Total project control

Last updated

Total project control (TPC) is a project management method that emphasizes continuous tracking and optimization of return on investment (ROI). It was developed by Stephen Devaux. It builds upon earlier techniques such as earned value management, critical path method, and program evaluation and review technique, but uses these to track and index projected project profitability as well as the more traditional cost and schedule. [1] In this way it aims to manage projects as profit and investment centers, rather than cost centers.

Contents

Introduced with TPC are a variety of project management metrics and techniques, among them critical path drag, [2] [3] the value breakdown structure (VBS), Devaux's Index of Project Performance (the DIPP), [4] Doubled Resource Estimated Duration (DRED), and Cost of Leveling with Unresolved Bottlenecks (CLUB).

The Project Management Institute's monthly magazine PM Network reviewed the TPC methodology as making "solid points about what can be done to maximize ROI during project execution." [5] In a 2015 PMI white paper on organizational project management, Joseph Sopko wrote about the DIPP: "The effect of project delivery of any new capability on program NPV should always be quantified and communicated to the project team by the project sponsor... DIPP is the ratio of EMV divided by ETC. As either the EMV is improved or the ETC is reduced, the effect on project value contribution is quantified." [6] He also wrote: "Tools and practices for managing projects and programs as investments have been defined... For example, critical path drag is a concept for evaluating how much any activity along the critical path can be shortened to optimize the project duration." [7]

Later enhancements

Since the total project control approach was introduced in the first edition of Devaux's 1999 book by that title, others have extended both the theory and the practice. In 2013, Tomoichi Sato of JGC Corporation in Yokohama suggested an "extended DIPP" based on risk-based project value. He wrote: "The key concept of Simple DIPP is to obtain the ratio of expected income to cost ETC, neglecting sunk costs in the past. Using RPV instead of expected income, the author proposes a criterion "extended DIPP". This represents the ratio of remaining RPV to cost ETC. If there are project alternatives which are mutually independent, the one with the highest extended DIPP should be chosen... To maximize the project portfolio value of a company, extended DIPP can be used as criteria for prioritisation." [8]

Additionally, critical path drag calculation has been coded into project scheduling software, both in Spider Project and as an add-on product to Microsoft Project from Boyle Project Consulting, PLLC. [9]

Sources

    • Devaux, Stephen A. (1999). Total Project Control: A Manager's Guide to Integrated Project Planning, Measuring, and Tracking (pp. xxiv–xxvi) New York, NY: Wiley. ISBN   0-471-32859-6.
  1. William Duncan and Stephen Devaux "Scheduling Is a Drag" Projects@Work on-line magazine
  2. Stephen A. Devaux "The Drag Efficient: The Missing Quantification of Time on the Critical Path" Archived 2013-03-13 at the Wayback Machine Defense AT&L magazine of the Defense Acquisition University.
  3. Stephen A. Devaux ["When the DIPP Dips: A P&L Index for Project Decisions"] Project Management Journal, Vol XXIII, No. 3, Sep 1992, pp. 45 - 49.
  4. Gary Heerkens "Eye on the Prize: The Business of Managing Projects" PM Network, June 2015, p. 72.
  5. Joseph Sopko "Organizational Project Management: Why Build and Improve?" PMI white paper, 2015, p. 20.
  6. Sopko "Organizational Project Management: Why Build and Improve?" PMI white paper, 2015, p. 19.
  7. Dr. Tomoichi Sato "Risk-based Project Value Analysis – Contributed Value and Procurement Cost"
  8. Thomas Boyle "Drag Calculation in BPC Logic Filter for Microsoft Project"

Further reading

Related Research Articles

Earned value management (EVM), earned value project management, or earned value performance management (EVPM) is a project management technique for measuring project performance and progress in an objective manner.

Project management is the process of leading the work of a team to achieve all project goals within the given constraints. This information is usually described in project documentation, created at the beginning of the development process. The primary constraints are scope, time, and budget. The secondary challenge is to optimize the allocation of necessary inputs and apply them to meet pre-defined objectives.

<span class="mw-page-title-main">Work breakdown structure</span> A deliverable-orientated breakdown of a project into smaller components.

