Takt time

Last updated

Takt time, or simply takt, is a manufacturing term to describe the required product assembly duration that is needed to match the demand. Often confused with cycle time, takt time is a tool used to design work and it measures the average time interval between the start of production of one unit and the start of production of the next unit when items are produced sequentially. For calculations, it is the time to produce parts divided by the number of parts demanded in that time interval. [1] The takt time is based on customer demand; if a process or a production line are unable to produce at takt time, either demand leveling, additional resources, or process re-engineering is needed to ensure on-time delivery.

Contents

For example, if the customer demand is 10 units per week, then, given a 40-hour workweek and steady flow through the production line, the average duration between production starts should be 4 hours, ideally. This interval is further reduced to account for things like machine downtime and scheduled employee breaks.

Etymology

Takt time is a borrowing of the Japanese word takuto taimu (タクトタイム), which in turn was borrowed from the German word Taktzeit, meaning 'cycle time'. The word was likely introduced to Japan by German engineers in the 1930s. [2]

The word originates from the Latin word "tactus" meaning "touch, sense of touch, feeling". [3] Some earlier meanings include: (16th century) "beat triggered by regular contact, clock beat", then in music "beat indicating the rhythm" and (18th century) "regular unit of note values". [4]

History

Takt time has played an important role in production systems even before the industrial revolution. From 16th-century shipbuilding in Venice, mass-production of Model T by Henry Ford, synchronizing airframe movement in the German aviation industry and many more. Cooperation between the German aviation industry and Mitsubishi brought takt to Japan, where Toyota incorporated it in the Toyota Production System (TPS). [3]

James P. Womack and Daniel T. Jones in The Machine That Changed the World (1990) [5] and Lean Thinking (1996) [6] introduced the world to the concept of "lean". Through this, Takt was connected to lean systems. In the Toyota Production System (TPS), takt time is a central element of the just-in-time pillar (JIT) of this production system.

Definition

Assuming a product is made one unit at a time at a constant rate during the net available work time, the takt time is the amount of time that must elapse between two consecutive unit completions in order to meet the demand.

Takt time can be first determined with the formula: [7]

Where
T   = Takt time (or takt), e.g. [work time between two consecutive units]
Ta = Net time available to work during the period, e.g. [work time per period]
D = Demand (customer demand) during the period, e.g. [units required per period]

Net available time is the amount of time available for work to be done. This excludes break times and any expected stoppage time (for example scheduled maintenance, team briefings, etc.).

Example:
If there are a total of 8 hours (or 480 minutes) in a shift (gross time) less 30 minutes lunch, 30 minutes for breaks (2 × 15 mins), 10 minutes for a team briefing and 10 minutes for basic maintenance checks, then the net Available Time to Work = 480 - 30 - 30 - 10 - 10 = 400 minutes.

If customer demand were 400 units a day and one shift was being run, then the line would be required to output at a minimum rate of one part per minute in order to be able to keep up with customer demand.

Takt time may be adjusted according to requirements within a company. For example, if one department delivers parts to several manufacturing lines, it often makes sense to use similar takt times on all lines to smooth outflow from the preceding station. Customer demand can still be met by adjusting daily working time, reducing down times on machines, and so on.

Implementation

Takt time is common in production lines that move a product along a line of stations that each performs a set of predefined tasks.

Takt in construction

With the adoption of lean thinking in the construction industry, takt time has found its way into the project-based production systems of the industry. Starting with construction methods that have highly repetitive products like bridge construction, tunnel construction, and repetitive buildings like hotels and residential high-rises, implementation of takt is increasing. [3]

According to Koskela (1992), an ideal production system has continuous flow and creates value for the customer while transforming raw materials into products. [8] Construction projects use critical path method (CPM) or program evaluation and review technique (PERT) for planning and scheduling. These methods do not generate flow in the production and tend to be vulnerable to variation in the system. Due to common cost and schedule overruns, industry professionals and academia have started to regard CPM and PERT as outdated methods that often fail to anticipate uncertainties and allocate resources accurately and optimally in a dynamic construction environment. [9] This has led to increasing developments and implementation of takt.

