Laguna Verde Nuclear Power Plant | |
---|---|
Country | Mexico |
Location | Alto Lucero, Veracruz |
Coordinates | 19°43′15″N96°24′23″W / 19.72083°N 96.40639°W |
Status | Operational |
Commission date | 1990 (Unit 1) 1995 (Unit 2) |
Owner | Mexican Government |
Operator | Comisión Federal de Electricidad (CFE) |
Nuclear power station | |
Reactor type | Boiling Water Reactors (BWR-5) |
Reactor supplier | GE |
Power generation | |
Units operational | 2 reactors |
Nameplate capacity | 1620 MW (2 x 810 MW) |
Annual net output | 4.782 TWh x 2 |
External links | |
Commons | Related media on Commons |
The Laguna Verde Nuclear Power Plant (LVNPP) is located on the coast of the Gulf of Mexico, in Alto Lucero, Veracruz, Mexico. It is the only nuclear power plant in Mexico [1] and produces about 4.5% of the country's electrical energy. It consists of two GE Boiling Water Reactors, also known as a BWR-5 reactor, each one with an installed capacity of 682 MW using low enriched uranium (3%) as fuel. Unit-1 (U-1) started its operation on July 29, 1990. Unit-2 (U-2) started its operation on April 10, 1995. Initial architects in 1975 for the plant were Burns and Roe Inc, and later Ebasco Services designed and supervised the project. The steam turbine and other components were manufactured by Mitsubishi Electric. The plant is owned and operated by Comisión Federal de Electricidad (CFE), the national electric company owned by the Mexican government.
Laguna Verde has been considered a strategic facility for the National Power System (SEN) due to its high power generation capacity, lowest operating cost, and frequency and voltage regulation capacity. All the electric power generated is delivered to its single client, the National Energy Control Center (CENACE). CENACE is entrusted with planning, directing, and supervising the transmission and distribution of electric power to end users. CENACE has classified LVNPP as Base Load Power Plant since the beginning of its operations.
The annual generation average for LVNPP starting 2005 to 2010 has been 10.5 TWh, electric energy sufficient to meet the demand of more than 4 million inhabitants.
In 2020, the Ministry of Energy authorized the operating license extension of unit 1 for an additional 30 years, to a 60-year lifetime until 2050. [2]
The generation of electric power at the CLV is based on the technology of nuclear fission of uranium atoms, which takes place in the reactor. The energy released by the nuclear fission is transferred as heat from the fuel to the cooling water, which boils into steam. The quality of steam is controlled through a separator and dryer. The separator and dryer are part of the internal processes of the reactor pressure vessel. The turbine transforms power from steam (kinetic energy) into mechanical energy causing an electric generator to move (electric power production). Once the steam has gone through the turbine, it is cooled in a condenser; the water obtained in this manner is pumped again toward the nuclear reactor, to restart the generation cycle.
Steam flow rate from each reactor is 3944 kilotons/hour (kt/h) to generate 682 MW of electric power. Both Reactor Units (U1 and U2) operate using 444 enriched uranium assemblies, storing power equal to 38.9 million oil barrels. This nuclear fuel is specifically designed to be admitted into the core of the reactor. The fuel is purchased only from qualified vendors worldwide. After 18 months of operation, between 25% and 30% of the nuclear fuel is replaced. This activity is called "Refueling Outage" process.
In 2007, CFE signed a contract with an investment of USD 600 million to increase the original capability of each of the units of Laguna Verde by 20%, equivalent to 255 MW, in order to tend the growth of the demand of electric power in Mexico. This power uprate will allow to LVNPP an additional annual generation of 2.1 TWh, equivalent to the demand of a city of 800,000 inhabitants.
