Mangorei Power Station

Last updated

Mangorei Power Station
New Zealand (relief map).png
Disc Plain red.svg
Location of Mangorei Power Station in New Zealand
CountryNew Zealand
Location Taranaki
Coordinates 39°07′08.9″S174°07′36.9″E / 39.119139°S 174.126917°E / -39.119139; 174.126917 for the dam
PurposePower
StatusOperational
Construction began1904
Opening date1906
Owner(s)New Plymouth Borough Council (1906 - 1993)
Taranaki Energy (1993 - 1995)
Powerco (1995 - 1998)
Manawa Energy (1998 -)
Operator(s) Manawa Energy
Dam and spillways
Type of dam Concrete-core earth
ImpoundsMangamahoe Stream
Height (foundation)27.4 metres
Length160 metres
Spillways 1
Reservoir
CreatesLake Mangamahoe
Mangorei Power Station
Coordinates 39°06′18.5″S174°07′07.7″E / 39.105139°S 174.118806°E / -39.105139; 174.118806
Operator(s) Manawa Energy
Commission date1906
Type Conventional
Turbines Four
Installed capacity 5 MW (6,700 hp) [1]
Annual generation 20.9 GWh (75 TJ) [1]
Website
Manawa

The Mangorei Power Station is a hydroelectric power facility near Mangorei in Taranaki in New Zealand which makes use of water from the Waiwhakaiho River (which is often written as Waiwakaiho) and the Mangamahoe Stream catchments.

Contents

History

Initial development

Of the first 14 publicly available electricity supplies in New Zealand, seven were in the province of Taranaki. Most of these were hydroelectric schemes, utilizing the seasonally consistent water supply provided by Mount Taranaki’s many streams. This development was driven by the demand for electric lighting by both town and rural dwellers plus farmers wishing to power their new electric shearing sheds, milking machines and separator.

In the late 19th century the New Plymouth Borough Council decided to investigate its options for constructing a hydro-electric power station to supply the town with electricity as well as providing a water supply. The nearby Waiwhakaiho River was identified as a suitable source of water. In 1898 a completion was held to design a scheme. The completion was judged by respected engineer Richard Liron Mestayer (1843 - 1921). [2]

The council decided not to proceed with any of the schemes put forward and instead engaged Mestayer in 1901 to design his own scheme, which was subsequently accepted. [2]

His design called for an intake on the Waiwhakaiho River from which water was conveyed 1,200 m (3,937 ft) to a powerhouse first by a tunnel that passed under the Mangamahoe Stream to a forebay on the hill, from which a 21 in (0.53 m) diameter steel penstock conveyed the water down to a manifold outside of the station from where the water was split to supply two turbines. [2] [3]

Construction begins

Mestayer's design was accepted, which lead to a construction contract being issued on 13 July 1903 to McWilliams and Andrews to build the scheme. [2] The tunnel was dug from the outlet, from a side drive about 16 chains (322 metres) from the outlet, and from a 82 ft (25 m) deep shaft about 21 chains (422 metres) from the outlet. From the side drive and also from the shaft the tunnel was driven in both directions. The alignment of the tunnel was laid out on the surface by Sladden & Palmer, Civil Engineers and Surveyors, and then transferred to the bottom of the shaft by means of heavy plumb bobs suspended from the top by very fine wires, with the plumb bobs themselves hanging in buckets of water to dampen their movement. The line thus transferred was produced in both directions by means of a theodolite. The line was marked inside the tunnel by iron spikes driven into the roof, and from which plumb bobs were suspended to guide the excavation. The levels were transferred from, the surface to the bottom of the shaft using a long steel tape, and then maintained as the work progressed by means of an engineer's level. [4]

The power scheme received a licence from the government to generate electricity on 24 February 1905, [5] and was completed in late 1905. [6]

The first electricity was received in New Plymouth in January 1906, with 120 street lights and the town hall being lit. [6] By the end of the year the power station which operated from dusk to midnight was supplying 41 customers. By 1907 demand had increased with the power station supplying 126 customers and 230 by 1912. [6]

The power station originally had two turbines each driving a 45 kW single-phase generator. [5] To meet increasing demand the station was enlarged under the supervision of borough engineer A.H. Kendall to accommodate an additional 150 hp turbine driving a 90 kW single-phase generator, which entered service in December 1907. [5] [7]

Expansion

With no storage capacity the 180 kW power station was strictly run of the river and was proving to be unreliable during periods of low summer flow. [6] The growth of the town, and the impending introduction of electric powered trams necessitated the need for more generation, as well as providing more water for water reticulation purposes. As a result, the council in 1909 employed Henry Westcott Climie, the principal of consulting engineers H.W. Climie & Son to investigate possible options. Climie identified that the generation output was limited by the size of the tunnel, which couldn't be taken out of service and enlarged without cutting off the power supply to the town. He offered three options, (a) build a weir across the Waiwhakaiho below the present intake so as to give a greater head of water; (b) divert a portion of the water from the Waiwhakaiho, at a point about thirty chains above the present intake, by means of a tunnel and open race into the Mangamahoe Stream, and build a dam across the latter a little below where the present tunnel passes under it, or (c) take the water off the Waiwhakaiho at the same point as proposed in (b) and convey it by means of a larger new tunnel through the hill to the power station. Climie's recommended option was (a) which he calculated would give an effective 876 hp, equivalent to nearly 660 kilowatts of electrical energy at an estimated cost of £5,137 for the civil works plus the cost of the additional turbines and generators. [8]

The council initially opted for option (a) but an inability to install a suitable foundation and a large flood caused this to be abandoned in favour of Climie's Option (c) which involved construction on the Waiwhakaiho River of a new intake 25 chains (502 m) further upstream, which diverted water by means of a 22 chain (442 m) long water race, 100 feet (30.48 metres) of which consists of a tunnel into the Mangamahoe Stream, where a 13 ft (3.96 m) high concrete gravity dam was constructed in 1914, just downstream of where the original tunnel had crossed it. [2] [9] Filling of the lake began in November 1914. From the dam the water was taken to a forebay, from where it entered the powerhouse, and the reticulation pipes of the town. This new diversion which cost approximately £4,000, captured not only water from the Waiwhakaiho but also all of the flow of Mangamahoe. [10]

As a result of the increased flow the total output of the power station increased to 750 kW. [11]

The new intake proved difficult to maintain as it frequently became blocked with large stones, gravel and branches which then had to be manually removed. As a result, improvements were made to its design which were completed on 16 January 1916. [12]

At the same time as efforts were being made to increase the supply of water two 250 kW generators ordered from Turnbull and Jones entered service in 1912 and 1913. In 1914 the original two 45 kW generators were replaced by a new 250 kW generator. [5]

In 1915 the council converted the transmission and distribution voltage on its system to 6.6 kV single-phase, which was upgraded in 1921 to three-phase. [11]

Damage to and replacement of the dam

On 25 March 1917 the bed of the Mangamahoe Stream was seriously scoured out immediately from under the tunnel where it passed under the dam to a depth of 6 ft (1.83 m) to 10 ft (3 m), which caused all of the water in the dam to be lost. [13]

A temporary sack dam was erected behind the breach which allowed an approximately 3 ft 6in (1.1 metre) head to be obtained in the reservoir. However it was difficult to regulate the flow of water while trying to avoid the risk of carrying away the dam at another place. [14] Rather than repair the damage which would have meant closing down the tunnel and to restricting the town's demand (including closing down the tramways and turning off the street lighting) to what could be supplied via a tie line from the Taranaki Electric Power Board it was decided to build a new dam 50 ft (15.24 m) downstream of the existing dam. A design for a new concrete dam which would give a 3 ft (914.40 mm) higher head than the existing dam was submitted to the council on 23 May 1917 and approved. [15]

