Barro Blanco Dam | |
---|---|
Location | Chiriqui Province, Panama |
Coordinates | 8°12.861′N81°35.653′W / 8.214350°N 81.594217°W |
Owner(s) | GENISA S.A. |
Dam and spillways | |
Type of dam | Gravity, roller compacted concrete |
Height | 44.91 m (147.3 ft) |
Height (foundation) | 61.09 m (200.4 ft) |
Reservoir | |
Surface area | 2.58 km2 (1.00 sq mi) |
Normal elevation | 103 m (338 ft) |
Power Station | |
Hydraulic head | 42.94 m (140.9 ft) |
Turbines | 1 x 1.98 MW Francis-type, 2 x 13.14 MW Kaplan-type |
Installed capacity | 28.56 MW |
Annual generation | 124.83 GWh Est. [1] |
Website http://www.genisa.com.pa/en/barro-blanco/ |
Barro Blanco is a gravity dam on the Tabasara River in the Chiriqui Province of Panama. It began generating in 2017 with capacity of 28.56 MW. Although the government had authorized the dam, it suspended construction in February 2015 after protests. The President of the Republic authorized the partial restart of construction in August 2015, but prohibited the filling of the reservoir pending a final agreement. [2] Important issues concerning the dam are controversial, such as the question whether the indigenous communities in the area initially had expressed their support or their opposition to the dam's construction and how well they had been informed about the project and its impacts prior to expressing their views.
The dam was designed to minimize the impact on the river, never leaving any section of the river dry. The roller-compacted concrete gravity dam is to have a maximum height of 44.91 m (147.3 ft) and a maximum reservoir surface of 2.58 km2 (1.00 sq mi), including 0.69 km2 (0.27 sq mi) currently occupied by the Tabasara River and 1.89 km2 (0.73 sq mi) that would be inundated, according to the project design document submitted to the UN Clean Development Mechanism Executive Board. [3] 0.07 km2 (0.027 sq mi) of the inundated land would be located In the indigenous territory (Comarca) of the Ngöbe–Buglé people. The installed capacity of the planned hydropower plant is 28.84 Megawatt.
The project developer is Generadora del Istmo S. A. (GENISA), a Panamanian special purpose company created specifically for this project. GENISA is owned by the Kafie family: the public registry lists Luis Kafie (President), Luis Jose Kafie (Treasurer and Director), Shukri Kafie (Director), Eduardo Kafie (Director), Eduardo Kafie Atala (Director) and Christoper Kafie (Director) as member of the board of GENISA.
The project is financed by loans that have been provided by two European state-owned banks that promote private sector investments in developing countries, the German Investment Corporation (DEG) and the Netherlands Development Finance Company (FMO), [4] as well as by the Central American Bank for Economic Integration (CABEI). CABEI approved a USD 25 million loan to the project developer in 2011. Total funding from the three banks amounts to USD 78.3 million. [5]
There is a long-standing conflict between the Ngäbe people and the government concerning mining and the construction of dams for hydropower generation in or near their territory. [6] The Ngäbe-Buglé Comarca was created in 1997 for the use of the Ngäbe and Buglé indigenous communities. [7] Despite this during the 1970s the Panamanian government proposed to dam the Tabasara with a 220MW hydroelectric project designed to supply energy to the proposed Colorado Copper Mines. This project was cancelled following widespread protests. [8] They had won the first battle of the Tabasara dams, however, during the 1990s another project was proposed - this time a 48MW dam, they again successfully defeated this proposal. [9] This thereafter resulted in the Panamanian government changing national law in order to repeal requirements related to participation from indigenous communities. [10]
This long history of conflict regarding their traditional and spiritual lands has resulted in the prolonged social mobilisation of the Ngäbe-Buglé communities.
According to GENISA, no indigenous village or houses would be inundated by the reservoir and no one would be resettled. However 5 hectares of stream bed will be flooded during the rainy season. The land to be inundated consists of ravines close to the river that are not suitable for agriculture or livestock grazing. [11] According to another source the area to be flooded is 1.89 km2 (0.73 sq mi), or 189 hectares. [3] However, critics allege that the livelihoods of some 5000 Ngöbe farmers who rely on the river for potable water, agriculture and fishing will be negatively impacted, [12] and primary forest would be cut down. They also say that the impacted communities have never provided their free, prior and informed consent to the project. [13]
Furthermore, they say that the habitat of the endangered Tabasará rain frog would be destroyed. [14] GENISA says that the Tabasará rain frog lives in several habitats in Panama, including in the Anton Valley hundreds of kilometers away from the site. [11]
In 2006, under the government of President Martín Torrijos, an international public tender was announced for various hydropower projects in Panama, including Barro Blanco. Among the four participating companies GENISA was selected. The Public Services Authority ASEP authorized GENISA to prepare studies and, subject to obtaining all relevant approvals, to develop the Barro Blanco project.
GENISA commissioned an Environmental Impact Study. As part of this study, in August 2007 in a public forum with the participation of local authorities, villagers close to the project were asked about their view of the dam. At the time, the indigenous M-10 Movement rejected the dam, because it considered indigenous people would lose their land, would not be able to use the river any more and because the environment would be harmed. However, most of the consulted people supported the project, because it would provide jobs, better road access and improved living standards. Some of those who were opposed to the project subsequently sold their land to the project developer. [3] In December 2007, GENISA and representatives of the Ngobe Bugle people signed a cooperation agreement that included safeguards for the fundamental rights of the indigenous people. [15]
In May 2008 the Panamanian Environmental Authority ANAM approved the project based on the study. [16] In December 2008 GENISA signed a Memorandum of Understanding in which it committed itself to implement a social development plan for the indigenous communities living next to the dam, including "infrastructure, health and education programs" during the construction and during the operation of the dam. [17]
In January 2009 a validation team consisting of the consulting firm AENOR working for the UN CDM Executive Board visited the area and confirmed "that the most relevant communities involved in the area of the project were consulted, all of them supported the project activity, and project participant (i.e. GENISA) has forecasted several social compensation measurements for the communities involved." [15] The International Rivers Network says that the validation report by AENOR was flawed, since allegedly only the non-indigenous population had been consulted and they had failed to take into account all comments received. [18] In 2009 the concession contract between the government and GENISA was signed. [16]
After presidential elections in early 2009, in June 2009 Ricardo Martinelli, a businessman who promised to quickly upgrade Panama's infrastructure, took office as President of Panama. In May 2009 GENISA requested a modification of the permit to increase the capacity by 52% to 28.8 Megawatt by moving the turbines to a lower elevation, without increasing the water level in the reservoir. The original environmental study and the permit referred to an installed capacity of only 19 Megawatt. In January 2010 ANAM approved the modification, and in January 2011 the concession contract was modified accordingly. [16] As of 2010, according to the UN CDM project document, 98% of the land to be inundated was owned by GENISA. [3]
According to critics, the environmental impact study was flawed, because impacts on biodiversity were assessed superficially and because the capacity of the plant was increased. [4] In late 2010 the European Investment Bank withdrew funding for the dam after an investigation into human rights abuses prompted by NGO protests. [18] In January 2011 DEG and FMO approved their loans for the project.
In February 2011, the Panamanian government proposed a new mining law that would facilitate the development of mining projects in indigenous areas, while the indigenous people had asked for a law banning mining in their territories. The proposal and the simultaneous launching of bids for a large copper mining project called Cerro Colorado triggered protests of indigenous people, including local communities from the Barro Blanco area, who blocked the Interamerican Highway for four days. The protests were violently suppressed. The conflict was temporarily ended through the San Felix agreement, signed in the village of San Felix. [6] Construction of the dam began in February 2011.
