Franki piling system

Last updated
A Franki pile Frankipilingprocess1.png
A Franki pile

The Franki piling system (also called pressure-injected footing) is a method used to drive expanded base cast-in-situ concrete (Franki) piles. [1] It was developed by Belgian Engineer Edgard Frankignoul in 1909. [2]

Contents

This method can be applied to different site conditions and is still widely used [2] [3] [4] due to its high tensile load capacity, and relatively low noise and ground vibration levels. [3]

History

Edgard Frankignoul applied for the production patent for the Franki pile in July 1909. He then co-founded the geotechnical company Frankipile (Société des Pieux Armés Frankignoul) with Liège aristocrat Edmond Baar with the goal of commercializing the Franki piling system. By 1929, the technique had been implemented by 34 international subsidiaries and license holders. [2]

The Franki pile process has undergone several reformations since it was conceived. The dry concrete plug was not introduced to the design until 1926. [2] Before this innovation, the casing had to be top-driven and equipped with a lost bottom plate. [1] The Franki pile with vibrated shaft and hydraulic vibrating hammer were manufactured starting from 1960 and 1971 respectively. [2]

Applications

Franki piles can be used as high-capacity deep foundation elements without the necessity of excavation or dewatering. [4] They are useful in conditions where a sufficient bearing soil can only be reached deeper in the ground, [5] [6] and are best suited to granular soil where bearing is primarily achieved from the densification of the soil around the base. [4] They are not recommended for use in cohesive soils where compaction of the base is not possible. [4] The Franki piling system is the quietest of the driven cast-in-place systems, and so is used in conditions where high noise levels could cause environmental problems. [3]

Installation of a Franki pile

  1. A charge of zero-slump concrete is poured into the bottom of a steel driving pipe that is placed vertically on the ground. A diesel-operated drop hammer is then driven on the concrete, forming a watertight concrete plug. [1] [4] [5] [6]
  2. The concrete plug is driven into the ground by the drop hammer. The pipe is also dragged into the ground due to friction developed between the steel and the concrete. [1] [4] [5] [6]
  3. When the desired depth is reached, the pipe is held in position by leads—structures which guide and align the pile and hammer. [7] The hammer is then applied to the concrete, driving it outwards through the bottom of the pile and forming a mushroom-shaped base. [1] [4] [5] [6]
  4. At this point, a cylindrical rebar cage can be driven into the concrete if supplementary reinforcement is desired. [1] [4] [5] [6]
  5. Additional charges of concrete are added and driven while the steel casing is simultaneously pulled up until the shaft of the pile is formed. [1] [4] [5] [6]

Variations

Related Research Articles

<span class="mw-page-title-main">Geotechnical engineering</span> Scientific study of earth materials in engineering problems

Geotechnical engineering is the branch of civil engineering concerned with the engineering behavior of earth materials. It uses the principles of soil mechanics and rock mechanics for the solution of its respective engineering problems. It also relies on knowledge of geology, hydrology, geophysics, and other related sciences. Geotechnical (rock) engineering is a subdiscipline of geological engineering.

<span class="mw-page-title-main">Foundation (engineering)</span> Lowest and supporting layer of a structure

In engineering, a foundation is the element of a structure which connects it to the ground, transferring loads from the structure to the ground. Foundations are generally considered either shallow or deep. Foundation engineering is the application of soil mechanics and rock mechanics in the design of foundation elements of structures.

In construction or renovation, underpinning is the process of strengthening the foundation of an existing building or other structure. Underpinning may be necessary for a variety of reasons:

<span class="mw-page-title-main">Caisson (engineering)</span> Rigid structure to provide workers with a dry working environment below water level

In geotechnical engineering, a caisson is a watertight retaining structure used, for example, to work on the foundations of a bridge pier, for the construction of a concrete dam, or for the repair of ships. Caissons are constructed in such a way that the water can be pumped out, keeping the work environment dry. When piers are being built using an open caisson, and it is not practical to reach suitable soil, friction pilings may be driven to form a suitable sub-foundation. These piles are connected by a foundation pad upon which the column pier is erected. Caisson engineering has been used at least since the 18th century, and was notably used in the construction of the Brooklyn Bridge, which was completed in 1883.

<span class="mw-page-title-main">Pile driver</span> Heavy equipment

A pile driver is a heavy-duty tool used to drive piles into soil to build piers, bridges, cofferdams, and other "pole" supported structures, and patterns of pilings as part of permanent deep foundations for buildings or other structures. Pilings may be made of wood, solid steel, or tubular steel, and may be driven entirely underwater/underground, or remain partially aboveground as elements of a finished structure.

<span class="mw-page-title-main">Deep foundation</span> Type of foundation

A deep foundation is a type of foundation that transfers building loads to the earth farther down from the surface than a shallow foundation does to a subsurface layer or a range of depths. A pile or piling is a vertical structural element of a deep foundation, driven or drilled deep into the ground at the building site.

A pile is a slender element cast in the ground or driven into it. Since pile construction as well as the final product are mostly invisible, engineers have often questioned their integrity, i.e. their compliance with project drawings and specifications. In fact, experience has shown that in piles, of all kinds flaws may occur. The purpose of integrity testing is to discover such flaws before they can cause any damage.

Dynamic load testing is a method to assess a pile's bearing capacity by applying a dynamic load to the pile head while recording acceleration and strain on the pile head. Dynamic load testing is a high strain dynamic test which can be applied after pile installation for concrete piles. For steel or timber piles, dynamic load testing can be done during installation or after installation.

High strain dynamic testing is a method of testing deep foundations to obtain information about their capacity and integrity, and in some cases, to monitor their installation. It is codified by ASTM D4945-12 - Standard Test Method for High-Strain Dynamic Testing of Piles.

<span class="mw-page-title-main">Pile bridge</span> Type of bridge

A pile bridge is a structure that uses foundations consisting of long poles, which are made of wood, concrete or steel and which are hammered into the soft soils beneath the bridge until the end of the pile reaches a hard layer of compacted soil or rock. Piles in such cases are hammered to a depth where the grip or friction of the pile and the soil surrounding it will support the load of the bridge deck. Bridging solely using the pile method is a rare occurrence today.

<span class="mw-page-title-main">Tieback (geotechnical)</span>

A tieback is a structural element installed in soil or rock to transfer applied tensile load into the ground. Typically in the form of a horizontal wire or rod, or a helical anchor, a tieback is commonly used along with other retaining systems to provide additional stability to cantilevered retaining walls. With one end of the tieback secured to the wall, the other end is anchored to a stable structure, such as a concrete deadman which has been driven into the ground or anchored into earth with sufficient resistance. The tieback-deadman structure resists forces that would otherwise cause the wall to lean, as for example, when a seawall is pushed seaward by water trapped on the landward side after a heavy rain.

<span class="mw-page-title-main">Tremie</span> Equipment for underwater concrete placement

A tremie is a watertight pipe, usually of about 250 mm inside diameter, with a conical hopper at its upper end above the water level. It may have a loose plug or a valve at the bottom end. A tremie is used to pour concrete underwater in a way that avoids washout of cement from the mix due to turbulent water contact with the concrete while it is flowing. This produces a more reliable strength of the product. Common applications include the following.

<span class="mw-page-title-main">Pile cap</span>

A pile cap is a thick concrete mat that rests on concrete or timber piles that have been driven into soft or unstable ground to provide a suitable stable foundation. It usually forms part of the deep foundation of a building, typically a multi-story building, structure or support base for heavy equipment, or of a bridge. The cast concrete pile cap distributes the load of the building into the piles. A similar structure to a pile cap is a "raft", which is a concrete foundation floor resting directly onto soft soil which may be liable to subsidence.

