wales

Split Rock Dam is a minor ungated concrete faced rock fill embankment dam with concrete chute spillway across the Manilla River upstream of Manilla in the north-western slopes region of New South Wales, Australia. The dam's purpose includes flood mitigation, irrigation, water supply and conservation. The impounded reservoir is called Split Rock Reservoir.

<span class="mw-page-title-main">Water supply and sanitation in Rwanda</span> Water supply and sanitation in Rwanda

Water supply and sanitation in Rwanda is characterized by a clear government policy and significant donor support. In response to poor sustainability of rural water systems and poor service quality, in 2002 local government in the Northern Byumba Province contracted out service provision to the local private sector in a form of public–private partnership. Support for public-private partnerships became a government policy in 2004 and locally initiated public-private partnerships spread rapidly, covering 25% of rural water systems as of 2007.

<span class="mw-page-title-main">Water supply and sanitation in Uganda</span>

The Ugandan water supply and sanitation sector made substantial progress in urban areas from the mid-1990s until at least 2006, with substantial increases in coverage as well as in operational and commercial performance. Sector reforms from 1998 to 2003 included the commercialization and modernization of the National Water and Sewerage Corporation (NWSC) operating in cities and larger towns, as well as decentralization and private sector participation in small towns.

Water supply and sanitation in Israel are intricately linked to the historical development of Israel. Because rain falls only in the winter, and largely in the northern part of the country, irrigation and water engineering are considered vital to the country's economic survival and growth. Large scale projects to desalinate seawater, direct water from rivers and reservoirs in the north, make optimal use of groundwater, and reclaim flood overflow and sewage have been undertaken. Among them is the National Water Carrier, carrying water from the country's biggest freshwater lake, the Sea of Galilee, to the northern part of the Negev desert through channels, pipes and tunnels. Israel's water demand today outstrips available conventional water resources. Thus, in an average year, Israel relies for about half of its water supply on unconventional water resources, including reclaimed water and desalination. A particularly long drought in 1998–2002 had prompted the government to promote large-scale seawater desalination. In 2022, 85% of the country's drinkable water was produced through desalination of saltwater and brackish water.

<span class="mw-page-title-main">Water supply and sanitation in Tunisia</span>

Tunisia has achieved the highest access rates to water supply and sanitation services among the Middle East and North Africa. As of 2011, access to safe drinking water became close to universal approaching 100% in urban areas and 90% in rural areas. Tunisia provides good quality drinking water throughout the year.

<span class="mw-page-title-main">Wemmershoek Dam</span> Dam in Western Cape, South Africa

Wemmershoek Dam is a rock-fill type dam located on the Wemmershoek River near Franschhoek and Paarl in South Africa. It was constructed between 1953 and 1957 on behalf of the City of Cape Town. With a reservoir capacity of 58,644 megalitres, it provides approximately 6.5% of the storage capacity of the Western Cape Water Supply System which supplies Cape Town and surrounding areas.

The Hwange Thermal Power Station is the biggest power plant in Zimbabwe with an installed capacity of 1520 MW. It is owned and operated by the national electricity company Zimbabwe Electricity Supply Authority. It was built in two stages and consists of 4 units of 120 MW each, 2 units of 220 MW each and 2 units of 300 MW each. Engineering Consultants, Merz & McLellan, were employed for the design and supervision of the construction of the power station. Construction of Stage 1 commenced in 1973, but was suspended in 1975 due to economic sanctions imposed on Rhodesia. Stage 1's units were commissioned from 1983 to 1986 with Stage 2's units following in 1986 and 1987.

<span class="mw-page-title-main">Siah Bishe Pumped Storage Power Plant</span> Dam in Chalus

The Siah Bisheh Pumped Storage Power Plant, also spelled Siyāhbisheh and Siah Bishe, is located in the Alborz Mountain range near the village of Siah Bisheh and 48 km (30 mi) south of Chalus in Mazandaran Province, Iran. The power plant uses the pumped-storage hydroelectric method to generate electricity during periods of high energy demand, making it a peaking power plant, intended to fulfill peak electricity demand in Tehran 60 km (37 mi) to the south. When complete it will have an installed generating capacity of 1,040 megawatts (1,390,000 hp) and a pumping capacity of 940 megawatts (1,260,000 hp). Planning for the project began in the 1970s and construction began in 1985. It was delayed from 1992 until 2001 and the first generator went online in May 2013. The remaining generators were commissioned by 1 September 2015. The power plant is the first pumped-storage type in Iran and will also use the country's first concrete-face rock-fill dam – two of them.

Water supply and sanitation in Lebanon is characterized by a number of achievements and challenges. The achievements include the reconstruction of infrastructure after the 1975–90 Civil War and the 2006 war with Israel, as well as the reform of the water and sanitation sector through a water law passed in 2000. The law created four Regional Water Establishments to consolidate numerous smaller utilities.

