Juba Nile Bridge

Last updated
Juba Nile Bridge
Sudan Juba bridge.jpg
steel bridge over white Nile
Coordinates 4°49′23″N31°36′31″E / 4.8230°N 31.6086°E / 4.8230; 31.6086
Carries Juba-Nimule Road
Crosses Nile River
Locale Juba, Jubek State
Location
Juba Nile Bridge

The Juba Nile Bridge is composed of two adjacent 252 meter spans over the White Nile in Juba, South Sudan, on the Juba-Nimule Road, and until 2022 provided the only access over the River Nile to South Sudan. It was built in 1972 during the regime of General Gaafar Nimeiry, from two World War II era bridges and it cost $2.5 million at the time. It was re-opened in January 2012 after major repair works following an accident in 2010 which left one lane of the bridge unusable for heavy vehicles. A new bridge, the Freedom Bridge, costing over 92 million dollar , was opened in 2022 a small distance upstream.

History

The original Nile bridge crossing at Juba was built in 1974 by the Dutch construction company De Groot International under a United Nations programme. [1] The United Nations High Commissioner for Refugees paid about one million dollar. The total cost of the bridge was 2.5 million. The Dutch government put up the remaining 1.5 million. [2] On 15 March 1974 it was opened by general Gaafar Nimeiry. Up until that time an irregular ferry service was the only way to cross the Nile river for hundreds of miles. After the Sudan civil war the United Nations Commissioner For Refugees asked for help from the Dutch government. The "Rijkswaterstaat Directie Bruggen" was asked to design a bridge and they came up with a practical design using World War II-era Bailey bridge material. The design for the bridge with six 43 meter spans also included walkways to the left and right, five pillars driven into the granite substrate, the landends and the road leading up to the bridge. More than 600 tons of steel, parts of a floating crane, a drilling rig and a bulldozer and a complete field kitchen and medical unit were transported to the site. The materials were shipped around the Cape and driven into Sudan from neighbouring Kenya. From the first order until the transport leaving the port of Rotterdam took 7 weeks, the transport took 10 weeks, and the total construction time on site was 14 weeks. One reason this tight schedule was a success was the setting up of a sober "campsite" where the 18 Dutch construction workers lived, working closely with locals to get the job done.

Following the collapse of one of the bridges due to hostilities, two replacement 252-metre Mabey Compact 200 bridges were installed in 2006. In 2010, one of these two Juba Nile Bridges was damaged, leaving it completely unusable for heavy vehicles. The bridges provided the only access over the Nile into much of South Sudan, since most goods and foodstuffs imported from Kenya and Uganda passed over the Juba-Nimule Road.

As of result of South Sudan's becoming an independent nation in 2011, newly elected president Salva Kiir made the repair of the Juba Nile Bridges one of his government's priorities during the administration's first 100 days. Funding for the repair was provided by the United States Agency for International Development (USAID) under the Accelerated Infrastructure Program, a cooperative agreement with the United Nations Office for Project Services (UNOPS). [3] A new bridge, the Freedom Bridge has been constructed by a Japanese company and after several delays and was opened in 2022. [4]

A local construction firm started the repair works in December 2010, fully reopening the bridge in mid-January 2012, ahead of the scheduled February completion date.

In October 2021 a new repair effort was made to ease travel to Juba. [5]

Related Research Articles

<span class="mw-page-title-main">Transport in Sudan</span>

Transport in Sudan during the early 1990s included an extensive railroad system that served the more important populated areas except in the far south, a meager road network, a natural inland waterway—the Nile River and its tributaries—and a national airline that provided both international and domestic service. Complementing this infrastructure was Port Sudan, a major deep-water port on the Red Sea, and a small but modern national merchant marine. Additionally, a pipeline transporting petroleum products extended from the port to Khartoum.

<span class="mw-page-title-main">Equatoria</span> Region in South Sudan

Equatoria is the southernmost region of South Sudan, along the upper reaches of the White Nile and the border between South Sudan and Uganda. Juba, the national capital and the largest city in South Sudan, is located in Equatoria. Originally a province of Anglo-Egyptian Sudan, it also contained most of northern parts of present-day Uganda, including Lake Albert and West Nile. It was an idealistic effort to create a model state in the interior of Africa that never consisted of more than a handful of adventurers and soldiers in isolated outposts.

<span class="mw-page-title-main">Gaafar Nimeiry</span> President of Sudan from 1969 to 1985

Gaafar Muhammad an-Nimeiry was a Sudanese military officer and politician who served as the fourth head of state of Sudan from 1969 to 1985, first as Chairman of the National Revolutionary Command Council and then as President.

<span class="mw-page-title-main">Juba</span> Capital and largest city of South Sudan

Juba is the capital and largest city of South Sudan. The city is situated on the White Nile and also serves as the capital of the Central Equatoria State. It is the most recently declared national capital and had a population of 525,953 in 2017. It has an area of 52 km2 (20 sq mi), with the metropolitan area covering 336 km2 (130 sq mi).

