Industry | Regional transmission organization |
---|---|
Founded | 1927 |
Headquarters | |
Area served | Delaware, Illinois, Indiana, Kentucky, Maryland, Michigan, New Jersey, North Carolina, Ohio, Pennsylvania, Tennessee, Virginia, West Virginia, and the District of Columbia, U.S. [2] |
Key people | Manu Asthana (President, CEO) [3] |
Members | 1,111 [2] |
Website | www |
PJM Interconnection LLC (PJM) is a regional transmission organization (RTO) in the United States. It is part of the Eastern Interconnection grid operating an electric transmission system serving all or parts of Delaware, Illinois, Indiana, Kentucky, Maryland, Michigan, New Jersey, North Carolina, Ohio, Pennsylvania, Tennessee, Virginia, West Virginia, and the District of Columbia.
PJM, headquartered in Valley Forge, Pennsylvania, was the world's largest competitive wholesale electricity market until the development of the European Integrated Energy Market in the 2000s. [4] More than 1,000 companies are members of PJM, which serves 65 million people and has 185 gigawatts of generating capacity. With 1,436 electric power generators and 85,103 miles of transmission lines, PJM delivered 783 terawatt-hours of electricity in 2021. [5]
Started in 1927, the pool was renamed the Pennsylvania-New Jersey-Maryland Interconnection (PJM) in 1956. The organization continues to integrate additional utility transmission systems into its operations.
The Federal Energy Regulatory Commission (FERC) regulates PJM [6] and approves its open access transmission tariff for the wholesale electricity market.
In 1927 the Public Service Electric and Gas Company, Philadelphia Electric Company, and Pennsylvania Power & Light Company formed a power pool called the Pennsylvania-New Jersey Interconnection. [7] The purpose of the power pool was to dispatch electric generating plants on a lowest cost basis, thereby reducing the electric costs for all members of the pool. [8]
After Baltimore Gas and Electric Company and General Public Utilities joined in 1956, the pool was renamed the Pennsylvania-New Jersey-Maryland Interconnection, or PJM. [9]
From 1996 to 1999, the FERC made a series of decisions which resulted in the restructuring of the U.S. electric utility industry. The FERC's intention in doing so was to open the wholesale power market to new players, with the hope that spurring competition would save consumers $4 to $5 billion per year and encourage technical innovation in the industry. [10]
Order No. 888 (Promoting Wholesale Competition Through Open Access Non-discriminatory Transmission Services by Public Utilities; Recovery of Stranded Costs by Public Utilities and Transmitting Utilities) directed utility owners of interstate transmission lines to provide FERC with proposed terms (including fee schedules, or "tariffs") under which new market participants would be granted open, non-discriminatory access to move (or "wheel") power through the existing transmission grid. FERC also ordered electric utilities to functionally separate transmission operations from their power plant and power marketing businesses. This unbundling of functions was aimed at eliminating conflicts of interest that might exist when the same company owned both the transmission system and the generating plants. [11]
Order No. 889 (Open Access Same-Time Information System) was designed to further level the playing field. It required the creation of an electronic system to ensure that all participants in the wholesale power market - new players and traditional electric utilities - had access to the same information about available transmission capacity and prices. [12]
FERC also endorsed the concept of appointing independent system operators (ISOs) to coordinate, control, and monitor the operation of electrical power systems, often within a single US state - a function that was traditionally the responsibility of vertically integrated electric utility companies. [13] PJM became an ISO in 1997. The concept of an independent system operator evolved into that of regional transmission organizations (RTOs). FERC's intention was that all U.S. companies owning interstate electric transmission lines would place those facilities under the control of an RTO. [14] In its Order No. 2000 (Regional Transmission Organizations), issued in 1999, FERC specified the minimum capabilities that an RTO should possess in order for the competitive generation market to function as intended. [15] PJM was designated an RTO by FERC in 2001.
In April 2002, Allegheny Power (AP) was the first external control area to join the PJM RTO as a market participant; "PJM Classic" and AP operated as a single control area, filling the roles of balancing authority, interchange authority, market operator and transmission operator.
During the Northeast Blackout of 2003, the transmission systems within the PJM operations area largely remained operational and were not affected by the power failure. [9] When the grid separated, a small portion of the Public Service Electric & Gas of New Jersey zone electrically separated from the Eastern Interconnection due to over-frequency relay operations.
In May 2004, Commonwealth Edison (ComEd) joined PJM as a separate balancing authority operating under the RTO. PJM was able to manage the two territories in a single market by a mechanism known as "the pathway", a set of firm contracts that transferred energy from ComEd through third party control areas to the eastern PJM markets and beyond. In October 2004, American Electric Power (AEP) and Dayton Power & Light (DPL) joined PJM, which allowed PJM to collapse back into a single control area.