<span class="mw-page-title-main">Vianden Pumped Storage Plant</span> Dam in Vianden

The Vianden Pumped Storage Plant is located just north of Vianden in Diekirch District, Luxembourg. The power plant uses the pumped-storage hydroelectric method to generate electricity and serves as a peaking power plant. Its lower reservoir is located on the Our River, bordering Germany, and the upper is elevated above on the nearby Saint Nicholas Mountain. Construction on the plant began in 1959 and the first pump-generators were commissioned in 1962. A tenth pump-generator was installed in 1976 bringing the plant's installed generating capacity to 1,096 megawatts (1,470,000 hp). The plant generates an average of 1,650 gigawatt-hours (5,900 TJ) annually but of course consumes even more. Generally the efficiency of this energy storage method is around 70–80%. The plant is owned by Société électrique de l'Our and RWE. Construction on an eleventh pump-generator began in 2010 and it is expected to be commissioned in 2013, which will bring the plant's installed capacity to 1,296 megawatts (1,738,000 hp).

The Dikgatlhong Dam is a dam near the village of Robelela on the Shashe River in Botswana, completed in December 2011. When full it will hold 400,000,000 cubic metres (1.4×1010 cu ft). The next largest dam in Botswana, the Gaborone Dam, has capacity of 141,000,000 cubic metres (5.0×109 cu ft).

Grahamstown Dam is a major off-stream earthfill Embankment dam with a controlled labyrinth spillway and baffle chute that stores water from the Williams River. The dam is located north of Newcastle, New South Wales, Australia. The dam's main purpose is water supply; it provides about 40 per cent of the potable water for the Hunter Region; and is its largest drinking water supply dam.

<span class="mw-page-title-main">Water supply and sanitation in Algeria</span>

Drinking water supply and sanitation in Algeria is characterized by achievements and challenges. Among the achievements is a substantial increase in the amount of drinking water supplied from reservoirs, long-distance water transfers and desalination at a low price to consumers, thanks to the country's substantial oil and gas revenues. These measures increased per capita water supply despite a rapidly increasing population. Another achievement is the transition from intermittent to continuous water supply in the capital Algiers in 2011, along with considerable improvements in wastewater treatment resulting in better water quality at beaches. These achievements were made possible through a public-private partnership with a private French water company. The number of wastewater treatment plants throughout the country increased rapidly from only 18 in 2000 to 113 in 2011, with 96 more under construction. However, there are also many challenges. One of them is poor service quality in many cities outside Algiers with 78% of urban residents suffering from intermittent water supply. Another challenge is the pollution of water resources. There has also been insufficient progress concerning reuse of treated water, a government priority in this dry country.

Katosi Water Works (KWW), also Katosi Water Treatment Plant is a water purification and distribution project in Uganda.

Gulu Water Supply and Sanitation Project (GWSSP), also Gulu Water Supply and Sewerage System, is a water intake, purification, distribution and waste water collection and disposal system in the city of Gulu, the largest urban centre in the Northern Region of Uganda. In October 2020, the Uganda government concluded Phase 1 of the improvement of water supply and sanitation in the city, with funding from the World Bank, KfW and the Government of Uganda. Phase 2 improvements are expected to start in 2021, with funding from the World Bank, KfW and the Commonwealth Development Corporation.

Moyo Water Supply and Sanitation System (MWSS), also Moyo Water Supply and Sewerage System is a water intake, purification, distribution and waste water collection and disposal system in Moyo Town and surrounding metropolis in Moyo District, Uganda.

Masaka–Mbarara Water Supply and Sanitation Project (MMWSSP), is a water intake, purification, distribution and waste water collection and disposal system in the cities of Masaka and Mbarara in the Central Region and the Western Region of Uganda. The project is intended to meet the water supply and sanitation needs of approximately 1,055,000 by 2030. The work is to be carried out by the Uganda Ministry of Water and Environment through the parastatal utility company, National Water and Sewerage Corporation (NWSC). Funding, have been provided by the French Development Agency and the European Union.

Rukungiri Water Supply and Sanitation Project (RWSSP), also Rukungiri Water Supply and Sewerage System, is a water intake, purification, distribution and waste water collection and disposal system in the town of Rukungiri, in the Western Region of Uganda. When completed, the system is expected to supply 9,600 cubic meters (9,600,000 L) of water daily, to about 120,000 people in the town of Rukungiri and neighboring communities in Rukungiri District and to parts of Ntungamo District. The infrastructure development project is being jointly funded by the World Bank and the Government of Uganda.

References

  1. 1 2 3 4 5 6 7 8 9 10 11 Inès Magoum (13 November 2023). "Rwanda: The capacity of the Karenge water plant will be tripled with $2M from OFID". Afrik21.africa. Paris, France. Retrieved 16 November 2023.
  2. 1 2 3 Mininfra (7 October 2020). "Government To Increase Production Capacity off Karenge Water Treatment Plant And Strengthen Its Distribution Network". Rwanda Ministry of Infrastructure (Mininfra). Kigali, Rwanda. Retrieved 16 November 2023.
  3. 1 2 Olalekan Adigun (September 2023). "Revamping Water Security: The Upgradation of Karenge Water Treatment Plant". BNN Network . Toronto, Ontario, Canada. Retrieved 16 November 2023.
  4. 1 2 Mike Kubwa (29 September 2023). "$52 Million to be Utilized in Karenge Water Treatment Plant Upgrade in Rwanda". Construction Review Online. Nairobi, Kenya. Retrieved 16 November 2023.