GE and CFE jointly performed the engineering analysis to determine the necessary plant modifications and to support the safety analysis report necessary for approval of the power uprate by the national nuclear regulator, the Comisión Nacional de Seguridad Nuclear y Salvaguardias , [3] [4]
Work began in 2008 by Iberdrola and Alstom and finished late 2010. The main modifications consist in a turbine and condenser retrofit and the replacement of the electric generator, main steam reheater and the feedwater heater. The budget for the project is USD 605 million. [5]
The following table shows the chronologic developments at Laguna Verde. [2]
YEAR | EVOLUTION |
---|---|
1976 | Implementation of the Quality Assurance Program as part of the international nuclear standard during the construction phase |
1982 | Implementation of the Quality Assurance Program in the operation phase |
1990 | Start of Reactor Unit 1 commercial operation |
1991 | World record broken for reaching 250 days of continuous operation (without interruptions) during the first generation cycle |
1995 | Start of Reactor Unit 2 commercial operation |
1995 | Laguna Verde used as a base to institutionalize the Total Quality program at the Comisión Federal de Electricidad (CFE) nationwide |
1995 | Accreditation of the Environmental Engineering Laboratory by the Mexican Accrediting Entity |
1997 | For the first time, CFE awards the Total Quality institutional prize, won by the Laguna Verde |
1997 | ISO 9001:1994 quality standard certification is obtained as part of the Continuous improvement program |
1999 | ISO 14001 quality standard certification was obtained |
1999 | Power generation boosted by 5% (sufficient to satisfy the needs of 200,000 persons) |
2002 | Certification in the Mexican Industrial Safety Standard NMX-SAST-001-IMNC-2000, which is the equivalent of the international OHSAS 18001. |
2003 | Certification in the ISO 9001:2000 Quality Standard based on process management. |
2004 | Laguna Verde reached Level-3 in the WANO excellence rating (maximum 1, minimum 5) |
2004 to 2007 | CLV significantly reduced the duration of refueling outage periods to 27 days |
2005 | Prize for the Nuclear Power Station with the best performance outside the USA given by WANO/ATLANTA |
2005 | Approval of the Extended Power Uprate Project (EPU) with an investment of $600 million USD, which will make it possible to increase the installed capacity by 20% compared with the original and which is strategically important to extend the station's useful life up to 50 years |
2006 and 2008 | Clean Industry biennial certification issued by the Mexican government through the Federal Environment Protection Agency as a result of complying with the 66 environment and safety standards |
2006 | Laguna Verde reached Level-2 in the WANO excellence rating, the highest level obtained by a nuclear power station outside the United States according to WANO/ATLANTA |
2006 | Recognition for world-class operation performance in Reactor Units 1 and 2 granted by General Electric |
2006 | Accreditation of the Metrology Laboratory by the Mexican Accrediting Entity |
2007 | Environmental Excellence Recognition (the highest award for the environment) obtained by the Mexican government because of high sustainability in the preservation of natural resources |
2008 | Laguna Verde obtains National Quality Prize 2007, which the highest recognition for policy and strategy quality and execution in congruence with the competitiveness and sustainability results obtained |
2008 to 2009 | Annual recognition as a Socially Responsible Enterprise awarded by the Mexican Centre for Philanthropy in compliance with ethical values, community support and respect and care for the environment |
2009 | Iberoamerican Quality Prize 2009 obtained, the highest award given by the Fundación Iberoamericana para Gestión de la Calidad (FUNDIBEQ/Iberoamerican Quality Management Foundation) |
2010 | Laguna Verde Manager receives the Nuclear Excellence Recognition delivered by WANO during Biennial Meeting, for promoting leadership that makes an extraordinary contribution to the promotion of Safe Operation Excellence at nuclear power stations |
Laguna Verde has obtained several awards. The plant received the National Quality Award (IFCT 2007), and Golden Award from Iberoamerican Foundation for Quality Management (FUNDIBEQ 2009).
In 2009, Laguna Verde obtained Annual recognition as a Socially Responsible Enterprise awarded by the Mexican Center for Philanthropy.[ citation needed ]
A pressurized water reactor (PWR) is a type of light-water nuclear reactor. PWRs constitute the large majority of the world's nuclear power plants. In a PWR, the primary coolant (water) is pumped under high pressure to the reactor core where it is heated by the energy released by the fission of atoms. The heated, high pressure water then flows to a steam generator, where it transfers its thermal energy to lower pressure water of a secondary system where steam is generated. The steam then drives turbines, which spin an electric generator. In contrast to a boiling water reactor (BWR), pressure in the primary coolant loop prevents the water from boiling within the reactor. All light-water reactors use ordinary water as both coolant and neutron moderator. Most use anywhere from two to four vertically mounted steam generators; VVER reactors use horizontal steam generators.
A boiling water reactor (BWR) is a type of light water nuclear reactor used for the generation of electrical power. It is the second most common type of electricity-generating nuclear reactor after the pressurized water reactor (PWR), which is also a type of light water nuclear reactor.
A nuclear power plant (NPP), also known as a nuclear power station (NPS), nuclear generating station (NGS) or atomic power station (APS) is a thermal power station in which the heat source is a nuclear reactor. As is typical of thermal power stations, heat is used to generate steam that drives a steam turbine connected to a generator that produces electricity. As of September 2023, the International Atomic Energy Agency reported that there were 410 nuclear power reactors in operation in 32 countries around the world, and 57 nuclear power reactors under construction.
The A2W reactor is a naval nuclear reactor used by the United States Navy to provide electricity generation and propulsion on warships. The A2W designation stands for:
A combined cycle power plant is an assembly of heat engines that work in tandem from the same source of heat, converting it into mechanical energy. On land, when used to make electricity the most common type is called a combined cycle gas turbine (CCGT) plant, which is a kind of gas-fired power plant. The same principle is also used for marine propulsion, where it is called a combined gas and steam (COGAS) plant. Combining two or more thermodynamic cycles improves overall efficiency, which reduces fuel costs.
Cogeneration or combined heat and power (CHP) is the use of a heat engine or power station to generate electricity and useful heat at the same time.