A work-breakdown structure (WBS) in project management and systems engineering is a deliverable-oriented breakdown of a project into smaller components. A work breakdown structure is a key project deliverable that organizes the team's work into manageable sections. The Project Management Body of Knowledge defines the work-breakdown structure as a "hierarchical decomposition of the total scope of work to be carried out by the project team to accomplish the project objectives and create the required deliverables."

Critical chain project management (CCPM) is a method of planning and managing projects that emphasizes the resources required to execute project tasks. It was developed by Eliyahu M. Goldratt. It differs from more traditional methods that derive from critical path and PERT algorithms, which emphasize task order and rigid scheduling. A critical chain project network strives to keep resources levelled, and requires that they be flexible in start times.

<span class="mw-page-title-main">Project Management Body of Knowledge</span>

The Project Management Body of Knowledge (PMBOK) is a set of standard terminology and guidelines for project management. The body of knowledge evolves over time and is presented in A Guide to the Project Management Body of Knowledge, a book whose seventh edition was released in 2021. This document results from work overseen by the Project Management Institute (PMI), which offers the CAPM and PMP certifications.

<span class="mw-page-title-main">Critical path method</span> Method of scheduling activities

The critical path method (CPM), or critical path analysis (CPA), is an algorithm for scheduling a set of project activities. It is commonly used in conjunction with the program evaluation and review technique (PERT). A critical path is determined by identifying the longest stretch of dependent activities and measuring the time required to complete them from start to finish.

Project management software (PMS) has the capacity to help plan, organize, and manage resource tools and develop resource estimates. Depending on the sophistication of the software, it can manage estimation and planning, scheduling, cost control and budget management, resource allocation, collaboration software, communication, decision-making, quality management, time management and documentation or administration systems. Numerous PC and browser-based project management software and contract management software products and services are available.

In project management, a schedule is a listing of a project's milestones, activities, and deliverables. Usually dependencies and resources are defined for each task, then start and finish dates are estimated from the resource allocation, budget, task duration, and scheduled events. A schedule is commonly used in the project planning and project portfolio management parts of project management. Elements on a schedule may be closely related to the work breakdown structure (WBS) terminal elements, the Statement of work, or a Contract Data Requirements List.

In project management, float or slack is the amount of time that a task in a project network can be delayed without causing a delay to:

Lean construction is a combination of operational research and practical development in design and construction with an adoption of lean manufacturing principles and practices to the end-to-end design and construction process. Unlike manufacturing, construction is a project-based production process. Lean Construction is concerned with the alignment and holistic pursuit of concurrent and continuous improvements in all dimensions of the built and natural environment: design, construction, activation, maintenance, salvaging, and recycling. This approach tries to manage and improve construction processes with minimum cost and maximum value by considering customer needs.

A glossary of terms relating to project management and consulting.

Return on investment (ROI) or return on costs (ROC) is a ratio between net income and investment. A high ROI means the investment's gains compare favourably to its cost. As a performance measure, ROI is used to evaluate the efficiency of an investment or to compare the efficiencies of several different investments. In economic terms, it is one way of relating profits to capital invested.

Benefits Realization Management (BRM) is one of the many ways of managing how time and resources are invested into making desirable changes.

The following outline is provided as an overview of and topical guide to project management:

<span class="mw-page-title-main">Critical path drag</span> Project management metric

Critical path drag is a project management metric developed by Stephen Devaux as part of the Total Project Control (TPC) approach to schedule analysis and compression in the critical path method of scheduling. Critical path drag is the amount of time that an activity or constraint on the critical path is adding to the project duration. Alternatively, it is the maximum amount of time that one can shorten the activity before it is no longer on the critical path or before its duration becomes zero.

Drag cost is a project management metric developed by Stephen Devaux as part of the Total Project Control (TPC) approach to project schedule and cost analysis. It is the amount by which a project’s expected return on investment (ROI) is reduced due to the critical path drag of a specific critical path activity Task or other specific schedule factor such as a schedule lag or other delaying constraint.

A value breakdown structure (VBS) is a project management technique introduced by Stephen Devaux as part of the total project control (TPC) approach to project and program value analysis.

<span class="mw-page-title-main">Spider Project</span> Project management software

Spider Project is a project management software, developed by a Russian company, Spider Project Team.

Devaux's Index of Project Performance is a project management performance metric formulated by Stephen Devaux as part of the total project control (TPC) approach to project and program value analysis. It is an index that integrates the three variables of a project into a single value-based index where: