La Vicaria Arch bridge | |
---|---|
Coordinates | 38°21′10″N2°15′28″W / 38.3528°N 2.2579°W |
Crosses | Segura River |
Locale | Yeste, Albacete |
Characteristics | |
Design | Tied arch bridge |
Total length | 260 metres (850 ft) |
Width | 11 metres (36 ft) |
Longest span | 168 metres (551 ft) |
Clearance above | 40 metres (130 ft) above the river |
History | |
Opened | August, 2007 |
Location | |
La Vicaria Bridge is a through arch bridge that spans the Segura River, where it meets La Fuensanta Reservoir near Yeste, in the province of Albacete, Spain. It forms part of a future road that will join Yeste with Letur and the neighbouring area to the east. The bridge has 2 vehicle lanes and 2 sidewalks.
La Fuensanta Reservoir and the River Segura divide the municipal district of Yeste into two parts. This village is the main town of an isolated and mountainous region in the southern part of the province of Albacete. The bridge provides direct access to the village from the east (previously it had only been accessible from the north) and, as a result of avoiding travelling around the large reservoir, reduces the journey time by 50 minutes.
The owner of the bridge, the Confederación Hidrográfica del Segura [1] (Segura Water Authority, that includes irrigation districts), decided to construct the bridge in order to resolve the old transportation problems of the Yeste population and to act as a landmark. As a result, they employed Ferrovial-Agromán as the builder and final designer. Ferrovial-Agromán gathered, and expanded on, previous ideas in order to find a complete solution that included an innovative construction process.
The structure is a 168 m through arch bridge with approaching spans, taking advantage of the natural valley's morphology and the width of the reservoir at this point. The foundations of the arches rest on the limestone rock on both hillsides at the reservoir's high water level.
La Vicaria Arch | Main Parameters |
---|---|
Total length (m) | 260 |
Spans length (m) | (20+25+170+25+20) |
Span / Rise (arch) | 3.4 |
Span / Depth section (crown of arch) | 140 |
Span / Depth section (base of arch) | 70 |
Span / Depth section (deck) | 134 |
The deck is a continuous composite structure, consisting of concrete and weathering steel, simply supported on piers using neoprene bearings and rigidly connected to the arches at their intersection. Its cross-section is made up of two longitudinal steel box beams of 1 m depth and cross brace each other by flange steel beams. The deck is in-situ concreted on precast slabs which work with the slab in service.
The arches span 168 m, of which 120 m is over the deck, with a 10° inward incline towards the deck. The rise is 49 m, of which 25 m is over the deck, and are crossed braced by six cross-beams with a similar outer section to that of the arch.
The arch sections are quasi-rectangular steel tubes, filled with self compacting concrete, formed by 4 metal plates that are folded and welded at their ends. Their width is constant along the length of the arch and their depth varies from 2.4 m to 1.2 m.
The deck is connected to the arch by 12 pairs of vertical hangers at the arches and the deck intersection point, 60 m from the centre of the bridge, rigidly joined by a cross brace.
Each arch is embedded at the ends in a reinforced concrete block (the smallest being 6 m long, 7 m high and 5 m wide) connected by means of a joint of 28 steel bars until reaching the suitable foundation surface in the rock. In order to avoid transmitting transversal force to the rocky mass, the blocks on each bank have been cross braced to each other using a reinforced concrete brace, which balances the reactions of the 2 arches on each bank.
The piers are Y-shaped and in-situ concrete. The deck connects to each pier via a cross-beam that connects two longitudinal beams. This arrangement allows the visual continuity of the depth section of the deck along the bridge, emphasizing its slenderness.
The through arch steel structure (arch + deck) was divided into 3 partial steel substructures:
Tied Arch
A temporary platform was erected at the bed of the reservoir on which the central 120 m of the steel deck was assembled. Falsework towers were erected at the same position as the final hangers and each semi-arch was divided into three steel transport segments, supported on the towers and joined to each other as well as to the ends of the deck. After the hangers were located, the shoring was removed; loading the steel tied arch bridge.
