Canning Dam | |
---|---|
Location | Ashendon, City of Armadale, Western Australia |
Coordinates | 32°9′9″S116°7′42″E / 32.15250°S 116.12833°E |
Construction began | 1933 |
Opening date | 1940 |
Construction cost | AU£1.1 million |
Operator(s) | Water Corporation |
Dam and spillways | |
Impounds | Canning River |
Height | 66 metres (217 ft) |
Length | 466 metres (1,529 ft) |
Reservoir | |
Creates | Canning Reservoir |
Total capacity | 90,352 megalitres (73,250 acre⋅ft) |
Catchment area | 804 square kilometres (310 sq mi) [nb 1] |
Surface area | 501 hectares (1.93 sq mi) |
Official name | Canning Dam |
Type | City of Armadale Municipal Inventory |
Designated | 1 December 2008 |
Reference no. | 3830 |
The Canning Dam and reservoir are a major source of fresh water for the city of Perth, Western Australia. The dam is situated on the Darling Scarp and is an impoundment of the Canning River. It is noted for its innovative structural and hydraulic design that was considered to be at the forefront of concrete gravity dam design at the time of construction in from 1933 to its completion 1940. [1] [2]
The Canning Dam was Perth's primary water supply up until the 1961 when other sources of fresh water were tapped, such as the Serpentine dam. [2] Currently the dam supplies approximately 20 percent of Perth's fresh water. Inflow into the Canning Reservoir is estimated to be 22 gigalitres (0.78 billion cubic feet), and it has a storage capacity of 90.352 gigalitres (3.1908 billion cubic feet).
Since its completion in 1940, the Canning Dam has contributed to a wide range of environmental and ecological problems in surrounding regions, problems include more common algal blooms, habitat loss and sedimentation. Despite these issues, Canning Dam and the adjacent parks and forests provide a variety of recreational activities for the public such as bushwalking, historic walks and picnic facilities.
Development of the Canning River as a source of water for Perth was first proposed in a report of the first Metropolitan Water Works Board of Perth in 1896. [1] Investigation of the site began in 1897 when engineer Thomas Hodgson surveyed and proposed the dam's current location as a possible site. [3] However, despite the recommendations of further inquiries, and an extreme shortage of water in some years, government funds were not allocated for the construction of a dam until the Great Depression in the 1930s.
In March 1923, Premier James Mitchell announced that the Canning River would be dammed as part of the Hills Water Supply Scheme, along with Churchman Brook Dam and Wungong Dam. The scheme was intended to rectify severe water shortages in metropolitan Perth. [4] In 1924 a small pipehead dam was built 6 kilometres (4 mi) downstream from the present Canning Dam. It was intended as only a quick fix to the water supply problem and it soon became apparent that a major reservoir was needed, although it was nine years before work on the current Canning Dam began. The new dam was completed in 1940 at a cost of AU£1.1 million. [5] Engineer Russell Dumas designed the dam and directed most of its construction. [1]
A further improvement was made in 1951 when a concrete-lined channel was constructed to divert stream flow from the nearby Kangaroo Gully catchment. The Canning Dam and reservoir was Perth's primary source of water until the boom growth of the city in the 1960s and the completion of Serpentine Dam in 1961. [1] In 1975 the reservoir was connected to Perth's Integrated Water Supply System by the Canning Tunnel. [6] Prior to its opening water had flowed through the Canning Contour Channel to Gosnells. [1]
The Canning Dam and reservoir still supplies approximately 20 percent of Perth's drinking water requirements and plays an important role in the context of the development of Perth.
The Canning reservoir is also used to store water from Kwinana Desalination Plant. [7] Treated water can be pumped from the plant to the reservoir through the Forrestdale Pumping Station.
The Canning Dam Catchment lies within the Darling Scarp which forms part of an Archaean Shield composed largely of granite with some invaded linear belts of metamorphosed sedimentary and volcanic rocks. [8]
The dam wall is situated in a narrow gorge running east and west, with rock sides sloping upward from the river bed. Behind the dam wall, the south branch of the Canning River joins the main stream, with the impounded water forming a lake which stretches back in three major arms to the east south-east and south. [8]
The catchment has an area of 804 square kilometres (310 sq mi). The reservoir is at 200 metres (660 ft) AHD and the highest point of the catchment, Mount Cooke is at 582 metres (1,909 ft) AHD. [8]
Climatically, the area receives about 900 millimetres (35 in) of rainfall per annum with most of this falling between May and September. [8] There is a large variability of rainfall across the catchment however, from between 700 and 1,300 millimetres (28 and 51 in). [8]
Since 1975 long-term average rainfalls at the dam wall have decreased by 20 percent and streamflow into the catchment by approximately 60 percent—the average annual inflow between 1948 and 1974 was 52 gigalitres (1.8 billion cubic feet) which had reduced to 22 gigalitres (0.78 billion cubic feet) between 1975 and 2004. [8] [9]
The construction of Canning Dam ended a long period during which Perth's water supply was generally unsatisfactory in quality (either due to salinity or bacterial pollution or both) and in quantity. [1] The project, the biggest public works program of the decade, stimulated significant growth in the local economy and provided desperately needed work for around five hundred men. [5]
Several innovative design concepts and construction methods which were new to Australia were introduced on the project, while others which were used on the nearby Wellington Dam, were improved upon at the Canning dam site.
At the Canning Dam, as with all dams, care had to be taken to prevent water seepage between the foundation rock and the structure of the dam. [1] At the Canning, in addition to cutting back the foundation to solid unfractured rock, a cut-off trench was sited near the upstream face of the dam, down stream of which a rock filled drain containing open jointed pipes was provided to intercept any seepage between the rock face and the concrete of the dam. The inclusion of an internal drainage system was considered innovative at the time. [1] Near-vertical tubular 8-inch (200 mm) cut-off drains were provided at 5-foot (1.5 m) intervals along the dam to relieve internal seepage through the concrete.
While state of the art materials-handling methods were used, in some instances labour-saving machinery worked beside operations intended to maximise the labour content. Sustenance workers were employed for chiefly on-site preparation, road construction, foundation excavation, clearing timber from the reservoir basin, and on some concreting operations. Skilled workers were required on the dam for fixing the formwork where the concrete was poured. These workers were probably employed at normal day labour rates, the main employment method used on the project. [1] Bulk handling of cement was also used for the first time in Australia; this saw a significant saving as opposed to bagged cement, which was the standard practice of the day.
Generally construction work proceeded smoothly, and from an engineering point of view there were few setbacks. [3] However, one did occur in the early stages of construction. In March 1934 a violent storm brought 130 mm (5.12 in) of rain in less than two days. As a result, the river rose rapidly, flooding the dam foundation workings. Pumps had to be installed and work resumed three days later.
The dam was completed in September 1940. When built it was the longest concrete gravity dam in Australia, [1] and also the second highest after the Burrinjuck Dam in New South Wales. As of 1997, of the 90 large concrete and masonry gravity dams in Australia, the Canning Dam is still the fifth highest and the sixth longest. [1] It is the largest concrete dam in Western Australia in terms of length of crest and volume of concrete.
The final cost of the dam was significantly less than had been originally budgeted for, [3] and the work was completed on schedule to a date that was calculated seven years previously.
Recently[ timeframe? ] the Canning Dam has been subjected to considerable cracking of the upper parts of the dam and upper gallery. Investigations have shown that cracking was due to strong alkali aggregate reactivity (AAR) in the concrete. [10] AAR results in swelling of the concrete, which may cause secondary compressive stresses, localised map cracks, and, ultimately structural cracks. In addition, the concrete tensile strength and elasticity significantly decreases. Many old concrete dams are known to suffer from AAR, including Fontana Dam in Tennessee and Pian Telessio dam in Italy. [11]
Extensive remedial works were undertaken between 1999 and 2001 to strengthen the dam wall. [12] This work involved removing the top 3.8 m (12 ft) of the existing dam wall and drilling/blasting through the dam wall plus up to a further 70 m (230 ft) into the bedrock below. The top section of the wall was then rebuilt using reinforced concrete. Finally, permanent, re-stressable ground anchors were installed through the formed and drilled holes from the crest to be stressed and grouted into the foundation rock. At time of completion, these were the largest capacity and longest permanent ground anchors installed in the world. [13]
An innovative drilling and blasting technique called penetrating cone fracture (PCF) was used in the remedial works process. PCF was chosen over conventional drilling and/or blasting techniques due to the reduced risk of damage to the existing structure from vibration, as well as lower noxious fume and dust levels. [14]
Since the construction of the Canning Dam, among other drinking water supply dams, water flow into the Canning River has been reduced by up to 96%. [15] A number of freshwater fish species endemic to the south-west of Western Australia are found in the Canning River system, however studies of fish and fish habitats in the area have shown that fish numbers are low due to a loss of habitat and a loss of linkage between breeding areas due to low flows, preventing fish migrating upstream and reaching important breeding and nursery grounds. [16] Stagnant water caused by a lack of water flow has provided a suitable habitat for successful breeding of an introduced pest, the mosquitofish. [17]
Damming of the Canning caused dramatic flow reductions that significantly altered downstream aquatic macroinvertebrate communities. [18] The lack of water flow has also resulted in a poor flushing effect below the dam wall. An excessive amount of nutrients from fertilizers and animal waste has caused algal blooms and eutrophication. [19]
Many river pools, which are an important summer refuge and habitat for aquatic and terrestrial flora and fauna, have been lost due to sedimentation and modification of the flow regime caused by impoundments in the Canning River. [17]
Periodic flooding of the Canning River from the dam is required to disperse seed, stimulate germination and ensure seedlings survive, recharge shallow groundwater tables that are important during periods of drought, and to discourage and prevent weed growth. [17] However, during times of low rainfall periodic flooding is reduced.