In January 2005, Duquesne Light Co. (DLCO) joined PJM. In May 2005, Dominion Virginia Power joined PJM, extending the southern border to North Carolina. FirstEnergy was added to PJM in June 2011, expanding the footprint across northern Ohio to the Michigan border. Areas of Ohio and Kentucky near Cincinnati covered by Duke Energy joined the PJM footprint in January 2012. In 2018, the Ohio Valley Electric Corporation (OVEC) integrated into PJM. [16] At this time[ when? ], PJM now borders 22 balancing authorities representing eleven market interfaces.[ citation needed ]
PJM uses a fifteen-year planning horizon for planning transmission system upgrades. Under PJM's Regional Transmission Expansion Planning (RTEP) process, PJM considers forecasts of load growth and additions of demand response, interconnection requests for new and planned retirements of existing generating plants, and possible solutions to mitigate congestion on the transmission system. [17] If the upgrade involves the construction of a new transmission line, local siting decisions involving the route of the new line are determined by the owner of the line and the state government.
As the largest RTO in North America, PJM has a significant role to play in reducing grid emissions. PJM has "facilitating decarbonization" [18] as one of its three strategic pillars.
PJM presents hourly a pie chart of its energy sources on the main page of its website. [19] It also provides access [20] to an historical hour by hour database of generation by fuel type, summarized here for 2022.
Carbon-emitting sources | Non-carbon-emitting sources | ||
167,111,041 | Coal | 15,964,309 | Hydro |
331,532,269 | Gas | 271,360,198 | Nuclear |
4,055,748 | Multiple Fuels | 5,383,905 | Other Renewables |
2,796,223 | Oil | 7,153,851 | Solar |
1,376,685 | Other | 32,161,464 | Wind |
506,871,966 | total emitting sources | 332,023,727 | total non-emitting sources |
60.4% | % from emitting sources | 39.6% | % from non-emitting sources |
PJM seriously lags the rest of the country in adding renewable energy. According to the Energy Information Administration (EIA), in 2021 nationwide 12% of US electric energy was produced by wind and solar. [21] Even a year later in 2022, PJM produced only 4.7% by wind and solar, as seen in the table above, although the PJM Independent Market Monitor reported wind and solar accounted for 6.8% of PJM energy in 2022 [22] which still lags the rest of the country significantly.
The low level of renewable generation on PJM is not improving significantly. In 2022, PJM was the only RTO which connected more fossil generation than renewables. [23]
As of 2022 [update] due to the volume of applications from renewable energy projects PJM has experienced difficulty in evaluating and integrating proposed new projects into its system. This may result in delays in utilization of significant projects that are being built or are planned, delaying the achievement of President Biden's goal of 100 percent carbon-free electricity by 2035. [24] [25] Transition to renewables may also be slowed by features of the PJM pricing models. In an August 2021 letter, the PJM PIEOUG (Public Interest and Environmental Organizations User Group) expressed concern that the capacity market resulted in “unintentional subsidies for fossil fueled resources or barriers to low carbon supply.” [26] Further, PJM has significantly increased interconnection charges. Since 2019 PJM has charged almost triple (increase from well under $100/Kw to well over $200/Kw) what it charged to interconnect before 2019. [23]
PJM is aware of the large backlog and slow pace in processing generation interconnection (GI) requests, and requested [27] significant changes to its interconnection process, described by PJM as: “... a comprehensive reform of the PJM interconnection process designed to more efficiently and timely process New Service Requests by transitioning from a serial “first-come, first-served” queue approach to a “first-ready, first-served” Cycle approach utilized by other regional transmission organizations (“RTOs”) and stand-alone transmission providers. ”
FERC approved the new GI process 11/29/22. [28] The PJM press release announcing FERC approval states “The proposal was widely supported by PJM stakeholders, who had worked with PJM to develop the new rules since the April 2021 inception of the Interconnection Process Reform Task Force.” However, one major stakeholder, the Organization of PJM States, [29] in its comments on the PJM proposal, indicated its recommendation for FERC approval was despite the process being “too slow”, and based on the expectation that much more was to be done to speed up interconnections. [30]
Prices are set in PJM by its operation of two markets: an energy market and a capacity market .
