Indira Paryavaran Bhawan | |
---|---|
General information | |
Type | Office |
Address | 166, Jor Bagh Road, Block 17, Lodhi Colony New Delhi, Delhi 110003, India |
Construction started | January 25, 2011 |
Completed | October 31, 2013 |
Inaugurated | February 28, 2014 |
Cost | INR209 Cr |
Owner | Ministry of Environment, Forest and Climate Change |
Technical details | |
Floor count | G+7 (+3 basements floors) |
Floor area | 32,000 sq.m |
Lifts/elevators | 7 |
Design and construction | |
Architecture firm | Central Public Works Department |
Awards and prizes | LEED India Platinum, GRIHA 5 Star |
Other information | |
Parking | 330 Cars |
References | |
[1] |
Indira Paryavaran Bhawan is India's first on-site net-zero building located in New Delhi, India. The building houses the Ministry of Environment, Forest and Climate Change (MoEFCC) accommodating three ministers and their offices along with about 600 officials. The building, designed and constructed by the Central Public Works Department (CPWD), was completed in 2013 at a cost of INR 209 Crore. [2]
The inauguration of the building, 28 February 2014, was conducted by the then prime minister Dr. Manmohan Singh. [2] The building is rated as a five-star GRIHA (Green Rating for Integrated Habitat Assessment) by MNRE and LEED India Platinum by Indian Green Building Council (IGBC) rating. The building has its own solar power plant, sewage treatment facility, fully automatic robotic multi-level car parking system facility & puzzle parking facility, and geothermal heat exchange system. [3]
Indira Paryavaran Bhawan consists of two blocks within the premises connected through a corridor. Each block is a G+7 storey structure with 3 basements. The total floor area of the campus is 32,000 sq.metre. Each floor consists of office spaces, meeting rooms, conference rooms etc. The building consists of 7 elevators and a central atrium located in between the two blocks. [2]
Indira Paryavaran Bhawan is located in a composite climate zone, a mix of hot, dry, humid, and cold climatic conditions, and the design involves multiple active, passive, and renewable strategies to achieve net zero goal.[ citation needed ] The building is divided into 5 sections: Vayu (Wind), Agni (Fire), Jal (Water), Prithvi (Earth), and Aakash (Space) depicting the 5 elements that all matters are composed of, as per Hinduism. Indira Paryavaran Bhawan is a set example that impinges on society's consciousness towards environmental awareness for adopting green building concepts in India. [4]
The Union environment ministry is facing a challenge of a garden variety - bird droppings, soiling the courtyard of Indira Paryavaran Bhawan, which houses it, and is amongst the India's highest green-rated buildings. Individuals or organizations which will offer the best solution will be awarded an amount of ₹1 lakh.
The orientation of the building is set towards north south direction, to accommodate natural daylight and air movement in the building, a central atrium and corridor provide cross ventilation within the building.[ citation needed ]
More than 50% of the area outside the building is covered with plantations, to conserve as many existing trees as possible, out of a total of 79 trees, only 19 trees are cut and 11 trees are transplanted. The pathways and circulation roads in the building are made with grass paver blocks for ground water percolation and ground water recharge. The 7th floor of building also consists of a terrace garden. [2]
The building is designed to ensure daylight in more than 75% of the floor space and to reduce dependency on active lighting devices. The central atrium located between the two blocks allows natural movement of air due to stack effect. The provision of windows further enhances the process of cross ventilation.[ citation needed ]
The building envelope construction comprises heavy weight construction. The external wall consists of 30 cm thick Autoclave Aerated Concrete (AAC) block, 7 cm thick mineral wool insulation, 12 cm thick air gap and 12 cm thick 'Fal-G' [proprietary blend of fly ash (Fa), lime (L) and gypsum (G)] block brick, and has a U-value of .221 W/m2K. The external roof of the building consists of 2 cm thick clay tile, 6 cm thick cement mortar, 4 cm thick PUF insulation, 6 cm thick brick bat coba, 6 cm thick cement mortar,10 cm thick concrete. High reflectance terrace tiles are installed on the building roof for roof cool treatment - low heat ingress, high strength and hard wearing. Windows installed in the building with uPVC (Unplasticized Polyvinyl Chloride) frame are hermetically sealed double glazed with gas filling with a U-Value of 0.26 W/m2K and SHGC of 0.32 and aluminium frame. [5]
Fly ash bricks and heat-insulating Autoclave Aerated Concrete blocks along with fly ash-based mortar and plaster are used for walls. Low energy materials and locally available stones are utilized for flooring. Bamboo jute composite that is rapidly renewable is used for door frames and shutters. Low VOC paints are used to improvise indoor air quality. [2]
Energy efficient lights are provided in the interior and exterior lighting system of the building. To maximize energy efficiency in lighting, the artificial lighting in the building is regulated using a lux-level sensor. The lighting power density is kept close to 5 W/m2 which is 50% more efficient than the Energy Conservation Building Code 2007 requirement (Lighting Power Density = 11 W/m2). [6] The lighting load is supplied by the building integrated photovoltaic (BIPV) power plant. [2]
The building is centrally air conditioned. Chilled beam system technology is used to meet 160 TR air conditioning load of the building. The process of air conditioning happens by convection currents rather than air supply by ducts. The chilled beams are used from second to sixth floor and this system has reduced energy utilization by up to 50% as compared to the conventional system. Integrated building management is utilized to control HVAC equipment and to monitor related systems. For energy efficiency, the room temperature is maintained at 26 ±1 °C. [7]
To minimize the load on the HVAC system, a vertical closed loop system of geothermal heat exchange system is implemented. This is the first time it has been adopted on a large scale in a government building in India. The system takes advantage of the difference between the ambient temperature and the temperature below the ground level. [7]
The vertical closed loop system consists of 180 vertical bores all over the premises to a depth of 80 meters. A minimum distance of 3 meters between any two bores is retained. Every bore has a 32mm outer diameter HDPE pipe U-loop and is connected in the central air conditioning plant room to the condenser water pipe system. A single U-Loop with a heat rejection capacity of 0.9TR results in a heat rejection capacity of 160TR from 180 vertical bores, resulting in reduction of cooling tower load and subsequent reduction in water consumption.[ citation needed ]
A building integrated photovoltaic (BIPV) Power Plant has been installed on the entire roof surface of the building and court area. This clean and green renewable energy system has helped in meeting the energy demand of the building to achieve the target of net-zero energy.[ citation needed ]
Parameter | Quantity |
Capacity of Power Generation | 930 kW Peak |
Annual Energy Requirement | 14,00,000 Unit (kWh) |
Annual Energy Generation | 14,00,000 Unit (kWh) |
Net Energy Consumption | ZERO |
Total area | 6000 m2 |
Total area of Solar panels | 4600 m2 |
Type of Photovoltaic panel | Mono Crystalline 20% efficiency |
Number of panels | 2844 |
Nature of Power Generation | Grid Interactive |
Automated parking system is used on all 3 levels of the basement. The first basement is designed for the lobby and puzzle parking system for car entry and exit. The second and third basement floors use robotic dolly parking systems. The capacity for the first basement is 49, the second basement is 126, and the third basement is 170. [7]
The landscape and horticulture design of planting native species along with efficient irrigation systems are utilized leading up to 50% reduction in water requirement. The remaining water demand is met by recycling and reusing wastewater, and by implementation of rainwater harvesting systems. Additionally, low discharge and efficient water fixtures are installed including sensor urinals and dual flow cisterns. [2]
Annual Consumption | Conventional Design | Indira Paryavaran Bhawan | Saving |
---|---|---|---|
Electricity | 22,00,000 kWh | 14,00,000 kWh | 40% |
Water | 20,000 kL | 9,000 kL | 55% |
The building has received the following awards. [8]
Month, Year | Award |
---|---|
February 2013 | The Project received an award from Adarsh/GRIHA of MNRE for exemplary demonstration of Integration of Renewable Energy Technologies |
January 2014 | The Project was accorded 5-Star Green Building Certification by GRIHA under MNRE |
A Trombe wall is a massive equator-facing wall that is painted a dark color in order to absorb thermal energy from incident sunlight and covered with a glass on the outside with an insulating air-gap between the wall and the glaze. A Trombe wall is a passive solar building design strategy that adopts the concept of indirect-gain, where sunlight first strikes a solar energy collection surface in contact with a thermal mass of air. The sunlight absorbed by the mass is converted to thermal energy (heat) and then transferred into the living space.
In passive solar building design, windows, walls, and floors are made to collect, store, reflect, and distribute solar energy, in the form of heat in the winter and reject solar heat in the summer. This is called passive solar design because, unlike active solar heating systems, it does not involve the use of mechanical and electrical devices.
Daylighting is the practice of placing windows, skylights, other openings, and reflective surfaces so that direct or indirect sunlight can provide effective internal lighting. Particular attention is given to daylighting while designing a building when the aim is to maximize visual comfort or to reduce energy use. Energy savings can be achieved from the reduced use of artificial (electric) lighting or from passive solar heating. Artificial lighting energy use can be reduced by simply installing fewer electric lights where daylight is present or by automatically dimming or switching off electric lights in response to the presence of daylight – a process known as daylight harvesting.
Spencer Plaza is a shopping mall located on Anna Salai in Chennai, Tamil Nadu, India, and is one of the modern landmarks of the city. Originally built during the period of the British Raj and reconstructed in 1985 on the site of the original Spencer's department store, it is the oldest shopping mall in India and was one of the biggest shopping malls in South Asia when it was built. It is one of the earliest Grade A commercial projects of the city, which were developed in the second half of the 1990s. As of March 2010, it is the 11th largest mall in the country, with a gross leasable (retail) area of 530,000 sq ft.
A building envelope or building enclosure is the physical separator between the conditioned and unconditioned environment of a building, including the resistance to air, water, heat, light, and noise transfer.
A Zero-Energy Building (ZEB), also known as a Net Zero-Energy (NZE) building, is a building with net zero energy consumption, meaning the total amount of energy used by the building on an annual basis is equal to the amount of renewable energy created on the site or in other definitions by renewable energy sources offsite, using technology such as heat pumps, high efficiency windows and insulation, and solar panels.
A ground-coupled heat exchanger is an underground heat exchanger that can capture heat from and/or dissipate heat to the ground. They use the Earth's near constant subterranean temperature to warm or cool air or other fluids for residential, agricultural or industrial uses. If building air is blown through the heat exchanger for heat recovery ventilation, they are called earth tubes.
The Barra system is a passive solar building technology developed by Horazio Barra in Italy. It uses a collector wall to capture solar radiation in the form of heat. It also uses the thermosiphon effect to distribute the warmed air through channels incorporated into the reinforced concrete floors, warming the floors and hence the building. Alternatively, in hot weather, cool nighttime air can be drawn through the floors to chill them in a form of air conditioning.
A ground source heat pump is a heating/cooling system for buildings that use a type of heat pump to transfer heat to or from the ground, taking advantage of the relative constancy of temperatures of the earth through the seasons. Ground-source heat pumps (GSHPs) – or geothermal heat pumps (GHP), as they are commonly termed in North America – are among the most energy-efficient technologies for providing HVAC and water heating, using far less energy than can be achieved by burning a fuel in a boiler/furnace or by use of resistive electric heaters.
Building-integrated photovoltaics (BIPV) are photovoltaic materials that are used to replace conventional building materials in parts of the building envelope such as the roof, skylights, or façades. They are increasingly being incorporated into the construction of new buildings as a principal or ancillary source of electrical power, although existing buildings may be retrofitted with similar technology. The advantage of integrated photovoltaics over more common non-integrated systems is that the initial cost can be offset by reducing the amount spent on building materials and labor that would normally be used to construct the part of the building that the BIPV modules replace. In addition, BIPV allows for more widespread solar adoption when the building's aesthetics matter and traditional rack-mounted solar panels would disrupt the intended look of the building.
The Green Building purports to be an environmentally conscious mixed-use development situated in Manchester. The Green Building was designed by Farrells, who aimed to create a sustainable environment on an unusual triangular plot, adjacent to Oxford Road station. The building was constructed by Taylor Woodrow as part of the Macintosh Village development, which was formerly a Dunlop tyre factory and also the birthplace of the Mackintosh raincoat.
The Green Building is a building located in the East Market District (NuLu) of Louisville, Kentucky. It is Louisville's first commercial Platinum LEED certified building, and Kentucky's first Platinum LEED adaptive reuse structure. The building, designed by Los Angeles architecture firm (fer) studio, was awarded Platinum certification in 2010. Design principals, Doug Pierson and Chris Mercier, are both former senior project architects with Frank Gehry's Los Angeles office, Gehry Partners LLP.
Sustainable refurbishment describes working on existing buildings to improve their environmental performance using sustainable methods and materials. A refurbishment or retrofit is defined as: "any work to a building over and above maintenance to change its capacity, function or performance' in other words, any intervention to adjust, reuse, or upgrade a building to suit new conditions or requirements". Refurbishment can be done to a part of a building, an entire building, or a campus. Sustainable refurbishment takes this a step further to modify the existing building to perform better in terms of its environmental impact and its occupants' environment.
The Samrat Ashok Convention Centre is a convention centre on North Gandhi Maidan Marg, Patna, Bihar with an estimated budget of ₹490 crore. The foundation stone of the centre was laid by Nitish Kumar, the chief minister of Bihar on 8 February 2014. An expected, around 16,500 metric tonnes of steel is used in construction, which is more than the volume of steel used in raising Eiffel Tower and Indira Gandhi International Airport, New Delhi. The capacity of the main auditorium is around 5000. The Samrat Ashoka Convention centre has three major signature buildings- 1) Bapu Sabahagaar, an auditorium of 5000 seating capacity, 2) Gyan Bhawan with 800 capacity auditorium, multipurpose hall and other conference halls of various capacities; and 3) Sabhyata Dwar. The centre was completed by April 2017 and has Gyan Bhawan, Bapu Sabhagaar, Multipurpose Hall, Plenary Hall, Modular Meeting Rooms with Basement Parking, Sabhyta Park With Sabhyata Dwar & food plaza. In February 2018, Samrat Ashoka Convention Kendra Patna won the 10th CIDC Vishwakarma Achievement Award for best construction projects in India.
The Glossary of Geothermal Heating and Cooling provides definitions of many terms used within the Geothermal heat pump industry. The terms in this glossary may be used by industry professionals, for education materials, and by the general public.
The David and Lucile Packard Foundation Headquarters is the corporate headquarters of the David and Lucile Packard Foundation, located in Los Altos, California. The Packard Foundation was created in 1964 by David Packard and his wife Lucile Salter Packard, one of the top 100 grant-making foundations in the United States, with the goals of improving the lives of children, enabling the creative pursuit of science, advancing reproductive health, and conserving and restoring the Earth’s natural systems. The David and Lucile Packard Foundation Headquarters is designed by EHDD to be the largest net zero energy building in California, and it has successfully reduced the energy use by 65% over conventional buildings.
The INTEGER Millennium House is a demonstration house in Watford, England that opened to the public in 1998. It was renamed The Smart Home after being refurbished in 2013. The house was originally intended to showcase innovations in design and construction, building intelligence, and environmental performance. The INTEGER design included many innovative features, including environmental technology such as a green roof and a grey water recycling system, home automation that included a building management system and an intelligent security system, and innovative technical systems such as under-floor trench heating. In 2013, the house was refurbished and retrofitted with a variety of new and upgraded features, including a building-integrated photovoltaic (BIPV) array, which altogether halved its carbon emissions and increased its energy efficiency by 50%. Since its creation, the house has garnered numerous awards, appeared on Tomorrow's World on BBC Television, hosted thousands of visitors, and influenced mainstream construction.
The CTBC Financial Park, or Chinatrust Commercial Bank Headquarters, is a skyscraper office complex located in Nangang District, Taipei, Taiwan. Construction of the complex began in 2010 and it was completed in 2013. The complex consists of three towers with a total floor area of 266,290 m2 (2,866,300 sq ft). The height of Block A is 139 m (456 ft), and it comprises 30 floors above ground, as well as five basement levels. The height of Block B is 99.4 m (326 ft), and it comprises 20 floors above ground, as well as five basement levels. The height of Block C is 66.7 m (219 ft), and it comprises 14 floors above ground, as well as five basement levels. It houses the headquarters of CTBC Financial Holding and is situated in close proximity to Nangang Software Park and Taipei Nangang Exhibition Center.
The Mosaic Centre for Conscious Community and Commerce is located in the suburban neighbourhood of Summerside in Edmonton, Alberta, Canada. While originally being designed for Oil Country Engineering Services, the building continues to focus on the engagement within local businesses and the interaction of its users. The main concept within the Mosaic was to build a healthy, sustainable building that continues to produce as much energy as it uses. Many different sustainability techniques were used throughout the design of the building, helping its net-zero energy status within a cold, northern climate.