Pavagada Solar Park

Last updated

Pavagada Solar Park
Pavagada Solar Park 2020.jpg
Pavagada Solar Park
Official nameShakti Sthala [1]
CountryIndia
Location Pavagada taluk, Tumkur district, Karnataka
Coordinates 14°15′N77°27′E / 14.25°N 77.45°E / 14.25; 77.45
StatusOperational
Construction beganOctober 2016
Commission date March 2018
Construction cost₹14,425 crore [2]
Owner(s)Karnataka Solar Power Development Corporation Ltd. (KSPDCL)
Solar farm
Type Flat-panel PV
Site resource5.5-6.0 kWh/m2 per day [3]
Site area13,000 acres (5,300 ha)
Power generation
Units operational2,050 MW [4]
Nameplate capacity
  • 2,050 MW
External links
Website kspdcl.in
Commons Related media on Commons

Pavagada Solar Park is a solar park covering an area of 53 square kilometres (13,000 acres) in Pavagada taluk, Tumkur district, Karnataka. Completed in 2019, the park has a capacity of 2,050 MW. As of April 2021, it is the world's third largest photovoltaic solar park after the 2,245 MW Bhadla Solar Park in Rajasthan and 2,200 MW Huanghe Hydropower Hainan Solar Park in China. It is the second largest in India.The total project cost was ₹14,800 crore (US$2.1 billion). [5]

Contents

History

Background

Karnataka Renewable Energy Development Ltd (KREDL) and the Solar Energy Corporation of India (SECI) established a joint venture company, the Karnataka Solar Power Development Corporation Ltd (KSPDCL), in March 2015 to implement solar power projects in Karnataka. [6] [7] The Chairman of the State High Level Clearance Committee (SLHCC) approved the KSPDCL's proposal to construct a solar power park in Pavagada taluk on 29 October 2015. [5] The project is spread over a total area of 13,000 acres (53 km2) which includes the 5 villages of Balasamudra, Tirumani, Kyataganacharlu, Vallur and Rayacharlu. [5]

Pavagada was chosen as the site for the project for several reasons. Apart from high solar radiation and availability of land, the region receives very little rainfall. Pavagada taluk is located in a semi-arid tract, atop an elevated plateau surrounded by rocky hills. The region has been declared drought hit by the Karnataka Government 54 times in the past 6 decades. The region is also sparsely populated and most of its residents are poor farmers. Many of the region's residents have migrated to Bangalore, located about 180 km away, for economic reasons. [6]

G.V. Balram, the managing director of KREDL, was born and raised in a village in Pavaguda taluk. He understood that farmers in the region were reluctant to sell their land due to emotional reasons. In order to aid in the development of the region and reduce economic migration, Balram offered farmers the option to lease the land required for the project rather than purchase it outright. [8] Landowners receive an annual payment of 21,000 (US$260) per acre under the terms of the lease which is valid for 25–35 years. For the entire land required for the park, the total compensation for the entire project amounts to 23-25 crore per year. The annual payment amount will increase by 5% every 2 years. [7]

Auctions

The KSPDCL utilized the "plug and play" model to implement the project. Under this model, the company acquires blocks of land, obtains all required government approvals for solar power generation, and then awards contracts to solar power developers (SPDs) through auctions. [6]

In April 2016, NTPC Limited, on behalf of KSPDCL, awarded contracts to 6 firms for the commissioning of a total of 500 MW of power at the Pavaguda Solar Park as follows: [9] [10] [11]

Work on the solar park began in October 2016. [7] In March 2017, the NTPC invited bids for a further 750 MW, split into six blocks of 125 MW each. [12] Due to infrastructure issues, this invitation was scrapped and the capacity was retendered in early 2017, with an additional 250 MW (total 1000 MW) which was reserved for "domestic content requirement" scheme, meaning that the components needed to be manufactured in India and not imported. [13]

Commissioning

On 14 December 2017, Fortum announced that it had connected a 100MW solar plant at Pavagada to the grid. [16] Tata Power Renewable Energy Ltd commissioned 100 MW at the park by 19 December, [17] and an additional 50 MW by 2 January 2018. [18] 600 MW of power was commissioned by 31 January 2018. [19] [20] and a further 1,400 MW are planned. [21]

Pavagada Solar Park had a total commissioned capacity of 1,400 MW by 9 April 2019 out of total 2,050 MW planned by December 2019. [22] [23] Another 450 MW was commissioned by November 2019 taking the total project capacity to 1850 MW, making it the largest solar power plant in the world at the time. [24]

Upon completion, Pavagada Solar Park was the world’s largest solar power plant. However, as of April 2021, it was the third largest photovoltaic solar park after the 2245 MW Bhadla Solar Park in Rajasthan and Huanghe Hydropower Hainan Solar Park in China 2200 MW. [25]

Wind energy

In March 2017, Karnataka Energy Minister DK Shivakumar told the Bangalore Mirror that the government was looking to generate wind energy by setting up windmills in Pavagada. Preliminary estimates from the KREDL indicate a potential wind power generation of 250-300 MW. [26]

See also

Related Research Articles

India is the third largest producer of electricity in the world. During the fiscal year (FY) 2022–23, the total electricity generation in the country was 1,844 TWh, of which 1,618 TWh was generated by utilities.

<span class="mw-page-title-main">Solar power by country</span>

Many countries and territories have installed significant solar power capacity into their electrical grids to supplement or provide an alternative to conventional energy sources. Solar power plants use one of two technologies:

<span class="mw-page-title-main">Solar power in India</span>

India's solar power installed capacity was 73.32 GWAC as of 31 December 2023.

<span class="mw-page-title-main">Renewable energy in India</span>

India is the world's 4th largest consumer of electricity and the world's 3rd largest renewable energy producer with 40% of energy capacity installed in the year 2022 coming from renewable sources. Ernst & Young's (EY) 2021 Renewable Energy Country Attractiveness Index (RECAI) ranked India 3rd behind USA and China. In FY2023-24, India is planning to issue 50 GW tenders for wind, solar and hybrid projects. India has committed for a goal of 500 GW renewable energy capacity by 2030. In line with this commitment, India's installed renewable energy capacity has been experiencing a steady upward trend. From 94.4 GW in 2021, the capacity has gone up to 119.1 GW in 2023 as of Q4.

The National Solar Mission is an initiative of the Government of India and State Governments to promote solar power. The mission is one of the several policies of the National Action Plan on Climate Change. The program was inaugurated as the Jawaharlal Nehru National Solar Mission by former Prime Minister Manmohan Singh on 11 January 2010 with a target of 20 GW by 2022. This was later increased to 100 GW by Prime Minister Narendra Modi in the 2015 Union budget of India. India increased its utility solar power generation capacity by nearly 5 times from 2,650 MW on 26 May 2014 to 12,288.83 MW on 31 March 2017. The country added 9,362.65 MW in 2017–18, the highest of any year. The original target of 20 GW was surpassed in 2018, four years ahead of the 2022 deadline.

<span class="mw-page-title-main">Hydroelectric power in India</span>

India is 5th globally for installed hydroelectric power capacity. As of 31 March 2020, India's installed utility-scale hydroelectric capacity was 46,000 MW, or 12.3% of its total utility power generation capacity. Additional smaller hydroelectric power units with a total capacity of 4,683 MW have been installed. India's hydroelectric power potential is estimated at 148,700 MW at 60% load factor. In the fiscal year 2019–20, the total hydroelectric power generated in India was 156 TWh with an average capacity factor of 38.71%.

<span class="mw-page-title-main">Solar power in Gujarat</span> Overview of solar power in Gujarat

Solar power in Gujarat, a state of India, is a fast developing industry given that the large state is mostly arid. It was one of the first states to develop solar generation capacity in India.

<span class="mw-page-title-main">NTPC Limited</span> National Thermal Power Corporation, Central Public Sector Undertaking coal mining

NTPC Limited, formerly known as National Thermal Power Corporation, is an Indian central Public Sector Undertaking (PSU) under the ownership of the Ministry of Power and the Government of India, who is engaged in the generation of electricity and other activities. The headquarters of the PSU are situated at New Delhi. NTPC's core function is the generation and distribution of electricity to State Electricity Boards in India. The body also undertakes consultancy and turnkey project contracts that involve engineering, project management, construction management, and operation and management of power plants.

<span class="mw-page-title-main">Vikram Solar</span> Indian solar energy company

Vikram Solar Limited is an Indian company based in Kolkata. It is one of the largest solar module manufacturers in India, with 3.5 GW module manufacturing capacity annually and the second-largest solar energy company in India by revenue. The company's primary business focus is manufacturing solar PV modules, and also carrying out engineering, procurement, and construction services and operations, and maintenance of solar power plants.

<span class="mw-page-title-main">Kamuthi Solar Power Project</span> Photovoltaic power station in Tamil Nadu, India

Kamuthi Solar Power Project is a photovoltaic power station spread over an area of 2,500 acres (10 km2) in Kamuthi, Ramanathapuram district, 90 km from Madurai, in the state of Tamil Nadu, India. The project was commissioned by Adani Power. With a generating capacity of 648 MWp at a single location, it is the world's 12th largest solar park based on capacity.

Ultra Mega Solar Power Projects, also known as Ultra Mega Solar Parks, are a series of solar power projects planned by the Ministry of New and Renewable Energy of the Union Government of India. Each power project has a minimum capacity of 500 MW.

<span class="mw-page-title-main">Bhadla Solar Park</span> Solar power array in Rajasthan, India

The Bhadla Solar Park is a solar power plant located in the Thar Desert of Rajasthan, India. It covers an area of 56 square kilometers and has a total installed capacity of 2’245 megawatts (MW), making it the largest solar park in the world as of 2023. The park was developed in four phases since 2015, with $775 million in funding from the Climate Investment Fund and $1.4 billion in funding from other sources. The park contributes to India's renewable energy goals and helps reduce greenhouse gas emissions by an estimated 4 million tons per year.

<span class="mw-page-title-main">NP Kunta Ultra Mega Solar Park</span> Solar park in Andhra Pradesh, India

The NP Kunta Ultra Mega Solar Park, also known as Ananthapuram - I Ultra Mega Solar Park or Kadiri Ultra Mega Solar Park, is a solar park occupying a total area of 32 square kilometres (12 sq mi) in Nambulapulakunta mandal of Kadiri Constituency in Kadiri Division of Sri Sathya Sai district of the Indian state of Andhra Pradesh it is 35 km away from Kadiri.

<span class="mw-page-title-main">Kurnool Ultra Mega Solar Park</span> 3rd Largest Solar Park in India

Kurnool Ultra Mega Solar Park in Andhra Pradesh is a solar park spread over a total area of 24 square kilometres (9.3 sq mi) in Panyam mandal of Kurnool district, Andhra Pradesh, with a capacity of 1000 MW. It was inaugurated by then chief minister of Andhra Pradesh Nara Chandrababu Naidu in 2019 The park was built at an investment of around 70 billion (US$880 million) by solar power developers and the Central and State governments. Solar power developers invested 10 billion (US$130 million), while the remaining 60 billion (US$750 million) was funded by APSPCL supported by a 2 billion (US$25 million) grant from the Union Government.

Kadapa Ultra Mega Solar Park is a solar park spread over a total area of 5,927.76 acres (23.9888 km2) in the Mylavaram mandal of Kadapa district, Andhra Pradesh.

Dholera Solar Park is a planned, large scale solar project in Dholera Special Investment Region (DSIR), Gujarat. It is categorised as an Ultra Mega Solar Power Project, by the Ministry of New and Renewable Energy of the Central Government of India; the capacity will be 5 GW by 2030.

NTPC Bhadla Solar Power Plant is a photovoltaic power station in Bhadla, Jodhpur district, India.

References

  1. Poovanna, Sharan (1 March 2018). "World's largest solar park Shakti Sthala designed by Ravindra bhan in Karnataka". Mint . Archived from the original on 28 August 2018. Retrieved 4 May 2021.
  2. Prabhu, Nagesh (30 September 2017). "1st phase of Pavagada solar park to be ready by Dec". The Hindu . Retrieved 4 May 2021.
  3. "India Solar Resource - Global Horizontal Irradiance - Annual Average, by NREL, National Renewable Energy Laboratory". National Renewable Energy Laboratory. Archived from the original on 29 March 2017. Retrieved 20 March 2017.
  4. Ranjan, Rakesh (27 December 2019). "World's Largest Solar Park at Karnataka's Pavagada is Now Fully Operational". mercomindia.com. Retrieved 4 May 2021.
  5. 1 2 3 "GoK order dated 13-06-2016 allocating 200MW solar generation plant with 15 minutes battery storage by Solar Energy Corporation Of India Limited in Pavagada Solar park" (PDF). KSPDCL. Archived (PDF) from the original on 8 March 2017. Retrieved 7 March 2017.
  6. 1 2 3 Poovanna, Sharan (6 March 2017). "How the world's largest solar park is shaping up in Karnataka". Mint . Archived from the original on 7 March 2017. Retrieved 7 March 2017.
  7. 1 2 3 "Solar power dawns on Pavagada villages". The New Indian Express . Archived from the original on 8 March 2017. Retrieved 7 March 2017.
  8. Jain, Amit (22 December 2015). "Solar energy to bring jobs and prosperity back to parched villages". World Bank . Archived from the original on 8 March 2017. Retrieved 7 March 2017.
  9. "Allocation of 500MW NTPC JNNSM Scheme (Open Category) power to ESCOMs of Karnataka proposed in 2000MW Pavagada Solar Park Area" (PDF). KSPDCL. Archived (PDF) from the original on 8 March 2017. Retrieved 7 March 2017.
  10. "Fortum wins 100 MW project in Pavagada solar park". India Today . Archived from the original on 8 March 2017. Retrieved 7 March 2017.
  11. Bureau, Our (13 April 2016). "Solar power producers bid below ₹5 a unit for Karnataka park". Business Line . Retrieved 7 March 2017.
  12. "India's NTPC invites bids for 750MW of solar in Karnataka". PV-Tech. Archived from the original on 20 March 2017. Retrieved 20 March 2017.
  13. Pavagada 750 MW capacity retendered
  14. "SB Energy Scores 200 Megawatts Of Solar In India At 4.16¢/kWh". cleantechnica.com. Archived from the original on 25 May 2018. Retrieved 25 May 2018.
  15. "50 MW of Solar Projects to be Developed in Pavagada Solar Park at a Tariff of ₹1.24/kWh". MERCOM India. Retrieved 20 May 2019.
  16. "Fortum Commissions 100 MW of Solar Project in Pavagada Solar Park - Mercom India". Mercom India. 14 December 2017. Archived from the original on 22 December 2017. Retrieved 19 February 2018.
  17. "TPREL Commissions 100 MW Solar Project at Pavagada Solar Park - Mercom India". Mercom India. 19 December 2017. Archived from the original on 22 December 2017. Retrieved 19 February 2018.
  18. "TPREL Commissions 50 MW DCR Solar Project in Pavagada Solar Park - Mercom India". Mercom India. 2 January 2018. Archived from the original on 19 February 2018. Retrieved 19 February 2018.
  19. "600 MW of Solar Projects Synchronized to the Grid at Karnataka's Pavagada Park". Archived from the original on 27 May 2018. Retrieved 18 February 2018.
  20. "1st phase of Pavagada solar park to be ready by Dec". The Hindu . Nagesh Prabhu. 30 September 2017. ISSN   0971-751X via www.thehindu.com.
  21. Kumar, B.S. Satish. "State to get 500 MW from Pavagada solar park next year". The Hindu. Retrieved 7 March 2017.
  22. "ReNew Power Commissions 300 MW Solar Plant in Pavagada". Business Standard . Archived from the original on 10 April 2019. Retrieved 10 April 2019.
  23. "Karnataka's Pavagada Solar Park to be Fully Operational by December 2019". Archived from the original on 12 April 2019. Retrieved 12 April 2019.
  24. "Karnataka's Pavagada Reaches 1850 MW Milestone with 100MW Avaada Commissioning" . Retrieved 10 December 2019.
  25. Duval, George (13 April 2021). "Reviewing The World's Largest Solar Power Plants". Semprius. Retrieved 4 May 2021.
  26. "For clean energy, Karnataka, AP are in their elements - Bangalore Mirror -". Bangalore Mirror . Archived from the original on 20 March 2017. Retrieved 20 March 2017.