The new dam was 109 ft (33.22 m)long at the top, 18 ft (5.49 m)high with a bottom thickness of 12 ft (3.7 m)and a top thickness of 2 ft (609.6 mm) widened by cornices to 2 ft 6in (760 mm), to form a footway, which extends over the by-wash in two 13 ft 6 in (4.1 m) spans. [10] This footbridge and the scour-valve platform were the only portions of the dam in which steel reinforcement was installed. The spillway was widened to 28 ft (8.5 m). No great difficulties were met during construction, except that it was necessary dig 4 ft (1.2 m) to 6 ft (1.8 m) lower than originally intended in order to find a hard, and watertight bottom which was found to extend for 60 ft (18.3 m) in length from the north end to the centre of the stream. Beyond this to the south end of the wall the excavation was taken down to a depth of from 8 ft (2.4 m) to 13 ft (4 m) lower than originally intended. A 30 in (762 mm) cast-iron gate valve was installed to allow emptying and letting sand out of the lake. [15]

By February 1918 the dam had finished and refilled with water. [15]

Mason's proposal

With the demand for electricity within the Borough of New Plymouth showing no sign of levelling off, and with applications for power been received from other local bodies, the council committed to expanding the Mangorei scheme.

The council in late 1918 engaged consulting engineer John Blair Mason (1858 to 1927) of Blair Mason, Lee, Owen and Cree Brown, to investigate the various options. Mason offered a number of options but Scheme D which also had a partial option called E11 became the preferred choice of the council. Scheme D called for tapping the Waiwhakaiho River at a new upstream intake and conveying the water via a tunnel to a lake created by a new 110 ft (34 m) high dam on the Mangamahoe Stream about 30 chains (603 m) above the existing dam. This high dam would give a head of 231 ft (70 m) above the powerhouse, submerge at least 30 acres (12 hectares) and with a 10 ft (3 m) draw off would provide 13,000,000 cubic feet (368,000 cubic metres) of storage. The lake would rise 2 ft (610 mm)above the saddle about half a mile (800 m) south of a forebay from whence it would be conveyed by water races and penstocks to the powerhouse. The actual storage required with a load factor of 0.45 to develop the maximum water power would amount to 7¼ million cubic ft (205,000 cubic metres). Mason estimated that this would give a maximum of 6,300 hp. His estimated cost for the project was £46,000. [16] Scheme E11 on the other hand he estimated would cost £11,700, of which only £1,300 need be regarded as temporary work, being the estimated cost of race and depreciation on pipe line. It involved constructing the weir, intake and tunnel portions of the permanent works of scheme D, which could reused if the council choose at a later date to proceed with the full scheme. From the outfall of the tunnel the water would be conveyed via a 140 chain (2,800 m) long water race to a penstock above the present forebay. From here up to 100 cusecs (2.8 cumecs) would be delivered to the powerhouse through new penstocks. [16]

Over the next two years the plans were modified, with scheme D being renamed Scheme 1, with a dam now giving a 237 ft (72.24 m) head, which would submerge 95 acres (38 hectares) and have a capacity of 50 million cubic feet (1.4 million cubic metres) with a 15 ft (5 m)draw off. This would require the building of two 1,400 ft (426.7 m) long embankments on the South side of the proposed reservoir to prevent the water overflowing the adjacent lands. There would also be three penstocks running from the forebay/surge chamber to the powerhouse. This scheme was expected to develop 9,000 hp. [17]

The partial scheme now known as E2 was basically as per Mason's but had an increased head and flow of 150 cusec which it was expected would produce an additional 2,000 hp on top of the power station's existing 900 hp. [17]

The council made the decision in 1919 [2] to proceed with the partial scheme. However its estimated cost had to the council's enormous disappointment increased by January 1920 to £112,000 and which they expected to make an annual profit of £13,800 on the electricity being generated. The loans to service this expenditure were approved by ratepayers. In October 1920, the estimate was further increased to £172,000 (which included contingencies of £12,000) with an expected annual profit on the electricity being generated dropping to £6,042. As a result, the council in November 1920 with approximately £60,000 already spent to date reluctantly had to go back to ratepayers to obtain approval to raise another £60,000 loan. [17]

The partial scheme

The partial scheme as completed in early 1923. [2] had a diversion weir and intake about a mile and a half above the previous intake. The new concrete diversion intake on the Waiwhakaiho River had a base 15 ft below the river level and rose to about 12 ft above the normal height of the river. it was divided into four valve chambers, with three ports open to the river on one face, and one on the other face of the intake. These could be opened or closed by gates as required.

From the intake the water was conveyed through the 1,800 ft (548 m) long Tunnel No. 1. A few feet of this tunnel was driven from the intake end, but the principal excavation work was being done from the opposite end of the tunnel. The haulage of the spoil from the driving was undertaken by pony-drawn trucks. The tunnel was light by electricity with airshafts at regular intervals. The excavation of the tunnel which was estimated to cost approximately £12,000 was undertaken by Payne and Blanchard Ltd using a workforce that varied between 13 and 25 men working in three shifts. [18]

At the exit of Tunnel No.1 a small 37 ft (11.3 m) high dam [2] (which was termed a "Turning Wall") with a concrete core was built to deflect the water into Water Race No. 1. This 1,115 ft (340 m) long race terminated at a 558 ft (170 m) long pipeline which took the water over the Mangamahoe Stream 36 ft (11 m) below to the 1,968 ft (600 m) long Water Race No. 2. This race then transitioned to 4,000 ft (1,219 m) long Tunnel No.2 which took it to a forebay/surge chamber 140 ft (42.7 m) higher up the hill than the existing surge chamber. From here a steel penstock conveyed the water down to the powerhouse.

This improved supply of water and increased head of 240 ft (73.2 m) [11] allowed the council to install two new 1,000 kVA generators, convert one of the existing 250 kW machines, to produce 750 kVA, and replace another 250 kW unit with a new 1,000 kVA unit. [5]

Defects were found in Tunnel No.2 which led the council in 1923 to dismiss their consulting engineers Blair Mason, Lee, Owen and Cree Brown, who had been responsible for overseeing all civil works. The council's electrical department was responsible for the electrical work.

On 27 April 1928 approximately 100 ft (30.5 m) of the southern end of the pipeline that carried water across the Mangamahoe Stream was destroyed by a landslide, which cut off the water supply to the power station for approximately two weeks until it was repaired. Until it was the supply the street light lighting and trams were switched off and New Plymouth's demand was restricted to what could be supplied via a tie line from the Taranaki Electric Power Board. [19]

Creation of Lake Mangamahoe

As the demand for electricity continued to rise and aware of the benefits of having a larger reservoir that would provide both generation storage capacity as well as delivering a reliable water supply to New Plymouth, the council committed to undertaking the full scheme by building a dam on the Mangamahoe Stream. The contract to build the dam was won by J. T. Julian and Son in March 1929 with a price of £35,310 7s 6d. [20] Construction started in 1929 with the diversion of the stream through a tunnel on the left abutment. [2] The foundations for the dam were then excavated and a trench dug for the concrete core.

Mechanical earth moving was just starting to be employed in New Zealand, and as a result tractors and scrapers were used to construct the dam.

The dam was completed in 1931 and submerged approximately 79 acres (32 hectares) of land to form Lake Mangamahoe. [21]

At the time of its completion the dam was the highest earth dam in Australasia. [1] The existing two water races and the pipeline over the Mangamahoe Stream were left in place and flooded by the lake. The New Plymouth Borough was connected to the Arapuni Power Station in 1934 which meant that the borough had a sufficient electricity supply.

By March 1948 the various modifications to the power station had resulted in it having an output of 3,750 kW, which was provided by one 90 kW, one 240 kW, one 750 kVA and three 1,000 kW generators. [5]

On 1 September 1983 the power station was added to the New Zealand Historic Places list as a Historic Place Category 2. [22]

Changes in ownership

As a result of the restructuring of the New Zealand electricity sector in the early 1990s, the electricity department of the New Plymouth City Council (trading as New Plymouth Energy) merged with the Taranaki Electric Power Board on 7 May 1993 to form Taranaki Energy Ltd. [6]

In 1995 Taranaki Energy Ltd merged with and took the name of Powerco. [6]

The introduction of the Electricity Industry Reform Act in 1998 required New Zealand's electricity companies to separate their network and retail businesses. As a result, Powerco having elected to remain a network company sold its five power stations (which including Mangorei) to Manawa Energy (formerly Trustpower).

Improvements

In recent years Manawa has undertaken extensive work on the linings of the supply tunnel to reduce friction. [1]

Design

A weir on the Waiwhakaiho River diverts water into the 1,800 ft (549 m), 7 ft 3 inch (2.2 m) diameter concrete lined Tunnel No.1 which conveys it to the top of Lake Mangamahoe.

This manmade lake was created by a dam at its northern end which impounds the Mangamahoe Stream above its confluence with the Waiwhakaiho River. The 27.4-metre-high earth dam, which is 160 m long at the crest, has a substantial curved concrete core running throughout its centre and set into the hard sandstone on each bank and is at least 6 m thick. The lake side has a 3-to-1 slope, with the surface exposed to the water surface lined with stone, while the downstream side has a 2-to-1 slope. [2]

To the west of it is an intake structure with four remotely controlled intake gates. From the intake structure the 4,000-foot-long (1,219 m), 7-foot-3-inch-diameter (2.2 m) Tunnel No.2 conveys the water from the lake to a 37-foot-diameter (11.2 m) forebay/surge chamber. From the forebay/surge chamber two steel penstocks carry the water down to the powerhouse which is located on Hydro Rd (S.H.3), Mangorei. In the powerhouse are one 700 kW generator and three 1.3 MW generators. [1] The generators discharge into a tailrace which flows into the Waiwhakaiho River, approximately six kilometres down stream of the intake.

Water is also taken via two intakes on the lake's western shore to a nearby water treatment plant, from where it is distributed to consumers in the New Plymouth area.

Operation

Resource consents which were granted in 1996 and which expire in June 2021 allow the power station to divert up to 10 cumecs of water from the Waiwhakaiho River and back into it. The power station is required to maintain a minimum flow in the river below the diversion weir. [23]

Lake Mangamahoe also serves as the water supply for New Plymouth and is a Wildlife Refuge. A trap and transfer programme manages any disruption to the migration of longfin eel.

The power station is embedded in Powerco's network behind Transpower's Carrington Street Substation.

The power station is operated remotely via a SCADA system from Manawa Energy's control centre in Tauranga.

See also

Notes

  1. 1 2 3 4 5 "Mangorei Power Station". Manawa. Retrieved February 12, 2019.
  2. 1 2 3 4 5 6 7 8 9 10 Offer, R.E. (1997). Walls for Water: Pioneer dam Building in New Zealand. Palmerston North: The Dunmore Press. pp. 87 to 92. ISBN   0-86469-313-3.
  3. Lambert, Ron (2015). "The Alchemy of the Engineer: Taranaki Hydro-electricity" (PDF). Kete New Plymouth.
  4. "The Water Works Tunnel", Taranaki Herald, April 15, 1905, retrieved February 19, 2018
  5. 1 2 3 4 5 6 Beeche, H.J. (1950). Electrical Development in New Zealand. Wellington: Neville Graham Dunning (for The Electric-Power Boards and Supply Authorities Association of New Zealand. p. 244.
  6. 1 2 3 4 5 6 Lonsdale, Chris; Winder, Virginia; McNaughton, Karyn (2013). A History of Powerco: Delivering New Zealand's Energy Future. New Plymouth: Powerco. pp. 109, 110.
  7. "The Electric Light Department". Taranaki Daily News. January 9, 1908. Retrieved February 13, 2019.
  8. "Water Power". Taranaki Herald. January 11, 1910. Retrieved February 13, 2019.
  9. "The New Intake", Taranaki Herald, November 13, 1914, retrieved February 19, 2018
  10. 1 2 "Borough Expansion", Taranaki Daily News, November 13, 1914, retrieved February 19, 2018
  11. 1 2 3 Speer, N.M. (1962). The Electric Supply Industry in New Zealand: Its Progress and Achievement. Wellington: The Electric Supply Authorities Association of New Zealand. pp. 197, 198.
  12. "New Plymouth's Electrical Department". Taranaki Daily News. May 8, 1916. Retrieved February 13, 2019.
  13. "Borough Council", Taranaki Herald, March 27, 1917, retrieved February 19, 2018
  14. "Borough Electrical Undertaking". Taranaki Herald. June 14, 1917. Retrieved February 13, 2019.
  15. 1 2 3 "The Waterworks Dam", Taranaki Daily News, May 15, 1918, retrieved February 19, 2018
  16. 1 2 "Electric Power", Taranaki Herald, February 10, 1919, retrieved February 19, 2018
  17. 1 2 3 "To the ratepayers", Taranaki Herald, November 10, 1920, retrieved November 20, 2018
  18. "Hydro Electric Development". Taranaki Herald. August 31, 1920. Retrieved February 13, 2019.
  19. "Hillside Slips Away", Stratford Evening Post, April 28, 1928, retrieved February 19, 2018
  20. "Mangamahoe Dam Tender", Patea Mail, March 15, 1929, retrieved February 19, 2018
  21. "New Plymouth District Lake Mangamahoe Management Plan". New Plymouth District Council. 2011. Retrieved February 17, 2019.
  22. "Mangorei Power Station". Heritage New Zealand. Retrieved February 10, 2019.
  23. "Trustpower Ltd Mangorei HEP Scheme Monitoring Programme Annual Report 2016-2017 Technical Report 2017-102" (PDF). Trustpower. March 2018. Retrieved February 10, 2019.

Further reading

Related Research Articles

<span class="mw-page-title-main">Micro hydro</span> Hydroelectric power generation of 5 to 100 kW of electricity

Micro hydro is a type of hydroelectric power that typically produces from 5 kW to 100 kW of electricity using the natural flow of water. Installations below 5 kW are called pico hydro. These installations can provide power to an isolated home or small community, or are sometimes connected to electric power networks, particularly where net metering is offered. There are many of these installations around the world, particularly in developing nations as they can provide an economical source of energy without the purchase of fuel. Micro hydro systems complement solar PV power systems because in many areas water flow, and thus available hydro power, is highest in the winter when solar energy is at a minimum. Micro hydro is frequently accomplished with a pelton wheel for high head, low flow water supply. The installation is often just a small dammed pool, at the top of a waterfall, with several hundred feet of pipe leading to a small generator housing. In low head sites, generally water wheels and Archimedes' screws are used.

<span class="mw-page-title-main">Rubicon Hydroelectric Scheme</span> Hydroelectric scheme in Victoria, Australia

The Rubicon Hydroelectric Scheme is a small run-of-the-river hydroelectric scheme located on the Rubicon and Royston Rivers, north east of Melbourne, 40 km (25 mi) south-west of Alexandra, Victoria, Australia. The scheme commenced in 1922, and was the first state-owned hydroelectric scheme to generate electricity in mainland Australia, and among the first in the world to be remotely controlled. For the first ten years of its operation it supplied on average 16.9% of electricity generated by the State Electricity Commission of Victoria. It is now owned and operated by AGL Energy and contributes approximately 0.02% of Victoria's energy supply.