A number of recreation activities occur in and around the dam and catchment area. [8] Canning Dam features a number of picnic areas (with gas barbecues), look outs and historic walks – many with disabled access. [20] Bushwalking occurs throughout the catchment, particularly along the Bibbulmun Track, which passes through the catchment about 10 km upstream of Canning Dam. Several mountain bike trails run either through the Canning National Park or adjacent State Forest areas. [21]
The Canning Reservoir, Canning River and tributaries are illegally fished for marron, especially during summer. Boating, fishing and swimming are prohibited in the reservoir for health and hygiene reasons. Unauthorised camping (including overnight stays and/or outside of designated areas) and unauthorised trail establishment occur more and more frequently in the Canning catchment. [8]
The dam received a Historic Engineering Marker from Engineers Australia as part of its Engineering Heritage Recognition Program. [22]
Warragamba Dam is a heritage-listed dam in the outer South Western Sydney suburb of Warragamba, Wollondilly Shire in New South Wales, Australia. It is a concrete gravity dam, which creates Lake Burragorang, the primary reservoir for water supply for the city of Sydney. The dam wall is located approximately 65 kilometres (40 mi) W of Sydney central business district, 4½ km SW of the town of Wallacia, and 1 km NW of the village of Warragamba.
Lake Argyle is Western Australia's largest and Australia's second largest freshwater man-made reservoir by volume. The reservoir is part of the Ord River Irrigation Scheme and is located near the East Kimberley town of Kununurra. The lake flooded large parts of the Shire of Wyndham-East Kimberley on the Kimberley Plateau about 80 kilometres (50 mi) inland from the Joseph Bonaparte Gulf, close to the border with the Northern Territory.
The Somerset Dam is a mass concrete gravity dam with a gated spillway across the Stanley River in Queensland, Australia. It is within the locality of Somerset Dam in the Somerset Region in South East Queensland. The main purpose of the dam is the supply of potable water for the Brisbane, Gold Coast and Logan City regions. Additionally, the dam provides for flood mitigation, recreation and for the generation of hydroelectricity. The impounded reservoir is called Lake Somerset.
The Blowering Dam is a major ungated rock fill with clay core embankment dam with concrete chute spillway impounding a reservoir under the same name. It is located on the Tumut River upstream of Tumut in the Snowy Mountains region of New South Wales, Australia. Purposes for the dam include flood mitigation, hydro-power, irrigation, water supply and conservation. The dam is part of the Snowy Mountains Scheme, a vast hydroelectricity and irrigation complex constructed in south-east Australia between 1949 and 1974 and now run by Snowy Hydro.
The Wivenhoe Dam is a rock and earth-fill embankment dam with a concrete spillway across the Brisbane River in South East Queensland, Australia. The dam takes it names from the local Wivenhoe Pocket rural community. The dam wall is located about 80 kilometres (50 mi) by road from the centre of Brisbane. The primary purpose of the dam is the supply of potable water for the Brisbane and Ipswich regions. South-east Queensland's largest dam also provides for flood mitigation control, hydroelectricity, and recreation. The impounded reservoir is called Lake Wivenhoe and the dam, the lake and a narrow strip of surrounding land forms a locality also called Lake Wivenhoe.
The Avon Dam is a heritage-listed dam at Avon, in the New South Wales Southern Highlands, Australia. It is one of four dams and weirs in the catchment of the Upper Nepean Scheme, providing water to the Macarthur and Illawarra regions, the Wollondilly Shire, and metropolitan Sydney. The arch dam across the Avon River was completed in 1927 under the supervision of Ernest Macartney de Burgh, the dam is currently managed by the Sydney Catchment Authority and is listed on the New South Wales State Heritage Register.
Tallowa Dam, completed in 1976, is a concrete gravity dam with central overflow spillway, located on the Shoalhaven River, downstream from the river's confluence with the Kangaroo River. The dam wall of 325 cubic metres (11,500 cu ft) is 43 metres (141 ft) high and 528 metres (1,732 ft) in length. At 100% capacity, the dam wall holds back approximately 85,500 megalitres and creates the impounded reservoir of Lake Yarrunga that has a surface area of 831 hectares, drawn from a catchment area of 5,750 square kilometres (2,220 sq mi). The spillway has a discharge capacity of 27,600 cubic metres per second (970,000 cu ft/s).
The Serpentine Dam is a major water supply dam for Perth, Western Australia. The dam is used to store water that is released at a controlled rate to regulate the level in the Serpentine Pipehead Dam reservoir, which in turn feeds water to the metropolitan trunk main network depending on demand. Construction of the dam was completed in 1961.
Mangrove Creek Dam, a concrete faced rockfill embankment dam, is the primary reservoir for water supply to residents of the Central Coast in New South Wales, Australia.
South Dandalup Dam is a dam in Western Australia. It is located where the South Dandalup River flows out of Lake Banksiadale. The dam was built in 1971 in response to rapid population growth in Perth, Western Australia's capital city, and a resources boom in the Pilbara.
Split Rock Dam is a minor ungated concrete faced rock fill embankment dam with concrete chute spillway across the Manilla River upstream of Manilla in the north-western slopes region of New South Wales, Australia. The dam's purpose includes flood mitigation, irrigation, water supply and conservation. The impounded reservoir is called Split Rock Reservoir.
Chaffey Dam is a minor ungated rock fill with clay core embankment dam with an uncontrolled morning glory spillway across the Peel River, located upstream of the city of Tamworth, in the New England region of New South Wales, Australia. The dam's purpose includes flood mitigation, irrigation, water supply, and water conservation.
Chichester Dam is a minor concrete gravity dam across the Chichester and Wangat rivers, upstream of Dungog, in the Hunter Region of New South Wales, Australia. The dam's main purpose is water supply for the Lower Hunter region. A mini hydro-electric power station operates at times of peak flow and is connected to the national grid. The impounded reservoir is Lake Chichester.
The Victoria Dam is a water supply dam providing water for the city of Perth, Western Australia. It is situated on the Darling Scarp near Lesmurdie, and crosses Munday Brook. Two dams have stood at the present site; the older dam was the first permanent water supply for the colony and also the first dam in Western Australia. It stood for almost 100 years before being replaced with the current dam.
Churchman Brook Dam is an earth-fill embankment dam approximately 30 kilometres (20 mi) southeast of Perth, Western Australia in the City of Armadale. The reservoir is a water source for Perth.
The Cotter Dam is a concrete gravity and rockfill embankment dam across the Cotter River, located in the Australian Capital Territory, Australia. Both the dam and river are named after early settler in the area Garrett Cotter. The impounded Cotter Reservoir is a supply source of potable water for the city of Canberra and its environs.
Oberon Dam or Fish River Dam is a major ungated concrete slab and buttress with earth embankment dam comprising a concrete ski jump chute spillway and fuse plug across the Fish River upstream of Oberon in the Central Tablelands region of New South Wales, Australia. The dam's purpose includes flood mitigation, industrial, and water supply. The impounded reservoir is called Lake Oberon.
The Tod Reservoir is located on the Eyre Peninsula in South Australia, in the localities of Whites Flat and Koppio, 27 km north of Port Lincoln. It is situated on the Tod River, the only stream on Eyre Peninsula, South Australia providing reliable flows; the reservoir is supplied by concrete channels fed from weirs constructed across the Tod River and its major tributary, Pillaworta Creek. The river was named after Robert Tod, who discovered it during explorations in 1839. The Tod River flows into Louth Bay in Spencer Gulf. The reservoir is listed on the South Australian Heritage Register.
The Meander Dam is a concrete gravity dam across the Upper Meander River, located in northern Tasmania, Australia. The impounded reservoir is called Lake Huntsman.
North Dandalup Dam is a dam in Western Australia. It is located 63.8 kilometres (39.6 mi) south of Perth in the Darling Scarp, which forms the western border of the Darling Ranges. Constructed in 1994, it was opened by the then state Premier Richard Court in October of that year. It was the final project in a dam-building scheme that also includes the Victoria and Conjurunjup Dams.
{{cite journal}}
: Cite journal requires |journal=
(help)