Berlin 380-kV electric line

Last updated
Cross section of a 400 kV cable Hochspannungskabel 400kV Querschnitt.JPG
Cross section of a 400 kV cable

The Berlin 380 kV electric line is a 38.3-km double-circuit high-voltage electric three-phase power line in Berlin. An unusual system for a municipality, it was installed by the West Berlin Bewag utility company during the division of the city. Since 1951, West Berlin had been cut off from the East Berlin and East German power networks, and maintained an independent power generation capacity that was not connected to any other power grid. Berlin was connected to the western European power grid in 1994, following German reunification, by extending the 380 kV line.

Contents

Concrete / steel lattice tower next to the Reuter West cooling tower HKW Reuter West Kuehlturm.jpg
Concrete / steel lattice tower next to the Reuter West cooling tower

The first section of the line, which entered service in 1977, was an interconnector that consisted of a 2.6 km overhead transmission line and an 8.1 km underground cable, which ran from Reuter power station in Spandau to Mitte substation in Tiergarten ("Mitte" means "central"; the district of Berlin-Mitte was then in East Berlin). It was the first time plastic insulators had been used. The overhead segment and an adjacent 110-kV line are the only overhead lines in former West Berlin. The underground section used water-cooled cable in an accessible tunnel. Both substations use totally enclosed SF6-insulated switchgear. They are the oldest 380 kV substations with SF6 technology in Germany. Another speciality of the Berlin power grid is that the first pylon near Reuter power station has been built as a 66-metre-high (217 ft) concrete structure with transversal steel lattice mimicking a chimney for aesthetical reasons.

After German reunification the line was extended 7.6 km further west to Teufelsbruch substation in Spandau Forest, near Berlin's western border, in 1994. The city was finally relinked to the western German power grid via a new 170 km (106 mi) transmission line to Helmstedt, just across the former inner-German border.

At the same time, the 380 kV line was extended into former East Berlin via a 6.3 km (3.9 mi) tunnel to Friedrichshain substation (1998), extended 5.2 km to Marzahn substation in 2000. [1] From Marzahn substation a 12 km long 380 kV overhead powerline was built in 1998 to Neuenhagen substation east of Berlin in order to create a second connector to the Western European grid. The tunnel is up to 30 m deep, and has a small inspection railway. [2] After the line was complete, several overhead lines in former East Berlin were dismantled. There are plans for further 380 kV lines to other parts of the high voltage grid north and west of Berlin. [3] [4]

Map

Berlin location map.svg
Red pog.svg
UW Teufelsbruch
Red pog.svg
UW KW Reuter
Red pog.svg
Chimney pylon
Red pog.svg
Lattice pylon
Red pog.svg
UW Mitte
Red pog.svg
UW Friedrichshain
Red pog.svg
UW Marzahn
Red pog.svg
UW Neuenhagen
Location of the 380 kV transversal line's components

Related Research Articles

<span class="mw-page-title-main">Overhead line</span> Cable that provides power to electric railways, trams, and trolleybuses

An overhead line or overhead wire is an electrical cable that is used to transmit electrical energy to electric locomotives, trolleybuses or trams. The generic term used by the International Union of Railways for the technology is overhead line. It is known variously as overhead catenary, overhead contact line (OCL), overhead contact system (OCS), overhead equipment (OHE), overhead line equipment, overhead lines (OHL), overhead wiring (OHW), traction wire, and trolley wire.

<span class="mw-page-title-main">Transmission tower</span> Structure used to support an overhead power line

A transmission tower is a tall structure, usually a lattice tower made of steel that is used to support an overhead power line. In electrical grids, transmission towers carry high-voltage transmission lines that transport bulk electric power from generating stations to electrical substations, from which electricity is delivered to end consumers; moreover, utility poles are used to support lower-voltage sub-transmission and distribution lines that transport electricity from substations to electricity customers.

<span class="mw-page-title-main">Kontek</span> HVDC connector between Germany and Denmark

The Kontek HVDC is a 170-kilometre (110 mi) long, monopolar 400 kV high-voltage direct current cable between Germany and the Danish island Zealand. Its name comes from "continent" and the name of the former Danish power transmission company "Elkraft", which operated the power grid on the Danish islands Lolland, Falster and Zealand and had the abbreviation "ek". As of today, the cable is operated by Energinet.dk in Denmark and 50Hertz Transmission GmbH in Germany.

<span class="mw-page-title-main">Baltic Cable</span>

The Baltic Cable is a monopolar HVDC power line running beneath the Baltic Sea that interconnects the electric power grids of Germany and Sweden. Its maximum transmission power is 600 megawatts (MW).

<span class="mw-page-title-main">GK Wien–Southeast</span>

The GK Vienna–Southeast was a back-to-back HVDC station linking the electric power grids of Austria and Hungary. It operated between June 1993 and October 1996.

<span class="mw-page-title-main">Pylons of Messina</span> Historic high-voltage towers in Italy

The Pylons of Messina are two free-standing steel towers, the Sicilian one in Torre Faro and the Calabrian one in Villa San Giovanni. They were used from 1955 to 1994 to carry a 220 kilovolt power line across the Strait of Messina, between the Scilla substation in Calabria on the Italian mainland at 38°14′42″N15°40′59″E and the Messina-Santo substation in Sicily at 38°15′57″N15°39′04″E.

<span class="mw-page-title-main">Overhead power line</span> Above-ground structure for bulk transfer and distribution of electricity

An overhead power line is a structure used in electric power transmission and distribution to transmit electrical energy along large distances. It consists of one or more conductors suspended by towers or poles. Since most of the insulation is provided by air, overhead power lines are generally the lowest-cost method of power transmission for large quantities of electric energy.

<span class="mw-page-title-main">Traction power network</span> Electricity grid for the supply of electrified rail networks

A traction network or traction power network is an electricity grid for the supply of electrified rail networks. The installation of a separate traction network generally is done only if the railway in question uses alternating current (AC) with a frequency lower than that of the national grid, such as in Germany, Austria and Switzerland.

<span class="mw-page-title-main">Boroughs and neighborhoods of Berlin</span> Areas within Berlin, Germany

Berlin is both a city and one of Germany's federated states. Since the 2001 administrative reform, it has been made up of twelve districts, each with its own administrative body. However, unlike the municipalities and counties of other German states, the Berlin districts are not territorial corporations of public law with autonomous competencies and property, but simple administrative agencies of Berlin's state and city government, the City of Berlin forming a single municipality since the Greater Berlin Act of 1920. Thus they cannot be equated to US or UK boroughs in the traditional meaning of the term.

TenneT is a transmission system operator in the Netherlands and in a large part of Germany.

<span class="mw-page-title-main">GKK Etzenricht</span>

GKK Etzenricht, an abbreviation of Gleichstromkurzkupplung Etzenricht, meaning Etzenricht HVDC-back-to-back station, was an HVDC back-to-back facility near Etzenricht in the district of Neustadt an der Waldnaab in Bavaria, Germany. It was built on the site of the Etzenricht substation, a 380 kV/220 kV/110 kV-substation, which went into service in 1970 and expanded afterwards several times. The facility was used between 1993 and 1995 for the exchange of power between Germany and the Czech Republic, operated by Bayernwerk AG.

<span class="mw-page-title-main">Civil and Electrical Projects Contracting Company</span> Saudi Arabian construction company

CEPCO is a construction company with corporate headquarters in Jeddah, Saudi Arabia, with offices throughout Saudi Arabia and in Middle East. CEPCO has been in business since 1977 and provides construction services in the fields of Civil & Infrastructure, Electrical, Horizontal Directional Drilling, Electromechanical, Oil, Gas & Power.

<span class="mw-page-title-main">50Hertz Transmission GmbH</span>

50Hertz Transmission GmbH, formerly named Vattenfall Europe Transmission, is one of four transmission system operators for electricity in Germany, and is wholly owned by Eurogrid GmbH, indirectly owned and managed by the Belgian transmission system operator Elia System Operator and Australian-based IFM Investors. The company is a member of the European Network of Transmission System Operators for Electricity (ENTSO-E).

<span class="mw-page-title-main">Electricity sector in Germany</span> Overview of the electricity sector in Germany

Germany's electrical grid is part of the Synchronous grid of Continental Europe. In 2020, due to COVID-19 conditions and strong winds, Germany produced 484 TW⋅h of electricity of which over 50% was from renewable energy sources, 24% from coal, and 12% from natural gas. This is the first year renewables represented more than 50% of the total electricity production and a major change from 2018, when a full 38% was from coal, only 40% was from renewable energy sources, and 8% was from natural gas.

Powerline river crossings comprise both overhead lines and cable tunnels beneath rivers and estuaries. Overhead power lines are supported on towers which are usually significantly taller than overland pylons and are more widely spaced to cross the river in a single span. Tall pylons ensure that the electricity cables which they support provide an adequate safety clearance for river traffic.

Viking Link is a 1,400 MW HVDC submarine power cable nearing completion between the United Kingdom and Denmark.

The Lower Lea Valley Cable Tunnels, known as the PLUG Project during construction, are a pair of 6 km cable tunnels running beneath the lower Lea Valley in east London. Constructed at a cost of £130m ahead of the 2012 London Olympic Games, they are owned by National Grid plc and UK Power Networks.

The River Medway Cable Tunnels are a pair of tunnels carrying high-voltage electricity transmission lines beneath the lower River Medway between the Isle of Grain and Chetney Marshes, Kent.

The Severn-Wye Cable Tunnel, also known as the Severn Cable Tunnel, carries high-voltage electricity transmission lines beneath the estuaries of the River Severn and River Wye between Newhouse (Mathern), Monmouthshire and Aust, South Gloucestershire.

References

  1. GmbH(info@portalhaus.de), Ein Produkt der PortalHaus Internetservices. "Bewag mit westeuropäischem Stromnetz verbunden". www.stromtip.de (in German).
  2. "50hertz.com > Grid > Grid developement[sic] > Onshore projects > 380-kV Berlin diagonal power link". www.50hertz.com.
  3. "50hertz.com > Grid > Grid developement[sic] > Onshore projects > Uckermark Line". www.50hertz.com.
  4. "50hertz.com > Grid > Grid developement[sic] > Onshore projects > 380 kV overhead line "Nordring Berlin"". www.50hertz.com.