<span class="mw-page-title-main">Ffestiniog Power Station</span> Dam in Ffestiniog, Gwynedd

The Ffestiniog Power Station is a 360-megawatt (MW) pumped-storage hydroelectricity scheme near Ffestiniog, in Gwynedd, north-west Wales. The power station at the lower reservoir has four water turbines, which can generate at full capacity within 60 seconds of the need arising. The scheme has a storage capacity of around 1.44 GWh (5.2 TJ) at maximum output for four hours, and the capacity to power the whole of North Wales for several hours.

Sidrapong Hydroelectric Power Station, located at the foothills of Arya Tea Estate 12 km (7.5 mi) from Darjeeling town, is the oldest hydel power station or hydroelectric power plant in India. commissioned on 10 November 1897, its original capacity was 2 × 65 kW, which was expanded in phases for increased demands to a total 1000 kW in 1916. Having reached the limit of the water supply, the machinery was replaced in 1931 for more-efficient triple-phase transmission.

Chenderoh Power Station or Chenderoh Dam is a hydroelectric power station in Chenderoh Lake, Kuala Kangsar District, Perak, Malaysia. It was constructed by Perak River Hydro-Electric Power Company Ltd and completed in 1930. The scheme was designed by consulting engineers Rendel, Palmer & Tritton of London and Vattenbyggnadsbyran (VBB) of Stockholm, Sweden. The architect was Osvald Almqvist.

The Catagunya Power Station is a run-of-the-river hydroelectric power station located in the Central Highlands region of Tasmania, Australia. The power station is situated on the Lower River Derwent catchment and is owned and operated by Hydro Tasmania.

<span class="mw-page-title-main">Monowai Power Station</span> Hydroelectric power station in New Zealand

The Monowai Power Station, fed by the Monowai River from Lake Monowai in Southland, New Zealand, was one of the earliest hydroelectric power stations in the country. Originally commissioned in 1925, it was refurbished between 2005 and 2007 and now contains modern turbines and plant, though the original buildings are still in use.

<span class="mw-page-title-main">Coleridge Power Station</span> Dam in Canterbury, New Zealand

The Coleridge Power Station is a hydroelectric facility at Lake Coleridge on the Rakaia River in Canterbury, New Zealand. The power station is owned and operated by Manawa Energy.

<span class="mw-page-title-main">Arnold Power Station</span>

The Arnold Power Station is a hydroelectric facility fed from Lake Brunner on the Arnold River in West Coast, New Zealand, owned and operated by TrustPower. Commissioned in 1932, the plant is rated at 3 megawatts (4,000 hp) and has an average annual output of 25 gigawatt-hours (90 TJ).

<span class="mw-page-title-main">Cobb Power Station</span> Hydroelectric power station in New Zealand

The Cobb Power Station is a hydroelectric facility on the Cobb River, in the Tasman District of New Zealand. The power station is located in Upper Tākaka, 112 km (70 mi) northwest of Nelson. Annual generation is approximately 190 gigawatt-hours (680 TJ). The initial stages of the construction of the station began as a privately-funded scheme in 1935, but the investor failed to raise the necessary capital. The national government took over building the station and the first power was produced in 1944, operating as a run-of-river station. A storage dam was completed in 1954. The resulting hydro lake is the highest in the country and at 596 m (1,955 ft), the station has New Zealand's highest hydraulic head of any power station.

<span class="mw-page-title-main">Tongariro Power Scheme</span> New Zealand hydroelectricity scheme

The Tongariro Power Scheme is a 360 MW hydroelectricity scheme in the central North Island of New Zealand. The scheme diverts water from tributaries of the Rangitikei, Whangaehu, Whanganui, and Tongariro rivers. These rivers drain a 2,600-square-kilometre (1,000 sq mi) area including Ruapehu, Ngauruhoe, Tongariro and the western Kaimanawa Ranges. The water diverted from these rivers is sent through canals and tunnels to generate electricity at three hydro power stations, Rangipo (120 MW), Tokaanu (240 MW) and Mangaio (2 MW). The water is then discharged into Lake Taupō where it adds to the water storage in the lake and enables additional electricity generation in the succession of power stations down the Waikato River.