Approaching spans and Cantilevers
The steel structure of the approaching spans of each bank were assembled on the ground and then placed, using a crane, on the piers. The steel bases of the arches (the distance from the arch's basement to the deck's intersection) were then placed in one single operation with a crane (33m in cantilever) and embedded into the foundation block. Having positioned the two pieces of the arches on one bank, they were joined at the top by means of a steel brace placed with a crane. Consequently, the crane placed the steel structure of the deck from pier to the arch-deck section.
Lifting
Once the three self-supporting partial steel structures had been built, the bowstring arch was raised into position, joining the three partial arches.
The side walls of the abutments contain retaining prestressed tendons which were used to fix the deck to the abutment during the lift. Once tensioned, the 470 ton bowstring was raised 40 m, using a lifting machine, to its final level, taking just eight hours by subcontractor ALE Lastra. The arches were then joined, the tendons in the abutments released and the decks connected.
Arches
In order to ensure that the balance of the loads applied to the arches was maintained throughout the curing process, the arches were filled with concrete in two phases. Each arch was divided into 5 m long watertight modules, filled alternately in each phase with self-compacting concrete.
Deck
Once the arch was rigid, precast slabs were situated over the steel beams of the deck and then it was concreted from the centre towards the exterior in order to reduce strains and forces acting during construction.
After the entire dead load of the bridge was loaded, dampers and shock absorbers were installed in order to reduce the vertical deflections produced by asymmetric live loads in the arch and to allow slow deflections in the deck due to thermal and rheological actions.
The bridge was completed in August 2007.
An arch bridge is a bridge with abutments at each end shaped as a curved arch. Arch bridges work by transferring the weight of the bridge and its loads partially into a horizontal thrust restrained by the abutments at either side. A viaduct may be made from a series of arches, although other more economical structures are typically used today.
A truss bridge is a bridge whose load-bearing superstructure is composed of a truss, a structure of connected elements, usually forming triangular units. The connected elements, typically straight, may be stressed from tension, compression, or sometimes both in response to dynamic loads. There are several types of truss bridges, including some with simple designs that were among the first bridges designed in the 19th and early 20th centuries. A truss bridge is economical to construct primarily because it uses materials efficiently.
Beam bridges are the simplest structural forms for bridge spans supported by an abutment or pier at each end. No moments are transferred throughout the support, hence their structural type is known as simply supported.
A plate girder bridge is a bridge supported by two or more plate girders.
The Francis Scott Key Bridge, more commonly known as the Key Bridge, is a six-lane reinforced concrete arch bridge carrying U.S. Route 29 (US 29) across the Potomac River between the Rosslyn neighborhood of Arlington County, Virginia, and the Georgetown neighborhood of Washington, D.C. Completed in 1923, it is Washington's oldest surviving road bridge across the Potomac River.
The Howrah Bridge is a balanced steel bridge over the Hooghly River in West Bengal, India. Commissioned in 1943, the bridge was originally named the New Howrah Bridge, because it replaced a pontoon bridge at the same location linking the twin cities of Howrah and Kolkata, which are located at the opposite banks of each other. On 14 June 1965, it was renamed Rabindra Setu after the Bengali poet Rabindranath Tagore, who was the first Indian and Asian Nobel laureate. It is still popularly known as the Howrah Bridge.
A tied-arch bridge is an arch bridge in which the outward-directed horizontal forces of the arch(es) are borne as tension by a chord tying the arch ends rather than by the ground or the bridge foundations. This strengthened chord may be the deck structure itself or consist of separate, independent tie-rods.
A girder bridge is a bridge that uses girders as the means of supporting its deck. The two most common types of modern steel girder bridges are plate and box.
The Lamar Boulevard Bridge is a historic arch bridge carrying Texas State Highway Loop 343 over Lady Bird Lake in downtown Austin, Texas, United States. The bridge features six open-spandrel concrete arches spanning 659 feet (201 m) and carries tens of thousands of vehicles daily across the lake. Completed in 1942, the Lamar Boulevard Bridge was the second permanent bridge to cross the Colorado River, and one of the last Art Deco-style open-spandrel concrete arch bridges built in Texas. The bridge was named an Austin Landmark in 1993 and added to the National Register of Historic Places in 1994.
