Flatbush Avenue station (Connecticut)

Last updated
Flatbush Avenue
CTtransit route 101 bus at Flatbush Avenue CTfastrak station, December 2015.JPG
Southbound bus at Flatbush Avenue station in December 2015
General information
LocationNew Park and Flatbush Avenues
West Hartford, Connecticut
Coordinates 41°44′31″N72°42′59″W / 41.7419°N 72.7164°W / 41.7419; -72.7164
Owned by ConnDOT (bus station)
Amtrak (rail line)
Operated by Connecticut Transit
Line(s) New Haven-Springfield Line
Tracks2
Bus routes101, 102, 121, 128
Bus stands2 side platforms
Connections31, 37 (on New Park Avenue)
153 (on Flatbush Avenue)
Construction
Bicycle facilitiesYes
AccessibleYes
History
OpenedMarch 28, 2015 (2015-03-28) [1] (CTfastrak)
Opening2022 (CTrail, planned) [2]
Services
Preceding station CT Transit Following station
Elmwood CTfastrak Kane Street
toward Hartford
Planned service
Preceding station Hartford Line logo.png CT Rail Following station
Newington Hartford Line
(future infill station)
Hartford
toward Springfield

Flatbush Avenue is a bus rapid transit station on the CTfastrak line, located near the intersection of Flatbush Avenue and New Park Avenue in West Hartford, Connecticut. It opened with the line on March 28, 2015. [1] The station consists of one island platform to the side of the busway, with passing lanes to allow express buses to pass buses stopped at the station. [3] A CTrail Hartford Line commuter rail platform is planned to open in 2022 under the name West Hartford. [2]

Contents

Railroad history

The New York and New England Railroad (and predecessor Hartford, Providence and Fishkill Railroad) operated a station named Charter Oak Park at Oakwood Street slightly to the south, serving the Charter Oak Park racing track and the Luna Park recreation area. It opened with the track in 1874, was rebuilt in 1900, and likely closed with the racetrack in 1940. [4] The New Haven Railroad had an adjacent Oakwood station on its parallel Springfield Line; it opened in 1874 and was closed in the late 1890s after the New Haven's purchase of the NY&NE rendered it redundant. [5]

Future plans

The Hartford Line commuter rail service between New Haven, Connecticut and Springfield, Massachusetts via Hartford commenced on June 16, 2018. [6] It initially connects to CTfastrak at Union Station. [7] Hartford Line stations adjacent to the CTfastrak stops at West Hartford (Flatbush Avenue) and Newington Junction are planned to open later. [8]

The 2012 environmental assessment for the Hartford Line included preliminary plans for four infill stations including West Hartford and Newington Junction; although they were not yet funded, this would allow future planning and construction to be expedited. [9] On January 12, 2015, the state announced that $5.75 million in funding would be made available for environmental mitigation and design at ten Hartford Line and New Haven Line stations, including design funding for Hartford Line platforms at West Hartford and Newington Junction. [10] In February 2017, the state announced an additional $50 million in funds, including money to complete design of West Hartford station. [11] Design will be completed by 2020. [12] The state aims to construct all infill stations on the line by 2022. [2]

Related Research Articles

<span class="mw-page-title-main">Newington, Connecticut</span> Town in Connecticut, United States

Newington is a town in Hartford County, Connecticut, United States. The town is part of the Capitol Planning Region. Located 8 miles (13 km) south of downtown Hartford, Newington is an older, mainly residential suburb located in Greater Hartford. As of 2023, the population is 30,527. The Connecticut Department of Transportation has its headquarters in Newington.

<span class="mw-page-title-main">New York, New Haven and Hartford Railroad</span> American Class I railroad (1872–1968)

The New York, New Haven and Hartford Railroad, commonly known as The Consolidated, or simply as the New Haven, was a railroad that operated principally in the New England region of the United States from 1872 to December 31, 1968. Founded by the merger of the New York and New Haven and Hartford and New Haven railroads, the company had near-total dominance of railroad traffic in Southern New England for the first half of the 20th century.

<span class="mw-page-title-main">Union Station (New Haven)</span> Railroad station in Connecticut

New Haven Union Station is the main railroad passenger station in New Haven, Connecticut. It is the third such station in the city of New Haven, preceded by both an 1848 built station in a different location, and an 1879 built station near the current station's location. Designed by noted American architect Cass Gilbert, the present beaux-arts Union Station was completed and opened in 1920 after the previous Union Station was destroyed by fire. It served the New York, New Haven and Hartford Railroad for the next five decades, but fell into decline following World War II along with the United States railroad industry as a whole.

<span class="mw-page-title-main">Shore Line East</span> Commuter rail service in southern Connecticut, US

Shore Line East (SLE) is a commuter rail service which operates along the Northeast Corridor through southern Connecticut, United States. The rail service is a fully owned subsidiary of the Connecticut Department of Transportation (CTDOT) and is operated under the CT Rail brand. SLE provides service seven days a week along the Northeast Corridor between New London and New Haven; limited through service west of New Haven to Bridgeport and Stamford has been suspended since 2020. Cross-platform transfers to Metro-North Railroad New Haven Line trains are available at New Haven for service to southwestern Connecticut and New York City. Pre-COVID, around 2,200 riders used the service on weekdays.

<span class="mw-page-title-main">Springfield Union Station (Massachusetts)</span> Train station in Springfield, Massachusetts, US

Springfield Union Station is a train and bus station in the Metro Center area of Springfield, Massachusetts. Constructed in 1926, Springfield Union Station is the fifth-busiest Amtrak station in the Commonwealth, and the busiest outside of Greater Boston.

<span class="mw-page-title-main">New Haven–Springfield Line</span> Railroad line in Connecticut and Massachusetts, U.S.

The New Haven–Springfield Line is a railroad line owned by Amtrak from New Haven, Connecticut, north to Springfield, Massachusetts, serving the Knowledge Corridor. As a branch of the Northeast Corridor just north of New Haven State Street station, it is served by approximately seven daily Northeast Regional round trips, some continuing from New Haven to Washington, D.C., along the Corridor and others terminating at New Haven as shuttles. On weekends, there is one train daily to Roanoke, Virginia. It is also served by the daily Vermonter, which starts in Washington, D.C., and continues north from Springfield, finally terminating in St. Albans, Vermont. The line is part of the Inland Route connecting Boston and New York via Hartford, Springfield, and Worcester, in contrast to the "Shore Line" along the Connecticut Shore and through Rhode Island.

<span class="mw-page-title-main">New Haven State Street station</span> Railroad station in Connecticut

New Haven State Street station is a commuter rail station located on State Street in downtown New Haven, Connecticut. The secondary railroad station in the city, it is located 0.8 miles (1.3 km) northeast of the much larger New Haven Union Station and is intended to offer easier access to New Haven's downtown business district. It is served by Shore Line East and Hartford Line commuter trains, Amtrak Hartford Line trains, Springfield-terminating Northeast Regional trains, and Valley Flyer trains, and a limited number of Metro-North Railroad New Haven Line trains. Originally proposed in 1996, State Street opened on June 7, 2002. A second platform opened on June 8, 2018, in time for the beginning of Hartford Line service.

<span class="mw-page-title-main">Hartford Union Station</span> Train station in Hartford, Connecticut, US

Hartford Union Station is a railroad station in Hartford, Connecticut, United States on the New Haven–Springfield Line. It is served by Amtrak Hartford Line, Northeast Regional, Valley Flyer, and Vermonter intercity rail service, plus CT Rail Hartford Line commuter rail service and CTfastrak bus rapid transit service.

<span class="mw-page-title-main">Hartford Line</span> CTrail commuter rail service in the US

The Hartford Line is a commuter rail service between New Haven, Connecticut, and Springfield, Massachusetts, using the Amtrak-owned New Haven–Springfield Line. The project is a joint venture between the states of Connecticut and Massachusetts, with support from the federal government as well. CT Rail-branded trains provide service along the corridor, and riders can use Hartford Line tickets to travel on board most Amtrak trains along the corridor at the same prices. The service launched on June 16, 2018.

<span class="mw-page-title-main">Windsor station (Connecticut)</span>

Windsor station is a historic railroad station on Amtrak's New Haven–Springfield Line, located in downtown Windsor, Connecticut. It is served by Amtrak Northeast Regional and Valley Flyer intercity service and CT Rail's Hartford Line commuter rail service. The nearby Hartford & New Haven Railroad-Freight Depot serves as the home of the Windsor Arts Center.

<span class="mw-page-title-main">Windsor Locks station</span> Train station in Windsor Locks, Connecticut, US

Windsor Locks station is an Amtrak and CT Rail train station in Windsor Locks, Connecticut, on the New Haven–Springfield Line. It is served by four Amtrak services - the Hartford Line shuttles, Northeast Regional, Valley Flyer, and Vermonter - as well as CT Rail Hartford Line commuter rail trains.

<span class="mw-page-title-main">Enfield station (Connecticut)</span>

Enfield station is a planned CTrail Hartford Line station in Enfield, Connecticut. As of September 2023, construction is expected to begin in 2025. A previous station at the site was open from 1844 to 1986.

<span class="mw-page-title-main">North Haven station</span>

North Haven is a planned regional rail station on the New Haven–Springfield Line near Route 40 and Route 5 in North Haven, Connecticut, to be served by the Hartford Line service. The project has been funded for design, with construction expected to cost $52 million.

<span class="mw-page-title-main">CT Fastrak</span> Bus rapid transit operations in Connecticut, US

CTfastrak is a regional bus rapid transit system currently operating between downtown Hartford and Downtown New Britain station in New Britain in central Connecticut. Operated by Connecticut Transit, it is the first bus rapid transit system in Connecticut and the second in New England after the MBTA Silver Line. CTfastrak opened on March 28, 2015 after fifteen years of planning and three years of construction.

<span class="mw-page-title-main">Downtown New Britain station</span>

Downtown New Britain is a bus rapid transit station and the terminus of the CTfastrak line, located just south of Route 72 off Columbus Boulevard and Main Street in New Britain, Connecticut. It opened with the line on March 28, 2015. The station consists of one side platform and one island platform, comprising a collective total of 19 bus bays for CTfastrak local and express services, plus local CT Transit buses which do not use the busway. The station is located at the site of New Britain's former railroad station, which saw service from 1850 to 1960.

<span class="mw-page-title-main">Cedar Street station</span>

Cedar Street is a bus rapid transit station on the CTfastrak line, located near the intersection of Cedar Street (CT-175) and Fenn Road in Newington, Connecticut. It opened with the line on March 28, 2015. The station consists of two side platforms serving the busway, with two center passing lanes to allow express buses to pass buses stopped at the station. Along with East Street, it serves Central Connecticut State University.

<span class="mw-page-title-main">Elmwood station (Connecticut)</span>

Elmwood is a bus rapid transit station on the CTfastrak line, located near the intersection of New Britain Avenue (CT-529) and New Park Avenue in West Hartford, Connecticut. It opened with the line on March 28, 2015. The station consists of two side platforms serving the busway, with two center passing lanes to allow express buses to pass buses stopped at the station.

<span class="mw-page-title-main">Parkville station (Connecticut)</span>

Parkville is a bus rapid transit station on the CTfastrak line, located near the intersection of Park Street and Francis Avenue in Hartford, Connecticut. It opened with the line on March 28, 2015. The station consists of two side platforms serving the busway, with two center passing lanes to allow express buses to pass buses stopped at the station.

<span class="mw-page-title-main">Newington Junction station</span>

Newington Junction is a bus rapid transit station on the CTfastrak line opened in 2015 located off Willard Avenue (CT-173) in the Newington Junction neighborhood of Newington, Connecticut.

<span class="mw-page-title-main">Barnum station</span> Proposed Metro-North Railroad station in Connecticut

Barnum station is a planned regional rail station to be located on the Metro-North Railroad's New Haven Line in East Bridgeport, Connecticut. The station will be named after the circus showman and former Bridgeport mayor P. T. Barnum, and will be located on the south side of Barnum Avenue between Seaview Avenue and Pembroke Street. A feasibility study was released in July 2013, followed by preliminary planning funding in July 2014 and an application for planning funding in June 2015. By January 2017, the station was planned to open in 2021. However, the project was indefinitely postponed in January 2019.

References

  1. 1 2 "Despite Snow, Thousands of Riders, Many First-Timers, Experience CTfastrak on First Day of Service" (Press release). Connecticut Department of Transportation. 28 March 2015. Archived from the original on 11 September 2015.
  2. 1 2 3 Healey, Will (October 21, 2016). "Officials discuss development around rail center". Journal-Inquirer. Retrieved November 25, 2016.
  3. "Station Site Plans". Connecticut Department of Transportation. Archived from the original on January 18, 2015. Retrieved January 17, 2015.
  4. "Track 12: CT Passenger Stations, C-CH". Tyler City Station. Retrieved 17 January 2015.
  5. "Track 12: CT Passenger Stations, O-P". Tyler City Station. Retrieved 17 January 2015.
  6. Porter, Mikaela; Owens, David (June 17, 2018). "Thousands Take A Free Ride On Hartford Line's Inaugural Run". Hartford Courant. Retrieved June 17, 2018.
  7. "Hartford Union Station". Hartford Line. Retrieved June 1, 2018.
  8. "Interactive Program Map". New Haven–Hartford–Springfield Rail Program. Retrieved June 1, 2018.
  9. CDM Smith. "Section 1.3: Station and Layover Site Concept Plans" (PDF). NEW HAVEN-HARTFORD-SPRINGFIELD LINE HIGH SPEED INTERCITY PASSENGER RAIL PROJECT ENVIRONMENTAL ASSESSMENT/ENVIRONMENTAL IMPACT EVALUATION: Volume II Concept Design Drawings and Environmental Resource Graphics. Connecticut Department of Transportation. pp. 36, 37. Retrieved 26 October 2015.
  10. "GOV. MALLOY, BOND COMMISSION APPROVE DESIGN OF RAIL STATIONS ON HARTFORD AND NEW HAVEN LINES" (Press release). State of Connecticut. 12 January 2015. Retrieved 26 October 2015.
  11. "CTDOT ANNOUNCES $50 MILLION IN ADDITIONAL FUNDING FOR NHHS RAIL PROGRAM" (Press release). Connecticut Department of Transportation. February 20, 2017.
  12. "Design Continues for New Hartford Line Stations" (PDF). New Haven-Hartford Springfield Rail Program Newsletter. Connecticut Department of Transportation. Summer 2017. p. 3.

Commons-logo.svg Media related to Flatbush Avenue station (Connecticut) at Wikimedia Commons