Dual Contracts

Last updated

The original "H" system that predated the contracts NYCS H System 1904-1918.jpg
The original "H" system that predated the contracts

The Dual Contracts, also known as the Dual Subway System, were contracts for the construction and/or rehabilitation and operation of rapid transit lines in the City of New York. The contracts were signed on March 19, 1913, by the Interborough Rapid Transit Company and the Brooklyn Rapid Transit Company. As part of the Dual Contracts, the IRT and BRT would build or upgrade several subway lines in New York City, then operate them for 49 years.

Contents

Most of the lines of the present-day New York City Subway were built or reconstructed under these contracts. The contracts were "dual" in that they were signed between the City and two separate private companies. Both the IRT and BRT (later Brooklyn–Manhattan Transit Corporation, or BMT) worked together to make the construction of the Dual Contracts possible.

Background

In the late 19th century and for most of the 20th century, New York was host to millions of immigrants each year. Many of the immigrants crowded into tenements and other apartment buildings in the inner city. This resulted in overpopulation of the buildings, and congestion of city streets. Manhattan's population had risen from 516,000 people in 1850 to 2.33 million people in 1910. [1] The population of the entire city had grown from 1.17 million people in 1860 to 3.44 million in 1900 and 4.77 million in 1910. [2] Living in Manhattan was becoming a hazard due to the higher probability of crime and overcrowding, and for the most part, the first subway line only served areas that were already developed. [3] The first subway lines to the outer boroughs were planned during the early 20th century. [4] Dispersion resulted in the expansion and development of the boroughs.

In 1906, Charles Evans Hughes was elected as the governor of New York, and the next year, he created the New York State Public Service Commission (PSC). The PSC was responsible for new rapid transit lines in New York City. Although the PSC had created ambitious plans for the expansion of the city's subway system, they only had $200 million on hand. [5] In 1911, George McAneny was appointed leader of the Transit Committee of the New York City Board of Estimate, which oversaw the subway expansion plans. [6]

Some opposed the Dual Contracts as they thought that the company owners and city officials were just looking for another way to produce personal revenue. [6] Reformists like Hughes and McAneny would not have it any other way than to see the expansion of the city and the subway. They wanted to see the inner city become less populated and spread the people to the outer boroughs of the city. They planned to expand the city and disperse the people by building subway lines which would hopefully result in new homes being built near the subway lines and the areas surrounding. This would lower population densities in the city and also made as a good reason to help prove the subway expansion as necessary.

Crowding

Before the Contracts, there was crowding in many of the forms of transportation in the city. The following is a list of annual ridership for each mode of transportation between June 30, 1910, and June 30, 1911:

In total, 924,058,050 passengers were carried that year over these six modes of transport. [7]

The New York Times noted that streetcar ridership had increased more than 25 times over between 1860, where there were 50.83 million annual riders, and 1910, where there were 1.531 billion annual riders. [2]

Planned effects

It was expected that, within five years of completion:

When completed, the rapid transit facilities of the City will have been more than trebled. During the year ended June 30, 1911, shortly after which the construction of the new system was begun, the existing rapid transit lines carried 798,281,850 passengers. The new Dual System will have a capacity of upwards of [3 billion], although it is not expected that such capacity will be demanded immediately upon the completion of the system. The combined trackage of the existing lines (including 7.1 miles of the Hudson and Manhattan Railroad) amounts to 303 miles of single track. To this will be added by the new lines of the Dual System 334 miles of single track, making a new system with 637 miles of single track. What this will mean to the City may be appreciated by considering how the existing lines will be amplified by the new additions and extensions. The Hudson and Manhattan road, however, is not to be a part of the Dual System. [7]

This system expansion was expected to be as big as, if not bigger, than the proposed Second System expansion put forth by the Independent Subway System in 1929 and 1939.