Maraetai Power Station is a hydroelectric power station on the Waikato River, in the North Island of New Zealand. It is the fifth of the eight hydroelectric power stations on the Waikato River, and at 360 MW, is the largest hydroelectric station on the Waikato.

<span class="mw-page-title-main">Snoqualmie Falls Hydroelectric Plant</span>

The Snoqualmie Falls Hydroelectric Plant is located just north of Snoqualmie in King County, Washington state, US. It is situated about 22 mi (35 km) east of Seattle. Located just below the Snoqualmie Falls, the power plant consists of two power houses, Plant 1 and Plant 2. Plant 1 was completed in 1899 and is located underground. It is the first completely underground hydroelectric power plant ever built in the world. Plant 2 was built in 1910 and is located along the right bank of the Snoqualmie River. Both plants receive water from a small reservoir created by a weir atop the falls. Plant 1 has an installed capacity of 13.7 MW and Plant 2 a capacity of 40.2 MW for a total installed capacity of 53.9 MW, enough to power 40,000 homes.

<span class="mw-page-title-main">Denawaka Ganga Mini Hydro Power Project</span> Dam in Ratnapura, Sabaragamuwa Province

Denawaka Ganga Mini Hydro Power Project is a run of river mini hydro power project located in Ratnapura, Sri Lanka. The install capacity of the project is 7.2 MW and the annual generation is 25GWh. The generated energy is fed into the national electric grid of Sri Lanka.

<span class="mw-page-title-main">Pupu Hydro Power Scheme</span> Historic power station in New Zealand

The Pupu Hydro Power Scheme is a small hydroelectric power station near Tākaka in the Golden Bay region of the South Island of New Zealand. It opened in 1929 as the first power station in the region and was the first public electricity supply in Golden Bay. After closing in 1980 following damage to the generator, the power scheme was fully restored by the local Pupu Hydro Society and many volunteer groups over the course of seven years and re-opened in 1988, again supplying electricity to the national grid.

The Omanawa Falls Power Station is a run of the river hydroelectric facility on the Omanawa River, in the Bay of Plenty in New Zealand. Built in 1915 to supply electricity to the town of Tauranga, it was the Southern Hemisphere's first underground power station.

The Motukawa Power Station is a hydroelectric power facility in Taranaki in New Zealand which makes use of water from the Manganui River. Water is drawn from behind a weir on the Manganui River near Tariki and diverts this water through a race to Lake Ratapiko and then through penstocks to the Motukawa Power Station. The power station discharges into the Mākara Stream, a tributary of the Waitara River.

The Kuratau power station is a hydroelectric power facility in Kuratau on the western side of Lake Taupō in New Zealand which makes use of water from the Kuratau River. The river is impounded behind a dam to form Lake Kuratau before discharging through the power station back into the river. The scheme is operated by Trustpower on behalf of its owner King Country Energy.

The Piriaka power station is a hydroelectric power facility in Manawatū-Whanganui in New Zealand which draws water from behind a weir on the Whanganui River near Piriaka and diverts it through a canal and penstock to the Piriaka Power Station, which is located approximately 9 km southeast of the town of Taumarunui, via SH4. The power station discharges back into the Whanganui River.

The Wairere Power Station is a hydroelectric power facility in the Waikato region in New Zealand which makes use of water from the Mokau River. Water is drawn from behind a dam above the Wairere Falls, which diverts the water through two penstocks to the Wairere Power Station, before being discharged back into the Mokau River. The station was commissioned in 1925 with the first generating unit. Three more generating units were added between 1938 and 1981 before a major refurbishment resulted in three of the units being replaced by a single generating unit in 2013-2014.