TB Flats I & II Wind Farm
Country United States
Location Wyoming
Coordinates 42°11′36.7″N106°7′15.4″W / 42.193528°N 106.120944°W / 42.193528; -106.120944
StatusOperational
Construction began2019
Commission date 2021 [1]
Owner PacifiCorp
Wind farm
Type Onshore
Hub height80-82 m
Rotor diameter110-136 m
Power generation
Make and modelVestas V110-2.0, Vestas V136-4.3 [2]
Nameplate capacity 301.1 MW

TB Flats I & II Wind Farm is a 301.1-megawatt onshore wind farm located in Carbon County and Albany County, Wyoming, United States. [3] The project was developed by Invenergy and later transferred to PacifiCorp as part of their Energy Vision 2020 initiative. It comprises 132 turbines manufactured by Vestas, specifically the V110-2.0 MW and V136-4.3 MW models. [2] [4]

Contents

Substation and transmission

The Aeolus substation near Medicine Bow serves as a critical connection point for TB Flats I & II, linking the wind farm to the broader PacifiCorp transmission grid. PacifiCorp’s Gateway South transmission project facilitates the delivery of wind-generated power to neighboring states. [1] [4]

Economic and environmental impact

The construction and operation of TB Flats I & II created between 1,100 and 1,600 jobs during the development phase and is expected to generate approximately $120 million in tax revenue over its lifetime. The wind farm contributes to diversifying Wyoming’s economy while providing clean, renewable energy capable of powering more than 100,000 homes annually. [5] [1]

Development and construction

The development of TB Flats I & II began under Invenergy in 2019. Construction was completed in 2020, with the farm becoming operational in 2021. The wind farm consists of three sections: [2]

Tb flats net generation Oct 2021 - Oct 2024 Tb flats net generation Oct 2021 - Oct 2024.png
Tb flats net generation Oct 2021 - Oct 2024
TB Flats Wind Farm Technical Details [2]
PartCountyTurbine ModelNumber of TurbinesUnit PowerTotal PowerRotor DiameterHub Height
Part 1Carbon, AlbanyVestas V110/2000282 MW56 MW110 m80-82 m
Part 2Vestas V136/4000-4200474 MW202.1 MW136 m
Part 3Vestas V136/4000-4200574 MW245.1 MW [7] 136 m

Energy production

TB Flats Wind Farm Monthly Net Generation (MWh) [8]
YearJanFebMarAprMayJunJulAugSepOctNovDecAnnual Total
202173,457163,903205,908443,268
2022175,066179,232144,418160,605119,58986,41762,14655,64263,94295,795141,891204,2431,488,986
2023151,082144,760126,643129,04881,06070,70964,37473,54773,81186,982170,857143,8951,316,768
2024131,988132,410140,130122,550122,272126,77363,75588,73659,62171,4211,059,656

See also

References

  1. 1 2 3 Ariana Fine (July 29, 2021). "PacifiCorp's TB Flats Wind Farm is Fully Operational". North American Windpower. Retrieved January 14, 2025.
  2. 1 2 3 4 "United States Wind Turbine Database Viewer". United States Geological Survey. Retrieved January 14, 2025.
  3. Nicole Pollack (October 2022). "Wyoming Wind Generation Doubled in Two Years - And More Is on the Horizon". Casper Star-Tribune. Retrieved January 14, 2025.
  4. 1 2 The Associated Press (August 26, 2021). "Utility Completes Wind Power Surge With Wyoming Projects". Buckrail. Retrieved January 14, 2025.
  5. "1.5M-Pound Trailers Haul Transformers To Huge New Wyoming Wind Substation". Cowboy State Daily. August 2, 2024. Retrieved January 14, 2025.
  6. "Electricity Data Browser - Plant 62516". U.S. Energy Information Administration (EIA). Retrieved January 14, 2025.
  7. Uprated turbines
  8. "Electricity Data Browser - Plant 62516". U.S. Energy Information Administration (EIA). Retrieved January 14, 2025.

Invenergy Official Website