On June 25, 2011, according to the project developer GENISA, the regional congress of the Kädriri, the local group of Ngäbe people, approved by public majority voting that the construction of the dam should continue, after having been authorized to take a decision by the General Congress of the Ngäbe-Buglé. [19] Also in June 2011 the UN Clean Development Mechanism (CDM) Board approved the carbon finance proposal that was to generate part of the revenue stream for the project. [4] On August 25, 2011, a Compensation and Benefits Agreement was signed between GENISA and the Board of the Regional Congress of the Kädriri. [17]
However, the conflict remained unresolved. The government called for a referendum on the dam, but the indigenous leader Silvia Carrera, elected as Cacica General in September 2011, initially rejected it. [6] An international campaign was started to stop construction of the dam and international funding for it. In March 2012 Parliament passed a modified version of the mining law that prohibited mining in the indigenous territory and required the approval of the Ngöbe Buglé General Congress for any future hydroelectric projects. [20] However, the traditional authorities of the Ngöbe criticized Silvia Carrera for having given in. They had asked for a complete ban on hydropower projects to be included in the law. [21]
Construction had to be halted in May 2012, because the local population occupied the site. The protests were suspended while "UN inspectors" were expected to visit the area. [22] In September 2012 an inspection team led by UNDP and consisting of representatives of the Catholic Church, the environmental agency ANAM, the electricity regulatory agency ASEP and the project developer GENISA, visited the area. The purpose of the inspection was to verify on the ground issues that had not been answered satisfactorily in the environmental impact assessment. The inspection team presented its report in December 2012, recommending a water flow simulation to understand the impact of sudden floods as well as a participatory rural appraisal. [23] In March 2013 an indigenous protester against the dam was killed by masked assailants. [24]
In July 2013, James Anaya, UN special rapporteur on the rights of indigenous people, visited Panama and spoke to the Ngöbe. In his report he concluded that the Ngöbe "were not properly consulted". [25] Prior to the visit 12 local and international civil society organizations had asked Anaya to conduct a formal investigation into the human rights impacts of the dam and to call on the government to "immediately halt the dam’s construction until the threats to the rights of the indigenous Ngӓbe people affected by the project have been fully addressed". [26]
On September 6, 2013, the United Nations released three reports on the water flow simulation, a participatory rural appraisal as well as an ecological and economic analysis conducted by two independent international experts, Gonzalo Castro de la Mata and Luis Lopez, showing that the dam had no impact on global biodiversity, but had "real and important impacts" on the indigenous populations living in the area. However, the report did not mention that any villages would be inundated. Furthermore, the experts concluded that "the local population had not been correctly consulted". They also concluded that the local population had "a rudimentary and often erroneous knowledge of the project, being a product of rumors, often without foundation". Together with the insufficient consultation this had created a climate of fear. [27]
In April 2014 Silvia Carrera, the Cacica General of the Comarca Ngäbe-Buglé, submitted a complaint to the Independent External Panels of DEG and FMO. In May 2015 the joint review of the panels found that the banks had failed to fully comply with the standards to which they had committed themselves. While the banks took significant steps to understand the situation as part of their due diligence process, they accepted an indigenous peoples report that was insufficient for the purpose to approve the credit in January 2011, requiring further investigations as a condition for disbursement, while their own standards would have required a fully satisfactory report at the time of approval. The two banks accepted the conclusions and committed themselves to "further raise the bar on the required level of information on stakeholder consultation available to (them) at the time of credit approval." [28] In the meantime, the government of Panama - since June 2014 led by a new President, Juan Carlos Varela - suspended the construction of the dam in February 2015 on the grounds that the environmental and social impact assessment was faulty pending the outcome of a court case that challenges the assessment. [29] In June 2015 new protests erupted, with protesters shutting down the Interamerican Highway for two days, as a result of which the President sent a riot squad to the area. [13] On August 10, 2015, President Varela and the Cacica General of the indigenous Comarca, Silvia Carrera, signed an agreement to the effect that the civil works of the dam would be completed, but that the electromechanical works would remain suspended and the dam would not be flooded until a final agreement had been reached. GENISA complained that it had been left out of the agreement and that the agreement violated the agreements concluded by the state with the company. [2] In September 2015 the environmental agency ANAM imposed a 775,200 USD fine on GEMISA for having failed to comply with the resettlement and compensation measures under the project. [30] On January 21, 2016, the indigenous movement 10 April claimed that the agreement had been violated, because tests to fill the reservoir had been made. [31] On January 28, 2016, a technical report was presented to the indigenous communities, showing that the dam was technically safe. Furthermore, a sub-commission consisting of the government and traditional authorities was created to further study the impacts of the project in view of a "final decision". [32] Filling of the reservoir began on May 24, leading to further protests and road blocks. In response, Vice-President and Minister of Foreign Affairs Isabel Saint Malo de Alvarado held talks with indigenous leaders early June 2016. Carrera said that the filling "was a violation of the rights of indigenous people in the area, and of the contract signed by President Juan Carlos Varela." [33] On August 22, 2016, Silva Carrera and President Varela signed another agreement. This agreement was voted down by the Ngäbe-Bugle General Congress in September 2016. The UN Clean Development Mechanism deregistered the dam in October 2016. [34]
In December 2016 the Supreme Court, whose decisions cannot be appealed, ruled against two legal actions by indigenous communities. In March 2017 the General Administrator of the National Authority for Public Services declared that the Ngäbe-Bugle General Congress never presented a formal rejection document to the government, meaning dam operations could begin. In the meantime, 11 houses and fields had been flooded by the rising waters of the reservoir. [34] Shortly after the declaration, the hydropower plant began its operation. In August 2017 three indigenous leaders who had been accused of causing damages to GENISA through their protests were acquitted by a court. [35]
Ngäbe-Buglé is the largest and most populous of Panama's five comarcas indígenas. It was created in 1997 from lands formerly belonging to the provinces of Bocas del Toro, Chiriquí, and Veraguas. The capital is known as Buäbiti in Guaymí and Llano Tugrí in Spanish.
