Sunrise Powerlink

Last updated

Sunrise Powerlink
Location
CountryUnited States
StateCalifornia
General directionEast-West
From 32°43′12″N115°43′00″W / 32.7200°N 115.7166°W / 32.7200; -115.7166
To 32°55′02″N117°01′52″W / 32.9171°N 117.0311°W / 32.9171; -117.0311
Ownership information
OwnerSan Diego Gas and Electric
PartnersPacific Gas and Electric,
Southern California Edison
OperatorSan Diego Gas and Electric
Technical information
Total length119 km (74 mi)

Sunrise Powerlink is a high-voltage power transmission line by San Diego Gas & Electric (SDG&E) in San Diego County, California and Imperial County, California. [1] The project was approved by the United States Forest Service (USFS) in July 2010, the U.S. Bureau of Land Management (BLM) in January 2009 and the California Public Utilities Commission (CPUC) in December 2008. SDG&E stated that the 117-mile (188 km) long 230/500 kilovolt power line would bring 1000 megawatts of renewable energy from the Imperial Valley to San Diego County. The cost of the project was estimated to be $1.9 billion for construction. [2] [3] SDG&E, which was to receive a guaranteed profit of over $1.4 billion from the construction of the line, claimed that the power line was necessary to support future growth of the San Diego region, and its economic benefits to the region would measure on the order of $100 million per year. However, the project has been called one of the most controversial projects ever proposed.

Contents

Construction began in December 2010 [2] and the line was energized in June 2012. [4] In constructing the line, 30,000 helicopter flight hours were used. [5] [6]

Construction

In June 2012, major construction activities on the Sunrise Powerlink Project were completed. The line was energized on June 17, following a prolonged testing and completion phase.

The overhead portion of the Sunrise Powerlink is proceeded on schedule with the construction of towers and tower foundations in Eastern San Diego County and Imperial County.

Work is also progressed on the new Suncrest Substation, which is a critical facility for the project. Upgrades to the existing San Luis Rey, Encina and Imperial Valley substations were also completed.

The underground portion of the line through Alpine also progressed with the installation of vaults under Alpine Boulevard. The vaults allow for the installation of the 230-kilovolt electrical cable and provide access for maintenance of the cable connections. Workers have also installed cable, which is fed into a manhole and "pulled" by a special machine through underground conduits.

The USFS issued a Record of Decision on July 13, 2010 that allows for a 19-mile (31 km) segment of the line to be built through the Cleveland National Forest. [7]

The Interior Board of Land Appeals (IBLA) within the U.S. Department of the Interior issued a decision [8] on May 14, 2010 rejecting the appeal filed by Backcountry Against Dumps (BAD) and other East County organizations. BAD sought to reverse the BLM's approval of the line.

"Because Backcountry has failed to establish any error of law or fact in the Record of Decision, we will affirm BLM's decision to approve the granting of Rights-of-Way to SDG&E for an electrical transmission line and related activity for the Sunrise Powerlink Transmission Project," the ruling stated.

The IBLA concluded that the BLM decision was consistent with the National Environmental Policy Act and the National Historic Preservation Act.

On December 9, 2010 ground was broken in Boulevard, California to mark the start of construction on the project's first tower. California Governor Arnold Schwarzenegger was at the ground breaking ceremony, along with several other local government leaders. During the ceremony, Schwarzenegger said the Sunrise Powerlink project should serve as an example to the nation of how to build green infrastructure. "We are well on our way to be an example for the rest of the nation, especially when it comes to infrastructure," Schwarzenegger said. [2]

Key Documents

Final Project Modification Report: On May 14, 2010, SDG&E submitted the Final Project Modification Report (PMR) [9] to the CPUC and the BLM. The PMR fine-tunes the approved route and enhances the environmental preservation and protection components of the transmission line. These changes were made in order to minimize impacts to sensitive resources, accommodate landowners where possible and reduce engineering constraints. Highlights of the PMR include:

Final Environmental Impact Report/Environmental Impact Statement: The Sunrise Powerlink Final Environmental Impact Report/Environmental Impact Statement was filed on October 13, 2008. [10]

Key Regulatory Findings

The project has generated much controversy since its conception, primarily due to questions concerning whether the line is necessary. However, it has been approved by all three major regulatory agencies that have jurisdiction over the project: the CPUC, BLM and USFS. In its final decision, the CPUC voted 4-1 on Dec. 18, 2008 to approve that the Sunrise Powerlink. [11] Both the CPUC administrative law judge and the presiding commissioner assigned to the proceeding recommended against approval. [12] The federal Bureau of Land Management approved the project on January 20, 2009. [13]

Renewable Energy

SDG&E has stated that the line is intended to carry renewable energy generated by the sun, wind and geothermal sources. [14] In its 4-1 decision to approve the line, the CPUC stated that the Sunrise Powerlink will facilitate the development of Imperial Valley renewable energy projects capable of generating 1,900 megawatts of clean power. [15] The decision further stated that this renewable energy would likely remain unavailable to San Diego without a new, secure transmission line. [15] However, in a dissenting opinion, CPUC Commissioner Dian Grueneich stated that the application should be denied for the following reasons: (1) It is not needed to meet SDG&E's renewable portfolio standard (RPS)obligation of 20% by 2010;(2) Assuming a 20% RPS, it is not economic and will potentially generate significant ratepayer costs; (3) It will have many significant and unmitigable impacts on the environment; and (4) Other alternatives will meet SDG&E's eventual reliability needs more economically and with fewer significant and unmitigable impacts on the environment. [16]

SDG&E is not legally obligated to carry any renewable energy on the line. [17] In response to that concern, SDG&E President & CEO Debra Reed stated in testimony before the commission that the utility would make three voluntary commitments if Sunrise is approved. She stated that SDG&E would: (1) not contract, for any length of term, with conventional coal generators that deliver power via Sunrise, (2) replace any currently approved renewable energy contract deliverable via Sunrise that fails with a viable contract with a renewable generator located in Imperial Valley, and (3) voluntarily raise SDG&E's renewable energy goal to 33 percent by 2020. [18] (SDG&E was the first investor-owned utility in California to make this commitment.) [19]

According to the Renewable Energy Transmission Initiative, east San Diego County, along with neighboring Imperial County and Northern Baja California, has a potential aggregate generating capacity of roughly 6,870 megawatts (MW) for solar energy, 3,495 MW for wind power and 2,000 MW for geothermal energy. Together, these renewable resources could potentially produce enough electricity to power 8 million homes at noon, on a sunny day, if the wind was turning windfarm turbine rotors at their theoretical maximum speed. Given Southern California capacity factors, however, of 28% for solar and 30% for wind, production at the quoted capacity would average one-third of that, or enough to power 2,666,000 homes. [20]

This will help meet several state and federal policies and mandates for the increased use of green energy, including:

Public Involvement

Public involvement during the public participation period of the project is a source of significant controversy. Community groups state that SDG&E failed to notify the public about the southern route which was ultimately selected by the CPUC. [25] SDG&E contends they performed all notifications as required by law, and that the project's environmental impact report included the southern route as one of the nine alternatives being considered. The CPUC later confirmed these statements. [26] [27] [28]

However, during this same period, SDG&E testified before the CPUC that the southern route was not feasible. [29] The media and public hearings therefore focused on the northern route through Anza Borrego State Park, and opponents of the project claimed there was no media or public focus on the possible southern routes. While the CPUC did not refute the claim that there was not media or public focus on the southern route, the CPUC has stated that the legally required notifications occurred. [26] [27] [28] SDG&E was required to notify property owners within 300 feet (91 m) of the proposed route.

After the last public participation hearing held by the CPUC in February 2008, [30] SDG&E notified the CPUC and that the southern route was feasible. [31] In October 2008, the CPUC fined SDG&E over $1.1 million for misleading the CPUC about the feasibility of the southern route. [32] However, there were no subsequent CPUC public participation hearings in San Diego for the residents along the southern route.

The CPUC approved the southern route in December 2008. After the approval of the route, SDG&E held workshops in communities along the route, where they were criticized by community members who stated that were just learning about this route for the first time. Those critical of the lack of notification included the Lakeside Planning Group. [25] [33] However, the CPUC provided proof that the Lakeside Planning Group received all documentation and notification, however, this notification occurred during the time in which SDG&E was stating in public testimony that the southern route was not feasible. The CPUC confirmed that no current members of the planning group provided comment. [27]

The CPUC and SDG&E state that they have held numerous workshops and community meetings to gather input and feedback on the Sunrise Powerlink. Community groups contend that the community meetings were not held until after the project was approved. The Final Environmental Impact Report documents the public involvement process, which included public meetings throughout the approval process, although none of those meetings were held in the impacted community of Lakeside. [28]

The most recent phase of the post-approval public involvement process is a series of Community Council meetings. SDG&E has created seven Community Councils along the route that give the public the opportunity to provide input and feedback on the permitting and construction of the Sunrise Powerlink. Members, who live and work in the communities they represent, are being encouraged to share what they learn with residents and businesses in their communities. Community Councils are being created in: Imperial Valley, Campo, Boulevard, Jacumba, Alpine, Lakeside and the City of San Diego.

SDG&E has been criticized for hand-picking community members to sit on the community councils. [34]

Support

The line is supported by the California Independent System Operator, [14] which oversees the state's power grid; the California Energy Commission, [35] the CPUC, the BLM, and the Community Alliance for the Sunrise Powerlink (CASP), a group of business leaders, individuals, government leaders and organizations that represent hundreds of thousands of people throughout California. [36] CASP believes the region needs improved access to reliable, renewable energy to maintain the region's economic competitiveness and quality of life. Three entities founded CASP in partnership with SDG&E: BIOCOM, the Downtown San Diego Partnership and the San Diego-Imperial Counties Labor Council. [37] Two more agencies have since become heavily involved in the group: The San Diego Regional Chamber of Commerce and the San Diego Regional Economic Development Corporation.

More than 75 elected officials support the Sunrise Powerlink, as do numerous business and labor organizations that represents tens of thousands of Californians. [38]

Opposition

The line is opposed by a diverse group of individuals, elected officials, community leaders and organizations. [39] One elected official is San Diego County Supervisor Dianne Jacob, who is actively opposed to the route, and has testified before the CPUC in opposition to the project. [40] [41] The project is also opposed by a non-profit utilities watchdog group, the Utilities Consumer Action Network . UCAN, in a joint action with the Center for Biological Diversity, is challenging the CPUC's approval in the California Supreme Court. [42] In addition, the project is also being litigated in federal court, by a coalition of three community groups; the Protect Our Communities Foundation , East County Community Action Coalition , and Back Country Against Dumps . These community groups are challenging the Bureau of Land Management's approval of the project on BLM land, on the grounds that the BLM failed to perform its legally required environmental reviews of the project. [43]

One of the community groups in opposition to the project, the East County Community Action Coalition, was formed in March 2009 in response to the approval of the route through the east county of San Diego. The grass-roots organization states that in just one year, its membership has surged to include groups and individuals that together represent over 79,000 individuals. [44] The coalition cites a variety of reasons for opposing the line, including the concern that the route will traverse some of the most fire prone areas of San Diego county, including the area that was burned in the 2003 Cedar Fire. The Cedar Fire is, to date, the deadliest fire in California's history, and ninth deadliest wildfire in U.S. history. [45]

The CPUC, in its final decision, stated that lower-voltage distribution lines, not high-voltage transmission lines like the Sunrise Powerlink, were responsible for most power-line related fires in the San Diego area. Further, the CPUC instituted mitigation measures to further reduce the risk of fire. [46]

Environmental Impact Report

The 11,000 page Environmental Impact Report conducted by the California Public Utilities Commission favored no transmission line as its first alternative. [12] Instead, the report recommended a mix of energy sources, including local solar generation. [12] San Diego County is one of the sunniest counties in the country and is a favorable venue for rooftop solar voltaic generation, as pointed out in a comprehensive report discussing various energy options for the region [footnote Bill Powers' Smart Energy Solutions report ]. The project has also generated controversy concerning the choice of route. Rather than following roads (e.g. Interstate 8) or existing transmission lines, SDG&E originally proposed to build it in wilderness, cutting across Anza-Borrego Desert State Park and Cleveland National Forest. The route approved by the California Public Utilities Commission avoids Anza-Borrego Desert State Park, and instead traverses the Cleveland National Forest and the communities of Jacumba, Boulevard, Campo, Japatul Valley, Lyons Valley, Alpine, and Lakeside. [47] The U.S. Forest Service is currently considering a proposed plan amendment and Record of Decision that would allow the line to cross a section of the Cleveland National Forest. [48] The project can not be built without Forest Service approval. SDG&E has stated that the Sunrise Powerlink is expected to be in service by 2012.

The project's Environmental Impact Report "Fire and Fuels Management" section lists numerous unmitigable significant impacts; known as Class 1 impacts, which are the highest level of impact that a project can have. [49] The final EIR states that, "San Diego County is an extremely fire-prone landscape. Winds originating from the Great Basin, locally known as Santa Anas, create extreme fire weather conditions characterized by low humidity, sustained high-speed winds, and extremely strong gusts. Santa Ana winds typically blow from the northeast over the Peninsular Range. As the air is forced through coastal mountain passes, wind speeds of 40 mph (64 km/h) can be maintained for hours with gusts from 70 to 115 mph (185 km/h) possible (Schroeder et al., 1964). Santa Ana winds create extremely dangerous fire conditions and have been the primary driver of most of California's catastrophic wildfires. Because of the presence of dense, dry fuels and periodic Santa Ana winds, southern California has been characterized as having one of the most fire-prone landscapes in the world.

The Final EIR cites the following unmitigable impacts: [49]

Wildland firefighters working around energized power lines are exposed to electrical shock hazards including: direct contact with downed power lines, contact with electrically charged materials and equipment due to broken lines, contact with smoke that can conduct electricity between lines, and the use of solid-stream water applications around energized lines. Between 1980 and 1999 in the U.S., there were 10 firefighter fatalities due to electrical structure contact during wildfire suppression (NFPA, 2001). Maintaining a minimum 500-foot (150 m) safety buffer greatly reduces the risk of electrical structure contact, and it also reduces the effectiveness of ground-based frontal attacks.

The presence of the overhead transmission line would reduce the effectiveness of firefighting (Class I) - Aerial and ground-based firefighting efforts would be compromised by the introduction of an overhead transmission line due to the introduction of various hazards as identified in the Containment Conflict Model results, including increasing the risk of transmission line contact by aircraft or water buckets, creating indefensible landscapes, and obstructing historical fire containment boundaries.

The outcome of not fighting a wildfire in an otherwise defensible landscape under favorable weather conditions is that it is able to build in size and intensity unchecked by firefighters who are forced to wait until the fire passes through the area. Delays in containment allow for rapid fire perimeter growth. With the increase in the fire perimeter comes the potential for wind-blown embers to ignite spot fires ahead of the fire front, which further complicates fire suppression activities.

Impact F-2: Presence of the overhead transmission line would increase the probability of a wildfire (Class I)- The presence of the overhead transmission line would create an ongoing source of potential wildfire ignitions for the life of the project. Line faults can be caused by such unpredictable events as conductor contact by floating debris, gunshots, and helicopter collisions; these events are rare but would be unavoidable. Impact F-2 is considered a significant impact because certain ignition sources are unavoidable. Due to the potential for unavoidable ignitions related to the presence of the overhead transmission line to occur during extreme fire weather, the presence of the project would significantly increase the likelihood of a catastrophic wildfire (Class I). The risk of ignitions and the risk of damage from a project-related ignition can be reduced, though not to a level that is less than significant.

Impact F-3: Presence of the overhead transmission line would reduce the effectiveness of firefighting. (Class I)- Aerial and ground-based firefighting efforts would be compromised by the introduction of an overhead transmission line due to the introduction of various hazards as identified in the Containment Conflict Model results, including increasing the risk of transmission line contact by aircraft or water buckets, creating indefensible landscapes, and obstructing historical fire containment boundaries. The outcome of not fighting a wildfire in an otherwise defensible landscape under favorable weather conditions is that it is able to build in size and intensity unchecked by firefighters who are forced to wait until the fire passes through the area. Delays in containment allow for rapid fire perimeter growth. With the increase in the fire perimeter comes the potential for wind-blown embers to ignite spot fires ahead of the fire front, which further complicates fire suppression activities."

In addition, numerous environmental groups believe that construction of the power line, as well as the power line itself, will be harmful to the environment, will cost ratepayers more than better alternatives, and will actually add more greenhouse gases than it will save. The Draft Environmental Impact Report [50] finds that several alternatives would be better for the environment than the Sunrise Powerlink.

However, the Environmental Impact Report itself is only one factor officials use in deciding the overall merits of a project. The Sunrise Powerlink EIR states that, "This EIR/EIS does not make a recommendation regarding the approval or denial of the project. It is purely informational in content, and will be used by the CPUC and BLM in considering whether to approve the Proposed Project or any of the alternatives analyzed in this EIR/EIS." [28]

Related Research Articles

<span class="mw-page-title-main">Pacific Gas and Electric Company</span> American utility company

The Pacific Gas and Electric Company (PG&E) is an American investor-owned utility (IOU). The company is headquartered at 300 Lakeside Drive, in Oakland, California. PG&E provides natural gas and electricity to 5.2 million households in the northern two-thirds of California, from Bakersfield and northern Santa Barbara County, almost to the Oregon and Nevada state lines.

<span class="mw-page-title-main">Southern California Edison</span> Electrical utility in Southern California, United States

Southern California Edison (SCE), the largest subsidiary of Edison International, is the primary electric utility company for much of Southern California. It provides 15 million people with electricity across a service territory of approximately 50,000 square miles.

<span class="mw-page-title-main">Southern California Gas Company</span> Natural gas utility company in California

The Southern California Gas Company is a utility company based in Los Angeles, California, and a subsidiary of Sempra. It is the primary provider of natural gas to Los Angeles and Southern California.

<span class="mw-page-title-main">California Public Utilities Commission</span> State government agency of California

The California Public Utilities Commission is a regulatory agency that regulates privately owned public utilities in the state of California, including electric power, telecommunications, natural gas and water companies. In addition, the CPUC regulates common carriers, including household goods movers, limousines, rideshare services, self-driving cars, and rail crossing safety. The CPUC has headquarters in the Civic Center district of San Francisco, and field offices in Los Angeles and Sacramento.

<span class="mw-page-title-main">San Diego Gas & Electric</span>

San Diego Gas & Electric (SDGE) provides natural gas and electricity to San Diego County and southern Orange County in southwestern California, United States. It is owned by Sempra, a Fortune 500 energy services holding company based in San Diego.

Path 46, also called West of Colorado River, Arizona-California West-of-the-River Path (WOR), is a set of fourteen high voltage alternating-current transmission lines that are located in southeast California and Nevada up to the Colorado River.

<span class="mw-page-title-main">Community Choice Aggregation</span> Alternative energy supply system

Community Choice Aggregation (CCA), also known as Community Choice Energy, municipal aggregation, governmental aggregation, electricity aggregation, and community aggregation, is an alternative to the investor-owned utility energy supply system in which local entities in the United States aggregate the buying power of individual customers within a defined jurisdiction in order to secure alternative energy supply contracts. The CCA chooses the power generation source on behalf of the consumers.