The Army Nuclear Power Program (ANPP) was a program of the United States Army to develop small pressurized water and boiling water nuclear power reactors to generate electrical and space-heating energy primarily at remote, relatively inaccessible sites. The ANPP had several accomplishments, but ultimately it was considered to be "a solution in search of a problem." The U.S. Army Engineer Reactors Group managed this program and it was headquartered at Fort Belvoir, Virginia. The program began in 1954 as the Army Reactors Branch and had effectively terminated by about 1977, with the last class of NPP operators graduating in 1977. Work continued for some time thereafter either for decommissioning of the plants or placing them into SAFSTOR. The current development of small modular reactors has led to a renewed interest in military applications.
The Enrico Fermi Nuclear Generating Station is a nuclear power plant on the shore of Lake Erie near Monroe, in Frenchtown Charter Township, Michigan on approximately 1,000 acres (400 ha). All units of the plant are operated by the DTE Energy Electric Company and owned by parent company DTE Energy. It is approximately halfway between Detroit, Michigan, and Toledo, Ohio. It is also visible from parts of Amherstburg and Colchester, Ontario as well as on the shore of Lake Erie in Ottawa County, Ohio. Two units have been constructed on this site. The first unit's construction started on August 4, 1956 and reached initial criticality on August 23, 1963, and the second unit received its construction permit on September 26, 1972. It reached criticality on June 21, 1985 and was declared commercial on November 18, 1988. The plant is connected to two single-circuit 345 kV Transmission Lines and three 120 kV lines. They are operated and maintained by ITC Transmission.
Quad Cities Generating Station is a two-unit nuclear power plant located near Cordova, Illinois, United States, on the Mississippi River. The two General Electric boiling water reactors give the plant a total gross electric capacity of approximately 1,880 MW. It was named for the nearby cities of Moline, Illinois, Rock Island, Illinois, Davenport, Iowa, East Moline, Illinois, and Bettendorf, Iowa — known as the Quad Cities.
A thermal power station, also known as a thermal power plant, is a type of power station in which the heat energy generated from various fuel sources is converted to electrical energy. The heat from the source is converted into mechanical energy using a thermodynamic power cycle. The most common cycle involves a working fluid heated and boiled under high pressure in a pressure vessel to produce high-pressure steam. This high pressure-steam is then directed to a turbine, where it rotates the turbine's blades. The rotating turbine is mechanically connected to an electric generator which converts rotary motion into electricity. Fuels such as natural gas or oil can also be burnt directly in gas turbines, skipping the steam generation step. These plants can be of the open cycle or the more efficient combined cycle type.
The Saxton Nuclear Experiment Station, also known as the Saxton Nuclear Generating Station or Saxton Nuclear Experimental Corporation Facility, was a small nuclear power plant located in Bedford County, near Saxton, Pennsylvania.
Nuclear Power Demonstration was the first Canadian nuclear power reactor, and the prototype for the CANDU reactor design. Built by Canadian General Electric, in partnership with Atomic Energy of Canada Limited (AECL) and the Hydro Electric Power Commission of Ontario it consisted of a single 22 MWe pressurized heavy water reactor (PHWR) unit located in Rolphton, Ontario, not far from AECL's Chalk River Laboratories. NPD was owned by AECL and operated by Ontario Hydro.
The National Atomic Energy Commission is the Argentine government agency in charge of nuclear energy research and development.
The Beloyarsk Nuclear Power Station was the third of the Soviet Union's nuclear plants. It is situated by Zarechny in Sverdlovsk Oblast, Russia. Zarechny township was created to service the station, which is named after the Beloyarsky District. The closest city is Yekaterinburg.
The Sizewell nuclear site consists of two nuclear power stations, one of which is still operational, located near the small fishing village of Sizewell in Suffolk, England. Sizewell A, with two Magnox reactors, is now in the process of being decommissioned. Sizewell B has a single pressurised water reactor (PWR) and is the UK's newest nuclear power station. A third power station, to consist of twin EPR reactors, is planned to be built as Sizewell C.
Spain has five active nuclear power plants with seven reactors producing 20% of the country's electricity as of 2023.
As required by the Constitution, the electricity sector is federally owned, with the Federal Electricity Commission essentially controlling the whole sector; private participation and foreign companies are allowed to operate in the country only through specific service contracts. Attempts to reform the sector have traditionally faced strong political and social resistance in Mexico, where subsidies for residential consumers absorb substantial fiscal resources.
The electricity sector in Finland relies on nuclear power, renewable energy, cogeneration and electricity import from neighboring countries. Finland has the highest per-capita electricity consumption in the EU. Co-generation of heat and electricity for industry process heat and district heating is common. Finland is one of the last countries in the world still burning peat.
The BN-800 reactor is a sodium-cooled fast breeder reactor, built at the Beloyarsk Nuclear Power Station, in Zarechny, Sverdlovsk Oblast, Russia. The reactor is designed to generate 880 MW of electrical power. The plant was considered part of the weapons-grade Plutonium Management and Disposition Agreement signed between the United States and Russia. The reactor is part of the final step for a plutonium-burner core The plant reached its full power production in August 2016. According to Russian business journal Kommersant, the BN-800 project cost 140.6 billion rubles.
General Electric's BWR product line of boiling water reactors represents the designs of a relatively large (~18%) percentage of the commercial fission reactors around the world.