The energy market [31] sets prices, paid to generators and paid by consumers, for the many GWhrs of electrical energy delivered on the PJM grid. The price is determined by using nodal pricing, also known as locational marginal pricing. [32] PJM publishes a map of energy price levels throughout its area. [33]
“PJM's capacity market, [34] called the Reliability Pricing Model, ensures long-term grid reliability.” Market participants are paid for their promise to be able to generate electricity (or reduce demand) three years in the future. FERC approved a December 2022 PJM proposal to adjust its capacity market operations. However, in a 2/21/23 press release [35] FERC noted “continuing disputes and frequent complaints about how PJM operates its capacity markets from an array of stakeholders” and FERC stated it will “examine the PJM Interconnection, L.L.C. capacity market and how best to guarantee it achieves the objective of ensuring resource adequacy at just and reasonable rates.” In response to this stated FERC intent, and in the belief “near-term changes to the Reliability Pricing Model (RPM) are necessary to ensure that PJM can maintain resource adequacy into the future”, the PJM board “decided to implement the Critical Issue Fast Path (CIFP) accelerated stakeholder process mechanism to further pursue stakeholder consensus that would inform a PJM Board decision on a potential FERC filing targeted for October 1, 2023.” [36]
The amount of capacity OPM purchases (and passes costs along to customers) is the amount it needs to serve expected peak load plus a margin to cover possible delivery interruptions such as generator or transmission outages. The peak load in 2022 was 147,820 MW on July 20. [37] PJM forecasts peak load to increase to 160,971 MW in 2033 and reach 167,567 MW in 2038. [38] As of June 2022, PJM’s stated capacity was 198,152 MW, [39] which is substantially greater than any peak load ever experienced, or any peak load forecast. One analysis concluded that PJM has been purchasing capacity significantly in excess of load plus target reserve margins, which resulted in “consumers paying for more capacity than needed, retaining older capacity that is no longer needed and should be retired, and acquiring new power plants that are not yet needed.” [40] In its “State of the Market Report for PJM” for 2022, [22] The PJM Independent Market Monitor found that noncompetitive outcomes in the capacity market “led to customers being overcharged by a combined $1.454 billion” in the two year period analyzed.
Electric power transmission is the bulk movement of electrical energy from a generating site, such as a power plant, to an electrical substation. The interconnected lines that facilitate this movement form a transmission network. This is distinct from the local wiring between high-voltage substations and customers, which is typically referred to as electric power distribution. The combined transmission and distribution network is part of electricity delivery, known as the electrical grid.
The Federal Energy Regulatory Commission (FERC) is an independent agency of the United States government that regulates the interstate transmission and wholesale sale of electricity and natural gas and regulates the prices of interstate transport of petroleum by pipeline. FERC also reviews proposals to build interstate natural gas pipelines, natural gas storage projects, and liquefied natural gas (LNG) terminals, in addition to licensing non-federal hydropower projects.
The North American Electric Reliability Corporation (NERC) is a nonprofit corporation based in Atlanta, Georgia, and formed on March 28, 2006, as the successor to the North American Electric Reliability Council. The original NERC was formed on June 1, 1968, by the electric utility industry to promote the reliability and adequacy of bulk power transmission in the electric utility systems of North America. NERC's mission states that it "is to assure the effective and efficient reduction of risks to the reliability and security of the grid".
A public utility company is an organization that maintains the infrastructure for a public service. Public utilities are subject to forms of public control and regulation ranging from local community-based groups to statewide government monopolies.
An electricity market is a system that enables the exchange of electrical energy, through an electrical grid. Historically, electricity has been primarily sold by companies that operate electric generators, and purchased by consumers or electricity retailers.
The electric power industry covers the generation, transmission, distribution and sale of electric power to the general public and industry. The commercial distribution of electric power started in 1882 when electricity was produced for electric lighting. In the 1880s and 1890s, growing economic and safety concerns lead to the regulation of the industry. What was once an expensive novelty limited to the most densely populated areas, reliable and economical electric power has become an essential aspect for normal operation of all elements of developed economies.
The Open Access Same-Time Information System (OASIS), is an Internet-based system for obtaining services related to electric power transmission in North America. It is the primary means by which high-voltage transmission lines are reserved for moving wholesale quantities of electricity. The OASIS concept was originally conceived with the Energy Policy Act of 1992, and formalized in 1996 through Federal Energy Regulatory Commission (FERC) Orders 888 and 889.
A regional transmission organization (RTO) in the United States is an electric power transmission system operator (TSO) that coordinates, controls, and monitors a multi-state electric grid. The transfer of electricity between states is considered interstate commerce, and electric grids spanning multiple states are therefore regulated by the Federal Energy Regulatory Commission (FERC). The voluntary creation of RTOs was initiated by FERC in December 1999. The purpose of the RTO is to promote economic efficiency, reliability, and non-discriminatory practices while reducing government oversight.
Demand response is a change in the power consumption of an electric utility customer to better match the demand for power with the supply. Until the 21st century decrease in the cost of pumped storage and batteries, electric energy could not be easily stored, so utilities have traditionally matched demand and supply by throttling the production rate of their power plants, taking generating units on or off line, or importing power from other utilities. There are limits to what can be achieved on the supply side, because some generating units can take a long time to come up to full power, some units may be very expensive to operate, and demand can at times be greater than the capacity of all the available power plants put together. Demand response, a type of energy demand management, seeks to adjust in real-time the demand for power instead of adjusting the supply.