<span class="mw-page-title-main">Louis Berger Group</span> Engineering consulting company

Louis Berger is a full-service engineering, architecture, planning, environmental, program and construction management and economic development firm based in Morristown, New Jersey. Founded in 1953 in Harrisburg, Pennsylvania by Dr. Louis Berger, the firm employed nearly 6,000 employees in more than 50 countries worldwide. The company was acquired by WSP Global in 2018.

<span class="mw-page-title-main">Magwi County</span> County in Equatoria, South Sudan

Magwi County, also Magwe County, is a county in Eastern Equatoria, South Sudan.

<span class="mw-page-title-main">Abel Alier</span> South Sudanese politician and judge (born 1933)

Abel Alier Kwai is a South Sudanese politician and judge who served as First Vice President of Sudan between 1971 and 1982 and as President of the High Executive Council of the Southern Sudan Autonomous Region between 1972 and 1978. Abel Alier was a politician who managed to complete his college education among many Southern Sudanese. He is an internationally respected judge, human-rights lawyer and activist on behalf of Christians in the Sudan. Former Vice President of Sudan (1971–1982), he served as the first president of the High Executive Council of Southern Sudan. He sits on the Permanent Court of International Arbitration in The Hague and is recognized as Sudan's most prominent Christian lawyer. His latest book is Southern Sudan: Too Many Agreements Dishonoured.

Nimule is a city in the southern part of South Sudan in Magwi County, Eastern Equatoria. It lies approximately 197 kilometres (122 mi), by road, southeast of Juba, the capital of South Sudan and largest city in the country. The town also lies approximately 120 kilometres (75 mi), by road, north of Gulu, Uganda, the nearest large city.

<span class="mw-page-title-main">Railway stations in Sudan</span>

Railway stations in Sudan include:

Railway stations in Uganda include:

<span class="mw-page-title-main">Rail transport in Sudan</span>

Sudan has 4,725 kilometers of narrow-gauge, single-track railways. The main line runs from Wadi Halfa on the Egyptian border to Khartoum and southwest to El-Obeid via Sennar and Kosti, with extensions to Nyala in Southern Darfur and Wau in Western Bahr al Ghazal, South Sudan. Other lines connect Atbara and Sennar with Port Sudan, and Sennar with Ad-Damazin. A 1,400-kilometer line serves the Al Jazirah cotton-growing region. There are plans to rehabilitate rail transport to reverse decades of neglect and declining efficiency. Service on some lines may be interrupted during the rainy season.

Gulu–Nimule Road is a road in the Northern Region of Uganda, connecting the city of Gulu in Gulu District and the town of Nimule in Eastern Equatoria State in South Sudan, just north of the international border between the two countries. The road, known as Highway A104 in Uganda, continues into South Sudan as Highway A43.

<span class="mw-page-title-main">India–Sudan relations</span> Bilateral relations

India–Sudan relations, also called Indian-Sudanese relations or Indo-Sudanese relations, refers to the international relations that exists between India and Sudan.

<span class="mw-page-title-main">Rail transport in South Sudan</span>

South Sudan does not have an extensive rail system. The current rail infrastructure, which was constructed between 1959–1962, and was left over from the previous Sudan government, is in a serious state of disrepair. It consists of a 248 kilometers (154 mi) narrow-gauge, single-track line that connects Babonosa (Sudan) with the city of Wau in South Sudan. The line was left in poor condition after the Second Sudanese Civil War after several parts of it were mined; the line was fully rehabilitated with United Nations funds.

The Juba–Nimule Road is a road in South Sudan connecting the capital city of Juba in the Eastern Equatoria and the town of Nimule in Magwi County.

The Freedom Bridge in Juba, South Sudan, is South Sudan's second permanent bridge over the Nile, the first being the Juba Nile Bridge, a Bailey type bridge built in 1976. The new bridge was officially opened on 19 May 2022.

<span class="mw-page-title-main">Greeks in South Sudan</span> Ethnic group

The Greeks in South Sudan represent the Omogenia in what became the Republic of South Sudan in 2011. The population is tiny in number – estimated at around 90 – but historically played an important role and has some prominent members, especially First Lady Mary Ayen Mayardit.

The Karuma–Juba High Voltage Power Line is a planned high voltage electricity power line, connecting the high voltage substation at Karuma, in Kiryandongo District, in the Western Region of Uganda, to another high voltage substation at Juba, in Jubek State, in South Sudan.

References

  1. "Dutch Newspaper Article". Digibron. Retrieved 1 January 2022.
  2. "Netherlands Gov". netherlandsandyou. Retrieved 1 January 2022.
  3. "Repaired Nile bridge improves access to South Sudan capital". UNOPS. Retrieved 12 December 2017.
  4. "Juba Bridge". Afro Tourism. Retrieved 12 December 2017.
  5. "Juba Bridge Repair 2021" . Retrieved 1 January 2022.