<span class="mw-page-title-main">Well</span> Excavation or structure to provide access to groundwater

A well is an excavation or structure created in the ground by digging, driving, or drilling to access liquid resources, usually water. The oldest and most common kind of well is a water well, to access groundwater in underground aquifers. The well water is drawn up by a pump, or using containers, such as buckets or large water bags that are raised mechanically or by hand. Water can also be injected back into the aquifer through the well. Wells were first constructed at least eight thousand years ago and historically vary in construction from a simple scoop in the sediment of a dry watercourse to the qanats of Iran, and the stepwells and sakiehs of India. Placing a lining in the well shaft helps create stability, and linings of wood or wickerwork date back at least as far as the Iron Age.

<span class="mw-page-title-main">Conductor pipe</span>

A conductor Pipe is a large diameter pipe that is set into the ground to provide the initial stable structural foundation for a borehole or oil well. The Conductor pipe is the first string of casing and is the largest diameter casing to be installed in a well. It can also be referred to as a drive pipe because it is often driven into the ground with a pile driver.

The Statnamic load test is a type of test for assessing the load-carrying capacity of deep foundations which is faster and less expensive than the static load test. The Statnamic test was conceived in 1985, with the first prototype tests carried out in 1988 through collaboration between Berminghammer Foundation Equipment of Canada and TNO Building Research of the Netherlands. Guidance on rapid load pile testing can be found in: Methods for Axial Compressive Force Pulse (Rapid) Testing of Deep Foundations. Sanken D7383 - 08 Standard Test.

<span class="mw-page-title-main">Steam hammer</span> Power hammer

A steam hammer, also called a drop hammer, is an industrial power hammer driven by steam that is used for tasks such as shaping forgings and driving piles. Typically the hammer is attached to a piston that slides within a fixed cylinder, but in some designs the hammer is attached to a cylinder that slides along a fixed piston.

<span class="mw-page-title-main">Screw piles</span> Construction component used for foundations

Screw piles, sometimes referred to as screw-piles, screw piers, screw anchors, screw foundations, ground screws, helical piles, helical piers, or helical anchors are a steel screw-in piling and ground anchoring system used for building deep foundations. Screw piles are typically manufactured from high-strength steel using varying sizes of tubular hollow sections for the pile or anchors shaft.

<span class="mw-page-title-main">Offshore embedded anchors</span> Type of marine mooring component

Offshore embedded anchors are anchors that derive their holding capacity from the frictional, or bearing, resistance of the surrounding soil, as opposed to gravity anchors, which derive their holding capacity largely from their weight. As offshore developments move into deeper waters, gravity-based structures become less economical due to the large size needed and the consequent cost of transportation.

<span class="mw-page-title-main">Olivier pile</span>

An Olivier pile is a drilled displacement pile:. This is an underground deep foundation pile made of concrete or reinforced concrete with a screw-shaped shaft which is performed without soil removal.

References

  1. 1 2 3 4 5 6 7 8 Franki Pile Archived 2011-07-11 at the Wayback Machine GRV AB, Retrieved November 22, 2010
  2. 1 2 3 4 5 History Franki Foundations Group Belgium, Retrieved December 7, 2010
  3. 1 2 3 4 5 Franki Piles Archived 2010-08-06 at the Wayback Machine Frankipile Australia, Retrieved December 8, 2010
  4. 1 2 3 4 5 6 7 8 9 Shamsher Prakash, Hari D. Sharma (1990). Pile foundations in Engineering Practice, p. 60. Wiley-Interscience ISBN   0-471-61653-2.
  5. 1 2 3 4 5 6 7 FRANKIPILE FRANKI Grundbau, Retrieved December 7, 2010
  6. 1 2 3 4 5 6 7 Dr. B.C. Punmia, Ashok Kumar Jain, B.C. Punmia, Arun Kr. Jain (2005). Soil Mechanics and Foundations, p. 763. Laxmi Publications (P) Ltd. ISBN   81-7008-081-9.
  7. piledrivers.org PDF, Land Based Rigs