Mount Coffee Hydropower Project

Last updated
Mount Coffee Hydropower Project
LocationWhite Plains, Montserrado County, Liberia
Coordinates 6°30′17″N10°38′54″W / 6.50472°N 10.64833°W / 6.50472; -10.64833 Coordinates: 6°30′17″N10°38′54″W / 6.50472°N 10.64833°W / 6.50472; -10.64833
Opening date1966
Operator(s)Liberia Electricity Corporation
Dam and spillways
Impounds Saint Paul River

The Mount Coffee Hydropower Project is a hydroelectric project in the West African nation of Liberia on the Saint Paul River. Built in 1966 with additional phases completed later, the project has a maximum generating capacity of 88 MW. [1] The Walter F. Walker Hydro Dam and generating facilities were extensively damaged during the First Liberian Civil War in 1990 and functioning was not restored until 2018. [2] [1]

Contents

History

In 1963, the Liberian government received a loan from the World Bank to develop a US$24.3 million hydro electric project. [3] Construction of the facility began in 1964 by the Monrovia Power Authority using Raymond Concrete Pile Company as the contractor and Stanley Consultants as the project managers. [3] In 1966, the power company completed the initial phase of the dam and began generating electricity. [4] The project was finished in 1967 and named the T. J. R. Faulkner W.F. Walker Hydroelectric Power Station. [3]

Initial generating capacity was 30 MW produced by two turbines, which was increased to 64 MW when two more turbines were added in 1973. [4] The Monrovia Power Authority became the Liberia Electricity Corporation on July 12, 1973. [3] In June 1990, the government announced plans to more than double the electricity generating capacity of the project and adding a reservoir to allow more generation during the dry season. [5] The plans called for a new 4,000 feet (1,200 m) dam to be built upriver on the Via River to provide storage capacity, while two 52 MW turbines would be added at the existing power generating plant. [5] The US$300 million expansion was never begun due to the Civil War. [5]

In July 1990, rebel forces under the command of Charles Taylor seized the dam and shut off power and water to Monrovia. [6] [7] During this First Civil War, the project's intake dam was destroyed on one end while the rest received other damage. [8] Other parts of the facilities were looted and destroyed in later years of the conflict. [8] Beginning in early 2005, proposals were made to repair the facility and restore power, [9] including a proposal by China. [10]

The United States Trade and Development Agency gave $400,000 to Liberia in February 2007 to study rebuilding and expanding the project. [11] The study showed no structural damage to the dam, [12] but that most of the project's facilities would need to be rebuilt at a cost of US$383 million. [13] As of August 2008, the Liberian government was considering privatization of the project for a fixed number of years as the nation did not have the resources to fund the repair. [13]

In May 2012, the Mt. Coffee Hydropower Rehabilitation Project was initiated with a series of surveying and engineering assessments of the feasibility of revitalizing the plant. [14] This work culminated with the signing of a contract in April 2013 with a Norwegian company (Norplan AS) and a German company (Fichtner GmbH) to revitalize the defunct power-plant by 2015. [14]

In December 2016, the first hydropower turbine and generator unit, with an installed capacity of 22 megawatts (MW), was officially dedicated and commissioned. The project, completed in 2018, raised the total installed capacity of the Mt. Coffee Hydropower Plant to 88 MW (four generating units of 22 MW each). [15] [1] The Mount Coffee Hydro Electric Dam is located in Mount Coffee, township of Harrisburg. White Plains is the site of the water filtration plant.

Details

Located in the Harrisburg Township of Careysburg District, Montserrado County, it lies on the Saint Paul River approximately 21 miles from Monrovia. [4] [16] The dam is a run-of the river style dam, in that there is no reservoir. [4] Due to the lack of a reservoir, the dependable generating capacity is only 10 MW, as that is the normal flow of the river during the dry season. [4] Prior to the First Liberian Civil War the plant produced 64MW of electricity, which accounted for 35% of all electricity generated in the nation. [17] In addition to electricity, the Liberia Water and Sewer Corporation used the project to provide drinking water to Monrovia and surrounding areas before the war. [16]

Related Research Articles

Small hydro Hydroelectric project at the local level with a few MW production

Small hydro is the development of hydroelectric power on a scale suitable for local community and industry, or to contribute to distributed generation in a regional electricity grid. Exact definitions vary, but a "small hydro" project is less than 50 megawatts (MW), and can be further subdivide by scale into "mini" (<1MW), "micro" (<100 kW), "pico" (<10 kW). In contrast many hydroelectric projects are of enormous size, such as the generating plant at the Three Gorges Dam at 22,500 megawatts or the vast multiple projects of the Tennessee Valley Authority.

Pumped-storage hydroelectricity Type of electric energy storage system using two reservoirs of water connected with a pump and a turbine

Pumped-storage hydroelectricity (PSH), or pumped hydroelectric energy storage (PHES), is a type of hydroelectric energy storage used by electric power systems for load balancing. The method stores energy in the form of gravitational potential energy of water, pumped from a lower elevation reservoir to a higher elevation. Low-cost surplus off-peak electric power is typically used to run the pumps. During periods of high electrical demand, the stored water is released through turbines to produce electric power. Although the losses of the pumping process make the plant a net consumer of energy overall, the system increases revenue by selling more electricity during periods of peak demand, when electricity prices are highest. If the upper lake collects significant rainfall or is fed by a river then the plant may be a net energy producer in the manner of a traditional hydroelectric plant.

Hydroelectricity Electricity generated by hydropower

Hydroelectricity, or hydroelectric power, is electricity produced from hydropower. In 2015, hydropower generated 16.6% of the world's total electricity and 70% of all renewable electricity, and was expected to increase by about 3.1% each year for the next 25 years.

Dams and reservoirs in Laos

Dams and reservoirs in Laos are the cornerstone of the Lao government's goal of becoming the "battery of Asia".

Robert Moses Niagara Power Plant Niagara River dam in New York State

The Robert Moses Niagara Hydroelectric Power Station is a hydroelectric power station in Lewiston, New York, near Niagara Falls. Owned and operated by the New York Power Authority (NYPA), the plant diverts water from the Niagara River above Niagara Falls and returns the water into the lower portion of the river near Lake Ontario. It uses 13 generators at an installed capacity of 2,525 MW (3,386,000 hp).

Run-of-the-river hydroelectricity

Run-of-river hydroelectricity (ROR) or run-of-the-river hydroelectricity is a type of hydroelectric generation plant whereby little or no water storage is provided. Run-of-the-river power plants may have no water storage at all or a limited amount of storage, in which case the storage reservoir is referred to as pondage. A plant without pondage is subject to seasonal river flows, thus the plant will operate as an intermittent energy source. Conventional hydro uses reservoirs, which regulate water for flood control, dispatchable electrical power, and the provision of fresh water for agriculture.

Bicaz-Stejaru Hydroelectric Power Station Dam in Bicaz, Neamț County, Romania

Dimitrie Leonida (Stejaru) Hydro Power Plant is a hydropower development on the Bistrița River, near Bicaz, Romania.

According to the International Hydropower Association, Canada is the world's fourth largest producer of hydroelectricity in the world in 2021 after the United States, Brazil, and China. In 2014, Canada consumed the equivalent of 85.7 megatonnes worth of oil of hydroelectricity, 9.8% of worldwide hydroelectric consumption. Furthermore, hydroelectricity accounted for 25.7% of Canada's total energy consumption. It is the third-most consumed energy in Canada behind oil and natural gas.

Hydroelectric power in the United States is, as of 2019, the second-largest renewable source of energy in both generation and nominal capacity. In 2019, hydroelectric power produced 38% of the total renewable electricity, and 6.6% of the total U.S. electricity.

Hòa Bình Dam Dam in Hòa Bình

The Hòa Bình Dam on the Black River is the largest hydroelectric dam in Vietnam from 1994 to 2012, and one of the largest in Southeast Asia, with a generating capacity of 1,920 MW. The Sông Đà Reservoir, with a capacity of 9 billion m³ was formed as the river was dammed.

Isimba Hydroelectric Power Station Ugandan power station

Isimba Hydroelectric Power Station is a 183.2 megawatts (245,700 hp) hydroelectric power station commissioned on 21 March 2019 in Uganda. Construction of this dam began in April 2015 and was completed in January 2019. Commercial operations began on 21 March 2019.

Koyna Hydroelectric Project

The Koyna Hydroelectric Project is the second largest hydroelectric power plant in India, just after Tehri Dam Project. It is a complex project with four dams including the largest dam on the Koyna River, Maharashtra hence the name Koyna Hydroelectric Project. The project site is in Satara district.

Denis-Perron dam Dam in Sept-Rivières Regional County Municipality, Québec

Denis-Perron dam is a rockfill embankment dam spanning the Sainte-Marguerite River, a tributary of the lower Saint Lawrence River, in eastern Quebec, Canada. Standing 171 metres (561 ft) high and 378 metres (1,240 ft) long, the dam is the primary component of Hydro-Québec's Sainte-Marguerite 3 hydroelectric project. The dam is the second highest in Quebec and the hydraulic head afforded to its power plant is also the largest in the province.

Çetin Dam Dam in Pervari and Şirvan discticts, Siirt Province

The Çetin Dam hydropower dam, currently being constructed on the Botan River in Siirt Province, Turkey, with an installed capacity of 420 MW. It is expected to complete by 2020.

