Tehachapi Energy Storage Project

Last updated

Tehachapi Energy Storage Project
Overhead View of Tehachapi Energy Storage Project, Tehachapi, CA.png
Overhead View of Tehachapi Energy Storage Project, Tehachapi, CA
Tehachapi Energy Storage Project
CountryUnited States
LocationTehachapi, Kern County, CA
Coordinates 35°7′24″N118°22′48″W / 35.12333°N 118.38000°W / 35.12333; -118.38000
StatusDecommissioned
Construction began2013
Commission date 2014
Decommission date2022
Owner(s)Southern California Edison
Operator(s)Southern California Edison
Site area6300 sq. ft.
Site elevation3966 ft.
Power generation
Nameplate capacity 8 MW
Storage capacity 32 MWh
External links
Website https://newsroom.edison.com/releases/sce-unveils-largest-battery-energy-storage-project-in-north-america
Commons Related media on Commons

The Tehachapi Energy Storage Project (TSP) is a 8MW/32MWh lithium-ion battery-based grid energy storage system at the Monolith Substation of Southern California Edison (SCE) in Tehachapi, California, sufficient to power between 1,600 and 2,400 homes for four hours. [1] At the time of commissioning in 2014, it was the largest lithium-ion battery system operating in North America and one of the largest in the world. [2] [3] [4] [5] TSP is considered to be a modern-day energy storage pioneer with significant accomplishments that have proven the viability of utility-scale energy storage using lithium-ion technology. [6] While originally envisioned as a research and development project, [7] TSP operated as a distribution-level resource for SCE and for calendar year 2020, SCE reported that TSP operated in the wholesale energy market with revenue exceeding operating and maintenance costs. [8] [9] In 2021, SCE began the decommissioning of TSP, which was followed by formal decommissioning by state regulators in 2022. [10] [11] The physical dismantlement of TSP is expected to be completed by the end of 2022. [12]

Contents

System

At a windy mountain pass on the edge of the Mojave Desert, North America’s most potent collection of batteries used for storing unused power is humming its way toward an electricity revolution. [13]

Whitney McFerron,Bloomberg

In May 2013, Southern California Edison awarded the TSP contract to a consortium led by LG Chem, the battery division of the South Korean industrial conglomerate LG Corporation. LG Chem supplied the battery systems while ABB supplied the inverters and LG CNS provided the engineering and construction support. [5]

The TSP system was one of the first to demonstrate the assembly of a large quantity of lithium-ion batteries into a single system on the order of megawatts of power and tens of megawatt-hours of energy to provide electric grid support. The project uses electric vehicle-grade batteries and demonstrates the synergies between batteries for the automotive and electric grid sectors. [14] During 2009 to 2014, more than 120 grid energy storage projects were commissioned, marking a significant turning point for grid batteries. [15] The TSP system had a significant role in this as a large, utility-owned system providing multiple energy services using commercially available products. [15]

The TSP system was designed and evaluated using an application-driven approach. [16] Energy storage for the wind farms at Tehachapi Pass [17] have been extensively studied before, including the impacts of energy storage at Monolith Substation. [18] As Edison International, parent company of Southern California Edison (SCE), describes, there is a continued interest in energy storage from utilities, along with a view that there will be technical innovations to help with managing the grid in a more efficient and reliable manner. [19]

The history of seismic activity in Kern County, [20] including damage to substation structures, [21] created some challenging system design requirements, such as having the populated battery racks designed and tested to meet IEEE 693-2005, Recommended Practice for Seismic Design of Substations recommendations. [22] [23] Since commissioning in 2014, the area has experienced not only seismic activity, [24] but also flash floods and subsequent mudslides. [25]

One key lesson learned is the importance of subscale testing by the electric utility prior to full system deployment so that the safety and operational controls and features could be fully evaluated. [26] [27] This was the first known use of a subscale system by an entity other than a manufacturer or integrator to facilitate full-scale testing, commissioning, and ongoing operations. [6] The mini-system test plan included two phases:

  1. Performing safety testing on the expected behavior of the batteries and battery management system during interruptions to communication paths during system startup and operation and
  2. Performing system acceptance tests on the Mini-System to verify correct operation of the control algorithms, test modes, and system response prior to performing the same tests on the full system. [6]

The original mini-system provided engineers with support for full system startup and commissioning, but, with only one battery section and one inverter lineup, engineers were unable to test the multi-inverter lineup-battery section operation of the system in the laboratory, such as inter-section balancing controls, multi-inverter operation, and symmetrical and unsymmetrical operation of the inverter lineups. [6] To more closely resemble the full system, the mini-system was expanded in December 2015 to include twice the number of each component, resulting in a system with two inverter controllers, inverter lineups, and battery sections. [6]

Mini-system used for sub-scale testing and evaluation Tehachapi Energy Storage Project - Mini - System.png
Mini-system used for sub-scale testing and evaluation

The TSP system is constructed of 608,832 lithium-ion battery cells that are enclosed into 10,872 modules of 56 cells each and then stacked in 604 racks. [2] [26] A bi-directional inverter or power conversion system (PCS) provides the DC-to-AC conversion during battery discharging and AC-to-DC conversion for battery charging. [26] The batteries are housed in a 6,300-square-foot (590 m2) building. [28] The TSP system can supply 32 megawatt-hours of energy, at a maximum rate of 8 megawatts. This is sufficient to power between 1,600 and 2,400 homes for four hours. [1] The amount of energy stored at TSP is equivalent to that stored in more than 2,000 Chevrolet Volt hybrid electric vehicles. [29]

Inside the Tehachapi Energy Storage Project during construction Utility4-SCE Tehachapi Photo2.jpg
Inside the Tehachapi Energy Storage Project during construction
Specifications for mini-system and full system [6] [30]
Mini-System at Pomona, CA (Original)Mini-System at Pomona, CA (December 2015 Expansion)Full System at Tehachapi, CA
Footprint77 square feet154 square feet6300-square-foot building
Power30 kW60 kW8 MW
Energy116 kWh232 kWh32 MWh
InverterOne mini-cabinetTwo mini-cabinetsTwo 40-foot containers
Sections124
Banks1232
Racks24604
Modules367210,872
Cells2,0164,032608,832

Deployment

TSP is an example of commercially available large-scale energy storage for electric grid applications [31] and part of the increasing fleet of energy storage systems. [32] The deployment of TSP has been part of the key foundation in developing energy storage in California [33] and for increasing grid reliability overall. [34] TSP is also providing improved integration and opportunities for better operation of renewable energy resources. [35]

In 2014, TSP was one of the large-scale energy storage projects in the interconnection queue for the California Independent System Operator (CAISO) with planned benefits including firming renewable generation, frequency regulation, spin and non-spin replacement reserves, ramp management, and energy price arbitrage. [36] The TSP system was tested using eight core tests performed by the grid operator or under market control. [37] Some of the lessons learned included the challenges related to outage scheduling, challenges with interconnection agreements, benefits of component validation testing at the factories, and preparing detailed step-by-step test plans in advance. [30] Both the utility and system provider gained important perspectives and insights during the design, construction, commissioning, and operating of the TSP system. [38] [6] [22]

To evaluate the 13 operational uses, SCE defined eight tests to measure the ability of TSP to respond to the following system needs or signals:

  1. Provide steady state voltage regulation at the local Monolith 66 kV bus
  2. Provide steady state voltage regulation at the local Monolith 66 kV bus while performing any other tests
  3. Charge during periods of high wind and discharge during low wind under SCE system operator control
  4. Charge during off-peak periods and discharge during on-peak periods under SCE system operator control
  5. Charge and discharge seconds-to-minutes as needed to smooth intermittent generation in response to a real-time signal
  6. Respond to CAISO control signals to provide frequency response
  7. Respond to CAISO control signals to provide spin and non-spin reserves
  8. Follow a CAISO market signal for energy price. [6]
Tehachapi Operational Uses and Tests [30]
Operational UseTest
12345678
TransmissionVoltage Support1XX
Decreased Losses2X
Diminished Congestion3X
Increased System Reliability4X
Deferred Transmission Investment5XX
Optimized Renewable-Related Transmission6XX
SystemSystem Capacity/Resource Adequacy7XX
Renewable Integration (firming & shaping)8X
Output Shifting9X
ISO MarketFrequency Regulation10X
Spin and Non-Spin Reserves11X
Deliver Ramp Rate12XX
Energy Price Arbitrage13X

The final project report for the United States Department of Energy after system deployment concludes that TSP is a modern-day energy storage pioneer, achieving a number of significant accomplishments that have proven the viability of utility-scale energy storage using lithium-ion technology. [6] These accomplishments include: [6]

Operation

Panoramic view of the battery building for the Tehachapi Energy Storage Project and Monolith Substation Tehachapi Energy Storage Project at Monolith Substation - Panorama.jpg
Panoramic view of the battery building for the Tehachapi Energy Storage Project and Monolith Substation

Since the start of market operations in 2016, TSP has been listed in the Monthly Electric Generator Inventory of the Energy Information Administration (EIA) as an electric generator. [39] During that time period, the EIA began publishing more-detailed energy storage information in its Annual Electric Generator Report, including battery capacity, charge and discharge rates, storage technology types, reactive power ratings, storage enclosure types, and expected usage applications. [40]

The operation of the TSP system has been described as a real-life example of grid-connected energy storage, [41] and some of the initial testing included storing wind energy at night and delivering it during the day when customers need it. [42] The California Independent System Operator (CAISO), a grid system operator, shares its operating experiences of TSP internationally with other grid operators as part of continued close collaborations. [43] The ongoing operation of the TSP system continues to provide grid services in the energy market and lessons learned for grid energy-storage systems. [44] [45]

In its annual report to the California Public Utilities Commission (CPUC) for calendar year 2020, SCE reported that TSP continued to operate in the CAISO wholesale market and that market benefits exceeded operating and maintenance costs. [9] In addition to market operations, SCE continued to collect operating data to evaluate the long-term operating characteristics of grid scale lithium-ion battery storage technology. [9]

TSP was taken offline on May 17, 2021 and on August 23, 2021, SCE submitted a request to the CPUC for the decommissioning of TSP due to the cost of safety upgrades and cybersecurity concerns. [10] On May 5, 2022, the CPUC formally decommissioned TSP, nine years after it came online. [11] [46] The physical dismantlement of TSP is expected to be completed by the end of 2022. [12] All of the battery cells will be recycled and the inverter will be repurposed. [12] TSP operated for more than four years beyond the original two-year demonstration period, which SCE considers to be significant due to the fact that TSP uses first-generation lithium-ion BESS products that are no longer in production. [10] The additional operational period has provided lessons learned about long-term operations, maintenance, and repairs. [10] Due to the system size, TSP will be one of the first and largest lithium-ion battery systems to undergo decommissioning. [10] SCE describes that: [10]

TSP was a highly successful project that helped transform the industry, demonstrate large lithium-ion BESS technology, increase operational experience for SCE, and provide value for California utility customers. The BESS far exceeded its original two-year demonstration; it's appropriate to decommission now.

Analysis

One of the major benefits of the TSP system is the wide range of studies and analyses performed by multiple organizations to address various aspects of the energy market. Operational information has been used as part of developing incentives for distributed energy storage for California, New York, Hawaii, and several other states. [47] The energy management system (EMS) and EMS structure for TSP have been studied to develop and determine the technical, market, and regulatory requirements for energy-storage systems. [48]

The University of California, Riverside has used TSP for the stochastic valuation of energy storage in wholesale power markets to determine optimal power dispatch sequences. [49] The findings from this study include:

  1. System performance is heavily affected by roundtrip efficiency and power-to-energy ratio.
  2. The optimal power-to-energy ratio for wholesale power market is much higher than the nominal configuration of 1-to-4 typically used in existing energy storage projects.
  3. The majority of revenues are from frequency regulation services. [50]

In a separate analysis, the University of California, Riverside used real market data from TSP to develop an optimal supply and demand bidding, scheduling, and deployment design framework based on the day-ahead and real-time market prices, location, size, efficiency, lifetime, and charge and discharge rates. [51] The topic of used and second-use batteries is also examined and analysis shows that by using one of the proposed bidding methods, TSP could still be profitable even after losing half of its energy capacity. [51]

Based on the studies described above, the University of California, Riverside performed an additional analysis for the scenarios where battery systems are investor-owned and independently operated and participating in existing markets. [52] The study proposes a new optimization framework to coordinate the operation of large, price-maker, and geographically dispersed energy storage systems in a nodal transmission-constrained energy market. [52]

The Institute of Electrical and Electronics Engineers (IEEE) published a collection of technical papers analyzing energy storage, including a review of TSP. [53] The review described how TSP met the project objectives and provided the required operational uses. [53] While there were some challenges, including control system issues and a poor transformer design, these issues were not related to the storage technology itself. [53] SCE continues to use its experiences from TSP in the development of additional energy storage projects. [53]

The Edison Electric Institute (EEI), which represents all investor-owned utilities in the United States, published a set of case studies and described how TSP has capabilities to provide nearly instantaneous maximum capacity for renewables ramping, which minimizes needs for traditional backup generators. [54] EEI also described that TSP remained operational after the 24-month pilot and testing period of the project. [54]

The European Commission performs an ongoing analysis of energy storage systems, including TSP, and has global collaborations with technical experts to exchange and to learn about operating details, challenges, and best practices. [55] Some of the challenges resolved for TSP included the programming logic, safety limits, and data aggregation, as well as the use of consistent paths for component communications. [55] The analysis also mentions how in general, the system integration and control aspects for energy storage systems need to be resolved and addressed by a European master plan. [55] In addition, recycling is a topic that needs to handled as market growth continues. [55]

PV Tech Power published a journal article describing how TSP and battery storage are being used as peaking capacity. [56] The article mentions that TSP provided support for the rapid expansion of renewable energy, as well as being a rare utility-scale battery with a 4-hour duration during the 2014 timeframe when it was commissioned. [56] The article explains how four hours is now considered to be the optimum duration for peaking capacity for two reasons: 1) Mitigating peak demand as solar power ramps down in the late afternoon and evening and 2) Providing the optimum cost point for lithium-ion batteries to provide that capacity. [56]

Awards and accolades

It seems an unlikely setting for a technology revolution: a wind-swept patch of Mojave Desert, squeezed in beside railroad tracks and a giant cement plant. But there it is, on the grounds of Southern California Edison’s Monolith substation near Tehachapi, Calif.: the largest battery for storing electricity in North America. [1]

Bill Loving,Edison International - Energized

Information sheet distributed during ribbon-cutting ceremony-Page 1 Tehachapi Energy Storage Project-Ribbon Cutting-Page 1.jpg
Information sheet distributed during ribbon-cutting ceremony-Page 1
Information sheet distributed during ribbon-cutting ceremony-Page 2 Tehachapi Energy Storage Project-Ribbon Cutting-Page 2.jpg
Information sheet distributed during ribbon-cutting ceremony-Page 2

An official ribbon-cutting ceremony, site tour, and presentation of a certificate of recognition from the California State Senate were held on September 24, 2014. [3] [57] [58] The ceremony speakers included Doug Kim (Director of Advanced Technology, Southern California Edison), Zack Scrivner (Supervisor, Kern County Board of Supervisors), Dr. Imre Gyuk (Energy Storage Program Manager, United States Department of Energy), Dr. Seokhwan Kwak (Vice President of Marketing, LG Chem), and Romeo Agbalog (Office of State Senator, Jean Fuller – 18th District). [58] Tours of the control room, battery room, and inverter enclosures were provided. [57] [58]

Upon commissioning, TSP was selected as a finalist for the 2014 Innovation Award for Energy Storage North America (ESNA) and elected to the ESNA Hall of Fame. [59] [60] Later in 2014, TSP was included in Innovations Across the Grid published by the Edison Foundation Institute for Electric Innovation, which described how the distribution grid is evolving to optimize the electric grid, integrate new resources, and provide customer solutions. [61] TSP was featured as a real-life, new energy resource case study. [61]

PBS science correspondent Miles O'Brien covered TSP in the December 15, 2015 edition of PBS NewsHour in a segment with Doug Kim of SCE that discussed the use of TSP to store energy generated by wind turbines. [42]

A hundred miles north of Los Angeles, in Tehachapi, California, the wind can be a bountiful resource, but, unfortunately, not at the right time. It blows hardest at night, spooling up these wind turbines to their peak output, when the demand for electricity is at it lowest.

Miles O'Brien, PBS NewsHour

So, matching the output of wind to when customers really need it, that's certainly one of the things that we're looking at with this system that you see here, because you can store energy.

Doug Kim, PBS NewsHour

In 2016, the California Energy Storage Alliance featured TSP in the lead position in a video with policymakers, utility executives, and energy storage pioneers titled Gamechangers: How Energy Storage Transforms the Power System, which describes how SCE pioneered the use of grid energy storage. [62] Region 6 of the IEEE awarded its Director's Award to SCE in 2016 with the successful completion of TSP as one of the key accomplishments. [63] The Energy Storage Association (ESA) awarded LG Chem the Brad Roberts Award for Outstanding Industry Achievement in 2017 for marketplace and industry accomplishments during the past several years, including the successful delivery and commissioning of TSP. [64] [65]

At the Kern County Energy Summit 2017, Vibhu Kaushik, SCE principal manager, described TSP as the start of utility-scale energy storage projects for SCE. [66]

…the story really started here in Kern County about five years ago when we built the world’s largest energy storage project, the Tehachapi Battery Storage Project. 8 megawatts 32 megawatt-hours. It got a lot of attention and made news everywhere as battery storage became a part of the energy mix at that time as people started looking at battery storage as a megawatt-size utility-scale resource.

Vibhu Kaushik, Kern County Energy Summit 2017, Southern California Edison’s Recent Energy Storage Projects

PBS featured TSP in the Search for the Super Battery episode of Nova in 2017. [67] Host and science writer David Pogue described how lithium-ion batteries are being installed on the grid and Doug Kim of SCE explained the use of TSP for smoothing, firming, and time shifting of wind power. [67]

The 2018 and 2019 Economic Round Table Reports from the Greater Antelope Valley Economic Alliance include TSP as a highlight in the Renewable Energy sections. [68] Kern County, California describes TSP as a key feature in its renewable energy portfolio [69] for storing energy from solar power and wind power and improving grid flexibility and reliability. [70] Kern County continues to cultivate energy storage as providing economic development opportunities for 2020 and beyond; [71] by 2023, storage facilities a hundred times bigger than TSP are operating in Kern, California and USA. [72]

In 2019, the U.S. Department of Energy featured TSP in Success Stories Spotlight: Solving Industry’s Energy Storage Challenges. [73] The case study examined two areas: technology advancement and impact. [73]   TSP advanced technology by showing the abilities of lithium-ion battery storage systems to ramp up nearly instantaneously to maximum power capacity. [73]   TSP also demonstrated technical capabilities for frequency regulation, decreased transmission losses, voltage stabilization, and deferred transmission investment. [73]  The case study describes how TSP was operated outside of a laboratory and at scale. [73] As a result, one of the important impacts of TSP is that it provided practical experience in operations and reliability under real-word conditions as one of the largest energy storage systems located on a high-traffic grid. [73]   The project provided hardware and software learning opportunities for the system supplier for future projects. [73]   Additional impacts included providing increased definition and development of the process for interconnecting energy storage systems to the grid. [73]   In turn, this provided improvements for integrating energy storage systems into power markets and providing financial data for the valuation of future projects. [73]   One additional impact mentioned was that the TSP provided an increased amount of renewable energy on the grid, as well as improved grid reliability and power quality. [73]

In 2021, Forbes mentioned TSP as a notable example of energy storage used by SCE for charging and discharging power from the electric grid in support of renewable energy and electric utility preparations for electrification and decarbonization. [74] Forbes explained that TSP can store and discharge energy at any time using lithium-ion batteries with a limited duration. [74]

See also

Related Research Articles

<span class="mw-page-title-main">Energy storage</span> Captured energy for later usage

Energy storage is the capture of energy produced at one time for use at a later time to reduce imbalances between energy demand and energy production. A device that stores energy is generally called an accumulator or battery. Energy comes in multiple forms including radiation, chemical, gravitational potential, electrical potential, electricity, elevated temperature, latent heat and kinetic. Energy storage involves converting energy from forms that are difficult to store to more conveniently or economically storable forms.

<span class="mw-page-title-main">Distributed generation</span> Decentralised electricity generation

Distributed generation, also distributed energy, on-site generation (OSG), or district/decentralized energy, is electrical generation and storage performed by a variety of small, grid-connected or distribution system-connected devices referred to as distributed energy resources (DER).

<span class="mw-page-title-main">Sodium–sulfur battery</span> Type of molten-salt battery

A sodium–sulfur (NaS) battery is a type of molten-salt battery that uses liquid sodium and liquid sulfur electrodes. This type of battery has a similar energy density to lithium-ion batteries, and is fabricated from inexpensive and non-toxic materials. However, due to the high operating temperature required, as well as the highly corrosive and reactive nature of sodium and sodium polysulfides, these batteries are primarily suited for stationary energy storage applications, rather than for use in vehicles. Molten Na-S batteries are scalable in size: there is a 1 MW microgrid support system on Catalina Island CA (USA) and a 50 MW/300 MWh system in Fukuoka, Kyusyu, (Japan).

<span class="mw-page-title-main">Southern California Edison</span> Electrical utility in Southern California, United States

Southern California Edison (SCE), the largest subsidiary of Edison International, is the primary electric utility company for much of Southern California. It provides 15 million people with electricity across a service territory of approximately 50,000 square miles.

<span class="mw-page-title-main">Grid energy storage</span> Large scale electricity supply management

Grid energy storage is a collection of methods used for energy storage on a large scale within an electrical power grid. Electrical energy is stored during times when electricity is plentiful and inexpensive or when demand is low, and later returned to the grid when demand is high, and electricity prices tend to be higher.

<span class="mw-page-title-main">Vehicle-to-grid</span> Vehicle charging system that allows discharge and storage of electricity

Vehicle-to-grid (V2G) describes a system in which plug-in electric vehicles (PEV) sell demand response services to the grid. Demand services are either delivering electricity or reducing their charging rate. Demand services reduce pressure on the grid, which might otherwise experience disruption from load variations. Vehicle-to-load (V2L) and Vehicle-to-vehicle (V2V) are related, but the AC phase is not sychronised with the grid, so the power is only available to an "off grid" load.

A virtual power plant (VPP) is a system that integrates multiple, possibly heterogeneous, power sources to provide grid power. A VPP typically sells its output to an electric utility. VPPs allow energy resources that are individually too small to be of interest to a utility to aggregate and market their power. As of 2024, VPPs operated in the United States, Europe, and Australia.

<span class="mw-page-title-main">Tehachapi Pass wind farm</span> Wind farm in the United States

The Tehachapi Pass wind farm is one of the first large-scale wind farms installed in the U.S., with around 710 megawatts (950,000 hp) produced by about 3400 wind turbines.

<span class="mw-page-title-main">Wind power in California</span> Electricity from large wind farms

Wind power in California had initiative and early development during Governor Jerry Brown's first two terms in the late 1970s and early 1980s. The state's wind power capacity has grown by nearly 350% since 2001, when it was less than 1,700 MW. In 2016, wind energy supplied about 6.9% of California's total electricity needs, or enough to power more than 1.3 million households. Most of California's wind generation is found in the Tehachapi area of Kern County, California, with some large projects in Solano, Contra Costa and Riverside counties as well. California is among the states with the largest amount of installed wind power capacity. In recent years, California has lagged behind other states when it comes to the installation of wind power. It was ranked 4th overall for wind power electrical generation at the end of 2016 behind Texas, Iowa, and Oklahoma. As of 2019, California had 5,973 megawatts (MW) of wind power generating capacity installed.

<span class="mw-page-title-main">Tehachapi Renewable Transmission Project</span>

The Tehachapi Renewable Transmission Project is a project involving the construction of approximately 173 miles (278 km) of new and upgraded high-voltage transmission lines for transmission of electricity from wind farms and other generating units in southeastern Kern County, California to Los Angeles County and San Bernardino County.

<span class="mw-page-title-main">Solar power in California</span>

Solar power has been growing rapidly in the U.S. state of California because of high insolation, community support, declining solar costs, and a renewable portfolio standard which requires that 60% of California's electricity come from renewable resources by 2030, with 100% by 2045. Much of this is expected to come from solar power via photovoltaic facilities or concentrated solar power facilities.

<span class="mw-page-title-main">Monolith, California</span> Unincorporated community in California, United States

Monolith is an unincorporated community in the Tehachapi Valley, in Kern County, California.

<span class="mw-page-title-main">Solar power in Hawaii</span> Overview of solar power in the U.S. state of Hawaii

The energy sector in Hawaii has rapidly adopted solar power due to the high costs of electricity, and good solar resources, and has one of the highest per capita rates of solar power in the United States. Hawaii's imported energy costs, mostly for imported petroleum and coal, are three to four times higher than the mainland, so Hawaii has motivation to become one of the highest users of solar energy. Hawaii was the first state in the United States to reach grid parity for photovoltaics. Its tropical location provides abundant ambient energy.

<span class="mw-page-title-main">Energy in California</span> Overview of the use of energy in California, U.S.

Energy in California is a major area of the economy of California. California is the state with the largest population and the largest economy in the United States. It is second in energy consumption after Texas. As of 2018, per capita consumption was the fourth-lowest in the United States partially because of the mild climate and energy efficiency programs.

<span class="mw-page-title-main">Tesla Powerpack</span> Large-scale battery energy storage product manufactured by Tesla Energy

The Tesla Powerpack was a rechargeable lithium-ion battery stationary energy storage product, intended for use by businesses or on smaller projects from power utilities. The device was manufactured by Tesla Energy, the clean energy subsidiary of Tesla, Inc. The Powerpack stores electricity for time of use load shifting, backup power, demand response, microgrids, renewable energy integration, frequency regulation, and voltage control. The first prototype Powerpacks were installed in 2012 at the locations of a few industrial customers. After July 22, 2022, the product was no longer listed for sale.

Younicos was a German-American technology company that developed and sold energy storage systems and control software. The company integrated battery technologies, power electronics and control software to create systems that respond to the energy management requirements of power networks of all sizes, including micro-grids.

<span class="mw-page-title-main">Battery storage power station</span> Energy storage system using electrochemical secondary cells

A battery storage power station, or battery energy storage system (BESS), is a type of energy storage power station that uses a group of batteries to store electrical energy. Battery storage is the fastest responding dispatchable source of power on electric grids, and it is used to stabilise those grids, as battery storage can transition from standby to full power in under a second to deal with grid contingencies.

<span class="mw-page-title-main">Duck curve</span> Graph showing the timing imbalance between peak demand and renewable electricity production

The duck curve is a graph of power production over the course of a day that shows the timing imbalance between peak demand and solar power generation. The graph resembles a sitting duck, and thus the term was created. Used in utility-scale electricity generation, the term was coined in 2012 by the California Independent System Operator.

<span class="mw-page-title-main">Tesla Megapack</span> Large-scale battery energy storage product manufactured by Tesla Energy

The Tesla Megapack is a large-scale rechargeable lithium-ion battery stationary energy storage product, intended for use at battery storage power stations, manufactured by Tesla Energy, the energy subsidiary of Tesla, Inc.

<span class="mw-page-title-main">Enel North America</span> American company headquartered in Andover, MA, United States

Enel North America is an American company headquartered in Andover, MA, United States. One of the renewable energy operators in North America, it was formed as a subsidiary of the global utility Enel S.p.A. in 2000. It has operations in the United States and Canada through its renewables and energy services businesses, with a portfolio including over 9.6 GW of renewable capacity, 160,000 EV charging stations, 4.7 GW of demand response capacity and 14 utility-scale battery energy storage systems, totaling 1,416 MWh of capacity under construction or in operation. It serves a customer base of over 4,500 businesses, utilities, and cities in North America.

References

Citations

  1. 1 2 3 Loving, Bill. "SCE Unveils Largest Battery for Storing Electricity in North America". Energized by Edison. Retrieved 2020-05-10.
  2. 1 2 International.
  3. 1 2 BakersfieldNow Staff (2014-09-23). "Large battery-energy storage project unveiled in Tehachapi". KBAK – BakersfieldNow – Channel 58. Retrieved 2020-05-11.
  4. "VIDEO: LG Chem switches on 32 MWh energy storage system in California". POWERGrid International. 2014-09-26. Retrieved 2020-05-13.
  5. 1 2 Business.
  6. 1 2 3 4 5 6 7 8 9 10 Pinsky, Naum; O'Neill, Lori (2017-03-31). "Tehachapi Wind Energy Storage Project – Technology Performance Report #3". U.S. Department of Energy – National Energy Technology Laboratory. doi:10.2172/1349233. OSTI   1349233.
  7. Gaillac, Loïc; Castaneda, Juan; Edris, Abdel-Aty; Elizondo, David; Wilkins, Carl; Vartanian, Charlie; Mendelsohn, David (May 2012). "Tehachapi Wind Energy Storage Project: Description of operational uses, system components, and testing plans". Pes T&D 2012. pp. 1–6. doi:10.1109/TDC.2012.6281676. ISBN   978-1-4673-1935-5. S2CID   39924779.{{cite book}}: |journal= ignored (help)
  8. "Energy Storage | Edison International". Southern California Edison. Archived from the original on 2020-11-11. Retrieved 2021-04-04.
  9. 1 2 3 "California Public Utilities Commission Advice Letter Number 4458-E: Tehachapi Storage Project, Continued Operations: Market Benefits and Energy Storage Costs". Southern California Edison. April 1, 2021. Retrieved 2022-01-28.
  10. 1 2 3 4 5 6 "California Public Utilities Commission Advice Letter Number 4568-E: Tehachapi Storage Project Decommissioning and Cost Recovery". Southern California Edison. 2021-08-23. Retrieved 2022-01-28.
  11. 1 2 McCarthy, Elizabeth (May 5, 2022). "Edison's First Generation Battery Storing Wind Energy Put to Rest". California Current. Retrieved 2022-05-06.
  12. 1 2 3 Gano, Eliza. "Saying Goodbye to Tehachapi's Groundbreaking Clean Energy Storage Facility". Energized by Edison. Retrieved 2022-11-11.
  13. McFerron, Whitney (October 14, 2014). "Giant Battery Unit Aims at Wind Storage Holy Grail: Commodities". Bloomberg.
  14. Silverstein, Ken (2014-10-12). "Electric cars have batteries. Why not power plants?". Christian Science Monitor. ISSN   0882-7729 . Retrieved 2020-05-16.
  15. 1 2 Hart, David; Sarkissian, Alfred (June 2016). "Deployment of Grid-Scale Batteries in the United States" (PDF). George Mason University – Prepared for Office of Energy Policy and Systems Analysis – U.S. Department of Energy.
  16. Rittershausen, Johannes; McDonagh, Mariko. "Moving Energy Storage from Concept to Reality: Southern California Edison's Approach to Evaluating Energy Storage" (PDF). Southern California Edison.
  17. "Tehachapi Scenic Self-Guided Wind Farm Tour" (PDF). Greater Tehachapi Chamber of Commerce.
  18. Muljadi, E.; Butterfield, C.P.; Yinger, R.; Romanowitz, H. (January 5–8, 2004). "Energy Storage and Reactive Power Compensator in a Large Wind Farm" (PDF). 42nd AIAA Aerospace Sciences Meeting and Exhibit. doi:10.2514/6.2004-352. ISBN   978-1-62410-078-9. OSTI   15005523.
  19. Strassel, Kim (March 26, 2015). "ECO:nomics: Developing Better Energy Storage". The Wall Street Journal.
  20. