Canada Line

Last updated

Canada Line
Translinkcanada.svg
Canadaline.svg
Canada Line Train 201807.jpg
Canada Line train pulling into Marine Drive station
Overview
Owner TransLink, InTransitBC
Locale Metro Vancouver, British Columbia
Termini
Stations16 (1 under construction)
Website thecanadaline.com
Service
Type Rapid transit
System SkyTrain
Operator(s) ProTrans BC
Rolling stock Rotem EMU, 2 cars per trainset
Daily ridership94,000 (2022) [1]
History
OpenedAugust 17, 2009;14 years ago (2009-08-17)
Technical
Line length19.2 km (11.9 mi)
Number of tracks2
Track gauge 1,435 mm (4 ft 8+12 in) standard gauge
Electrification 750 V DC third rail
Operating speed80 km/h (50 mph)
Route map
Canada Line Canada Line highlighted in teal
Canada Line.svg
BSicon HUBa.svg
BSicon BOOT.svg
SeaBus
to Lonsdale Quay
Translinkseabus.svg
BSicon HUB.svg
BSicon KINTaq.svg
BSicon CONTfq.svg
West Coast Express
to Mission
Translinkwce.svg
BSicon PORTALf.svg
BSicon HUBaq.svg
BSicon KINTa-L denim.svg
BSicon HUBrf.svg
BSicon tKINTa-R cerulean.svg
Waterfront
Translinkbusrapid.svg Translinkexpo.svg
BSicon tSTRl denim.svg
BSicon mtKRZto cerulean+denim.svg
BSicon tCONTfq denim.svg
Expo
Line
BSicon tBHF cerulean.svg
Vancouver City Centre
BSicon tBHF cerulean.svg
Yaletown–Roundhouse
BSicon tbKRZW cerulean.svg
BSicon tBHF cerulean.svg
Olympic Village
BSicon tINT cerulean.svg
Broadway–City Hall
Translinkbus.svg
BSicon tBHF cerulean.svg
King Edward
BSicon etpBHF cerulean.svg
33rd Avenue (future)
BSicon tINT cerulean.svg
Oakridge–41st Avenue
Translinkbusrapid.svg
BSicon tBHF cerulean.svg
Langara–49th Avenue
BSicon etpBHF cerulean.svg
57th Avenue (future)
BSicon htBHFe@g cerulean.svg
Marine Drive
BSicon hbKRZW cerulean.svg
North Arm Bridge
over Fraser River
BSicon hSTR cerulean+GRZq.svg
Vancouver Zone 1
Richmond Zone 2
BSicon lhSTRa@fq.svg
BSicon uKDSTaq.svg
BSicon STR cerulean.svg
BSicon uhABZr+r.svg
Operations and
Maintenance Centre
BSicon dRP4q.svg
BSicon hSKRZ-G4hlru cerulean.svg
BSicon dRP4q.svg
BSicon hBHF cerulean.svg
Bridgeport
BSicon hSHI2+l cerulean.svg
BSicon hSHI2+r cerulean.svg
BSicon hSTR cerulean.svg
BSicon ehpBHF cerulean.svg
BSicon hSTR cerulean.svg
BSicon hBHF cerulean.svg
Aberdeen
BSicon hSTR cerulean.svg
BSicon hBHF cerulean.svg
Lansdowne
BSicon hSTR cerulean.svg
BSicon hKBHFe cerulean.svg
Richmond–Brighouse
BSicon hbKRZW cerulean.svg
Middle Arm Bridge
over Fraser River
BSicon dRP4q.svg
BSicon hSKRZ-G4hlru cerulean.svg
BSicon dRP4q.svg
BSicon lhSTRe@g.svg
BSicon BHF cerulean.svg
Templeton
BSicon BHF cerulean.svg
Sea Island Centre
BSicon ehpBHFa cerulean.svg
YVR Terminal 3 (future)
BSicon hKINTe cerulean.svg
YVR–Airport
BSicon FLUG.svg

Wheelchair symbol.svg All stations are accessible

The Canada Line is a rapid transit line in Greater Vancouver, British Columbia, Canada, that is part of the SkyTrain system. The line is owned by TransLink and InTransitBC and is operated by ProTrans BC. Coloured turquoise on route maps, it operates as an airport rail link between Vancouver, Richmond, and the Vancouver International Airport (YVR). The line comprises 16 stations and 19.2 kilometres (11.9 mi) of track; the main line runs from Vancouver to Richmond while a 4-kilometre (2.5 mi) spur line from Bridgeport station connects to the airport. [2] It opened on August 17, 2009, ahead of the 2010 Winter Olympics. [3]

Contents

The Canada Line was anticipated to have 100,000 boardings per day in 2013 and 142,000 boardings per day by 2021, but it has consistently exceeded early targets. [4] Ridership has grown steadily since opening day, with average ridership of 83,000 per day in September 2009, [5] 105,000 per day in March 2010, [6] and over 136,000 passengers per weekday in June 2011. [7] During the 17 days of the 2010 Winter Olympics, the line carried an average of 228,190 passengers per day. [8]

Governance of the project was through Canada Line Rapid Transit Inc. (CLCO), formerly RAV Project Management Ltd. (RAVCO), a reflection of the original "Richmond–Airport–Vancouver" name). [9] The line was built by SNC-Lavalin, and InTransitBC is under contract with TransLink to manage the line for its first 35 years, until 2044. The Canada Line is operationally independent from British Columbia Rapid Transit Company, which operates SkyTrain's Expo and Millennium lines [10] but is considered a part of the SkyTrain network. Like the other two SkyTrain lines in Metro Vancouver, it is also light metro rapid transit, using fully automated trains on grade-separated guideways. [11] However, the trains are powered by conventional motors with third rail electrical pickup rather than the linear induction system used on the other SkyTrain lines.

Route

Canada Line bridge over the Fraser River North Arm Bridge shot from SkyTrain 3622.JPG
Canada Line bridge over the Fraser River

The Canada Line begins in Downtown Vancouver at Waterfront station (0.0 km [0 mi]) in a cut-and-cover subway tunnel beneath Granville Street. It quickly goes into twin-bored tunnels, heading southwest beneath Granville Street, then curving southeast to follow Davie Street through Yaletown. The tunnels then dive deeper to pass below False Creek before rising back up to Olympic Village station (2.7 km [1.7 mi]). There, the line transitions back to a cut-and-cover tunnel (which is noted by the tunnel changing from a circular to a square shape), heading south under Cambie Street. This section has some portions where the two sets of tracks are stacked vertically. The line emerges from the ground just south of 64th Avenue, climbing to an elevated guideway. [12]

The line continues elevated across the North Arm Bridge over the North Arm of the Fraser River, leaving Vancouver and entering Richmond. Just beyond Bridgeport station (11.1 km [6.9 mi]) at a flying junction, the line splits, with the Richmond branch heading south on elevated tracks along No. 3 Road and terminating at Richmond–Brighouse station (14.5 km [9.0 mi]). The airport branch turns west and crosses the Middle Arm Bridge over the Middle Arm of the Fraser River, connecting to stations on Sea Island and terminating at YVR–Airport station (15.0 km [9.3 mi]). Portions of the airport branch are at grade in order to accommodate a future elevated taxiway for aircraft over the line. Both branches narrow to a single track as they approach their respective terminus stations. Just before Bridgeport station is the Operations and Maintenance Centre (OMC) facility, which houses Canada Line trains that are not in use.

Stations

Station construction was designed as a two-stage process. Sixteen original stations opened at the same time as the line did. Three additional stations are planned, and may be built in the future. The stations are listed below.

Each Canada Line station is slightly different in appearance, designed to blend in with the surrounding neighbourhood. For example, Langara–49th Avenue station is designed to fit into the area's low-density residential neighbourhood.[ citation needed ]

The five busiest stations have platforms 50 metres (160 ft) long, while the rest of the stations have 40-metre (130 ft) platforms that can be easily extended to 50 metres. The termini at YVR–Airport and Richmond–Brighouse stations are single-tracked, whereas the Waterfront station terminus is double-tracked. The double-tracking is necessary to accommodate the three-minute headways between trains on the Waterfront–Bridgeport portion of the line. King Edward station is the only station with a stacked configuration, and Broadway–City Hall station is the only station with a double-height ceiling over the platforms. Vancouver City Centre station is linked to Pacific Centre mall and Vancouver Centre Mall, in addition to having street level access. All direct transfers to the Expo and Millennium Lines must be made at Waterfront station; there is no direct connection from Vancouver City Centre station to Granville station. However, it is possible to transfer between those two stations via a short walk through Pacific Centre or Vancouver Centre Mall.

Stations were configured to allow for the future installation of fare gates, and received fare gates in 2013 as part of full implementation throughout all SkyTrain stations. Every station has an up escalator and an elevator, but only the three terminal stations have down escalators. [13]

Until late 2019, six stations (Vancouver City Centre, Olympic Village, Broadway–City Hall, Marine Drive, Templeton, and YVR–Airport) were equipped with self-service flight check-in kiosks which allowed customers to check into their flights at Vancouver International Airport while at these stations. [14] [15]

StationCityConnectionsLocation
Waterfront Vancouver Granville, between Pender and Hastings
Vancouver City Centre Granville at Georgia
Yaletown–Roundhouse Davie near Mainland
Olympic Village Cambie at West 2nd Ave
Broadway–City Hall Translinkbus.svg 99 B-Line Cambie at West Broadway
King Edward Cambie at King Edward
Oakridge–41st Avenue Translinkbusrapid.svg R4 RapidBus Cambie at West 41st; next to Oakridge Centre
Langara–49th Avenue Cambie at West 49th; near Langara College
Marine Drive Cambie at Marine
Bridgeport Richmond Major transit exchange for suburban buses; branches split; adjacent to River Rock Casino Resort
Richmond–Brighouse branch
Aberdeen RichmondNo. 3 at Cambie; adjacent to Aberdeen Centre
Lansdowne No. 3 at Lansdowne; adjacent to Lansdowne Centre
Richmond–Brighouse No. 3 at Saba; adjacent to Richmond Centre
YVR–Airport branch
Templeton RichmondNorth of Grant McConachie Way; east of Templeton
Sea Island Centre Near Air Canada service centre
YVR–Airport BSicon FLUG.svg YVR Attached by walkways to YVR Main Terminal

Additional stations

Provisions have been made to allow for the addition of the following infill stations in the future:

Transit connections

Canada Line (sky blue) as part of the Metro Vancouver transit system in 2016 Vancouver Transit Network Map (svg).svg
Canada Line (sky blue) as part of the Metro Vancouver transit system in 2016

Many transit services connect with the Canada Line and form an important part of the service. With the opening of the line, most bus routes in Richmond, and connecting services from White Rock, Tsawwassen, and Ladner, doubled their service frequency. Waterfront station provides connections to the R5 Hastings St, Expo Line, West Coast Express, and SeaBus. Broadway–City Hall provides a connection to the 99 B-Line service.

There are currently only two routes serving Vancouver International Airport: the N10 NightBus, running parallel to the Canada Line along Granville Street, and route 412, running between Airport South and Bridgeport station. [28] [29] Riders on these bus routes are not subject to the YVR AddFare. [30] The Airport Station exchange was downgraded to a regular bus stop on September 7, 2009, a few weeks after the opening of the line. Bus routes that used this loop were discontinued (as in the case of the 424 and the 98 B-Line), short-turned (as in the case of the 100, renamed 100 Marpole Loop), or redirected to Bridgeport station (as in the case of the 620, C90, and C92). [31]

Work began in May 2021 to extend the Millennium Line from VCC–Clark station west along Broadway to the new Arbutus station, allowing for a transfer to the Canada Line at Broadway–City Hall station. [32] As indicated in material presented by the City of Vancouver at public meetings in early 2006, this station was designed with such a future extension in mind. A "knock-out" panel was installed in the concourse that would facilitate construction of a connection between the station and a Broadway-corridor SkyTrain extension.

The Canada Line uses the same fare system as the rest of the transit system managed by TransLink, with two exceptions: [33]

The Canada Line operates on a "Fare Paid Zone" system. Passengers are required by law to possess a valid fare when they are in Fare Paid Zones. Fare Paid Zones are clearly marked, and fares can be bought from Compass Vending Machines at all stations. Fare inspections are mostly conducted by the South Coast British Columbia Transportation Authority Police Service. Passengers who fail to pay the fare or do not have a valid fare may be fined $173 and/or removed from the station or train. [34]

Canada Line attendants are the customer service staff for the Canada Line. They are easily identifiable by their green uniforms. They provide customer service, troubleshoot certain problems with the trains, observe and report safety issues, and check fares.

Technology

A train parked at the Canada Line Operations and Maintenance Centre near Bridgeport station Canada Line Train.jpg
A train parked at the Canada Line Operations and Maintenance Centre near Bridgeport station

The Canada Line uses a fleet of trains built by Rotem, a division of Hyundai Motor Group. The trains are powered by conventional electric motors, rather than the linear induction motors used by the Expo and Millennium Line's Bombardier ART trains. Canada Line trains are operated by the same SelTrac automated train control system used in the rest of the SkyTrain network.

The selection of Rotem was largely a consequence of the request for proposals process for the public-private partnership, whose terms did not allow Bombardier to consider efficiencies in combining operations or rolling-stock orders for the new line with those for the existing system. [35] This placed all bidders on a level playing field, albeit at the cost of not necessarily picking the most efficient choice for long-term operation. The RFP also required that the system have a capacity of 15,000 passengers per hour in each direction (leaving the choice of technology and platform length to the proponent) and a maximum travel time between the airport and downtown Vancouver of 24 minutes. [36]

The fleet consists of 20 fully automated two-car articulated trains, for a total of 40 cars. [37] The capacity of the trains is estimated at 334 people per pair of cars (comfortably) or 400 people at crush load. The trains have a top speed of 80 kilometres per hour (50 mph) in normal operation and 90 kilometres per hour (56 mph) in catch-up mode. [38] Each married pair of gangway-connected cars is 41 metres (134 ft 6 in) long and 3 metres (9 ft 10 in) wide, and longer and wider than the Bombardier ART fleet used on the Expo and Millennium lines. [39] Each train has LED electronic displays on the exterior to indicate the terminus station and on the interior to display the next station and the terminus station, a useful feature considering the line has two branches.

In 2018, twelve additional trainsets were ordered by Translink from Hyundai Rotem at a cost of $88 million to increase capacity on the line. [40] The sole-source contract allowed for commonality between the two train models, and reduced the number of specialized tools and parts required. [41] These were delivered in 2019 and 2020. [42] [43]

Canada Line Hyundai Rotem specifications

Name

During the planning and public consultation stages, the line was known as the "Richmond-Airport-Vancouver Line", or RAV for short. The name "Canada Line" was adopted in 2005 to coincide with the beginning of construction. [48] Some early documents also refer to it as the "Olympic Line", [49] in recognition of the 2010 Winter Olympics, continuing the practice by which the Expo and Millennium lines were named after significant events occurring at the time of construction. This name was adopted for the demonstration modern streetcar service that operated along the Downtown Historic Railway for a two-month period centred on the Olympics. [50]

Timeline

Project funding

The Canada Line was built as a public-private partnership. Funding was provided by both government agencies and a private partner, the proponent. As of March 2009, the entire project was expected to cost $2.054 billion. The premier of BC stated that the project was on budget and ahead of schedule. [67] When approved in December 2004, the cost was given as $1.76 billion. [68]

The public contributions to the budget come from the following sources:

These sums are all in 2006 dollars, except for the government of Canada's contribution, which will be paid out when constructed, and is estimated to be equivalent of $419 million 2003 dollars. [70]

The private partner was expected to contribute $200 million, and be responsible for any construction cost overruns. [71] As of November 7, 2009, InTransitBC has invested $750 million. InTransitBC is a joint venture company owned by SNC-Lavalin, the Investment Management Corporation of BC (bcIMC), and the Caisse de dépôt et placement du Québec. [72] [73]

The BC government had committed $370 million, but when the bid came in over budget, it contributed an extra $65 million. TransLink also put in extra money by committing money from the sale of the Sexsmith Park and Ride in Richmond and from the introduction of a special fare in the Airport Zone. [68]

In November 2004, bid costs were reduced by postponing the construction of a walkway between Waterfront station and the cruise ship terminal, removing Westminster station, and moving Richmond Centre station and the end of the line several hundred metres north. TransLink would further pay for the cost of reinstallation of the trolley wires along Cambie. As a way to further reduce the best and final offer, RAVCO no longer required that the proponent provide for 59 ticket vending machines and 38 ticket validating machines or for a police unit to operate on the RAV line. RAVCO also shifted responsibility for moving trolley wires from SNC-Lavalin to TransLink. [74] Costs were also decreased due to decisions to single-track sections on the Richmond and airport branches. The Richmond branch was single-tracked from Ackroyd Road onward in large part due to Richmond's city council pressuring for the visual profile of the overhead line to be reduced for esthetic reasons.

On July 11, 2006, a decision was made to relocate Broadway station half a block north at a cost of $3 million to allow for better integration of the station with Broadway and a new development in the area. The funding was provided as follows: one third from the City of Vancouver, one third from TransLink, and one third from surplus funding available to CLCO. [75]

In February 2007, TransLink approved the addition of a pedestrian and bicycle path to the Canada Line Bridge and agreed not to postpone the construction of a station at 2nd Avenue (Olympic Village station), but instead build it to be ready when the line opens. The $10 million cost of the bridge bike path was paid for by TransLink and not considered part of the cost of the Canada Line. The Olympic Village station cost an additional $29 million. [76]

RAVCO was set up by the agencies funding the transit line to oversee project design, procurement, construction, and implementation. This TransLink subsidiary, later renamed Canada Line Rapid Transit Inc (CLCO), made distributions to the builder as work progressed.

The table below lists the year-by-year contributions (in millions of dollars) made by various governments on a year-by-year basis up to December 31, 2008. [77] [78] Contributions by TransLink are total disbursements minus contributions from the City of Vancouver, the government of British Columbia, and the government of Canada. Calculations show that TransLink has contributed $271 million to date. It has committed an additional $52 million in its 2009 budget.

YearVancouverBC governmentCanadian governmentTotal disbursements through TransLinkAirport disbursements
2008$7.1$59.6$93.4$163.2$46.8
2007$14.9$58.4$167.4$336.7$94.6
2006$6.9$17.2$125.6$322.5$108.4
2005$1.1$117.1$108.9$209.4$15.7

The private sector will operate the line for 35 years in return for a share of its operating revenue.

In early 2006, TransLink decided not to install turnstiles at Canada Line stations, but stations would be designed to accommodate controlled access to allow TransLink to install them for less cost if it wished to do so in the future. [79] On April 9, 2009, TransLink, the provincial government, and the government of Canada announced joint funding of $100 million to introduce turnstiles at all 49 SkyTrain stations. [80] While a large portion of this funding will be used on the Expo and Millennium Lines, a portion will be used on the Canada Line stations. The federal government is contributing $30 million and the province is adding $40 million toward fare gates, or controlled access gates.

Construction

Construction began in October 2005 and was completed in August 2009.

At initial completion, the line comprised the following construction elements:

Segment typeLength
Tunnel9,080 m
(29,790 ft)
Elevated7,349 m
(24,111 ft)
Bridge614 m
(2,014 ft)
At-grade1,385 m
(4,544 ft)

In addition to the 18.4 kilometres (11.4 mi) of track above, there are about 500 metres (1,600 ft) of track in the OMC.

Controversies

Opponents have claimed that the approval process was undemocratic and dishonest. In 2004, critics said that the projected ridership figures were grossly inflated; [81] ridership projections were exceeded in 2010 and subsequent years. [6] [7] Opponents also argued that the official claim that the project had nothing to do with Vancouver's bid to host the 2010 Winter Olympics was not credible. [82]

Public-private partnerships

Opponents of the RAV line's public-private partnership (P3) believe it was politically motivated and that it will cost more money because of the private involvement. However, the private involvement allowed for construction costs to be known and fixed up front. After raising its contribution to $435 million, the BC minister of transport and premier reaffirmed that this was the final contribution and that any cost overruns would be the responsibility of the proponent. [83] The Canadian Union of Public Employees opposed the use of a P3 to design, build, and operate the Canada Line. The P3 process did not allow precise plans to be developed with public consultation, but limited discussion to certain abstract parameters, while leaving actual design details to the private partner.

Ridership projections

Before the building of the line, TransLink had projected that it would require a 100,000 passenger/day average to reach the "break even point". They also projected that it would take about three years for capacity to reach this point and that TransLink would be responsible for the loss. However, the Canada Line reached its projected ridership goal in late 2010, three years early. [84] In 2017, TransLink CEO Kevin Desmond suggested that the Canada Line was underbuilt for its ridership, especially because more people moved into transit-oriented developments along the line following its completion. [85] In 2019, former Vancouver city councillor Gord Price noted that the desire to have the line open in time for the 2010 Winter Olympics, as well as not exceeding the budget, led to cautious decision making. [86] [87] In 2018, 20 additional trainsets were purchased to increase capacity on the line by 35 percent. [88] [43]

Alignment and grade separation

Vancouver

Although the latest proposal for rapid transit did not include an option for rapid transit down the Arbutus corridor along the abandoned CPR right of way, Vancouver council reopened debate on this issue. Given that the rail right of way is currently zoned for transit use with space available for transit lines, running the line down the Arbutus corridor may have been more cost-effective than tunnelling under Cambie. The planners and RAVCO, however, countered that the Arbutus corridor does not have the major concentration of transit destinations and origins that exist along the Cambie Street corridor, such as Vancouver City Hall, Vancouver General Hospital, Oakridge Centre, and Langara College, which are necessary to provide the ridership required for this project to be successful. Also the Arbutus corridor is longer than the Cambie corridor and would cause longer travel times. The Cambie corridor further had greater potential for future ridership growth. [89]

The Project Definition Report further specified that any service had to be able to travel from Waterfront station in downtown Vancouver to the airport in 25 minutes or less. At-grade transit, either along Cambie or the Arbutus corridor, was ruled out as a result. The reason or origin for this exact requirement was not specified, although travel times were considered an important factor in attracting new riders and in retaining existing riders, who were now required to make an extra transfer relative to the existing bus service.

All partner contributions were made upon the specifications set in the Project Definition Report. Any "significant change" would allow each partner to reconsider its respective contribution. As the Arbutus corridor proposal could not meet the specifications, this could put participation of funding partners in jeopardy.

Residents along Cambie Boulevard created the Cambie Boulevard Heritage Society in 1994, which opposed any alteration to a wide green centre median that is currently a grassy area with various species of trees, including cherry trees donated by the City of Yokohama on occasion of the 1967 Canadian Centennial. The residents had already been mobilized in 1989 in response to the possibility of elevated rail along Cambie Boulevard. [90] In effect the residents were opposed to surface, trench, or elevated rail along much of Cambie Street. Even cut-and-cover construction raised concerns over construction impacts and temporary traffic diversions. Cost and ridership risks were also concerns to property tax–paying residents. Advertisements asked residents to join "to prevent Vancouver's worst traffic nightmare and from burdening ourselves and our children with unnecessary tax risks for years to come". The society suggested that the line instead be constructed along Arbutus, where its impact and cost would be minimal. [91] Despite the society's concerns, one of the final two proposals for the Canada Line in 2004 involved a trench in the centre of Cambie Street from 49th to 64th Avenues.

On June 18, 2004, the TransLink Board voted 6–6 to oppose sending the project to the "best and final offer" stage. Opponents of the project favoured a proposal to build a line along the Cambie corridor involving a minimal amount of tunnelling, at a saving of about $300 million over the previously fully grade-separated proposal. The province responded to the suggestion by withdrawing funding until after the 2010 Olympics; Minister of Transport Kevin Falcon said that such a change of scope could no longer be accommodated in the time left before 2010. Mayors and councillors sitting on the TransLink Board, however, could not come to an agreement on this alternate plan of action. [92] The impasse created a stir in the business community, which joined together and called for the province to take over control of the project. "The Coalition FOR a Lower Mainland Rapid Transit Solution" in a newspaper ad called on the premier to "please rescue our rapid transit". The Vancouver Board of Trade, the Council of Tourism Associations, and Tourism Vancouver led the call on the premier. [93] While the board ultimately voted to proceed, the incident had lasting repercussions for TransLink.

Richmond

When the results of the bidding process indicated that an elevated option in Richmond was the winning bid, Richmond council engaged in some last-minute opposition to the RAV line and refused to give RAVCO the green light.

Objections to the elevated line included its visual impact and the impact and cost of any extensions into Richmond. The line would have varied impact on businesses along No. 3 Road.


In November 2004, a survey of 11,750 people was conducted by RAVCO to determine if people in Richmond supported an elevated or at-grade service in Richmond. Of the respondents, 58 percent favoured an elevated option. [94]

Closure and dismantling of 98 B-Line busway on No. 3 Road at Capstan Way to make way for Canada Line, April 2006 98laneclosed.jpg
Closure and dismantling of 98 B-Line busway on No. 3 Road at Capstan Way to make way for Canada Line, April 2006

Even after the survey, however, another option was brought forward. On November 22, 2004, Richmond council considered whether an elevated guideway along No. 3 Road in Richmond was appropriate. If an at-grade service was not feasible, council had instructed staff to look into the possibility of relocating the elevated guideway further west, along Minoru Boulevard. In response, residents along Minoru Boulevard presented a petition containing 666 signatures opposing the Minoru alignment. In the petition they "indicated that if Translink and RAVCO were not prepared to construct an at-grade system on No. 3 Road, then the project should be abandoned in favour of bus service on No. 3 Road." [95]

When further surveys and public consultation conducted by city staff in December indicated that residents did not support the realignment along Minoru Boulevard, council was left to either turn down the development or support the best and final offer. They chose to go ahead with the project. As a final compromise, part of the elevated track in Richmond was single-tracked to reduce visual impact.

Impact on local businesses

One side of the street was cut off from traffic and parking was affected. Cambie Street cut, Dec 21, 2007.jpg
One side of the street was cut off from traffic and parking was affected.
The "business is open" logo Businessopen.png
The "business is open" logo

For the entire consultation process, it was assumed that any underground construction along the Cambie corridor would be by bored tunnel.[ citation needed ] It was only upon the publication of the winning bid that it became apparent that the portion of the line from 64th to 2nd Avenues would be constructed using cut-and-cover construction. This raised concern over the disruption of local business on Cambie Street. Businesses in Yaletown and No. 3 Road in Richmond would also be affected by the construction. Although construction in the downtown was mostly by bored tunnel, businesses in Yaletown were caught off guard when it turned out that Yaletown-Roundhouse station would be north of Pacific Boulevard on Davie Street, rather than south of Pacific Boulevard. [96] InTransitBC responded by launching an advertising campaign promoting local business on the line. [97] [98] Despite these efforts, businesses on Cambie Street experienced significant loss of business. After numerous failed appeals to the provincial government for compensation, store operators unsuccessfully sued for compensation. However, since the completion of the Canada Line, the line has been linked to rising property values along Cambie Street and in Richmond. [99]

Impact on expansion of other transit options

It had been pointed out that construction of the Canada Line would do little to improve transit or alleviate congestion on the Broadway corridor to UBC, which serves more than 100,000 weekday trips on bus services, with many trips continuing to University of British Columbia. In addition, the Evergreen Extension rapid transit project was delayed (until 2016). As TransLink is solely responsible for funding bus operations, any shortage of funding may translate into cuts in bus service.

Hiring practices

There were several labour disputes related to wages and unionization between employees and contractors working on the construction of the Canada Line. To excavate the final 2 kilometres (1.2 mi) of the tunnel underneath the downtown core a crew of 36 Latin American workers were brought to Canada from Costa Rica, Ecuador and Colombia in April 2006. The employer, a joint partnership of SELI Canada and SNC (Pacific) engaged workers to assemble the tunnel boring machine (TBM) and begin excavations. Pay stubs and testimony evidence from the workers indicated that they were paid US$1,000 monthly in exchange for 65-hour work weeks (less than $4 per hour). The Latin Americans, all on temporary work permits, joined the Construction and Specialized Workers Unions Local 1611 and, in a majority vote, won union certification on June 23, 2006. This was the first time in Canadian history that a group of temporary foreign workers in the construction industry had successfully exercised their right to form a union. Before the union had a chance to begin collective bargaining, workers' wages were increased to $14.21 per hour and hours were reduced to 40 hours per week with overtime concessions as required by BC labour law. The union was not consulted, and the unilateral pay raise led to an unfair labour practice complaint from the CSWU 1611. The BC Labour Relations Board (BCLRB) sided with the employer's (SELI–SNCP) explanation that there had been a mistake in calculations of wages during the months before the workers voted to join the union. The employer stalled negotiations for a collective agreement until they were ordered back to the bargaining table in August 2006 by the BCLRB. [100]

In September, bargaining broke down. On September 21, 2006, CSWU 1611 workers threatened a strike vote to bring the employer back to the bargaining table. [101]

After almost two years of litigation, the BC Labour Relations Board ruled against the union's claims of unfair labour practices. [102]

In a separate complaint, the union claimed discrimination against the workers based on their country of origin. Even with the newly imposed wage of $14.21 per hour, the Latin Americans were earning half the wages of European (Italian, Spanish and Portuguese) workers with whom they worked alongside and performed the same underground TBM operations.

On November 9, 2007, the BC Human Rights Tribunal ruled that the Latin American workers had been intimidated to sign a petition against being represented by their union. [103] [104] The tribunal found that the workers were intimidated and coerced to sign a petition in the fear of possibly losing future job prospects with their employer. The petition would have prevented them from being represented by a union before the tribunal and would also have created evidence that could have jeopardized the ongoing investigation by the tribunal over perceived discrimination. [105]

Upon completion of the tunnels in March 2008, the workers were laid-off and returned to their home countries. [106] Only five of the workers were re-hired by SELI after their arrival back to their home countries.

On December 3, 2008, the BC Human Rights Tribunal found in favour of the discrimination complaint. [107] The decision prohibits employers from discrimination based on a workers' country of origin. Migrant workers must not suffer wage discrimination based on low wage labour markets in their countries of origin. The Latin Americans workers were awarded the difference in wages with an additional $10,000 each in punitive damages. The total award averaged approximately $50,000 per worker or $2.5 million.

SELI Canada appealed the decision to the BC Supreme Court. In December 2012, SELI agreed to a settlement offer by the union. The Latin American workers voted unanimously to accept a settlement. The settlement provided payments worth 50% of the original award. [108]

Notes

    Related Research Articles

    <span class="mw-page-title-main">SkyTrain (Vancouver)</span> Automated rapid transit system in Metro Vancouver, Canada

    SkyTrain is the medium-capacity rapid transit system serving the Metro Vancouver region in British Columbia, Canada. SkyTrain has 79.6 km (49.5 mi) of track and uses fully automated trains on grade-separated tracks running on underground and elevated guideways, allowing SkyTrain to hold consistently high on-time reliability. In 2023, the system had a ridership of 141,339,300, or about 446,400 per weekday as of the fourth quarter of 2023.

    <span class="mw-page-title-main">Richmond, British Columbia</span> City in British Columbia, Canada

    Richmond is a city in the coastal Lower Mainland region of British Columbia, Canada. Mainly a suburban city, it occupies almost the entirety of Lulu Island, between the two estuarine distributaries of the Fraser River. Encompassing the adjacent Sea Island and several other smaller islands and uninhabited islets to its north and south, the suburb neighbours Vancouver and Burnaby on the Burrard Peninsula to the north, New Westminster and Annacis Island to the east, Delta to the south, and the Strait of Georgia to the west.

    <span class="mw-page-title-main">Vancouver International Airport</span> Airport in Richmond, British Columbia, Canada

    Vancouver International Airport is an international airport located on Sea Island in Richmond, British Columbia, serving the city of Vancouver and the Lower Mainland region. It is located 12 km (7.5 mi) from Downtown Vancouver. YVR is the second busiest airport in Canada by passenger traffic, behind Toronto Pearson International Airport in Ontario. As a trans-Pacific hub, the airport has more direct flights to China than any other airport in North America or Europe. It is a hub for Air Canada and WestJet. Vancouver International Airport is one of eight Canadian airports that have US Border Pre-clearance facilities. It is also one of the few major international airports to have a terminal for scheduled float planes.

    <span class="mw-page-title-main">SeaBus</span> Passenger-only ferry service in Metro Vancouver, Canada

    The SeaBus is a passenger-only ferry service in Metro Vancouver, British Columbia, Canada. It crosses Burrard Inlet to connect the cities of Vancouver and North Vancouver. Owned by TransLink and operated by the Coast Mountain Bus Company, the SeaBus forms an important part of the region's integrated public transportation system. In 2023, the SeaBus had a ridership of 5,127,000, or about 14,300 per weekday as of the fourth quarter of 2023.

    <span class="mw-page-title-main">TransLink (British Columbia)</span> Transportation authority in Metro Vancouver, Canada

    TransLink, formally the South Coast British Columbia Transportation Authority and previously the Greater Vancouver Transportation Authority, is the statutory authority responsible for the regional transportation network of Metro Vancouver in British Columbia, Canada, including public transport, major roads and bridges. Its main operating facilities are located in the city of New Westminster.

    <span class="mw-page-title-main">West Coast Express</span> Canadian commuter railway

    The West Coast Express is a commuter railway serving the Lower Mainland region of British Columbia, Canada. It is owned and operated by the region's transit authority, TransLink. Opened in 1995, it provides a link between Metro Vancouver and the Fraser Valley Regional District and is the only commuter railway in Western Canada. In 2023, the system had a ridership of 1,304,400, or about 5,600 per weekday as of the fourth quarter of 2023.

    <span class="mw-page-title-main">Millennium Line</span> Rapid transit line in Metro Vancouver, Canada

    The Millennium Line is the second line of the SkyTrain rapid transit system in the Metro Vancouver region of British Columbia, Canada. The line is owned and operated by BC Rapid Transit Company, a subsidiary of TransLink, and links the cities of Vancouver, Burnaby, Coquitlam and Port Moody. The line was opened in 2002 and was named in recognition of the new millennium.

    <span class="mw-page-title-main">Cambie Street</span> Street in Vancouver, Canada

    Cambie Street is a street in Vancouver, British Columbia, Canada. It is named for Henry John Cambie, chief surveyor of the Canadian Pacific Railway's western division.

    <span class="mw-page-title-main">98 B-Line</span> Former express bus service in Metro Vancouver, Canada

    The 98 B-Line was a bus rapid transit line in Metro Vancouver, British Columbia, Canada, that began service in September 2000. It linked Richmond to Downtown Vancouver, with a connection to Vancouver International Airport. It travelled mainly along Granville Street in Vancouver and a dedicated bus lane on No. 3 Road in Richmond. It was operated by Coast Mountain Bus Company and was funded by TransLink. The route was 16 kilometres (9.9 mi) long. The line carried over 18,000 passengers daily. It was discontinued in September 2009, shortly after the opening of the Canada Line, which replaced it.

    <span class="mw-page-title-main">99 B-Line</span> Express bus service in Metro Vancouver, Canada

    The 99 B-Line is an express bus line with bus rapid transit elements in Metro Vancouver, British Columbia, Canada. It travels along Broadway, a major east–west thoroughfare, and connects the University of British Columbia (UBC) to Commercial–Broadway station on the SkyTrain system. It is operated by Coast Mountain Bus Company and funded by TransLink.

    <span class="mw-page-title-main">Transportation in Vancouver</span>

    Transportation in Vancouver, British Columbia, has many of the features of modern cities worldwide. Unlike many large metropolises, Vancouver has no freeways into or through the downtown area. A proposed freeway through the downtown was rejected in the 1960s by a coalition of citizens, community leaders and planners. This event "signalled the emergence of a new concept of the urban landscape" and has been a consistent element of the city's planning ever since.

    <span class="mw-page-title-main">Aberdeen station (SkyTrain)</span> Metro Vancouver SkyTrain station

    Aberdeen is an elevated station on the Canada Line of Metro Vancouver's SkyTrain rapid transit system. It is located in Richmond, British Columbia, Canada. It is named after the adjacent Aberdeen Square and Aberdeen Centre, the largest of Richmond's Asian-themed malls.

    <span class="mw-page-title-main">Bridgeport station (SkyTrain)</span> Metro Vancouver SkyTrain station

    Bridgeport is an elevated station on the Canada Line of Metro Vancouver's SkyTrain rapid transit system. It is located in Richmond, British Columbia, Canada, south of Vancouver. The Canada Line branches outbound at this station, with one branch heading westward to YVR–Airport station at the Vancouver International Airport and the other heading south to Richmond–Brighouse station in the commercial centre of Richmond.

    <span class="mw-page-title-main">YVR–Airport station</span> Metro Vancouver SkyTrain station

    YVR–Airport is an elevated station on the Canada Line of Metro Vancouver's SkyTrain rapid transit system. The station is located at Vancouver International Airport's main terminal in Richmond, British Columbia, and is one of the outbound termini of the Canada Line, the other being Richmond–Brighouse.

    <span class="mw-page-title-main">Sea Island Centre station</span> Metro Vancouver SkyTrain station

    Sea Island Centre is an at-grade station on the Canada Line of Metro Vancouver's SkyTrain rapid transit system. The station is located on Sea Island in Richmond, British Columbia.

    <span class="mw-page-title-main">Templeton station</span> Metro Vancouver SkyTrain station

    Templeton is an at-grade station on the Canada Line of Metro Vancouver's SkyTrain rapid transit system. The station is located in Richmond, British Columbia, south of the city of Vancouver, and is built on the Grauer Lands on the eastern portion of Sea Island.

    <span class="mw-page-title-main">King Edward station</span> Metro Vancouver SkyTrain station

    King Edward is an underground station on the Canada Line of Metro Vancouver's SkyTrain rapid transit system. The station is located at the intersection of Cambie Street and King Edward Avenue in Vancouver, British Columbia, Canada, and serves the neighbourhoods of Riley Park–Little Mountain and South Cambie. The station is within walking distance of BC Children's Hospital, Nat Bailey Stadium, and Queen Elizabeth Park.

    The SkyTrain rapid transit system in Greater Vancouver, Canada, was conceived as a legacy project of Expo 86 and was finished in time to showcase the fair's theme: "Transportation and Communication: World in Motion – World in Touch". Construction was funded by the provincial and federal governments. Vancouver had plans as early as the 1950s to build a monorail system, with modernist architect Wells Coates pencilled in to design it; that project was abandoned. The lack of a rapid transit system was said to be the cause of traffic problems in the 1970s, and the municipal government could not fund the construction of such a system. During the same period, Urban Transportation Development Corporation, then an Ontario crown corporation, was developing a new rapid transit technology known as an "Intermediate Capacity Transit System". In 1980, the need for rapid transit was great, and Ontario needed buyers for its new technology. "Advanced Rapid Transit" was selected to be built in Vancouver to showcase the Ontario project at Expo 86.

    <span class="mw-page-title-main">Capstan station</span> Metro Vancouver SkyTrain station

    Capstan is an elevated station under construction on the Canada Line of Metro Vancouver's SkyTrain rapid transit system. It will be located at the intersection of No. 3 Road and McMyn Way, one block north of Capstan Way in Richmond, British Columbia, Canada, and will be the first infill station on the Canada Line when completed. It is expected to open in 2024.

    References

    1. "Transit Service Performance Review" (PDF). TransLink. Retrieved June 23, 2023.
    2. "Frequently Asked Questions". Canada Line/TransLink. Archived from the original on August 31, 2009. Retrieved June 17, 2009.
    3. "Canada Line linking Vancouver and Richmond to open Aug. 17". Vancouver Sun. Archived from the original on August 7, 2009. Retrieved August 4, 2009.
    4. Canada Line Archived August 30, 2006, at the Wayback Machine
    5. 1 2 "Cubic, TransLink Report Record Use of New Fare Collection System for Canada Line" (Press release). September 30, 2009. Retrieved October 10, 2009.
    6. 1 2 "Are you prepared to travel during the 2010 Winter Games in Vancouver?". VANOC Communications. January 20, 2010. Archived from the original on July 7, 2011.
    7. 1 2 "TransLink reports transit ridership heading for a new record". Translink. August 22, 2011. Archived from the original on October 20, 2011. Retrieved December 28, 2009.
    8. 1 2 "TransLink carried 26 million passengers during Games". Vancouver Sun. Retrieved March 23, 2010.[ permanent dead link ]
    9. "TransLink Operating Companies". TransLink. Archived from the original on August 22, 2008. Retrieved December 2, 2008.
    10. "Frequently Asked Questions, Canada Line". Rapid Transit Office, City of Vancouver. Retrieved December 2, 2008.
    11. "Overview and Route Map". InTransitBC. Archived from the original on December 16, 2006. Retrieved December 17, 2006.
    12. Hasiuk, Mark. "Disabled advocate down on Canada Line station design". The Vancouver Courier. Archived from the original on January 31, 2009. Retrieved December 3, 2008.
    13. "Other Locations". yvr.ca. Archived from the original on December 5, 2019. Retrieved March 1, 2021.
    14. "Other Locations". yvr.ca. Archived from the original on April 29, 2016. Retrieved March 1, 2021.
    15. 1 2 3 Chan, Kenneth (August 19, 2015). "Four stations could be added to SkyTrain Canada Line". DailyHive. Archived from the original on March 20, 2018. Retrieved August 4, 2017.
    16. "Developer Onni to pay for new Canada Line station in Vancouver". CBC News. March 30, 2016. Retrieved August 4, 2017.
    17. "Challenges derail arrival of new Canada Line station on Cambie Street in South Vancouver". Georgia Straight Vancouver's News & Entertainment Weekly. June 26, 2017. Retrieved December 18, 2017.
    18. "Sun Tech City development may be shelved". Richmond Review. April 3, 2009. Retrieved August 3, 2009.
    19. "Richmond cash starts design work on new Canada Line station". Vancouver Sun. November 16, 2017. Retrieved December 18, 2017.
    20. Chan, Kenneth (May 3, 2019). "Richmond successfully raises $32 million to build Canada Line's new Capstan Station". Daily Hive. Archived from the original on May 4, 2019. Retrieved July 9, 2019.
    21. Chan, Kenneth (October 8, 2019). "Construction on Canada Line's new Capstan Station could begin in a year". Daily Hive. Archived from the original on October 9, 2019. Retrieved November 10, 2019.
    22. Saltman, Jennifer (December 3, 2019). "New Capstan Station in Richmond running behind schedule". Vancouver Sun. Retrieved December 15, 2019.
    23. "Capstan Station".
    24. "Construction on SkyTrain's new Capstan Station to begin in August". July 30, 2021.
    25. Chan, Kenneth (September 2, 2021). "Construction officially begins on Canada Line's new $52 million Capstan Station". DailyHive. Retrieved November 8, 2022.
    26. "YVR: Your Airport 2027" (PDF). 2007. Retrieved February 22, 2022.
    27. "NightBus". www.translink.ca. Retrieved April 1, 2024.
    28. "412 Bridgeport Station/Sea Island South". www.translink.ca. Retrieved April 1, 2024.
    29. "Questions and answers about the YVR AddFare". The Buzzer blog. January 9, 2010. Retrieved April 1, 2024.
    30. "Connecting Transit Services". TransLink. Archived from the original on August 9, 2009. Retrieved July 29, 2009.
    31. "Broadway Subway Project reaches major construction phase". BC Gov News | Transportation and Infrastructure. May 13, 2021. Retrieved April 27, 2022.
    32. "Canada Line YVR AddFAre". translink.ca. TransLink. Archived from the original on March 24, 2018. Retrieved January 1, 2018.
    33. "Fare Infraction FAQs". TransLink. Archived from the original on January 17, 2018. Retrieved January 16, 2018.
    34. 1 2 "Canada Line launched as partners unveil vehicle" (Press release). November 25, 2005. Archived from the original on September 18, 2009. Retrieved December 17, 2006.
    35. Best and Final Offer Stage Report & Recommendations Archived March 4, 2009, at the Wayback Machine (PDF)
    36. "New Canada Line trains double capacity of current SkyTrain cars". CBC News. December 15, 2007. Retrieved April 26, 2023.
    37. "Canada Line Fact Sheet The Canada Line Vehicle" (PDF). canadaline.ca (TransLink). December 14, 2007. Archived from the original (PDF) on March 26, 2009. Retrieved June 16, 2015.
    38. "Canada Line Fact Sheet The Canada Line Vehicle" (PDF). canadaline.ca (TransLink). December 14, 2007. Archived from the original (PDF) on March 26, 2009. Retrieved June 16, 2015.
    39. Chan, Kenneth (February 24, 2018). "TransLink accelerates full order of 80 new SkyTrain cars by 2020". Daily Hive - Urbanized. Retrieved April 26, 2023.
    40. "NOI-Customized Train Cars". service.ariba.com. Retrieved February 13, 2018.
    41. Saltman, Jennifer (July 22, 2019). "New Canada Line cars headed for Vancouver". Vancouver Sun. Retrieved April 26, 2023.
    42. 1 2 Little, Simon (January 21, 2020). "Metro Vancouver's Canada Line adds first 4 of dozen new trains, boosting service". Global News. Retrieved April 26, 2023.
    43. 1 2 3 4 5 6 7 8 9 "Canada Line Fact Sheet The Canada Line Vehicle" (PDF). canadaline.ca (TransLink). December 14, 2007. p. 2. Archived from the original (PDF) on March 26, 2009. Retrieved June 16, 2015.
    44. "RFP No. CAP 27-10 New Orange and Red Line Vehicles" (PDF). Hyundai Rotem. Archived from the original (PDF) on August 21, 2021.
    45. "Railway Systems-Project Record View". Hyundai-Rotem. Hyundai Rotem. Retrieved January 8, 2017.
    46. "Urban Rail Signalling Projects". Thales Group. Archived from the original on May 12, 2012. Retrieved October 9, 2011.
    47. "Canada Line Launcher As Partners Unveil Vehicle". Transport Canada. September 25, 2005. Archived from the original on September 18, 2009. Retrieved June 10, 2009. The Honourable David L. Emerson... gathered to unveil the Canada Line name and the vehicle design for the Richmond-Airport-Vancouver Rapid Transit Project.
    48. Chiu, Viven; Rault, Patrick (January 2003). "The Richmond-Airport-Vancouver Rapid link Project: The RAVP/Olympic line" (PDF). Study Marigni. Archived from the original (PDF) on July 14, 2011. Retrieved June 10, 2009. With the Whistler-Vancouver Olympic bid, this issue has been put under pressure, and the name of this line is temporarily chosen accordingly, in this study. Like recommended by previous studies, this study considers a line opening in phase with the 2010 Olympic game, it must be clear that the rail link need is studied independently of the Olympic bid, and its realization should not be tied to the Olympic bid success.... The Olympic line is considered as a regional link more than a local service.
    49. "Olympic Line". The City of Vancouver. Archived from the original on April 8, 2010. Retrieved June 7, 2010.
    50. Summary of Intermediate Capacity Transit System Studies, 10-year Development Plan 1995–2006, BC Transit, Stephen Gardner and Glen Leicester, March 1995, page 11
    51. A Long-Range Transportation Plan for Greater Vancouver, Transport 2021 Report, September 1993, 65 pages, A joint Project of the GVRD and the Province of British Columbia
    52. Summary of Intermediate Capacity Transit System Studies, 10-year Development Plan 1995–2006, preface
    53. 98BLine_BRT_Evaluation Study, September 1993, page 6, IBI group, Transport Canada
    54. Skytrain line to Airport Proposed, Vancouver Sun, June 25, 1998, by Scott Simpson
    55. Richmond-downtown link on transit wish list, Vancouver Sun, Amy O'Brian, December 5, 2002
    56. Bill C-49, Budget Implementation Act, 2001, Part 6,37th parliament, 1st session.
    57. Frances Bula, Secret plan to explain federal RAV funds, Vancouver Sun, October 4, 2004
    58. RAV line resurrected as B.C. offers to cover cost overruns, Vancouver Sun, Nicholas Read, Ayesha Bhatty, and Jim Beatty, June 11, 2004
    59. Hop Aboard, RAV proponents urge, Gordon Campbell, Vancouver Sun, June 17, 2004
    60. The Road Less Travelled, TransLink's Improbable Journey from 1999 to 2008, Trevor Wales, 2008, page 43, says it occurred in October 2004
    61. "Canada Line Delivers a Smooth Ride". The Globe and Mail . Canada. December 28, 2009. Retrieved December 28, 2009.
    62. "Vancouver drivers urged to forgo cars when viaducts close this week". Vancouver Sun. February 2, 2010. Archived from the original on October 27, 2017. Retrieved October 4, 2018.
    63. "Twitter / TransLink BC: Record day on Canada Line". Twitter.com. February 12, 2010. Retrieved May 19, 2012.
    64. "The Buzzer blog " A huge weekend for transit, plus Canada Line increases trains today". Buzzer.translink.ca. February 15, 2010. Retrieved May 19, 2012.
    65. "Rise in transit use called Olympic legacy". BC Local News. Archived from the original on July 7, 2011. Retrieved February 11, 2011.
    66. Press release, Office of the Premier, March 27, 2009
    67. 1 2 Richmond keeps RAV on track, Joel Baglole and Jonathan Fowlie, with files from Jim Beatty and Frances Bula. The Vancouver Sun, November 30, 2004, pg. B.2
    68. TransLink Annual Report 2008, page 64
    69. Canada Line Final Project Report: Competitive Selection Phase, Final Assessment of Value for Money Archived October 25, 2007, at the Wayback Machine , July 29, 2005, figure 3, page 15
    70. "About Us". InTransitBC. Archived from the original on February 3, 2007. Retrieved December 17, 2006.
    71. About Archived May 31, 2009, at the Wayback Machine , InTransitBC
    72. Canada Line Info Bulletin No. 14 Archived July 6, 2011, at the Wayback Machine March 3, 2006. Information on the nature of the public/private partnership.
    73. RAV line builder shaves ,2m off price: 'I think we have a fully financed project': McCallum, Jonathan Fowlie, The Vancouver Sun, November 29, 2004. pg. A.1.
    74. Vancouver council minutes, July 11, 2006
    75. RAV bridge to take pedestrians, Frank Luba, The Province, February 17, 2005. pg. A.21
    76. TransLink annual report 2006, 2007 and 2008
    77. Airport authority Annual Report 2006, 2007, 2008
    78. Canada Line Fact Sheet No. January 22, 24, 2006
    79. No turnstiles for SkyTrains until 2012, August 14, 2009, British Columbia, CBC News
    80. "Come clean on RAV line, MacPhail tells Campbell][https://thetyee.ca/Views/2005/11/28/RAVReward/ Larry Campbell's RAV Reward". BC NDP. Archived from the original on February 28, 2004. Retrieved February 13, 2018.
    81. "Privatization: Cabinet leak proves Liberals will do anything for a P3". Canadiandemocraticmovement.ca. October 4, 2004. Archived from the original on April 15, 2012. Retrieved May 19, 2012.
    82. Campbell's 'kaputski' on RAV line financing tops the list of keepers so far, Vaughn Palmer, The Vancouver Sun, December 3, 2004. p. A3
    83. Sinoski, Kelly (June 2, 2010). "Canada Line races toward capacity". Global News. Retrieved April 26, 2023. The line has been recording an average of 94,000 trips per day – just shy of its capacity of 100,000 riders, a number TransLink had not expected to reach until 2013.
    84. "Canada Line is definitely under-built, says TransLink CEO". dailyhive.com. Archived from the original on December 31, 2017. Retrieved February 22, 2021.
    85. Kretzel, Lasia (August 16, 2019). "Canada Line changed direction of transit in Metro Vancouver: former councillor". CityNews Vancouver. Retrieved April 26, 2023.
    86. Molko, David (February 14, 2020). "'Confidence' the biggest transportation legacy of Vancouver Olympics, experts say". British Columbia. Retrieved April 26, 2023.
    87. Fong, Jim (January 21, 2020). "Canada Line increasing its commuter capacity by 35% by spring 2020". CTV News British Columbia. Retrieved April 26, 2023.
    88. Community Consultation Discussion Guide and Feedback Form, March 2003, Translink and RAVP, p.9
    89. Cambie Boulevard trees leave activist smiling, Sandra Thomas, The Vancouver Courier, November 2, 2007
    90. Help Save Cambie Boulevard, and so much more, Vancouver Courier, February 22, 2004, p. 21, paid ad
    91. Vancouver Sun, June 18, 19, 22
    92. Business Coalition wants Victoria to take over RAV line, Brian Morton, Vancouver Sun, June 23, 2004
    93. Councillors say they could forego RAV, Jonathan Fowlie, Vancouver Sun, November 25, 2004
    94. Minutes, Richmond Council General Purpose Committee Meeting, November 22, 2004
    95. Yaletown RAV stop stirs it up, William Boei, The Vancouver Sun, December 7, 2005. pg. B.2
    96. "Business is open, are you?" (PDF) (Press release). InTransitBC. March 20, 2006. Archived from the original (PDF) on February 17, 2007. Retrieved March 9, 2007.
    97. Krangle, Karenn (March 4, 2003). "Translink seeks public input on rapid Richmond route; [Final Edition]". Vancouver Sun. p. B.2.
    98. Stuek, Wendy (January 10, 2011). "Canada Line workers to take strike vote". Globe and Mail. Canada. Archived from the original on February 3, 2013. Retrieved January 20, 2011.
    99. Mark Brown, BCLRB vice-chair, July 30, 2006 "The Employer cannot simply refuse to meet to bargain collectively based on its view of the Union's applications. The Employer cannot set preconditions to the commencement of collective bargaining. In doing so, the Employer has violated Sections 11 and Section 47 (the requirement to bargain in good faith and begin bargaining within 10 days of certification) of the BC Labour Code." Brown ordered the Employer to meet with the union within 10 days.
    100. "Labour strife plagues Canada Line construction". CKNW News Talk 980. Archived from the original on September 27, 2007. Retrieved October 19, 2006.
    101. http://www.lrb.bc.ca/decisions/B040$2008.pdf [ dead link ]
    102. "BC transit line builders coerced workers, tribunal rules". Canadian Broadcasting Corporation. Retrieved December 23, 2007.
    103. "Official document on the ruling" (PDF). BC Human Rights Tribunal. Archived from the original (PDF) on September 23, 2015. Retrieved December 23, 2007.
    104. "Canada Line companies intimidated foreign workers: Tribunal". Global Television Network . Archived from the original on December 4, 2007. Retrieved December 23, 2007.
    105. Union calls SLCP-SELI Joint Venture's Canada Line foreign-worker lay-offs "a set up" – Journal of Commerce Archived May 2, 2013, at the Wayback Machine . Journalofcommerce.com. Retrieved July 26, 2013.
    106. "C.S.W.U. Local 1611 v. SELI Canada and others (No. 8), 2008 BCHRT 436" (PDF). Archived from the original (PDF) on September 23, 2015. Retrieved July 25, 2013.
    107. "Canada Line Temporary Foreign Workers paid B.C. Human Rights Tribunal settlement". YouTube. Journal of Commerce. June 28, 2013. Retrieved July 26, 2013.
    Template:Attached KML/Canada Line
    KML is from Wikidata