East Coast Main Line Route Utilisation Strategy

Last updated

The East Coast Main Line Route Utilisation Strategy (RUS), published by Network Rail in February 2008, [1] [2] [3] was the seventh RUS.

Contents

RUSs are established by the Office of Rail Regulation (ORR) unless the latter objects within 60 days. A letter formally confirming establishment, but with some qualifications, was sent by ORR to NR in April 2008, [4] and the RUS is included in NR's map as established. [5]

The scope includes the whole of Strategic Route 8 - East Coast Main Line [6] and Route 9 - North East Routes, [7] and part of Route 5 (the Hitchin-Cambridge line). Not strictly within the scope but relevant to the service mix forming present and future utilisation of the RUS area are parts of Route 11 (to Sheffield and to Lincoln, and the diversionary joint GN/GE route from Peterborough to Doncaster via Lincoln), Route 10 (to Hull and to Bradford) and Route 24 (to Aberdeen).

As with other RUSs, the ECMLRUS took into account a number of responses, [8] [9] including the Office of Rail Regulation (ORR). [10]

The routes and services covered by the RUS are varied in type. At the London end and in the vicinity of other major cities are inner suburban and metro-like services, which are vital commuter routes; across the RUS area there are cross-country and fast medium-distance passenger services, including inter-city services; there are long-distance (and in the British context very long distance) high-speed passenger services (LDHS) from London to a number of major cities in Scotland and northern England; and there are significant freight flows that use part of the area. A number of issues arise from the mix and intensity of these services, and the RUS addresses these in 10 groups.

Some issues are closely related to other RUSs: Scotland RUS (Edinburgh Waverley station and Portobello junction); Freight RUS.

Some issues were passed to later RUSs: Lancashire & Cumbria [11] Yorkshire & Humber (Y&H RUS), [12] the Network RUS, West Coast Main Line (WCML). [13]

The RUS needs to be seen against existing contingent and prospective schemes, especially against the Thameslink project, which will see a step-change in services continuing through central London onto the network south of London. The timing of some interventions identified in the RUS are dependent on certain works in this programme being brought forward.[ citation needed ]

Groups of gaps and issues, with recommendations

A number of routes and services suffer from overcrowding of passengers in each usually 3-hour peak periods (mostly divided into a middle 'high' peak hour and two 'shoulder' peaks). In almost all cases these problems are foreseen, in the absence of interventions, to get worse owing to forecast growth in passenger traffic. These are simply referred to as "peak crowding" in the detail below.

London inner suburban services

The inner suburban services mainly comprise services from Welwyn Garden City on the main ECML route and from Hertford North on the Hertford loop, branching off just south of Stevenage and immediately north of Alexandra Palace, to Kings Cross, or to Moorgate, branching off at Finsbury Park via the Northern City Line, in deep-level large-gauge tube tunnel south of Drayton Park. The Hertford loop is the main freight corridor at this end of the ECML, as it is cleared to W9, rather than W8.

Peak crowding Crowding is acute, especially on the southern part of the Hertford loop; the recommendation is to lengthen all peak trains to 6 cars, and increase frequency to Moorgate to 10 trains per hour (tph) in both directions, subject to the implementation of Options A and B below. When rolling stock is replaced, attention should be given to the new stock's internal layout.

Increase off-peak service levels to 4tph There is an aspiration for a minimum 4tph: this service level is recommended on Monday-Saturday; it may be combined with extension to 2tph via the Hertford Loop to Stevenage. On Monday-Friday between the peaks, increased revenue would cover the extra costs; at other times other benefits need to be taken into account.

London outer suburban services

Peak crowding Peak crowding is set to get worse especially on the Cambridge line, and this will constrain the number of passengers unless capacity is increased. The main recommendation is to increase trains in the peak to 12 cars, requiring platform lengthening in several places, such as Royston and Letchworth with others delivered via the Thameslink programme, and other infrastructure changes, including a new island platform at Cambridge and power and stabling enhancements; some paths used by stopping trains north of Welwyn Garden City should be used for outer suburban services.

LDHS services

Peak crowding and off-peak demand Generally lengthening of existing maximum formations is impracticable for a number of reasons, though the Intercity Express Programme (IEP) will provide an opportunity for greater capacity. The recommendation of the RUS is to increase the capacity of the LDHS lines to provide 8tph in the peak and 6tph off-peak (increased from 6 and 5 respectively), together with a repeating pattern every one or two hours; this will require very significant infrastructure changes as described below.

Aspiration to speed up journeys between London, Yorkshire, the North East and Scotland The same infrastructure changes will allow LDHS services to run with a marginal acceleration in timing.

