| Parc Cynog | |
|---|---|
| | |
Location of Parc Cynog within Wales | |
| Country | Wales, United Kingdom |
| Coordinates | 51°45′29″N4°31′34″W / 51.758°N 4.526°W |
| Status | Operational |
| Commission date | 2001 |
| Owner | Vattenfall |
| Operator | Nuon Renewables |
| Wind farm | |
| Type | Onshore |
| Power generation | |
| Units operational | 11 |
| Nameplate capacity | 8.4 MW |
Parc Cynog is a wind farm operated by Nuon Renewables in Wales. [1] [2]
Parc Cynog Windfarm was built in 2001, and currently consists of eleven wind turbines.
There were originally five turbines on site which are Micon M1800-750/48 turbines built in 2001, by 2009, a further six turbines were installed by Enercon Wind Energy. The turbine type used was Enercon E48/800KW.
The windfarm is owned by Vattenfall. [3]