Contracts

1910 plan for IRT expansion 1910 IRT plan.png
1910 plan for IRT expansion

Contracts 1 and 2

Built before the Dual Contracts, the first regularly operated subway in New York City was built by the city and leased to the Interborough Rapid Transit Company (IRT) for operation under city Contracts 1 and 2. Until 1918, when the new "H" system that is still operated – with separate East Side and West Side lines – was placed in service, it consisted of a single trunk line below 96th Street with several northern branches. The system had four tracks between Brooklyn Bridge–City Hall and 96th Street, allowing for local and express service on that portion.

Contract 1 was for the original 28 stations of the subway system that opened on October 27, 1904, from City Hall to 145th Street, as well as for stations opened before 1908 on several IRT extensions. The original system as included in Contract 1 was completed on January 14, 1907, when trains started running across the Harlem Ship Canal on the Broadway Bridge to 225th Street, [8] and the Contract 2 portion was opened to Atlantic Avenue on May 1, 1908. [9]

Contracts 3 and 4

The Dual Contracts were signed on March 19, 1913. The contracts bound Interborough Rapid Transit Company and the Brooklyn Rapid Transit Company (BRT; later BMT) to build and operate lines for 49 years. [10] Contract 3 was signed between the City and the IRT. Contract 4 was signed between the City and the Municipal Railway Company, a subsidiary of the BRT, formed especially for the purpose of contracting with the city for construction of the lines.

Under the terms of Contracts 3 and 4, the city would build new subway and elevated lines, and rehabilitate and expand certain existing elevated lines, and lease them to the private companies for operation. The expansions would total 618 miles (995 km) of new trackage across both systems; by comparison, the existing systems had 296 miles (476 km) of tracks. The city's third major rapid transit company, the Hudson & Manhattan Railroad (now PATH), was excluded from the contracts. [2] The projected $337 million cost would be borne mostly by the City, which was to pay $226 million, and the companies would pay the difference. [11] [2] The City's contribution was in cash raised by bond offerings, while the companies' contributions were variously by supplying cash, facilities and equipment to run the lines.

Queensboro Plaza

Queensboro Plaza track plan Queensboro Plaza.png
Queensboro Plaza track plan

The contract negotiations were long and sometimes acrimonious. For instance, when the IRT was reluctant to cede the BRT's proposed access to Midtown Manhattan via the Broadway Line, the city and state negotiators immediately offered the BRT all of the lines under proposal. This included lines that would have only been operable using IRT rolling stock dimensions, such as the upper Lexington Avenue Line and both lines in Queens. The IRT quickly gave in to the "invasion" of Midtown Manhattan by the BRT. [12] [13]

The assignment of the proposed lines in Queens proved to be an imposition on both companies. Instead of one company enjoying a monopoly in that borough, both proposed lines—a short line to Astoria, and a longer line reaching initially to Corona, and eventually to Flushing—were assigned to both companies, to be operated in what was called "joint service". The lines would start from a large interchange station, Queensboro Plaza. The IRT would access the station from both the 1907 Steinway Tunnel and an extension of the Second Avenue Elevated from Manhattan over the Queensboro Bridge. The BRT would feed the Queens lines from the 60th Street Tunnel in Manhattan. Technically the line was under IRT "ownership", but the BRT/BMT was granted trackage rights in perpetuity, essentially making it theirs also. [12] [13]

The BRT had a big disadvantage, as both Queens lines were built to IRT specifications. This meant that IRT passengers had a one-seat ride to Manhattan destinations, whereas BRT passengers had to make a change at Queensboro Plaza. This came to be important when service was extended for the 1939 World's Fair, as the IRT was able to offer direct express trains from Manhattan, and the BRT was not. This practice lasted well into the municipal ownership of the lines, and was not ended until 1949. Both companies shared in the revenues from this service. To facilitate this arrangement originally, extra long platforms were constructed along both Queens routes, so separate fare controls/boarding areas could be established. This quickly turned out to be operationally unworkable, so eventually a proportionate formula was worked out. The bonus legacy of this construction was that the IRT was able to operate 11-car trains on this line, and when the BMT took over the Astoria Line, minimal work had to be done to accommodate 10-car BMT units. [13]

Conditions

The large Chambers Street station was the BMT's Manhattan hub. Chambers Street BMT 019.JPG
The large Chambers Street station was the BMT's Manhattan hub.
The large Coney Island Terminal in Brooklyn was the BMT's largest terminal outside of Manhattan. Oblique view of south facade along Surf Avenue and obscured east elevation. Looking northwest. - Stillwell Avenue Station, Intersection of Stillwell and Surf Avenues, Brooklyn, Kings HAER NY-325-11 (cropped).tif
The large Coney Island Terminal in Brooklyn was the BMT's largest terminal outside of Manhattan.
The IRT rebuilt the Steinway Tunnel, originally a trolley tunnel, for subway use. Concrete Benches on the No. 7 line (8510309583).jpg
The IRT rebuilt the Steinway Tunnel, originally a trolley tunnel, for subway use.

Several provisions were imposed on the companies, which eventually led to their downfall and consolidation into city ownership in 1940:

There were other conditions in regards to specific operations of the lines, as part of a deal between the IRT, the BMT, and the Public Service Commission. Many of the conditions applied all across the dual system. For example:

Some conditions applied only to certain parts of the system:

IRT lines

Under the original system, the original line and early extensions built for the IRT are:

The following lines were built under the Dual Contracts for the IRT: [7]

The following lines were rebuilt with extra tracks: [7]

Some of the IRT lines proposed under the Contracts were not built. Most notably, there were plans to build an IRT line to Marine Park, Brooklyn (at what is now Kings Plaza) under either Utica Avenue, using a brand-new line, or Nostrand Avenue and Flatbush Avenue, using the then-new IRT Nostrand Avenue Line. There were also alternate plans for the Nostrand Avenue Line to continue down Nostrand Avenue to Sheepshead Bay. [16]

BMT lines

1911 plan, giving all the contracts to the BRT 1911 BRT plan.jpg
1911 plan, giving all the contracts to the BRT
1924 map of the BMT Dual Contracts lines 1924 BMT dual contracts map.jpg
1924 map of the BMT Dual Contracts lines

All Manhattan and Queens BMT lines were built under the Dual Contracts, as were all subway and some elevated lines in Brooklyn. [7]

Newly built lines and line segments

Grade-separated rights-of-way built to replace surface railroads

Existing rights-of-way rehabilitated and expanded

Effects

As reformists predicted, the Dual Contracts resulted in city expansion. People moved to the newly built homes along the newly built subway lines. These homes were affordable, about the same cost as the houses in Brooklyn and Manhattan. [11] The Dual Contracts were the key to dispersion of the city's congested areas. The Dual Contracts helped lower high population areas and probably helped save lives as people were no longer living in heavily diseased areas. According to the Federal Census of New York City for 1920 the population in Manhattan below 59th Street decreased from 1910 to 1920. The census resulted in the following:

People were allowed to move to better parts the same cost and could have a better and more comfortable life in the suburbs. They could still commute to work every day as most of the better off city workers who moved to the outer boroughs did. [11] This also helped the business districts as people could still work.

Related Research Articles

<span class="mw-page-title-main">Interborough Rapid Transit Company</span> Defunct subway operator in New York City (1904–1940)

The Interborough Rapid Transit Company (IRT) was the private operator of New York City's original underground subway line that opened in 1904, as well as earlier elevated railways and additional rapid transit lines in New York City. The IRT was purchased by the city in June 1940, along with the younger BMT and IND systems, to form the modern New York City Subway. The former IRT lines are now the A Division or IRT Division of the Subway.

<span class="mw-page-title-main">Brooklyn Rapid Transit Company</span> Former transit holding company in New York City

The Brooklyn Rapid Transit Company (BRT) was a public transit holding company formed in 1896 to acquire and consolidate railway lines in Brooklyn and Queens, New York City, United States. It was a prominent corporation and industry leader using the single-letter symbol B on the New York Stock Exchange.

<span class="mw-page-title-main">103rd Street–Corona Plaza station</span> New York City Subway station in Queens

The 103rd Street–Corona Plaza station is a local station on the IRT Flushing Line of the New York City Subway, located at the intersection of 103rd Street and Roosevelt Avenue. It is served by the 7 train at all times.

<span class="mw-page-title-main">Junction Boulevard station</span> New York City Subway station in Queens

The Junction Boulevard station is an express station on the IRT Flushing Line of the New York City Subway, located at the intersection of Junction Boulevard and Roosevelt Avenue in Corona, Queens. It is served by the 7 train at all times and by rush hour peak-direction <7> express service.

<span class="mw-page-title-main">Queensboro Plaza station</span> New York City Subway station in Queens

The Queensboro Plaza station is an elevated New York City Subway station at Queens Plaza in the Long Island City neighborhood of Queens. It is near the east end of the Queensboro Bridge, with Queens Boulevard running east from the plaza. The station is served by the 7 and N trains at all times, the W train on weekdays, and the <7> train rush hours in the peak direction.

<span class="mw-page-title-main">90th Street–Elmhurst Avenue station</span> New York City Subway station in Queens

The 90th Street–Elmhurst Avenue station is a local station on the IRT Flushing Line of the New York City Subway, located at 90th Street and Elmhurst Avenue in Elmhurst, Queens. It is served by the 7 train at all times.

<span class="mw-page-title-main">69th Street station (IRT Flushing Line)</span> New York City Subway station in Queens

The 69th Street station is a local station on the IRT Flushing Line of the New York City Subway. Located at 69th Street and Roosevelt Avenue in the Woodside, Queens, it is served by the 7 train at all times.

<span class="mw-page-title-main">52nd Street station (IRT Flushing Line)</span> New York City Subway station in Queens

The 52nd Street station is a local station on the IRT Flushing Line of the New York City Subway. Located at the intersection of 52nd Street and Roosevelt Avenue in Woodside, Queens, it is served by the 7 train at all times.

The IRT Flushing Line is a rapid transit route of the New York City Subway system, named for its eastern terminal in Flushing, Queens. It is operated as part of the A Division. The Interborough Rapid Transit Company (IRT), a private operator, had constructed the section of the line from Flushing, Queens, to Times Square, Manhattan between 1915 and 1928. A western extension was opened to Hudson Yards in western Manhattan in 2015, and the line now stretches from Flushing to Chelsea, Manhattan. It carries trains of the 7 local service, as well as the express <7> during rush hours in the peak direction. It is the only currently operational IRT line to serve Queens.

<span class="mw-page-title-main">History of the New York City Subway</span>

The New York City Subway is a rapid transit system that serves four of the five boroughs of New York City, New York: the Bronx, Brooklyn, Manhattan, and Queens. Its operator is the New York City Transit Authority (NYCTA), which is controlled by the Metropolitan Transportation Authority (MTA) of New York. In 2016, an average of 5.66 million passengers used the system daily, making it the busiest rapid transit system in the United States and the seventh busiest in the world.

The BMT Astoria Line is a rapid transit line in the B Division of the New York City Subway, serving the Queens neighborhood of Astoria. It runs south from Ditmars Boulevard in Astoria to 39th Avenue in Long Island City above 31st Street. It then turns west and serves Queensboro Plaza over Queens Plaza.

Starting in 1899, the Brooklyn Rapid Transit Company and Brooklyn–Manhattan Transit Corporation operated rapid transit lines in New York City — at first only elevated railways and later also subways.

<span class="mw-page-title-main">Eighth Street–New York University station</span> New York City Subway station in Manhattan

The Eighth Street–New York University station is a local station on the New York City Subway's BMT Broadway Line. Located at the intersection of Eighth Street and Broadway in Greenwich Village, Manhattan, it is served by the R train at all times except late nights, the W train on weekdays, the N train during late nights and weekends, and the Q train during late nights. It serves the main campus of New York University.

<span class="mw-page-title-main">57th Street–Seventh Avenue station</span> New York City Subway station in Manhattan

The 57th Street–Seventh Avenue station is an express station on the BMT Broadway Line of the New York City Subway. Located in Midtown Manhattan at the intersection of 57th Street and Seventh Avenue, it is served by the N and Q trains at all times, the R train at all times except late nights, and the W train on weekdays. It is directly adjacent to Carnegie Hall.

<span class="mw-page-title-main">Seventh Avenue station (BMT Brighton Line)</span> New York City Subway station in Brooklyn

The Seventh Avenue station is a station on the BMT Brighton Line of the New York City Subway, located at the intersection of Seventh Avenue, Park Place and Flatbush Avenue in Park Slope and Prospect Heights, Brooklyn. The station is served by the Q train at all times and by the B train on weekdays only.

<span class="mw-page-title-main">28th Street station (BMT Broadway Line)</span> New York City Subway station in Manhattan

The 28th Street station is a local station on the BMT Broadway Line of the New York City Subway, located at 28th Street and Broadway in Manhattan. It is served by the R train at all times except late nights, the W train on weekdays, the N train during late nights and weekends and the Q train during late nights.

The New York City Subway's B Division consists of the lines that operate with lettered services, as well as the Franklin Avenue and Rockaway Park Shuttles. These lines and services were operated by the Brooklyn–Manhattan Transit Corporation (BMT) and city-owned Independent Subway System (IND) before the 1940 city takeover of the BMT. B Division rolling stock is wider, longer, and heavier than those of the A Division, measuring 10 or 9.75 ft by 60 or 75 ft.

References

Notes

  1. Derrick 2001, p. 2.
  2. 1 2 3 4 "618 MILES OF TRACK IN THE DUAL SYSTEM; City Will Have Invested $226,000,000 When Rapid Transit Project Is Completed". The New York Times. August 3, 1913. Retrieved April 25, 2018.
  3. Derrick 2001, p. 2–3.
  4. Derrick 2001, p. 265.
  5. Derrick 2001, p. 4–5.
  6. 1 2 Derrick 2001, p. 6.
  7. 1 2 3 4 5 "The Dual System of Rapid Transit (1912)". nycsubway.org.
  8. The New York Times , Farthest North in Town by the Interborough, January 14, 1907, page 18
  9. The New York Times, Brooklyn Joyful Over New Subway, May 2, 1908, page 1
  10. "Subway Contracts Solemnly Signed; Cheers at the Ceremonial Function When McCall Gets Willcox to Attest" (PDF). The New York Times. March 20, 1913. ISSN   0362-4331 . Retrieved January 11, 2018.
  11. 1 2 3 Derrick 2001, p. 7.
  12. 1 2 Public Service Commission 1913, chapter 1.
  13. 1 2 3 Rogoff 1960.
  14. 1 2 3 4 5 6 7 8 9 10 11 12 13 14 "Terms and Conditions of Dual System Contracts". nycsubway.org. Retrieved February 16, 2015.
  15. "M'ADOO EXTENSION TO BE READY IN 1911; Head of Hudson & Manhattan Road Promises It After the Board of Estimate Approves. BUSINESS MEN GRATIFIED Mr. McAdoo Also Happy – He Will Begin at Once to Complete the Jersey-Grand Central Route". The New York Times. June 5, 1909. ISSN   0362-4331 . Retrieved April 24, 2018.
  16. "TRANSIT OUTLOOK BRIGHT IN BROOKLYN; First Branch Lines on Assessment Plan Likely to be Built in That Borough". The New York Times. March 6, 1910. ISSN   0362-4331 . Retrieved August 9, 2016.
  17. "Lower Manhattan Lost in Population" (PDF). The New York Times. Retrieved November 5, 2013.

Sources