Irregular service intervals Owing to the need to provide a reasonable level of services to secondary destinations on the ECML, long-distance services do not currently adhere to a regular clockface pattern. This will also be alleviated by the changes described above.

Direct services to destinations on and off main ECML As outlined above, moving to a more regular pattern under enhanced capacity would safeguard and regularise services to the secondary destinations on the ECML. The ECMLRUS makes no particular recommendation on choice of services serving destination off the ECML, but leaves it to the normal industry practices to decide.

Anglo-Scottish service frequency To be delivered as part of a package addressing several gaps, as described above.

Regional connectivity This will be improved by the capacity enhancements and the opportunity provided to develop a more standard service pattern, possibly, in some cases, including direct services branching off the ECML (as happens now to Hull and to Sunderland).

ECML service pattern north between York and Edinburgh

In general the pattern of frequent but irregular services is largely dictated by the LDHS timetable (itself not on a standard pattern), the timing of cross-country services which are constrained by critical points off the ECML, and the needs of freight services.

South of Newcastle a critical physical section is the 2-track line between Northallerton and Newcastle. Timetable developments should endeavour to even out the gaps especially through Durham.

Various stakeholders, with potential access to funds, have aspirations for improved services and facilities, including new stations at East Linton (west of Dunbar) and Reston (north-west of Berwick).

Scotland Dunbar station has a single platform, forcing northbound services stopping there to cross over to the other line; a second platform is recommended, which will allow additional trains to stop there and/or marginally improve journey times and performance, and in turn may help make other interventions more feasible. Though there is an aspiration for improved local services over the Scottish section, the RUS does not unequivocally recommend any of them, except for an hourly service from Dunbar to Edinburgh, extending an existing east–west service across Edinburgh. Options east of Edinburgh could be considered further by Transport Scotland.

South and West Yorkshire services

Peak crowding into Leeds (services via Wakefield Westgate) There is some crowding on the route from Doncaster which includes 6 local stations and Wakefield Westgate. This issue was deferred to the Yorkshire and Humber RUS.

Links between regional centres Leeds-Sheffield services can be provided via Wakefield or via Barnsley (outside the ECML RUS area). This issue was deferred to the Yorkshire and Humber RUS.

Funders' aspirations South Yorkshire Passenger Transport Executive and West Yorkshire Passenger Transport Executive have various aspirations. Robin Hood Airport Sheffield Doncaster has an aspiration for an adjacent station, at Finningly on the Doncaster-Lincoln line. These schemes were all passed to the Yorkshire and Humber RUS.

Sheffield/Doncaster – London flows The area can be reached from London via either the ECML or the Midland Main Line (MML). This issue was deferred to the Network RUS.

Tees Valley services

Peak crowding into Middlesbrough There is such crowding on local trains; the recommendation is to lengthen the trains to 3 cars, by cascade of stock compatible with platform lengths.

Schemes remitted from North East RPA Various schemes have been mooted for improving Tees valley services. The only recommendations endorsed by the RUS are improving line speeds in Tees Valley and Durham Coast lines as renewals become due, and possible occasional extra stops on the London-Sunderland service. Some projects might be delivered by the proposed Tees Valley Metro.

Tyneside local services

Peak crowding into Newcastle The recommendation is to lengthen the trains to 3 cars, by cascade of suitable stock; platform lengths need to be taken into account.

Schemes remitted from North East RPA The only recommendation endorsed by the RUS comprises minor improvements in linespeeds in Tyne Valley (Newcastle-Carlisle) lines as renewals become due.

Network flexibility

While there are specific geographically-based issues, as described above, there are types of existing constraints in the network capability which affect both those issues (directly) and efficiency of the network as a whole. Those more generic issues, within which there is a degree of overlap, comprise:

In turn those generic issues have a geographical impact which the RUS examines under the following line sections:

Freight RUS specific gaps

Port of Tyne – Tursdale Jn (Freight RUS Gap 12) Recommended reinstatement of Boldon East curve

Hare Park Jn – South Kirkby Jn (Freight RUS Gap A) Passed to Y&H RUS

Separation of east–west coal traffic to Eggborough/Drax/Ferrybridge power stations (Freight RUS Gap B) Recommended remodelling of Joan Croft/Shaftholme junctions (avoiding coal freight use of the ECML to Hambleton Junction).

Peterborough Crescent Junction – Doncaster Loversall Carr Junction (Freight RUS Gap C) See Option C below

W9/W10/W12 gauge aspirations A programme of feasibility work had been developed.