The Ranchita Rocks Music Festival was a three-day annual music festival held at the Golightly Farms Ranch in Ranchita, California. The 2008 event had six stages, featuring classic and contemporary rock performances. as well as comedy acts, camping, crafts vendors, a kids' zone, healing arts, food, beer & wine, drum circles, and a fire breathing fire truck with aerial performers.

<span class="mw-page-title-main">Solar power in California</span>

Solar power has been growing rapidly in the U.S. state of California because of high insolation, community support, declining solar costs, and a renewable portfolio standard which requires that 60% of California's electricity come from renewable resources by 2030, with 100% by 2045. Much of this is expected to come from solar power via photovoltaic facilities or concentrated solar power facilities.

The California Desert Protection Act of 2010 was legislation proposed by U.S. Senator Dianne Feinstein. The stated aim of the legislation was "to provide for conservation, enhanced recreation opportunities, and development of renewable energy in the California Desert Conservation Area."

The Rice Solar Energy Project was a 150 MW concentrating solar power facility project proposed for Rice Valley in the southern Mojave Desert, within Riverside County in southern California. It was put on indefinite hold in 2014.

The Centinela Solar Energy Project is a 170 megawatt (MW) photovoltaic power plant located on 2,067 acres (836 ha) of previously disturbed private land southwest of El Centro, California. The project planned to provide at least 235 jobs, generate more than $30 million in tax revenue over its life-time, and deliver enough electricity to power about 82,500 homes. Imperial County gave a green-light to the solar power plant on December 27, 2011, and Secretary of the Interior Ken Salazar approved the right-of-way over 19 acres for the connecting power line on public land.

Hope For The Hills (HFTH) is a non-profit grassroots organization based in Chino Hills, California, USA. It is protesting a 5-mile segment of 500kV overhead transmission lines that occupy a 150-foot right of way through a residential area in Chino Hills. The segment is part of the Tehachapi Renewable Transmission Project (TRTP). On July 11, 2013 Hope for the Hills won its long fight when the California Public Utilities Commission voted to put the lines underground.

<span class="mw-page-title-main">Energy in California</span> Overview of the use of energy in California, U.S.

Energy in California is a major area of the economy of California. California is the state with the largest population and the largest economy in the United States. It is second in energy consumption after Texas. As of 2018, per capita consumption was the fourth-lowest in the United States partially because of the mild climate and energy efficiency programs.

<span class="mw-page-title-main">Genesis Solar Energy Project</span> Concentrated solar thermal power station in the Mojave Desert of California

The Genesis Solar Energy Project is a concentrated solar power station located in the Mojave Desert on 1,920 acres (780 ha) of Bureau of Land Management land, in eastern Riverside County, California. The plant is owned/managed by Genesis Solar, LLC, a subsidiary of NextEra Energy Resources, LLC. The Genesis Solar Energy Project is located about 25 miles (40 km) west of Blythe, in the Lower Colorado River Valley. The plant was built in the Colorado Desert along an ancient trade route that native people had traveled for thousands of years. The route traversed the Sonoran Desert and enabled trade between the Colorado River and the coast.

The Chokecherry and Sierra Madre Wind Energy Project is large-scale wind farm located near Rawlins, Wyoming, currently under construction. If completed as scheduled in 2026, it is expected to become the largest wind farm in the United States and one of the largest in the world. Located largely on federal lands, the project is being built in conjunction with the TransWest Express transmission line to supply power to the California market. Originally slated for completion in 2020, the goal was extended to 2026 in 2019 amid permitting, environmental, and construction delays.

<span class="mw-page-title-main">San Diego Climate Action Plan</span> Climate impact reduction blueprint for San Diego, California

The San Diego Climate Action Plan was adopted by the city of San Diego in December 2015. It is a local climate action plan whose rules are defined by the California global warming Solutions Act of 2006, with the goal of reducing greenhouse gas emissions. Through this plan, the city initially set goals of eliminating half of all greenhouse emissions and sourcing all energy from renewable sources by the year 2035. With a coalition of business owners, environmental advocates, and community leaders, Mayor Kevin Faulconer approved the Climate Action Plan. The Climate Action Plan consists of several policies to ensure the economic and environmental growth of the city of San Diego. It was referred to in The San Diego Union-Tribune as "the most aggressive climate action plan in California."

The White Pine Energy Station was a proposed coal-fired power plant that was to be built in White Pine County, Nevada. The plant was to be built in the county's Steptoe Valley, and would be located 34 miles north of the city of Ely. White Pine Energy Associates, LLC, a subsidiary of LS Power, announced the project in February 2004, with plans to begin construction in 2006, with the possibility of having it operational in 2010. The 1,590-megawatt project would consist of three units, each producing 530 megawatts.

<span class="mw-page-title-main">Camp Fire (2018)</span> 2018 wildfire in Northern California

The Camp Fire was the deadliest and most destructive wildfire in California's history, and the most expensive natural disaster in the world in 2018 in terms of insured losses.

The 2019 California power shutoffs, known as public safety power shutoff (PSPS) events, were massive preemptive power shutoffs that occurred in approximately 30 counties in Northern California and several areas in Southern California from October 9 to November 1, 2019, and on November 20, 2019, by Pacific Gas and Electric Company (PG&E), Southern California Edison (SCE), and San Diego Gas & Electric (SDG&E). The power shutoffs were an attempt to prevent wildfires from being started by electrical equipment during strong and dry winds. The shutoffs initially affected around 800,000 customer accounts, or about 2.5 million people, but expanded to cause over 3 million people to lose utility-provided electrical power by late October as more utility companies from around the state also did preemptive power shutoffs.