The Clean Development Mechanism (CDM) is a United Nations-run carbon offset scheme allowing countries to fund greenhouse gas emissions-reducing projects in other countries and claim the saved emissions as part of their own efforts to meet international emissions targets. It is one of the three Flexible Mechanisms defined in the Kyoto Protocol. The CDM, defined in Article 12 of the Protocol, was intended to assist non-Annex I countries achieve sustainable development and reduce their carbon footprints, and to assist Annex I countries achieve compliance with greenhouse gas emissions reduction commitments.
The Ngäbe are an indigenous people within the territories of present-day Panama and Costa Rica in Central America. The Ngäbe mostly live within the Ngäbe-Buglé comarca in the Western Panamanian provinces of Veraguas, Chiriquí and Bocas del Toro. They also have five indigenous territories in southwestern Costa Rica, encompassing 23,600 hectares: Coto Brus, Abrojos Montezuma, Conte Burica, Altos de San Antonio and Guaymi de Osa. In the early 21st century, there are approximately 200,000-250,000 speakers of the Ngäbere language.
Guaymí, or Ngäbere, also known as Movere, Chiriquí, and Valiente, is spoken by the indigenous Ngäbe people in Panama and Costa Rica. The people refer to themselves as Ngäbe and to their language as Ngäbere. The Ngäbes are the most populous of Panama's several indigenous peoples. The language is centered in Panama within the semi-autonomous indigenous reservation known as the Comarca Ngäbe-Buglé. Beginning in the 1950s, Costa Rica began to receive Ngäbe immigrants, where they are found in several indigenous reservations: Abrojos Montezuma, Conteburica, Coto Brus, Guaymí de Alto Laguna de Osa, and Altos de San Antonio.
The history of the Baháʼí Faith in Panama begins with a mention by ʻAbdu'l-Bahá, then head of the Baháʼí Faith, in the book Tablets of the Divine Plan, published in 1919; the same year, Martha Root made a trip around South America and included Panama on the return leg of the trip up the west coast. The first pioneers began to settle in Panama in 1940. The first Baháʼí Local Spiritual Assembly of Panama, in Panama City, was elected in 1946, and the National Spiritual Assembly was first elected in 1961. The Baháʼís of Panama raised a Baháʼí House of Worship in 1972. In 1983 and again in 1992, some commemorative stamps were produced in Panama while the community turned its interests to the San Miguelito and Chiriquí regions of Panama with schools and a radio station. The Association of Religion Data Archives estimated there were some 41,000 Baháʼís in 2005 while another source places it closer to 60,000.
Khudoni Hydro Power Plant, hereinafter referred to as Khudoni HPP, is a projected power plant on Enguri River, in Samegrelo-Zemo Svaneti, Georgia that has 3 turbines with a nominal capacity of 233.3 MW each having a total capacity of 700 MW. The power plant is associated with a planned 200.5-metre (658 ft) tall concrete double-arch-gravity dam. According to the Georgian government-commissioned and the World Bank-supported study the construction of Namakhvani, Paravani and Khudoni hydro power plants are the most attractive scenarios for the development of Georgia's energy sector.
Loharinag Pala Hydropower Project is a run-of-the-river hydroelectricity generating project planned by the National Thermal Power Corporation (NTPC) Ltd to have an output capacity of 600 MW. The project is located on the river Bhagirathi, the headstream of the Ganges River at Loharinag Pala, below the confluence of the Songad River, next to NH 34 in Uttarkashi District of Uttarakhand state, India. This is about 100 kilometres (62 mi) upstream of the Tehri Dam.
The Myitsone Dam is a large dam and hydroelectric power development project which was planned to be built in northern Myanmar. The proposed construction site is at the confluence of the Mali and N’mai rivers and the source of the Irawaddy River. As of 2017 the project is suspended, but China has been lobbying to revive the dam.
The proposed Kallak mine is a, highly controversial, plan to exploit one of the largest unexploited iron ore deposits in Sweden.
The Lower Se San 2 Dam is a hydroelectric dam under development on the Se San River in Stung Treng Province, northeastern Cambodia. The Se San River is a major tributary of the Mekong River. The dam site is located 25 kilometres (16 mi) east of the provincial capital, also named Stung Treng. The first turbine began producing electricity in November 2017. The dam was officially opened on December 18, 2018.
The Don Sahong is a hydroelectric dam commissioned in 2020 on the Mekong River in Siphandone area of Champasak Province, Laos, less than two kilometers upstream of the Laos–Cambodia border.
The Jirau Dam is a rock-fill dam with an asphalt-concrete core, in the Madeira River in the state of Rondônia, Brazil. The dam's hydroelectric power stations have 50 turbines each 75 MW resulting total installed capacity of 3,750 MW. The power plant's first unit was commissioned in September 2013, the 16th in November 2014, 24th in February 2015, the 41st in December 2015, and the last in December 2016. Most of the power is designed to be exported to south-eastern Brazil via the Rio Madeira HVDC system.
Silvia Carrera Concepción is the current General Cacique of the Ngöbe-Buglé Comarca autonomous indigenous territory of western Panama. She was elected in September 2011.
The Baram Dam, also known as Baram 1 Dam and Baram Hydro-electric Dam Project is a proposed gravity dam on the Baram River in Sarawak, Malaysia. The site of the dam is 250 kilometres (160 mi) inland from Miri, the second largest city in Sarawak. The dam is part of the Sarawak Corridor of Renewable Energy and, if completed, would support a 1,200 MW power station. In November 2015, the Sarawak Chief Minister Tan Sri Adenan Satem announced that the Sarawak government had decided to shelf the Baram Dam because the people in Baram did not welcome the plan.
Mining and hydroelectric projects in Panama are heavily discussed topics in Panama due to several laws for the protection of the native inhabitants and the neo-liberal plans of the government. Since the beginning of 2011 large protests against such mining and hydroelectric projects have been held by the indigenous inhabitants of Panama.
Sibon noalamina is a species of snail-eating snake discovered in 2012 from western Panama. It belongs to the genus Sibon. It has a striking defensive mechanism from predators by mimicking the light and dark stripes of venomous coral snakes.
The Kaliwa Low Dam was proposed by the Philippine Government in 2012, was one of several bulk water supply projects on the upper portion of the Kaliwa River Watershed that have been proposed but ultimately shelved by the Philippine Government since the 1970s.
Moglicë Hydro Power Plant is a large hydroelectricity plant on the river Devoll situated near the village Moglicë, Albania. The project consists of a large power plant with an installed capacity of 197 MW and an average annual production of 475 GWh. It was built by Devoll Hydropower, an Albanian company owned by Norwegian power company Statkraft. The asphalt-core rock-fill dam is 320 m long, 150 m high and 460 m wide. The dam is anticipated to be the world's highest of its kind upon completion. The reservoir has a surface area of 7.2 km2, and a storage capacity of about 380 million m3. The power plant is part of the Devoll Hydropower Project and construction on it began in June 2013. Main structures of dam were completed in June 2019. Commercial operations were started in June 2020.
The New Bong Escape Hydropower Project is a privately owned 84 MW run-of-the-river project located on Jhelum River 7.5 km downstream of the 1,070 MW Mangla Dam, a major multi-purpose water storage project commissioned. It is about 120 km from Islamabad, the capital city of Pakistan. The project commenced commercial operations on 23 March, 2013 and has the distinction of being Pakistan and AJ&K’s first hydropower IPP. By developing a bankable framework this trendsetting project has paved the way for rapid and full scale development of Pakistan and AJ&K’s hydropower potential.