Elimination of Class 92 OHLE restrictions The introduction of IEP trains will trigger re-assessment of all electric traction requirements.

775m freight train operations Recommended that during the development of renewals and enhancements the aspiration for such services be accommodated where possible.

Station gaps

Congestion relief at King's Cross Being addressed by the major redevelopment already envisaged.

Congestion relief at Finsbury Park This station suffers from severe congestion at peak times, and services are set to expand. Various options were to be examined, but would probably include re-instating of a disused platform (see Option A below).

Congestion relief at Peterborough To be taken forward in conjunction with partial remodelling (see Option C below).

Car parking There are particular problems at several inner suburban stations, Royston, Hertford North, Hatfield, Stevenage and Sunderland. More strategically increased parking at other locations may be developed to encourage access to the network.

Interchange with other transport modes No specific problems were identified, but interfaces with Transport for London services will need to be addressed at Kings Cross, Finsbury Park and Highbury & Islington.

Access to ECML from area around M25 This aspiration will need to be subject to a full multi-modal study.

Major infrastructure enhancements proposed

Conversion of goods line south of Alexandra Palace for passengers use (Option A)

This intervention underpins the other two options below, but is justifiable in its own right owing to speed, capacity and performance benefits. It involves adapting the Up (southbound) goods line between Alexandra Palace and Finsbury Park to passenger use, including additional platforms at Alexandra Palace, Hornsey and Harringay and a reopened platform at Finsbury Park. LDHS trains will achieve a three-minute speed increase, and southbound inner-suburban trains exiting from Hertford-loop can be totally segregated.

Works to enable up to 10 tph peak services on Hertford Loop to Moorgate (Option B)

In addition to Option A, additional power supplies (in any case to be provided by Thameslink) and signalling providing a four-minute headway in the tunnel from south of Finsbury Park area to Moorgate are both required. There would be some jeopardy to performance, but this is outweighed by the increased frequency.

Works to support extra long-distance and freight services (Option C)

These are by far the largest set of infrastructure interventions recommended by the RUS. They would allow up to 8 LDHS tph on ECML, with consequent other benefits, and the forecast freight increase.

Upgrading of the GN/GE Joint Line from Peterborough to Doncaster, via Lincoln This is mainly to provide for re-routed (to free up paths on ECML) and additional daytime freight traffic between these cities, but would also have the major benefit of providing a substantial diversionary route (though not electrified) in times of disruption or scheduled maintenance on the ECML. It is estimated to cost a quarter of the cost of four-tracking the corresponding stretch of the ECML, and remains significantly more cost-effective than alternatives comprising partial four-tracking of ECML plus shorter diversions for freight. Typical linespeed on the enhanced GN/GE route would be 75 miles per hour (mph) for intermodal (container) trains at W9/W10 gauge and 60 mph for heavy freight at RA10 availability. While the route is 10 miles longer than the equivalent stretch of the ECML, freight trains will run throughout at the appropriate linespeed, rather than having to be looped to allow passenger services to pass. The use of this route will also be compatible with the prospective W9/W10 cleared route from Felixstowe to Peterborough. Selectively linespeed may be increased for passenger trains on this route.

Additional platforms on the second Down (northbound) slow line at Hornsey and Harringay Again this option allows segregation of Moorgate to Hertford Loop services to reflect the similar service in the southbound direction. North of Alexandra Palace the diverging northbound line to the Hertford Loop is already grade separated. The intervention also provides for flexibility for accommodating stopping and semi-fast services.

Grade separation of the northbound link from Hitchin to the Cambridge line At present all northbound trains towards Cambridge have to cross the fast lines through Hitchin. The purpose of this proposal is to provide a flyover for this line to clear all the other lines north of Hitchin station on the main route (direction of Stevenage). Additionally, the junction of the merging (southbound) line from Cambridge would be remodelled to provide access to the fast line before reaching Hitchin station.

Partial remodelling of Peterborough and Doncaster layouts There would be a requirement to alter the arrangements at both ends to facilitate the use of the alternative route. At Peterborough this will be combined with arrangements to provide better accommodation for other passenger services off the ECML.

Subsequent developments

In March 2009 Network Rail published its CP4 Delivery Plan 2009, including Enhancements programme: statement of scope, outputs and milestones, [14] confirming most of the recommended interventions. Specific projects, scheduled to cost about one billion pounds in total, with their reference and page numbers in the document, are given below:

Related Research Articles

Great Northern Railway (Great Britain) Defunct British railway company

The Great Northern Railway (GNR) was a British railway company incorporated in 1846 with the object of building a line from London to York. It quickly saw that seizing control of territory was key to development, and it acquired, or took leases of, many local railways, whether actually built or not. In so doing, it overextended itself financially.

Northern City Line

The Northern City Line is a commuter railway line in England, which runs from Moorgate station to Finsbury Park in London with services running beyond. It is part of the Great Northern Route services, and operates as the south-eastern branch of the East Coast Main Line (ECML). It is underground from Moorgate to Drayton Park in Highbury, from which point it runs in a cutting until joining the ECML south of Finsbury Park. Its stations span northern inner districts of Greater London southwards to the City of London, the UK's main financial centre. Since December 2015, its service timetable has been extended to run into the late evenings and at weekends, meeting a new franchise commitment for a minimum of six trains per hour until 23:59 on weekdays and four trains per hour at weekends.

Finsbury Park station London Underground and railway station

Finsbury Park is an intermodal interchange station in north London. It serves a number of National Rail, London Underground and bus services. The station is the third busiest Underground station outside Zone 1, with over 33 million passengers using the station in 2019.

Moorgate station London Underground and railway station

Moorgate is a central London railway terminus and connected London Underground station on Moorgate in the City of London. Main line railway services for Hertford, Welwyn Garden City, Stevenage and Letchworth are operated by Great Northern, while the Underground station is served by the Circle, Hammersmith & City, Metropolitan and Northern lines.

East Coast Main Line Railway link between London and Edinburgh and London and Leeds

The East Coast Main Line (ECML) is a 393-mile long (632 km) electrified railway between London and Edinburgh via Peterborough, Doncaster, York, Darlington, Durham and Newcastle. The line is a key transport artery on the eastern side of Great Britain running broadly parallel to the A1 road.

Essex Road railway station Railway station in Greater London, England

Essex Road is a National Rail station in Canonbury in Greater London, England, and is on the Northern City Line between Old Street and Highbury & Islington, 1 mile 59 chains (2.8 km) down the line from Moorgate, and is in Travelcard Zone 2. The station is at the junction of Essex Road, Canonbury Road and New North Road, with the present entrance on Canonbury Road. Operated by Great Northern, it is the only deep-level underground station in London served exclusively by National Rail trains. Between 1933 and 1975 the station was operated as part of the London Underground, as a short branch of the Northern line. Between 1922 and 1948 the station name was Canonbury & Essex Road. The name reverted to the original form in 1948.

Harringay railway station Railway station in London

Harringay railway station is in Harringay in the London Borough of Haringey, north London. It is on the Great Northern Route that forms part of the East Coast Main Line, 3 miles 32 chains (5.5 km) down the line from London King's Cross, and is situated between Finsbury Park to the south and Hornsey to the north. It opened on 1 May 1885.

Dartford Loop Line

The Dartford Loop Line is one of three lines linking London with Dartford in Kent, England. It lies to the south of the other two: the North Kent Line and the Bexleyheath Line.

Alexandra Palace railway station National Rail station in London, England

Alexandra Palace railway station is on the Great Northern Route that forms part of the East Coast Main Line, and takes its name from the nearby Alexandra Palace in the London Borough of Haringey, north London. It is 4 miles 78 chains (8.0 km) down the line from London King's Cross and is situated between Hornsey and either New Southgate on the main line or Bowes Park on the Hertford Loop Line which diverges from the main line just north of Alexandra Palace.

Peterborough railway station Railway station serving the city of Peterborough, within Cambridgeshire, England

Peterborough railway station serves the city of Peterborough, Cambridgeshire, England. It is 76 miles 29 chains (122.9 km) down the East Coast Main Line from London King's Cross. The station is a major interchange serving both the north–south ECML, as well as long-distance and local east–west services. The station is managed by London North Eastern Railway. Ticket gates came into use at the station in 2012.

Peterborough–Lincoln line

The Peterborough–Lincoln line is a railway line linking Peterborough and Lincoln Central, via Sleaford and Spalding. Between Lincoln and Spalding, the line follows the route of the former Great Northern and Great Eastern Joint Railway.

Hitchin railway station Railway station in Hertfordshire, England

Hitchin railway station serves the town of Hitchin in Hertfordshire. It is located approximately 1 mile (1.6 km) north east of the town centre and 31 miles 74 chains (51.4 km) north of London King's Cross on the East Coast Main Line.

Great Northern route Suburban rail service in Great Britain

The Great Northern route is the name given to suburban rail services run on the southern end of Britain's East Coast Main Line and its associated branches. Services operate to or from London King's Cross and London Moorgate in London. Destinations include Hertford North, Welwyn Garden City, Stevenage, Peterborough, Cambridge, and King's Lynn. Services run through parts of Greater London, Hertfordshire, Bedfordshire, Cambridgeshire, and Norfolk.