References

  1. "Sunrise Powerlink - Welcome". sdge.com. Archived from the original on July 20, 2016.
  2. 1 2 3 Soto, Onell R. (December 9, 2010). "Governor calls Sunrise Powerlink example to nation". San Diego Union-Tribune . San Diego.
  3. Gerry Akin and Art Holland (August 1, 2012). "Sunrise Powerlink Inspires Innovation". www.tdworld.com. Archived from the original on March 18, 2020.
  4. SDG dedicates sunrise powerlink transmission link elp.com [ dead link ]
  5. "SDG&E, State and Local Officials Dedicate New Sunrise Powerlink 'Green Energy' Superhighway". sdge.com.
  6. Sunrise Powerlink Helicopter Operations on YouTube
  7. "The San Diego Union-Tribune - San Diego, California & National News".
  8. "About the Interior Board of Land Appeals". Archived from the original on June 17, 2010. Retrieved May 20, 2010.
  9. "SDG&E Sunrise Powerlink Project: Home".
  10. "SDG&E Sunrise Powerlink Project: Final EIR/EIS".
  11. "CPUC Approves SDG&E's Sunrise Transmission Project to Support California's Renewable Energy Goals". ca.gov.
  12. 1 2 3 "CPUC Issues Proposed Decisions in Sunrise Transmission Line Proceeding". ca.gov.
  13. "BLM Approves the Sunrise Powerlink Project (01-20-2009)". blm.gov. January 30, 2009.
  14. 1 2 California ISO Board Approves Sunrise/GreenpathTransmission Project http://www.caiso.com/1847/1847bb8a57f70.pdf
  15. 1 2 Sunrise Powerlink Final Decision http://docs.cpuc.ca.gov/PUBLISHED/AGENDA_DECISION/95357.htm#P263_8685.
  16. "Decision of Administrative Law Judge" (PDF). cpuc.ca.gov. October 31, 2008. Retrieved September 27, 2023.
  17. CPUC website, http://www.cpuc.ca.gov/NR/rdonlyres/0D666D07-B64D-4DB2-A3E1-6D27DBF27D4D/0/powerlink_dissent.pdf
  18. Sunrise Powerlink Final Decision http://docs.cpuc.ca.gov/PUBLISHED/AGENDA_DECISION/95357.htm#P2877_450757
  19. Roth, Sammy (July 1, 2020). "Want jobs and clean energy? This overlooked technology could deliver both". Los Angeles Times . Retrieved July 2, 2020.
  20. RETI Phase 2A Final Report, September 2009 http://www.energy.ca.gov/2009publications/RETI-1000-2009-001/RETI-1000-2009-001-F-REV2.PDF
  21. New Energy for America Plan Fact Sheet, "Archived copy" (PDF). Archived from the original (PDF) on November 3, 2008. Retrieved November 5, 2008.{{cite web}}: CS1 maint: archived copy as title (link)
  22. CPUC Web site, RPS page, http://www.cpuc.ca.gov/PUC/energy/Renewables/
  23. Governor Schwarzenegger Advances State's Renewable Energy Development http://gov.ca.gov/press-release/11073/
  24. AB32 language, http://www.arb.ca.gov/cc/docs/ab32text.pdf
  25. 1 2 Alpine Fact Sheet cpuc.ca.gov
  26. 1 2 3 Lakeside Fact Sheet cpuc.ca.gov
  27. 1 2 3 4 Summary cpuc.ca.gov
  28. "SignOnSanDiego.com > News > Metro -- SDG&E power line route plan zapped". signonsandiego.com.
  29. "SignOnSanDiego.com > News > Metro -- Last chance to speak up on Sunrise plan". signonsandiego.com.
  30. "SDG&E Powerlink Shocker". NBC 7 San Diego. October 22, 2008.
  31. "SignOnSanDiego.com > News > Business -- SDG&E lied about power line project, PUC believes". signonsandiego.com.
  32. "Archived copy" (PDF). Archived from the original (PDF) on July 21, 2011. Retrieved February 27, 2010.{{cite web}}: CS1 maint: archived copy as title (link)
  33. "POWERLINK OPPONENTS ACCUSE SDG&E OF EXCLUDING OPPONENTS FROM POWERLINK COUNCILS". East County Magazine.
  34. California Energy Commission 2005 Integrated Energy Policy Report, page 100, http://www.energy.ca.gov/2005publications/CEC-100-2005-007/CEC-100-2005-007-CMF.PDF
  35. CASP Web site, www.supportsunrise.com
  36. "Labor, business leaders back power line," North County Times, July 25, 2006 http://www.nctimes.com/business/article_d9edbfee-5974-5d76-8507-2102690d92c6.html
  37. "泰州阜讯教育咨询有限公司".
  38. "Sunrise Powerlink opponents are of all stripes". The San Diego Union-Tribune. May 23, 2009.
  39. "Archived copy" (PDF). Archived from the original (PDF) on December 2, 2009. Retrieved February 27, 2010.{{cite web}}: CS1 maint: archived copy as title (link)
  40. "Archived copy" (PDF). Archived from the original (PDF) on June 15, 2011. Retrieved February 27, 2010.{{cite web}}: CS1 maint: archived copy as title (link)
  41. "Sunrise PowerLink faces Supreme Court battle | UCAN". Archived from the original on February 21, 2010. Retrieved February 27, 2010.
  42. "Archived copy" (PDF). Archived from the original (PDF) on July 27, 2011. Retrieved February 27, 2010.{{cite web}}: CS1 maint: archived copy as title (link)
  43. "Googleアナリティクスについて". eastcountyaction.org.
  44. "The Ten Deadliest US Wildfires | Epic Disasters". Archived from the original on March 29, 2010. Retrieved February 27, 2010.
  45. Sunrise Powerlink Final Decision http://docs.cpuc.ca.gov/PUBLISHED/AGENDA_DECISION/95357.htm#P2499_350278
  46. "State regulators OK Powerlink" San Diego Union-Tribune, Dec. 19, 2008 http://www3.signonsandiego.com/stories/2008/dec/19/1n19puc233950-state-regulators-ok-powerlink/
  47. "CPUC Says No to New Hearing," North County Times, July 14, 2009 http://www.nctimes.com/articles/2009/07/14/news/sandiego/z2ba13208691ae916882575f3007083c9.txt
  48. 1 2 Fire and Fuels Management – Contents cpuc.ca.gov
  49. Draft Environmental Impact Report