The Infinity Bridge is a public pedestrian and cycle footbridge across the River Tees in the borough of Stockton-on-Tees in northern England. The bridge is situated one kilometre downriver of Stockton town centre, between the Princess of Wales Bridge and the Tees Barrage. It connects the Teesdale Business Park and the University of Durham's Queen's Campus in Thornaby-on-Tees on the south bank of the Tees with the Tees Valley Regeneration's £320 million North Shore development on the north bank.
The Godavari Arch Bridge is a bowstring-girder bridge that spans the Godavari River in Rajahmundry, India. It is the latest of the three bridges that span the Godavari river at Rajahmundry. The Havelock Bridge being the earliest, was built in 1897, and having served its full utility, was decommissioned in 1997. The second bridge known as the Godavari Bridge is a truss bridge and is India's third longest road-cum-rail bridge crossing a water body.
The Cala Galdana Bridge is a steel arch bridge over Algendar Creek on the island of Menorca, Spain. It is the first vehicular bridge constructed in duplex stainless steel.
The Adomi Bridge is a latticed steel arch suspension bridge crossing the Volta River at Atimpoku in Ghana in West Africa. It is the first permanent bridge to span the Volta River, which drains south into the Gulf of Guinea, and is Ghana's longest suspension bridge. It provides the main road passage, just south of the Akosombo Dam, between the Eastern Region and the Volta Region of Ghana. It was opened in 1957 by Kwame Nkrumah, Ghana's first president. The iconic crescent-shaped arch bridge is featured in Ghanaian stamps and currency.
A Rigid-frame bridge is a bridge in which the superstructure and substructure are rigidly connected to act as a continuous unit. Typically, the structure is cast monolithically, making the structure continuous from deck to foundation. The connections between members are rigid connections which transfer bending moment, axial forces, and shear forces. A bridge design consisting of a rigid frame can provide significant structural benefits, but can also be difficult to design and/or construct.
A launching gantry is a special-purpose mobile gantry crane used in bridge construction, specifically segmental bridges that use precast box girder bridge segments or precast girders in highway and high-speed rail bridge construction projects. The launching gantry is used to lift and support bridge segments or girders as they are placed while being supported by the bridge piers instead of the ground.
Burdekin River Rail Bridge is a heritage-listed former railway bridge on the Great Northern railway over the Burdekin River at Dotswood, Charters Towers Region, Queensland, Australia. It was designed by Henry Charles Stanley and built from c. 1896 to 1899 by Swanson Brothers. It is also known as Macrossan Bridge. It was added to the Queensland Heritage Register on 21 October 1992.
The Quechee Gorge Bridge is a historic bridge, carrying U.S. Route 4 (US 4) across Quechee Gorge, near the Quechee village of Hartford, Vermont. Built in 1911, it is Vermont's oldest surviving steel arch bridge. It was listed on the National Register of Historic Places in 1990.
The Hassayampa Bridge is a bridge spanning the Hassayampa River in Hassayampa, Arizona, located in Maricopa County. The bridge was completed in 1929 and was listed on the National Register of Historic Places in 1988. The bridge was scheduled for demolition in 1983.
The Yowaka River bridge is a heritage-listed road bridge that carries the Princes Highway across the Yowaka River at Greigs Flat, New South Wales, Australia. It was built in 1936. The bridge is also known as the Yowaka Bridge near Eden. The bridge is owned by Transport for NSW. It was added to the New South Wales State Heritage Register on 20 June 2000.
The West Fifth Street Bridge is a historic cantilever concrete girder bridge in downtown Austin, Texas. Built in 1931, the bridge carries Fifth Street across Shoal Creek to link central Austin with neighborhoods that were then the city's western suburbs. It is one of only a handful of curved cantilever girder bridges in Texas, built as part of the city's 1928 master plan for urban development and beautification. The bridge was added to the National Register of Historic Places in 2019.
3D model of the bridge in Sketchup
Improving Infrastructure Worldwide, IABSE Symposium, Weimar, 19–21.09.2007