The energy policy of the United States is determined by federal, state, and local entities. It addresses issues of energy production, distribution, consumption, and modes of use, such as building codes, mileage standards, and commuting policies. Energy policy may be addressed via legislation, regulation, court decisions, public participation, and other techniques.
Southwest Power Pool (SPP) manages the electric grid and wholesale power market for the central United States. As a regional transmission organization, the nonprofit corporation is mandated by the Federal Energy Regulatory Commission to ensure reliable supplies of power, adequate transmission infrastructure and competitive wholesale electricity prices. Southwest Power Pool and its member companies coordinate the flow of electricity across approximately 60,000 miles of high-voltage transmission lines spanning 14 states. The company is headquartered in Little Rock, Arkansas.
The Midcontinent Independent System Operator, Inc., formerly named Midwest Independent Transmission System Operator, Inc. (MISO) is an Independent System Operator (ISO) and Regional Transmission Organization (RTO). It provides open-access transmission service and monitors the high-voltage transmission system in the Midwestern United States, in Manitoba, Canada, and in a southern U.S. region that includes much of Arkansas, Mississippi, and Louisiana. MISO also operates one of the world's largest real-time energy markets. The 15 states covered by MISO are: Arkansas, Illinois, Indiana, Iowa, Kentucky, Louisiana, Michigan, Minnesota, Mississippi, Missouri, Montana, North Dakota, South Dakota, Texas, and Wisconsin.
ISO New England Inc. (ISO-NE) is an independent, non-profit regional transmission organization (RTO), headquartered in Holyoke, Massachusetts, serving Connecticut, Maine, Massachusetts, New Hampshire, Rhode Island, and Vermont.
A National Interest Electric Transmission Corridor (NIETC) corridor is a geographic region designated by the United States Department of Energy where electricity transmission limitations are adversely affecting American citizens. The Energy Policy Act of 2005 granted the Federal Energy Regulatory Commission (FERC) the authority to create these regions to increase transmission capacity within a short timeframe. If state and local governments fail to issue permits to increase transmission capacity in these areas, FERC can issue federal permits empowering project directors to use eminent domain to purchase property needed to complete projects.
The United States has the second largest electricity sector in the world, with 4,178 Terawatt-hours of generation in 2023. In 2023 the industry earned $491b in revenue at an average price of $0.127/kWh.
In the electric power industry, a transmission service request is an application requesting a transmission-owning utility to allocate physical capacity in the form of transmission service rights (TSRs) for the transmission of electric power. Every TSR includes at least three components: 1) a point of delivery (POD), where the power is injected into the utility's transmission network; 2) a point of receipt (POR), where the power is withdrawn from the utility's transmission network; 3) the amount of power, or capacity, in megawatts to be reserved. In order to receive TSR, a transmission customer (TC) must complete a transmission service request and go through a system impact study to determine if the existing transmission facilities can reliably accommodate the physical transfer of the electric power. If the capacity is not available, the transmission customer may decide to pay to upgrade the transmission network.
The electrical power grid that powers Northern America is not a single grid, but is instead divided into multiple wide area synchronous grids. The Eastern Interconnection and the Western Interconnection are the largest. Three other regions include the Texas Interconnection, the Quebec Interconnection, and the Alaska Interconnection. Each region delivers power at a nominal 60 Hz frequency.
Resource adequacy in the field of electric power is the ability of the electric grid to satisfy the end-user power demand at any time. RA is a component of the electrical grid reliability. For example, sufficient unused generation capacity shall be available to the electrical grid at any time to accommodate major equipment failures and drops in variable renewable energy sources. The adequacy standard should satisfy the chosen reliability index, typically the loss of load expectation (LOLE) of 1 day in 10 years.
Load serving entity (LSE) in a deregulated electricity market is a company or government agency that is obligated by law or via a long-term contract to provide electrical power to end-users. The term is used in regulation, yet is vague and thus subject to prolonged political wrangling. For example, the US law defines an LSE as an obligation-bound provider of electricity directly to consumers or to a utility that serves the consumers. FERC defines the LSE as "any entity, including a load aggregator or power marketer, that serves end-users within a control area and has been granted the authority or has an obligation pursuant to state or local law, regulation, or franchise to sell electric energy to end-users located within the control area".
{{cite book}}
: CS1 maint: multiple names: authors list (link){{cite book}}
: CS1 maint: multiple names: authors list (link)America's 2030 target picks up the pace of emissions reductions in the United States, compared to historical levels, while supporting President Biden's existing goals to create a carbon pollution-free power sector by 2035 and net zero emissions economy by no later than 2050