Duber Khwar Hydroelectric Plant Dam in Pattan, Kohistan, KPK, Pakistan

Duber Khwar Hydropower Plant is located near the town of Pattan in Kohistan, Khyber Pakhtunkhwa, Pakistan on the Duber Khwar River, a right bank tributary of Indus River. It is approximately 300 km NW from Islamabad, the federal capital of Islamic Republic of Pakistan.

Thailand has set targets and policies for the development of its energy sector for 2035, with priority being given to indigenous renewable energy resources, including hydropower.

Kulekhani Reservoir Dam in Kulekhani, Makwanpur District, Narayani Zone

The Kulekhani Dam is a rock-fill dam on the Kulekhani River near Kulekhani in Makwanpur District of Narayani Zone, Nepal. The primary purpose of the dam is hydroelectric power generation and it supports the 60 MW Kulekhani I and 32 MW Kulekhani II Hydropower Stations. Construction began in 1977 and Kulekhani I was commissioned in 1982. Kulekhani II was commissioned in 1986 and a third power station, the 14 MW Kulekhani III was expected to be commissioned in May 2015 but was delayed due to issues with the builder. The US$117.84 million project received funding from the World Bank, Kuwait Fund, UNDP, Overseas Economic Cooperation Fund and OPEC Fund. It is owned by Nepal Electricity Authority.

Dzoraget Hydroelectric Power Station Dam in Lori Region, Dzoraget Village, Armenia

The Dzoraget Hydroelectric Power Station is situated in Dzoraget village, Lori Region, Armenia. The plant is located on the coast of Debed River, but it uses the flows of the waters of Dzoraget River. Construction of the Dzoraget HPP started in 1927 and it was launched on 15 November 1932 with the full installed capacity of 22.32 MW. As of 1980, the plant uses three generators with an installed capacity of 26.2 MW. The Dzoraget Hydro Power Plant is considered to be small size power plant. There is a little water storage behind the weir, as Dzoraget HPP is a run-of-the-river plant.

Tapovan Vishnugad Hydropower Plant Dam in Chamoli District, Uttarakhand

The Tapovan Vishnugad Hydropower Plant is a 520 MW run-of-river hydroelectric project being constructed on Dhauliganga River in Chamoli District of Uttarakhand, India. The plant is expected to generate over 2.5 TWh of electricity annually.

References

  1. 1 2 3 Jonathan Nash (July 23, 2018). "Success of Mount Coffee Hydropower Plant Helps Liberia Shine Brighter". Millennium Challenge Corporation blog.
  2. The Analyst (January 4, 2005). "Liberia;Liberian Engineer Presents Project For Hydro Dam Construction, But Faces Stone Wall". Africa News.
  3. 1 2 3 4 "History". Liberia Electricity Corporation. Archived from the original on 2009-02-10. Retrieved 2008-10-26.
  4. 1 2 3 4 5 First State of the Environment Report for Liberia – 2006. Archived 2009-04-11 at the Wayback Machine United Nations Development Programme. 2006, p. 4445. Retrieved on October 19, 2008.
  5. 1 2 3 "Liberia expands hydropower", Engineering News-Record, June 7, 1990. McGraw-Hill, Inc., Vol. 224, No. 23; p. 27.
  6. Huband, Mark. "Retreating Liberian rebel leader urges peace talks" United Press International, October 7, 1990.
  7. "Worldwide: Liberia blackout", The Independent , July 1, 1990, Foreign News Page, p. 14.
  8. 1 2 Desk Study on the Environment in Liberia. United Nations Environment Programme. 2004, p. 30. Retrieved on October 19, 2008.
  9. The Analyst. "Liberia; Liberian Engineer Presents Project For Hydro Dam Construction, But Faces Stone Wall", Africa News, January 4, 2005.
  10. "Weekly Recap", Power, Finance and Risk, March 25, 2005.
  11. Liberia's Post-War Recovery: Key Issues and Developments. Congressional Research Service. Retrieved on October 19, 2008.
  12. Wrokpoh, Patrick K. (February 25, 2008). "No structural damage done to hydro". The Inquirer.
  13. 1 2 STAR Radio (August 22, 2008). "Liberia needs about 383m dollars to rebuild hydroelectric plant". BBC Monitoring International Reports. Global News Wire.
  14. 1 2 "LEC Signs Consulting Services Agreement with Norplan/Fichtner for Mt. Coffee Owner's Engineer". Press and News. Mt Coffee PIU. April 24, 2013. Retrieved 24 September 2013.
  15. http://mtcoffeeliberia.com/?p=1878 [ dead link ]
  16. 1 2 "Montserrado County Development Agenda" (PDF). Republic of Liberia. 2008. Retrieved 2008-10-14.
  17. Restoring the Battered and Broken Environment of Liberia One of the Keys to a New and Sustainable Future. United Nations Environment Programme. Retrieved on October 19, 2008.