Murman in Rostock in 2021 | |
Class overview | |
---|---|
Builders | |
Operators | Rosmorrechflot Marine Rescue Service [1] [2] [3] |
Built | 2010–present |
In service | 2015–present |
Planned | 5 |
Building | 3 |
Completed | 2 |
General characteristics | |
Type | Icebreaker, salvage ship |
Displacement | 5,000–6,000 t (4,900–5,900 long tons) |
Length | 85–87 m (279–285 ft) |
Beam | 18–19 m (59–62 ft) |
Draft | 6–6.5 m (20–21 ft) |
Ice class | RS Icebreaker6 |
Installed power | Four diesel generators |
Propulsion |
|
Speed | 15 knots (28 km/h; 17 mph) |
Capacity |
|
Crew |
|
Aviation facilities | Helideck for Kamov Ka-32 |
Project MPSV06 refers to a series of Russian icebreaking multipurpose salvage ships.
One vessel based on the original Project MPSV06 design, Kerchenskiy Proliv , has been under construction at Amur Shipbuilding Plant in Russia since 2010 and is expected to enter service in 2024. Two vessels based on a slightly modified Project MPSV06-NY design, Beringov Proliv and Murman, were built at Nordic Yards Wismar in Germany in 2015. Two further vessels based on a modernized Project MPSV06M design, Pevek and Anadyr, are under construction at Yantar Shipyard in Kaliningrad with delivery scheduled for 2024.
The federal programs Modernization of the transport system of Russia (2002–2010) and Development of the transport system of Russia (2010–2015) included the recapitalization of the Russian maritime emergency rescue fleet, much of which dated back to the Soviet times and was approaching the end of its service life, with 17 new vessels of various types. [4] 6.67 billion rubles of federal funding were allocated for the construction of four 7-megawatt icebreaking multipurpose rescue vessels. [5] The technical project referred to as MPSV06 was developed by Marine Engineering Bureau. [6]
The construction of the first Project MPSV06 vessel was awarded to the Russian shipyard Amur Shipbuilding Plant in December 2009 [7] and the keel of the vessel, tentatively named Spasatel Petr Gruzinskiy, [8] was laid on 21 July 2010. [9] However, construction of the 3.6 billion ruble icebreaker was later suspended due to serious deficiencies in the design documentation. [7] The construction was later resumed and in March 2019 the technical readiness of the vessel was about 40%. [10] By February 2020, Amur Shipbuilding Plant was reportedly "ahead of schedule" and the vessel, renamed Kerchenskiy Proliv , was launched on 30 October 2020. [11] On 29 September 2024, the vessel left Komsomolsk-on-Amur under tow with pontoons attached to its hull to reduce draught during the voyage along the Amur River. Kerchenskiy Proliv will be towed to Vladivostok for final outfitting, sea trials, and eventual delivery to the customer. [12]
On 19 December 2012, the German shipbuilder Nordic Yards based in Wismar was awarded a 150 million euro contract for the construction of the two further Project MPSV06 icebreaking multipurpose salvage ships. [13] [14] Due to modifications to the original design, the German-built vessels are referred to as separate subclass, MPSV06-NY. [15] The vessels were launched together on 21 September 2014. [16] The lead ship, Beringov Proliv , was delivered by the shipyard on 10 October 2015 [17] and the second vessel of the series, Murman, in late November. [18] The official commissioning ceremonies were held on both vessels in December. [19] [20]
The fourth icebreaking multipurpose salvage vessel included in the federal budget was built to a different design by the Russian-owned Arctech Helsinki Shipyard in Finland in 2014. [21] The vessel, Baltika, is a so-called oblique icebreaker which can break a channel wider than the vessel's beam with its asymmetric hull. [22]
One of the thirteen federal-scale national projects adopted by Russia for 2019–2024, Comprehensive plan for modernization and expansion of main infrastructure, included the expansion of the ice-strengthened rescue fleet to support the development of the Northern Sea Route. Among the 16 planned ships were three 7-megawatt icebreaking multipurpose rescue vessels. [21] [23]
In June 2021, the Kaliningrad-based Yantar Shipyard was awarded the construction of the first vessel based on a modernized design referred to as Project MPSV06M. [24] The construction of the second vessel with a contract price of 7.463 billion rubles was awarded to the same shipyard in November 2022. [25] As of December 2023 [update] , the vessels Pevek and Anadyr have been laid down with delivery initially scheduled for 2024. [26] [27] In May 2024, the delivery of Pevek was postponed to 2026. [28]
As of December 2023 [update] , the construction of the third planned vessel has not been awarded.