The Freight Route Utilisation Strategy is a Route Utilisation Strategy in the United Kingdom, published by Network Rail in March 2007. It is one of only two which have the perspective of the network as whole. It was included in a map published by the Office of Rail Regulation (ORR) as established in May 2007. As with other RUSs, the Freight RUS took into account a number of responses to a Draft for Consultation, including those from the ORR.

The Scotland Route Utilisation Strategy is a Route Utilisation Strategy, published by Network Rail in March 2007, the third RUS to be published. The railways in Scotland are divided into three strategic routes, namely Route 24, Route 25 (Highlands) and Route 26 together with parts of Route 8 and Route 18. The three strategic routes form the scope of Network Rail's Scotland Route Utilisation Strategy. Separate RUSs for the ECML and WCML encompass the relevant parts of routes 8 and 18. The Edinburgh Crossrail service, which provides a direct route between Stirling, Dunblane and Bathgate in the west to Newcraighall in the east, operates over part of the ECML east of Edinburgh Waverley to Portobello Junction.

The North West Route Utilisation Strategy (NWRUS) is a Route Utilisation Strategy, published by Network Rail in May 2007. It was the fifth RUS to be produced. It was included in a map published by the Office of Rail Regulation as established in May 2007. It was the first of no fewer than 5 RUSs which cover specific routes in the north-west of England; the others are the Lancashire & Cumbria RUS, the Yorkshire & Humber RUS, the Merseyside RUS, and the West Coast Main Line RUS. In particular it "broadly covers the Manchester journey to work area, the City lines into Liverpool Lime Street and routes from Manchester to Kirkby, Southport and Blackpool", corresponding to Network Rail's then Route 20 - North West Urban.

The Greater Anglia Route Utilisation Strategy is a Route Utilisation Strategy published by Network Rail in December 2007. It was the sixth RUS to be produced. The area covered includes the whole of Route 5 West Anglia (WA) and Route 7 Great Eastern (GE), which both focus for passenger purposes on London Liverpool Street, and the London Fenchurch Street services from Route 6. As with other RUSs, the Greater Anglia RUS took into account a number of responses, including the Office of Rail Regulation (ORR).

Network Rail's (NR) South London Route Utilisation Strategy (SLRUS), published in March 2008 (SLRUS) was the eighth Route Utilisation Strategy to be produced. By default, RUSs are established by the Office of Rail Regulation (ORR) unless the latter objects within 60 days. The RUS is included in NR's map as established.

The Yorkshire and Humber Route Utilisation Strategy is a Route Utilisation Strategy (RUS), published by Network Rail in July 2009; it was the twelfth RUS to be completed, not counting the partially completed Network RUS.

Werrington Dive Under Major railway junction in Cambridgeshire, England

Werrington Dive Under is a replacement dual track grade separated railway junction at Werrington Junction, 3 miles (5 km) north of Peterborough railway station in Cambridgeshire, England. The junction leads to the Great Northern/Great Eastern Joint line (GN/GE) which goes through Spalding to Lincoln and beyond. Completed and opened in December 2021, the dive under allows trains on the west side of the East Coast Main Line (ECML) to access the GN/GE line without conflicting with the faster passenger services on the ECML.

References

  1. East Coast main Line RUS
  2. ATOC press release on ECMLRUS
  3. London Connections appraisal
  4. "ORR letter to Network Rail confirming establishment" (PDF). Archived from the original (PDF) on 24 March 2009. Retrieved 14 April 2009.
  5. Network Rail RUS Programme and Map
  6. Route 8 - East Coast Main Line
  7. "Route 9 - North East Routes" (PDF). Archived from the original (PDF) on 7 June 2011. Retrieved 14 April 2009.
  8. "London TravelWatch response to consultation". Archived from the original on 14 October 2007. Retrieved 14 April 2009.
  9. Rail Freight Group response to consultation
  10. "ORR's response to consultation" (PDF). Archived from the original (PDF) on 14 December 2007. Retrieved 14 April 2009.
  11. "Lancashire & Cumbria RUS" (PDF). Archived from the original (PDF) on 7 June 2011. Retrieved 14 April 2009.
  12. "Yorkshire & Humber RUS" (PDF). Archived from the original (PDF) on 27 March 2009. Retrieved 14 April 2009.
  13. West Coast Main Line RUS Scoping document, section 4.4.2 p.6
  14. "NR Enhancements delivery plan" (PDF). Archived from the original (PDF) on 2 September 2009. Retrieved 14 April 2009.