National Solar Mission

Last updated

National Solar Mission (NSM)
Mission statement Achieve 100 GW solar capacity by 2022
Type of projectSolar energy mission
CountryIndia
Prime Minister(s) Manmohan Singh (2010–14)
Narendra Modi (2014–present)
Ministry Ministry of New and Renewable Energy
Launched11 January 2010;13 years ago (2010-01-11)
Closed2022;1 year ago (2022)(?) [ citation needed ]

The National Solar Mission is an initiative of the Government of India and State Governments to promote solar power. The mission is one of the several policies of the National Action Plan on Climate Change. [1] The program was inaugurated as the Jawaharlal Nehru National Solar Mission [2] by former Prime Minister Manmohan Singh on 11 January 2010 [3] with a target of 20 GW by 2022. This was later increased to 100 GW by Prime Minister Narendra Modi in the 2015 Union budget of India. [4] India increased its utility solar power generation capacity by nearly 5 times from 2,650 MW on 26 May 2014 [5] to 12,288.83 MW on 31 March 2017. The country added 9,362.65 MW in 2017–18, the highest of any year. [6] The original target of 20 GW was surpassed in 2018 (counting only utility installed capacity), four years ahead of the 2022 deadline.

Contents

India had a total rooftop solar installed capacity of 6.1 GW as of 30 June 2021. [7]

Objective

Global Horizontal Irradiance in India. India GHI Solar-resource-map GlobalSolarAtlas World-Bank-Esmap-Solargis.png
Global Horizontal Irradiance in India.

The objective of the National Solar Mission is to establish India as a global leader in solar energy, by creating the policy conditions for its diffusion across the country as quickly as possible. Under the original plan, the Government aimed to achieve a total installed solar capacity of 20 GW by 2022. This was proposed to be achieved in three phase. The first phase comprised the period from 2010 to 2013, the first year of the 12th five-year plan. The second phase extended up to 2017, while the third phase would have been the 13th five-year plan (2017–22). Targets were set as 1.4 GW in the first phase, 11–15 GW by the end of the second phase and 22 GW by the end of the third phase in 2022. [9]

The Government revised the target from 20 GW to 100 GW on 1 July 2015. To reach 100 GW by 2022, the yearly targets from 2015 to 2016 onwards were also revised upwards. [10] India had an installed solar capacity of 161 MW on 31 March 2010, about 2 and half months after the mission was launched on 11 January. By 31 March 2015, three months before the targets were revised, India had achieved an installed solar capacity of 3,744 MW. [10]

Year-wise targets

To meet the scaled up target of 100,000 MW, MNRE has proposed to achieve it through 60 GW of large and medium scale solar projects, and 40 GW through rooftop solar projects.

Year-wise Targets (in MW) [10]
Category2015–162016–172017–182018–192019–202020–212021–22Total
Rooftop Solar2004,8005,0006,0007,0008,0009,00040,000
Ground Mounted Solar projects1,8007,20010,00010,00010,0009,5008,50057,000
Total2,00012,00015,00016,00017,00017,50017,50097,000

Growth of utilities installed solar capacity

The following table records the growth of the utilities installed solar capacity in India for every year of the National Solar Mission. All capacities are as on 31 March of the listed year.

Growth of utilities installed solar capacity
YearInstalled capacityAnnual growth (MW)Annual growth (%)
2010161 MW
2011461 MW300 MW186.34%
20121,205 MW744 MW161.39%
20132,319 MW1,114 MW92.45%
20142,632 MW [11] 313 MW13.50%
20153,744 MW [12] 1,112 MW42.25%
20166,762.85 MW [13] 3,018.85 MW80.63%
201712,288.83 MW [6] 5,525.98 MW81.71%
201821,651.48 MW [14] 9,362.65 MW76.19%
201928,180.71 MW [15] 6,529.23 MW30.16%
202034,627.82 MW [16] 6,224.96 MW22.09%
202146,265.14 MW [17] 11,637.32 MW33.61%
2022

Rooftop solar capacity

India had a total rooftop solar installed capacity of 6.1 GW as of 30 June 2021. The country added 862 MW of rooftop solar capacity during the first half of 2021, recording a 210% increase over the same period in 2020. [7]

Phase 1 (2010–13)

The first phase of this mission aims to commission 1000 MW of grid-connected solar power projects by 2013. The implementation of this phase is in hands of a subsidiary of National Thermal Power Corporation, the largest power producer in India. The subsidiary, NTPC Vidyut Vyapar Nigam Ltd (NVVN), [18] laid out guidelines for selection of developers for commissioning grid connected solar power projects in India. See JNNSM Phase 1 Guidelines. While NVVN is the public face of this phase, several other departments and ministries will play a significant role in formulating guidelines. NVVN will sign power purchase agreements with the developers. Since NVVN is not a utility, it will sell purchased power to different state utilities via separate agreements.

Technologies

For Phase 1 projects, NVVN started with a proposal for 50:50 allocation towards solar PV and solar thermal. The latter is quite ambitious given India has no operational solar thermal projects and less than 10MW of solar PV projects. While growing at a rapid pace lately, solar thermal technologies are still evolving globally. The first batch of projects allotted for Phase 1 included 150MW of Solar PV and 500MW of Solar Thermal. NVVN issued Request for Selection document outlining criteria for selection of projects under the Phase 1. See Solar Thermal RFS, Solar PV RfS

A growing solar PV industry in India is hoping to take off by supplying equipment to power project developers. Well known equipment manufacturers started increasing their presence in India and may give competition to local Indian manufacturers. Due to generally high temperatures in India, crystalline silicon-based products are not the most ideal ones. Thin film technologies like amorphous silicon, CIGS and CdTe could be more suitable for higher temperature situations.

Solar thermal technology providers barely have a foothold in India. A few technology providers like Abengoa [19] have some Indian presence in anticipation of demand from this mission.

NVVN Solar PV allotment process for Phase 1

NVVN issued Request for Selection notice for allotment of capacity to Independent Power Producers (IPPs). See NVVN Solar PV RfS. 150MWs of Solar PV and 470MW of Solar Thermal were up for allotment under the first batch of Phase 1 projects. Project size per IPP was fixed at 5MW for Solar PV and 100MW for Solar Thermal projects. To avoid allocating entire capacity to a select few corporate, guidelines required no two projects to have the same parent company or common shareholders. In case of over subscription, a reverse bidding process was to be used to select the final IPPs based on lowest tariff they offer. Several hundred IPPs responded to this RfS.

The approach for reverse bidding and methodology to calculate the discount to be offered was presented by Shri Shakti Alternative Energy Ltd through a webinar on 19 October 2010 on the eve of the reverse bidding by NVVN Download presentation on Reverse Bidding by NVVN – What to Expect. [20] The quantum of discount would depend on project site location (i.e. solar radiation), technology used, simulated energy generation, capital cost and interest cost. Multivariate analysis was carried out using key variables like capital cost, interest and the capacity utilization factor (i.e. CUF which is actual generation of the plant and depends on the location (radiation) and technology used) to calculate the levelized tariff for a target equity IRR based on which the discount to be offered can be determined.

The final 30 solar PV projects [21] selected had bids between INR 10.95 to INR 12.75. The Solar Thermal projects selected had bids between INR 10.24 to INR 12.24. PPAs were signed with IPPs in early January.

2014–present

In December 2014, the Government of India introduced a scheme to establish at least 25 solar parks and Ultra Mega Solar Power Projects to add over 20 GW of installed solar power capacity. The Central Government provides financial support for the construction of these solar projects. [22] As of December 2016, the Central Government has provided in-principle approval to set up 34 solar parks across 21 states. [23] Each power project has a minimum capacity of 500 MW. [24]

Domestic content complaint

Guidelines for the solar mission mandated cells and modules for solar PV projects based on crystalline silicon to be manufactured in India. That accounts to over 60% of total system costs. For solar thermal, guidelines mandated 30% project to have domestic content. A vigorous controversy emerged between power project developers and solar PV equipment manufacturers. The former camp prefers to source modules by accessing highly competitive global market to attain flexible pricing, better quality, predictable delivery and use of latest technologies. [25] The latter camp prefers a controlled/planned environment to force developers to purchase modules from a small, albeit growing, group of module manufacturers in India. [26] Manufacturers want to avoid competition with global players and are lobbying the government to incentivise growth of local industry[ citation needed ].

Market responded to domestic content requirement by choosing to procure thin film modules from well established international players. A significant number of announced project completions are using modules from outside India. [27] [28]

US Trade Representative has filed a complaint at World Trade Organization challenging India's domestic content requirements in Phase II of this Mission, citing discrimination against US exports and that industry in US which has invested hugely will be at loss. US insists that such restrictions are prohibited by WTO. India however claims that it is only an attempt to grow local potential and to ensure self sustenance and reduce dependence [29]

See also

Related Research Articles

<span class="mw-page-title-main">Electricity sector in India</span> Power generation and distribution

India is the third largest producer of electricity in the world. During the fiscal year (FY) 2022–23, the total electricity generation in the country was 1,844 TWh, of which 1,618 TWh was generated by utilities.

<span class="mw-page-title-main">Solar power by country</span>

Many countries and territories have installed significant solar power capacity into their electrical grids to supplement or provide an alternative to conventional energy sources. Solar power plants use one of two technologies:

<span class="mw-page-title-main">Solar power in Australia</span>

Solar power is a fast-growing industry in Australia. As of June 2023, Australia's over 3.52 million solar PV installations had a combined capacity of 32,095 MW photovoltaic (PV) solar power, of which at least 4,389 MW were installed in the preceding 12 months. In 2019, 59 solar PV projects with a combined capacity of 2,881 MW were either under construction, constructed or due to start construction having reached financial closure. Solar accounted for 12.4% of Australia's total electrical energy production in 2021.

<span class="mw-page-title-main">Solar power in Spain</span>

Spain is one of the first countries to deploy large-scale solar photovoltaics, and is the world leader in concentrated solar power (CSP) production.

<span class="mw-page-title-main">Solar power in India</span>

Solar power is a fast developing industry in India. The country's solar installed capacity was 71.61 GWAC as of 31 August 2023. Solar power generation in India ranks fourth globally in 2021.

For solar power, South Asia has the ideal combination of both high solar insolation and a high density of potential customers.

<span class="mw-page-title-main">Solar power in China</span>

China is the largest market in the world for both photovoltaics and solar thermal energy. China's photovoltaic industry began by making panels for satellites, and transitioned to the manufacture of domestic panels in the late 1990s. After substantial government incentives were introduced in 2011, China's solar power market grew dramatically: the country became the world's leading installer of photovoltaics in 2013. China surpassed Germany as the world's largest producer of photovoltaic energy in 2015, and became the first country to have over 100 GW of total installed photovoltaic capacity in 2017.

<span class="mw-page-title-main">Solar power in the United States</span>

Solar power includes solar farms as well as local distributed generation, mostly on rooftops and increasingly from community solar arrays. In 2022, utility-scale solar power generated 145.6 terawatt-hours (TWh), or 3.4% of electricity in the United States. Total solar generation that year, including estimated small-scale photovoltaic generation, was 204 TWh.

Between 1992 and 2022, the worldwide usage of photovoltaics (PV) increased exponentially. During this period, it evolved from a niche market of small-scale applications to a mainstream electricity source. From 2016-2022 it has seen an annual capacity and production growth rate of around 26%- doubling approximately every three years.

<span class="mw-page-title-main">Solar power in California</span>

Solar power has been growing rapidly in the U.S. state of California because of high insolation, community support, declining solar costs, and a renewable portfolio standard which requires that 60% of California's electricity come from renewable resources by 2030, with 100% by 2045. Much of this is expected to come from solar power via photovoltaic facilities or concentrated solar power facilities.

<span class="mw-page-title-main">Renewable energy in India</span>

India is world's 3rd largest consumer of electricity and world's 3rd largest renewable energy producer with 40% of energy capacity installed in the year 2022 coming from renewable sources. Ernst & Young's (EY) 2021 Renewable Energy Country Attractiveness Index (RECAI) ranked India 3rd behind USA and China. In FY2023-24, India is planning to issue 50 GW tenders for wind, solar and hybrid projects. India has committed for a goal of 500 GW renewable energy capacity by 2030. In line with this commitment, India's installed renewable energy capacity has been experiencing a steady upward trend. From 94.4 GW in 2021, the capacity has gone up to 119.1 GW in 2023 as of Q4.

<span class="mw-page-title-main">Solar power in Greece</span>

Development of solar power in Greece started in 2006 and installations of photovoltaic systems skyrocketed from 2009 because of the appealing feed-in tariffs introduced and the corresponding regulations for domestic applications of rooftop solar PV. In 2019, 90% of the around 2.5 GWp capacity was installed in 2011, 2012 and 2013. However, funding the FITs created an unacceptable deficit of more than €500 million in the Greek "Operator of Electricity Market" RES fund. To reduce that deficit, new regulations were introduced in August 2012 including retrospective feed-in tariffs reduction, with further reductions over time. These measures enabled the deficit to be erased by 2017.

<span class="mw-page-title-main">Solar power in Gujarat</span> Overview of solar power in Gujarat

Solar power in Gujarat, a state of India, is a fast developing industry given that the large state is mostly arid. It was one of the first states to develop solar generation capacity in India.

<span class="mw-page-title-main">Solar power in South Africa</span> Overview of the use of solar power in South Africa

Solar power in South Africa includes photovoltaics (PV) as well as concentrated solar power (CSP). In 2016, South Africa had 1,329 MW of installed solar power capacity. Installed capacity is expected to reach 8,400 MW by 2030.

Under its commitment to the EU renewable energy directive of 2009, France has a target of producing 23% of its total energy needs from renewable energy by 2020. This figure breaks down to renewable energy providing 33% of energy used in the heating and cooling sector, 27% of the electricity sector and 10.5% in the transport sector. By the end of 2014, 14.3% of France's total energy requirements came from renewable energy, a rise from 9.6% in 2005.

<span class="mw-page-title-main">Mahindra Susten</span>

Mahindra Susten Pvt. Ltd., formerly Mahindra EPC Services Pvt. Ltd. , is part of the US$19 billion Mahindra Group. They are a portfolio company under the Cleantech arm of Mahindra Partners.

<span class="mw-page-title-main">Power sector of Andhra Pradesh</span>

Power sector of Andhra Pradesh is divided into 4 categories namely Regulation, Generation, Transmission and Distribution. Andhra Pradesh Electricity Regulatory Commission (APERC) is the regulatory body. APGENCO deals with the electricity production and also maintenance, proposes new projects and upgrades existing ones as well. The APGENCO also set up a Special Purpose Vehicle (SPV), named as Andhra Pradesh Power Development Company Limited (APPDCL), a joint venture company of APGENCO and IL&FS to set up Krishnapatanam thermal power project.

<span class="mw-page-title-main">Solar power in the United Arab Emirates</span>

While being a major oil producing country, the United Arab Emirates (UAE) has taken steps to introduce solar power on a large scale. However, solar power still accounts for a small share of energy production in the country. The country was the 6th top carbon dioxide emitter per capita in the world in 2009, with 40.31 tonnes, but is planning to generate half of its electrical energy by 2050 from solar and nuclear sources, targeting 44% renewables, 38% gas, 12% coal, and 6% nuclear energy sources.

<span class="mw-page-title-main">Vikram Solar</span> Indian solar energy company

Vikram Solar Limited is an Indian company based in Kolkata, one of the largest solar module manufacturers in India with 3.5 GW module manufacturing capacity annually and the second-largest solar energy company in India by revenue. The company's primary business focus is manufacturing solar PV modules, and also carries out engineering, procurement, and construction services and operations and maintenance of solar power plants.

Kadapa Ultra Mega Solar Park is a solar park spread over a total area of 5,927.76 acres (23.9888 km2) in the Mylavaram mandal of Kadapa district, Andhra Pradesh.

References

  1. "India's National Action Plan on Climate Change – Highlights". Archived from the original on 23 February 2012. Retrieved 7 June 2012.
  2. JNNSM Inauguration
  3. "Ministry of New and Renewable Energy – Scheme / Documents". Mnre.gov.in. Archived from the original on 31 January 2018. Retrieved 14 September 2016.
  4. "Revision of cumulative targets under National Solar Mission from 20,000 MW by 2021–22 to 1,00,000 MW". pib.nic.in. Retrieved 27 March 2017.
  5. "India's solar capacity to cross 20GW in next 15 months: Piyush Goyal". Money Control. 17 March 2017. Retrieved 18 March 2017.
  6. 1 2 Chandrasekaran, Kaavya (6 April 2017). "India's solar energy capacity expanded by record 5,525 MW". The Economic Times. Retrieved 6 April 2017.
  7. 1 2 "India adds record-high rooftop solar capacity of 521 MW in April-June". The Hindu. 21 September 2021. Retrieved 1 November 2021.
  8. "Global Solar Atlas" . Retrieved 4 December 2018.
  9. "Jawaharlal Nehru National Solar Mission Phase II – Policy Document" (PDF). Ministry of New & Renewable Energy. December 2012. Retrieved 27 March 2017.
  10. 1 2 3 Kapoor, Tarun (1 July 2015). "Scaling up of Grid Connected Solar Power Projects" (PDF). Ministry of New and Renewable Energy. Archived from the original (PDF) on 26 February 2017.
  11. "ALL INDIA INSTALLED CAPACITY (IN MW) OF POWER STATIONS (As on 31.03.2014) (UTILITIES)" (PDF). CEA. Retrieved 27 March 2017.
  12. "ALL INDIA INSTALLED CAPACITY (IN MW) OF POWER STATIONS LOCATED IN THE REGIONS OF MAIN LAND AND ISLANDS (As on 31.03.2015) (UTILITIES)" (PDF). CEA. Retrieved 27 March 2017.
  13. "ALL INDIA INSTALLED CAPACITY (IN MW) OF POWER STATIONS (As on 31.03.2016) (UTILITIES)" (PDF). CEA. Retrieved 27 March 2017.
  14. "ALL INDIA INSTALLED CAPACITY (IN MW) OF POWER STATIONS (As on 31.03.2018) (UTILITIES)" (PDF). CEA. Retrieved 19 May 2018.
  15. "ALL INDIA INSTALLED CAPACITY (IN MW) OF POWER STATIONS (As on 31.03.2019) (UTILITIES)" (PDF). CEA. Retrieved 18 April 2019.
  16. "ALL INDIA INSTALLED CAPACITY (IN MW) OF POWER STATIONS (As on 31.03.2020) (UTILITIES)" (PDF). CEA. Retrieved 10 April 2020.
  17. "ALL INDIA INSTALLED CAPACITY (IN MW) OF POWER STATIONS (As on 30.09.2021) (UTILITIES)" (PDF). Retrieved 16 October 2021.
  18. NVVN
  19. "abengoa". Archived from the original on 7 July 2011. Retrieved 12 May 2010.
  20. Webinar On Reverse Bidding Strategy
  21. "NVVN Phase 1 Batch 1 Solar PV Projects" (PDF).
  22. "Scheme for Development of Ultra Mega Solar Parks". Pib.nic.in. Retrieved 24 July 2016.
  23. "Large-scale solar projects in India at the mercy of poor infra". www.moneycontrol.com. 15 December 2016. Retrieved 20 March 2017.
  24. Smiti Mittal (15 September 2014). "India Considers Adding 20 GW Capacity Through Ultra Mega Solar Power Projects". Cleantechnica.com. Retrieved 24 July 2016.
  25. [Kevin Roebuck, Solar PPA: High-impact Strategies – What You Need to Know: Definitions, Adoptions, Impact, Benefits, Maturity, Vendors, pg. 87]
  26. domesticPro
  27. "First Solar to supply modules for an Indian Solar PV developer".
  28. "Trina supplying modules for an Indian Solar PV plant".
  29. "US challenges India's Domestic Rules in National Solar Mission". news.biharprabha.com. Indo-Asian News Service. Retrieved 11 February 2014.