Greater Anglia Route Utilisation Strategy

Last updated

The Greater Anglia Route Utilisation Strategy is a Route Utilisation Strategy published by Network Rail in December 2007. [1] It was the sixth RUS to be produced. The area covered includes the whole of Route 5 West Anglia (WA) and Route 7 Great Eastern (GE), which both focus for passenger purposes on London Liverpool Street, and the London Fenchurch Street services from Route 6. As with other RUSs, the Greater Anglia RUS took into account a number of responses, [2] [3] [4] [5] [6] [7] including the Office of Rail Regulation (ORR). [8]

Contents

The routes and services covered by the RUS are varied in type. The key issues are peak crowding on inner suburban, outer suburban and some long-distance services, and the capacity of the routes to handle growing container freight traffic; however off-peak service gaps on main passenger routes are dealt with, and the routes also include a number of relatively lightly used services, though with some peak 'spikes'.

Like other strategies in this series, recommendations are divided into short-term (Control Period 3, CP3, the remaining 18 months to March 2009), medium-term (CP4, five years to March 2014), and long-term (CP5, thereafter). A summary of recommendations for each of the strategic routes (as described above) is also provided.

As with several other RUSs the chief solution recommended for peak crowding is to add cars to the trains, which in many cases will require platform extensions, or less commonly to provide additional services, which may require other infrastructural enhancements. The RUS also picks up from the Freight RUS the enhancements desired on the Ipswich-Peterborough freight route.

Recommendations

Short term

The short-term improvements are mainly minor enhancements to improve performance, but include the extension of the bay platform at Grays to accommodate 8-car trains.

Medium term (2009–14)

Thameside route: Minor infrastructure works and additional rolling stock to allow all main line peak-service trains to be extended progressively to 12-car formation; the extension of platforms on the Tilbury loop and Ockendon branch to handle 12 cars, to allow all main line peak-service trains to be extended progressively to 8 or 12-car formation.

Great Eastern route: All services to include a stop at Stratford, requiring a platform extension, to provide improved connectivity with TfL's system, to even out the peak flows, and release additional paths on the route; three additional trains per hour (tph) in each peak 3-hour period (12-car in the high peaks, 8 in the shoulder peaks), one from Colchester, one from Chelmsford, one from Southend; extending peak hour Southminster branch trains to 12-car; minor infrastructure works and replacement rolling stock in 5-car formation to provide more seats in the peak on the main line to Norwich; construction of a turnback facility at Chadwell Heath, to extend existing and additional morning peak services, and provide a regulating facility during times of disruption; power supply to be enhanced for some of these options.

West Anglia route: The extension of remaining non-compliant platforms on the Liverpool Street-Cambridge route and at Stansted Airport to handle 12 cars; the reinstatement of 9-car trains in the peaks on the Hertford East, Enfield Town, Cheshunt via Southbury and Chingford branch services, requiring a small amount of infrastructure; a shuttle service between Cheshunt and Seven Sisters, where a power-operated turnback would be provided, and where interchange with London Underground is available, should be introduced during the peaks; stabling and maintenance facilities for the larger, enhanced fleet; removal of the three level crossings between Tottenham Hale and Waltham Cross; power supply to be enhanced for some of these options and likely future requirements.

Freight Accommodating growth in freight traffic, predominantly containers from the Haven ports, mainly via the cross-country route to the ECML at Peterborough and the WCML at Nuneaton (for which W10 clearance works are in hand), but also via the paths remaining on the Great Eastern Main Line (GEML).

Cross-country passenger services There is an aspiration to provide hourly services on various cross country routes; the case for Ipswich-Peterborough is good, providing compatible timetabling with the freight service is possible; Ipswich-Lowestoft and Cambridge-Norwich would require infrastructure works and needs to be evaluated later, especially as passenger growth trends emerge.

Greater Anglia perspective Doubling of Haughley Junction (on the Cambridge-Stowmarket route), full commissioning of Ely West Curve, and accommodating Class 6 freight trains, all to improve performance.

Longer term (to 2019, and beyond)

Thameside route Continued lengthening of (mainly shoulder) peak trains to 12-car formation.

Great Eastern route Continued lengthening of (mainly shoulder) peak trains to 12-car formation; additional stabling facilities.

West Anglia Four-tracking of the route between Coppermill Junction (south of Tottenham Hale station) and Broxbourne junction, where the Cambridge/Stansted and Hertford East lines diverge; an additional tunnel and platform edge on the Stansted Airport branch; 1 additional tph serving Stansted; up to six peak time extra tph, including four into Stratford as a terminus; after Crossrail implementation (which releases GE paths between Liverpool Street and Stratford) extending these Stratford services to Liverpool Street, and diverting some Chingford services via a reinstated Hall Farm Curve and Stratford, in turn releasing paths between Hackney Downs and Bethnal Green.

Freight Accommodating further growth in freight traffic, including higher capacity in the Leicester area in line with scheduled resignalling.