Space scheduling

Takt, as used in takt planning or takt-time planning (TTP) for construction, is considered one of the several ways of planning and scheduling construction projects based on their utilization of space rather than just time, as done traditionally in the critical path method. Also, to visualize and create flow of work on a construction site, utilization of space becomes essential. [10] Some other space scheduling methods include:

Comparison with manufacturing

In manufacturing, the product being built keeps moving on the assembly line, while the workstations are stationary. On contrary, construction product, i.e. the building or infrastructure facilities being constructed, is stationary and the workers move from one location to another. [14]

Takt planning needs an accurate definition of work at each workstation, which in construction is done through defining spaces, called "zones". Due to the non-repetitive distribution of work in construction, achieving work completion within the defined takt for each zone, becomes difficult. Capacity buffer is used to deal with this variability in the system. [15]

The rationale behind defining these zones and setting the takt is not standardized and varies as per the style of the planner. Work density method (WDM) is one of the methods being used to assist in this process. Work density is expressed as a unit of time per unit of area. For a certain work area, work density describes how much time a trade will require to do their work in that area (zone), based on: [16]

  1. the product's design, i.e., what is in the construction project drawings and specifications
  2. the scope of the trade's work,
  3. the specific task in their schedule (depending on work already in place and work that will follow later in the same or another process),
  4. the means and methods the trade will use (e.g., when prefabricating off-site, the work density on-site is expected to decrease),
  5. while accounting for crew capabilities and size.

Benefits of takt time

Once a takt system is implemented there are a number of benefits:

Problems of takt time

Once a takt system is implemented there are a number of problems:

See also

Related Research Articles

<span class="mw-page-title-main">Lean manufacturing</span> Methodology used to improve production

Lean manufacturing is a method of manufacturing goods aimed primarily at reducing times within the production system as well as response times from suppliers and customers. It is closely related to another concept called just-in-time manufacturing. Just-in-time manufacturing tries to match production to demand by only supplying goods that have been ordered and focus on efficiency, productivity, and reduction of "wastes" for the producer and supplier of goods. Lean manufacturing adopts the just-in-time approach and additionally focuses on reducing cycle, flow, and throughput times by further eliminating activities that do not add any value for the customer. Lean manufacturing also involves people who work outside of the manufacturing process, such as in marketing and customer service.

<span class="mw-page-title-main">Kanban</span> Japanese business method

Kanban is a scheduling system for lean manufacturing. Taiichi Ohno, an industrial engineer at Toyota, developed kanban to improve manufacturing efficiency. The system takes its name from the cards that track production within a factory. Kanban is also known as the Toyota nameplate system in the automotive industry.

Kaizen is a concept referring to business activities that continuously improve all functions and involve all employees from the CEO to the assembly line workers. Kaizen also applies to processes, such as purchasing and logistics, that cross organizational boundaries into the supply chain. Kaizen aims to eliminate waste and redundancies. Kaizen may also be referred to as zero investment improvement (ZII) due to its utilization of existing resources.

The Toyota Production System (TPS) is an integrated socio-technical system, developed by Toyota, that comprises its management philosophy and practices. The TPS is a management system that organizes manufacturing and logistics for the automobile manufacturer, including interaction with suppliers and customers. The system is a major precursor of the more generic "lean manufacturing". Taiichi Ohno and Eiji Toyoda, Japanese industrial engineers, developed the system between 1948 and 1975.

Target costing is an approach to determine a product's life-cycle cost which should be sufficient to develop specified functionality and quality, while ensuring its desired profit. It involves setting a target cost by subtracting a desired profit margin from a competitive market price. A target cost is the maximum amount of cost that can be incurred on a product, however, the firm can still earn the required profit margin from that product at a particular selling price. Target costing decomposes the target cost from product level to component level. Through this decomposition, target costing spreads the competitive pressure faced by the company to product's designers and suppliers. Target costing consists of cost planning in the design phase of production as well as cost control throughout the resulting product life cycle. The cardinal rule of target costing is to never exceed the target cost. However, the focus of target costing is not to minimize costs, but to achieve a desired level of cost reduction determined by the target costing process.

<span class="mw-page-title-main">Operations management</span> In business operations, controlling the process of production of goods

Operations management is concerned with designing and controlling the production of goods and services, ensuring that businesses are efficient in using resources to meet customer requirements.

Lean thinking is a management framework made up of a philosophy, practices and principles which aim to help practitioners improve efficiency and the quality of work. Lean thinking encourages whole organisation participation. The goal is to organise human activities to deliver more benefits to society and value to individuals while eliminating waste.

Muda is a Japanese word meaning "futility", "uselessness", or "wastefulness", and is a key concept in lean process thinking such as in the Toyota Production System (TPS), denoting one of three types of deviation from optimal allocation of resources. The other types are known by the Japanese terms mura ("unevenness") and muri ("overload"). Waste in this context refers to the wasting of time or resources rather than wasteful by-products and should not be confused with waste reduction.

<span class="mw-page-title-main">Value-stream mapping</span> Lean-management method for analyzing the current state and designing a future state

Value-stream mapping, also known as material- and information-flow mapping, is a lean-management method for analyzing the current state and designing a future state for the series of events that take a product or service from the beginning of the specific process until it reaches the customer. A value stream map is a visual tool that displays all critical steps in a specific process and easily quantifies the time and volume taken at each stage. Value stream maps show the flow of both materials and information as they progress through the process.

Cellular manufacturing is a process of manufacturing which is a subsection of just-in-time manufacturing and lean manufacturing encompassing group technology. The goal of cellular manufacturing is to move as quickly as possible, make a wide variety of similar products, while making as little waste as possible. Cellular manufacturing involves the use of multiple "cells" in an assembly line fashion. Each of these cells is composed of one or multiple different machines which accomplish a certain task. The product moves from one cell to the next, each station completing part of the manufacturing process. Often the cells are arranged in a "U-shape" design because this allows for the overseer to move less and have the ability to more readily watch over the entire process. One of the biggest advantages of cellular manufacturing is the amount of flexibility that it has. Since most of the machines are automatic, simple changes can be made very rapidly. This allows for a variety of scaling for a product, minor changes to the overall design, and in extreme cases, entirely changing the overall design. These changes, although tedious, can be accomplished extremely quickly and precisely.

<span class="mw-page-title-main">Production leveling</span> Technique for reducing the mura (unevenness) which in turn reduces muda (waste)

Production leveling, also known as production smoothing or – by its Japanese original term – heijunka (平準化), is a technique for reducing the mura (unevenness) which in turn reduces muda (waste). It was vital to the development of production efficiency in the Toyota Production System and lean manufacturing. The goal is to produce intermediate goods at a constant rate so that further processing may also be carried out at a constant and predictable rate.

Muri is a Japanese word meaning "unreasonableness; impossible; beyond one's power; too difficult; by force; perforce; forcibly; compulsorily; excessiveness; immoderation", and is a key concept in the Toyota Production System (TPS) as one of the three types of waste.

A lean laboratory is one which is focused on processes, procedures, and infrastructure that deliver results in the most efficient way in terms of cost, speed, or both. Lean laboratory is a management and organization process derived from the concept of lean manufacturing and the Toyota Production System (TPS). The goal of a lean laboratory is to reduce resource usage and costs while improving productivity, staff morale, and laboratory-driven outcomes.

A glossary of terms relating to project management and consulting.

Demand flow technology (DFT) is a strategy for defining and deploying business processes in a flow, driven in response to customer demand. DFT is based on a set of applied mathematical tools that are used to connect processes in a flow and link it to daily changes in demand. DFT represents a scientific approach to flow manufacturing for discrete production. It is built on principles of demand pull where customer demand is the central signal to guide factory and office activity in the daily operation. DFT is intended to provide an alternative to schedule-push manufacturing which primarily uses a sales plan and forecast to determine a production schedule.

Lean IT is the extension of lean manufacturing and lean services principles to the development and management of information technology (IT) products and services. Its central concern, applied in the context of IT, is the elimination of waste, where waste is work that adds no value to a product or service.

Lean services is the application of lean manufacturing production methods in the service industry. Lean services have among others been applied to US health care providers and the UK HMRC.

<span class="mw-page-title-main">Industrial engineering</span> Branch of engineering which deals with the optimization of complex processes or systems

Industrial engineering is an engineering profession that is concerned with the optimization of complex processes, systems, or organizations by developing, improving and implementing integrated systems of people, money, knowledge, information and equipment. Industrial engineering is central to manufacturing operations.

Lean product development (LPD) is an approach to product development that specializes in minimizing waste. Other core principles include putting people over the product and creating new values in services and physical products. This method of product development has been adopted by companies such as Toyota

<span class="mw-page-title-main">Production planning</span> Step in the production cycle

Production planning is the planning of production and manufacturing modules in a company or industry. It utilizes the resource allocation of activities of employees, materials and production capacity, in order to serve different customers.

References

  1. Liker, Jeffrey K. (2004). The Toyota way: 14 management principles from the world's greatest manufacturer. New York: McGraw-Hill. ISBN   0-07-139231-9. OCLC   54005437.
  2. Graban, Mark; Ducharme, Colin; Ruddick, Todd. "Takt Time" (PDF).
  3. 1 2 3 Haghsheno, Shervin; Binninger, Marco; Dlouhy, Janosch; Sterlike, Simon (20 July 2016). History and Theoretical Foundations of Takt Planning and Takt Control (PDF). 24th Annual Conference of the International Group for Lean Construction. Boston. pp. 53–62. Retrieved 22 November 2020.
  4. "Takt" . Retrieved 2020-11-15.
  5. Womack, James P. (2007). The machine that changed the world: the story of lean production--Toyota's secret weapon in the global car wars that is revolutionizing world industry. Jones, Daniel T., Roos, Daniel. (1st trade pbk. ed.). New York: Free Press. ISBN   978-0-7432-9979-4. OCLC   85814817.
  6. Womack, James P. (2003). Lean thinking: banish waste and create wealth in your corporation. Jones, Daniel T. (1st Free Press ed., rev. and updated ed.). New York: Free Press. ISBN   0-7432-4927-5. OCLC   51031471.
  7. Hopp, Wallace J. (2011). Factory physics. Spearman, Mark L. (Third ed.). Long Grove, Illinois. ISBN   978-1-57766-739-1. OCLC   718450337.{{cite book}}: CS1 maint: location missing publisher (link)
  8. Koskela, L. (1992). Application of the New Production Philosophy to Construction (Technical report). Stanford University (published September 1992).
  9. Abbasi, Saman; Taghizade, Katayoon; Noorzai, Esmatullah (2020-12-01). "BIM-Based Combination of Takt Time and Discrete Event Simulation for Implementing Just in Time in Construction Scheduling under Constraints". Journal of Construction Engineering and Management. 146 (12): 04020143. doi:10.1061/(ASCE)CO.1943-7862.0001940. ISSN   1943-7862. S2CID   225165221.
  10. Sacks, R.; Treckmann, M.; Rozenfeld, O. (2009-12-01). "Visualization of Work Flow to Support Lean Construction". Journal of Construction Engineering and Management. 135 (12): 1307–1315. doi:10.1061/(ASCE)CO.1943-7862.0000102. ISSN   0733-9364.
  11. Yamín, René A.; Harmelink, David J. (2001-10-01). "Comparison of Linear Scheduling Model (LSM) and Critical Path Method (CPM)". Journal of Construction Engineering and Management. 127 (5): 374–381. doi:10.1061/(ASCE)0733-9364(2001)127:5(374). ISSN   0733-9364.
  12. Brioso, Xavier; Murguia, Danny; Urbina, Alonso (19 June 2017). Teaching Takt-Time, Flowline, and Point-to-point Precedence Relations: A Peruvian Case Study (PDF). Creative Construction Conference. Procedia Engineering. Creative Construction Conference 2017, CCC 2017, 19-22 June 2017, Primosten, Croatia. Vol. 196. Primosten, Croatia. pp. 666–673. doi: 10.1016/j.proeng.2017.08.056 . Retrieved 22 November 2020.
  13. Kenley, Russell. (2010). Location-based management for construction: planning, scheduling and control. Seppänen, Olli. London: Spon Press. ISBN   978-0-415-37050-9. OCLC   317118189.
  14. Tommelein, Iris D. (9 July 2017). Collaborative Takt Time Planning of Non-Repetitive Work (PDF). 25th Annual Conference of the International Group for Lean Construction. Heraklion, Greece. pp. 745–752. doi: 10.24928/2017/0271 . Retrieved 22 November 2020.
  15. Linnik, Meeli; Berghede, Klas (31 August 2013). An Experiment in Takt Time Planning Applied to Non-Repetitive Work (PDF). 21th Annual Conference of the International Group for Lean Construction. Fortaleza, Brazil. pp. 609–618. Retrieved 22 November 2020.
  16. Jabbari, Arman; Tommelein, Iris D.; Kaminsky, Philip M. (2020-10-01). "Workload leveling based on workspace zoning for takt planning". Automation in Construction . 118: 103223. doi: 10.1016/j.autcon.2020.103223 . ISSN   0926-5805. S2CID   224887268.
  17. Laraia, Anthony C.; Patricia E. Moody; Robert W. Hall (1999). The Kaizen Blitz: accelerating breakthroughs in productivity and performance. New York: John Wiley and Sons. ISBN   978-0-471-24648-0.[ page needed ]

Further reading