All three Project MPSV06 variants are similar in size with length overall of about 85–87 metres (279–285 ft), beam of about 18–19 metres (59–62 ft), draft of about 6–6.5 metres (20–21 ft), and displacement of about 5,000–6,000 tonnes (4,900–5,900 long tons). The general layout of the vessel includes a helideck for Kamov Ka-32 forward, deckhouse amidships, and an open working deck with two 32-tonne cranes, 80-tonne A-frame, and other equipment aft. The vessels have a crew of 26 as well as accommodation for 12 supernumeraries and capacity for 95 survivors. [6] [29] [27] [30]
The ships' fully-integrated diesel-electric power plant consists of four main diesel generators supplying power for both propulsion as well as service loads while underway. In the first three vessels, the main power plant consists of four 3,000-kilowatt (4,000 hp) six-cylinder Wärtsilä 6L32 medium-speed diesel engines. [31] [29] However, the international sanctions against Russia and the Finnish engine manufacturer's exit from the Russian market in 2022 means the same engines cannot be used in the modernized variants. [32]
For main propulsion, all MPSV06 variants are fitted with two 3,500-kilowatt (4,700 hp) electrically-driven azimuth thrusters. [6] Kerchenskiy Proliv was originally provided with Rolls-Royce (today Kongsberg Maritime) Z-drive thrusters which may have become unserviceable while the vessel's construction was suspended. [33] Beringov Proliv and Murman were fitted with ABB Azipod ICE 1400 units. [34] The propulsion equipment selected for Pevek and Anadyr has not been identified. For maneuvering in ports and for dynamic positioning, the vessels have transverse bow thrusters. [6]
All Project MPSV06 variants are strengthened to Russian Maritime Register of Shipping ice class Icebreaker6 which is intended for icebreaking operations in non-Arctic freezing seas where the ice is up to 1.5 metres (5 ft) thick. [6] The vessel's continuous icebreaking capability is 1.5–2 knots (2.8–3.7 km/h; 1.7–2.3 mph) in 1-metre (3.3 ft) level ice with 20–25 centimetres (7.9–9.8 in) snow cover. [30] In open water, the ships have a design speed of 15 knots (28 km/h; 17 mph) and economical speed of 11 knots (20 km/h; 13 mph). [6]
Name | Project | Builder | Yard number | IMO number | Keel laid | Launched | Delivered | Port of registry | Status | Image | Ref |
---|---|---|---|---|---|---|---|---|---|---|---|
| MPSV06 | Amur Shipbuilding Plant (Komsomolsk-on-Amur, Russia) | 360 | 9936082 | 21 July 2010 | 30 October 2020 | 2024 (current estimate) [35] | Vladivostok | Launched | [31] | |
Beringov Proliv | MPSV06-NY [15] | Nordic Yards Wismar (Wismar, Germany) | 217 | 9682411 | 12 November 2013 | 21 September 2014 | 10 October 2015 | Korsakov [2] | In service | [2] [29] [36] | |
Murman | MPSV06-NY [15] | Nordic Yards Wismar (Wismar, Germany) | 218 | 9682423 | 12 November 2013 | 21 September 2014 | 21 November 2015 | Murmansk | In service | [3] [37] [38] | |
Pevek | MPSV06M | Yantar Shipyard (Kaliningrad, Russia) | 24 March 2022 [26] | 2024 (initial) 2026 (current estimate) [28] | Under construction | ||||||
Anadyr | MPSV06M | Yantar Shipyard (Kaliningrad, Russia) | 24 May 2023 [27] | 2024 (planned) | Under construction |
A nuclear-powered icebreaker is an icebreaker with an onboard nuclear power plant that produces power for the vessel's propulsion system. Although more expensive to operate, nuclear-powered icebreakers provide a number of advantages over their diesel-powered counterparts, especially along the Northern Sea Route where heavy power demand associated with icebreaking, limited refueling infrastructure along the Siberian coast, and endurance required make diesel-powered icebreaker operations challenging. As of 2023, Russia is the only country that builds and operates nuclear-powered icebreakers, having built a number of such vessels to aid shipping along the Northern Sea Route and Russian arctic outposts since the Soviet era.
The Krivak class, Soviet designation Project 1135 Burevestnik, are a series of frigates and patrol ships built in the Soviet Union primarily for the Soviet Navy since 1970. Later some sub-branches, like the Nerey (Nereus) were designed for coastal patrol by the KGB Border Troops. Until 1977, the ships in the class were considered to be large anti-submarine warfare vessels.
The Zaliv Shipbuilding Yard is located in Kerch, Crimea and specializes in the construction of tankers and container carriers, and the repair of ships of different types and tonnage.
The Ivan Gren class, Russian designation Project 11711, is a class of landing ship that is being built for the Russian Navy. The class was to be composed of two vessels, Ivan Gren and Pyotr Morgunov, but later it was announced that the Russian Navy intends to acquire several more vessels of a modified design.
A double acting ship is a type of icebreaking ship designed to travel forwards in open water and thin ice, but turn around and proceed astern (backwards) in heavy ice conditions. In this way, the ship can operate independently in severe ice conditions without icebreaker assistance but retain better open water performance than traditional icebreaking vessels.
Arctech Helsinki Shipyard was a Finnish shipbuilding company that focused primarily on icebreakers and other icegoing vessels for arctic conditions.
An oblique icebreaker is a special type of icebreaker designed to operate not only ahead and astern, but also obliquely (sideways) with a large angle of attack. In this way, a relatively small icebreaker is capable of opening a wide channel in ice for large merchant ships.
Viktor Chernomyrdin, also known through her Russian design number Project 22600 or type size series designation LK-25, is a Russian icebreaker. Launched at Baltic Shipyard and outfitted at Admiralty Shipyard in Saint Petersburg, she is the largest and most powerful diesel-electric icebreaker built in Russia.
Baltika is a Russian icebreaker built by Arctech Helsinki Shipyard in Helsinki, Finland. She is the first ship ever built with an asymmetric hull that allows her to operate not only ahead and astern, but also obliquely (sideways) with a large angle of attack. In this way, the relatively small oblique icebreaker is capable of opening a wide channel in ice for large merchant ships.
Polaris is a Finnish icebreaker. Built in 2016 by Arctech Helsinki Shipyard, she is the most powerful icebreaker ever to fly the Finnish flag and the first icebreaker in the world to feature dual-fuel engines capable of using both low-sulfur marine diesel oil (LSMDO) and liquefied natural gas (LNG). Polaris was initially ordered by the Finnish Transport Agency, but the ownership was transferred to the state-owned icebreaker operator Arctia after delivery.
Project 21900 icebreakers and their derivative designs are a series of Russian diesel-electric icebreakers built in the 2000s. They are also sometimes referred to using the type size series designation LK-16.
Novorossiysk is a Russian Project 21900M diesel-electric icebreaker. She was built by Vyborg Shipyard in Russia and delivered to Rosmorport in 2016.
RV Kronprins Haakon is a Norwegian icebreaking polar research vessel owned by the Norwegian Polar Institute. The shiptime use is divided between the main users, the University of Tromsø (50%), Norwegian Polar Institute (30%) and Norwegian Institute of Marine Research (20%). She was built at Fincantieri shipyard in Genova, Italy, and delivered in 2018.
Yantar Shipyard is a Russian shipbuilding company based in Kaliningrad, Russia.
Yantar (Янтарь) is a special purpose intelligence collection ship built for the Russian Navy. The ship has been operated by the Russian Navy's Main Directorate of Underwater Research (GUGI) since 2015 and is reportedly a spy ship. The vessel's home port is Severomorsk, where it is attached to the Northern Fleet. It is the lead ship of its class, with two sister ships. Almaz was launched in 2019 and was intended to serve with the Pacific Fleet, and Burilichev was laid down in 2021.
The Vanino–Kholmsk train ferry is the ferry connection across the Strait of Tartary in Russia that connects Vanino in Khabarovsk Krai and Kholmsk in Sakhalin Oblast. This ferry connects Sakhalin Island with mainland Russia and its distance is 260 km. It is operated by Sakhalin Shipping Company.
Sibir is a Russian Project 22220 nuclear-powered icebreaker. Built by Baltic Shipyard in Saint Petersburg, the vessel was laid down in 2015, launched in 2017, and delivered in December 2021.
Dikson is a Russian icebreaker and the final vessel in a series of three subarctic icebreakers built at Wärtsilä Helsinki shipyard in Finland in 1982–1983. The vessel's sister ships are Mudyug and Magadan.
Project MPSV12 salvage ships are a series of Russian ice-strengthened multipurpose salvage ships. This class of vessels are bigger than Project MPSV07 salvage ships but smaller than the Project MPSV06 salvage ships. The first four vessels of this class were named after the Russian rivers Bakhtemir, Kalas, Beysug and Piltun.