Crossrail Within this timeframe the east-west London Crossrail project is scheduled to be opened; this will subsume GE inner suburban services at 10-car formation.

Combined effect through time by route

The benefit cost ratios of the recommendations over time is estimated as:

Subsequent developments

Grays bay platform extension authorised to completion.

Report by Passenger Watch on car parking restrictions. [9]

NR CP4 Delivery Plan 2009

In March 2009 Network Rail published its CP4 Delivery Plan 2009, including Enhancements programme: statement of scope, outputs and milestones, [10] confirming several of the recommended interventions. Specific projects, with their reference and page numbers in the document, are given below:

Related Research Articles

<span class="mw-page-title-main">Custom House station</span> Railway and DLR station in London

Custom House is a railway station on the Docklands Light Railway (DLR) – on which it is branded Custom House for ExCeL – and on the Elizabeth line, by the Royal Docks, in Custom House in the London Borough of Newham, London, England. It is situated in Travelcard Zone 3. It takes its name from the old Custom House, which formerly stood nearby, and ExCeL London which it serves.

<span class="mw-page-title-main">Great Eastern Main Line</span> Important railway corridor in England, UK

The Great Eastern Main Line is a 114.5-mile (184.3 km) major railway line on the British railway system which connects Liverpool Street station in central London with destinations in east London and the East of England, including Shenfield, Chelmsford, Colchester, Ipswich and Norwich. Its numerous branches also connect the main line to Southminster, Braintree, Sudbury, Harwich and a number of coastal towns including Southend-on-Sea, Clacton-on-Sea, Walton-on-the-Naze and Lowestoft.

<span class="mw-page-title-main">Tottenham Hale station</span> London Underground and railway station in the London Borough of Haringey

Tottenham Hale is a National Rail and London Underground interchange station located in Tottenham Hale in north London, England. On the National Rail network it is on the West Anglia Main Line, 6 miles (9.7 km) from London Liverpool Street, and is served by Greater Anglia and Stansted Express. On the Underground it is on the Victoria line between Blackhorse Road and Seven Sisters. The station is in Travelcard Zone 3.

<span class="mw-page-title-main">Northumberland Park railway station</span> National Rail station in London, England

Northumberland Park railway station is on the Lea Valley line that forms part of the West Anglia Main Line, serving the ward of Northumberland Park in Tottenham, north London. It is 6 miles 73 chains (11.1 km) down the line from London Liverpool Street and is situated between Tottenham Hale and Meridian Water. Its three-letter station code is NUM and it is in Travelcard zone 3. It is one of the stations that can be used to access Tottenham Hotspur Stadium.

<span class="mw-page-title-main">West Anglia Main Line</span> Mainline railway line in East Anglia, England

The West Anglia Main Line is one of the two main lines that operate out of Liverpool Street. It runs generally north through Cheshunt, Broxbourne, Harlow, Bishop's Stortford and Audley End to Cambridge, with branches between serving Stratford, Hertford and Stansted Airport. The line runs along the boundary between Hertfordshire and Essex for much of its length.

<span class="mw-page-title-main">Shenfield railway station</span> National Rail station in Essex, England

Shenfield railway station is on the Great Eastern Main Line in the East of England, serving the town of Shenfield, Essex. As well as being a key interchange for medium- and long-distance services on the main line, it is also the western terminus of a branch line to Southend Victoria and one of the two eastern termini of the Elizabeth line. It is 20 miles 16 chains (32.51 km) down the line from Liverpool Street and is situated between Brentwood and either Ingatestone on the main line or Billericay on the branch line. Its three-letter station code is SNF.

<span class="mw-page-title-main">Bishop's Stortford railway station</span> Railway station in Hertfordshire, England

Bishop's Stortford railway station is on the West Anglia Main Line serving the town of Bishop's Stortford in Hertfordshire, England. It is 30 miles 27 chains (48.8 km) down the line from London Liverpool Street and is situated between Sawbridgeworth and Stansted Mountfitchet stations. Its three-letter station code is BIS.

<span class="mw-page-title-main">Harlow Town railway station</span> Railway station in Essex, England

Harlow Town railway station is on the West Anglia Main Line serving the town of Harlow in Essex, England. It is 22 miles 59 chains (36.6 km) down the line from London Liverpool Street and is situated between Roydon and Harlow Mill stations. Its three-letter station code is HWN.

The Cross London Route Utilisation Strategy (CLRUS) was the second of the route utilisation strategies (RUS) published by Network Rail (NR), in August 2006. It was included in a map published by the Office of Rail Regulation as established in May 2007.

The Freight Route Utilisation Strategy is a Route Utilisation Strategy in the United Kingdom, published by Network Rail in March 2007. It is one of only two which have the perspective of the network as whole. It was included in a map published by the Office of Rail Regulation (ORR) as established in May 2007. As with other RUSs, the Freight RUS took into account a number of responses to a Draft for Consultation, including those from the ORR.

The Scotland Route Utilisation Strategy is a Route Utilisation Strategy, published by Network Rail in March 2007, the third RUS to be published. The railways in Scotland are divided into three strategic routes, namely Route 24, Route 25 (Highlands) and Route 26 together with parts of Route 8 and Route 18. The three strategic routes form the scope of Network Rail's Scotland Route Utilisation Strategy. Separate RUSs for the ECML and WCML encompass the relevant parts of routes 8 and 18. The Edinburgh Crossrail service, which provides a direct route between Stirling, Dunblane and Bathgate in the west to Newcraighall in the east, operates over part of the ECML east of Edinburgh Waverley to Portobello Junction.

The North West Route Utilisation Strategy (NWRUS) is a Route Utilisation Strategy, published by Network Rail in May 2007. It was the fifth RUS to be produced. It was included in a map published by the Office of Rail Regulation as established in May 2007. It was the first of no fewer than 5 RUSs which cover specific routes in the north-west of England; the others are the Lancashire & Cumbria RUS, the Yorkshire & Humber RUS, the Merseyside RUS, and the West Coast Main Line RUS. In particular it "broadly covers the Manchester journey to work area, the City lines into Liverpool Lime Street and routes from Manchester to Kirkby, Southport and Blackpool", corresponding to Network Rail's then Route 20 - North West Urban.

The East Coast Main Line Route Utilisation Strategy (RUS), published by Network Rail in February 2008, was the seventh RUS.

Network Rail's (NR) South London Route Utilisation Strategy (SLRUS), published in March 2008 (SLRUS) was the eighth Route Utilisation Strategy to be produced. By default, RUSs are established by the Office of Rail Regulation (ORR) unless the latter objects within 60 days. The RUS is included in NR's map as established.

Strategic Route 5 - West Anglia was the designation given by Network Rail, from 2004 to 2009, to a grouping of railway lines in the East of England that encompassed the West Anglia Main Line and its various branch lines. The route provided key services to Cambridge and Stansted Airport as well as supporting suburban services in North London and rural services in Cambridgeshire, Norfolk and Suffolk.

Strategic Route 7 - Great Eastern was the designation given by Network Rail, from 2004 to 2009, to a grouping of railway lines in the East of England that encompassed the Great Eastern Main Line and its various branch lines. The route serviced the regional centres of Colchester, Ipswich and Norwich as well as the ports of Felixstowe and Harwich.

Strategic Route 6 - North London Line and Thameside was the designation Network Rail gave to a grouping of railway lines in Greater London and the East of England region that encompassed the London, Tilbury and Southend Line and overground commuter lines within London. The route provided key services to Southend and London suburban areas as well as supporting various freight routes within London.

The Merseyside Route Utilisation Strategy is a Route Utilisation Strategy published by Network Rail in March 2009. It was the eleventh RUS to be produced. By default, RUSs are established by the Office of Rail Regulation (ORR) unless the latter objects within 60 days. The RUS is included in Network Rail's map as established.

The Kent Route Utilisation Strategy (KRUS) is a Route Utilisation Strategy (RUS), published by Network Rail (NR) in January 2010. it was the thirteenth RUS to be completed, not counting the partially completed Network RUS. By default, RUSs are established by the Office of Rail Regulation (ORR) unless the latter objects within 60 days; and the ORR have confirmed no objection to the establishment of the Kent RUS.

The Sussex Route Utilisation Strategy is a Route Utilisation Strategy (RUS), published by Network Rail (NR) in January 2010. It was the fourteenth RUS to be completed, not counting the partially completed Network RUS. By default, RUSs are established by the Office of Rail Regulation (ORR) unless the latter objects within 60 days, and the ORR have confirmed no objection to the establishment of the Sussex RUS.

References

  1. Greater Anglia RUS. Networkrail.co.uk. Retrieved on 11 January 2012.
  2. Tfl's response to consultation. (PDF). Retrieved on 11 January 2012.
  3. Rail Freight Group response to consultation. Railfreightgroup.com. Retrieved on 11 January 2012.
  4. c2c response to consultation Archived 21 December 2010 at the Wayback Machine . Nationalexpressgroup.com. Retrieved on 11 January 2012.
  5. London TravelWatch response to consultation Archived 14 October 2007 at the Wayback Machine
  6. Ipswich Borough Council response to consultation [ permanent dead link ]. Cms.ipswich.gov.uk (6 January 2012). Retrieved on 11 January 2012.
  7. London Councils’ TEC Executive Sub-Committee response Archived 20 July 2011 at the Wayback Machine . None. Retrieved on 11 January 2012.
  8. ORR's response to consultation Archived 14 December 2007 at the Wayback Machine . (PDF). Retrieved on 11 January 2012.
  9. Report by Passenger Watch on car parking restrictions. None. Retrieved on 11 January 2012.
  10. CP4 Delivery Plan Archived 2 September 2009 at the Wayback Machine . (PDF). Retrieved on 11 January 2012.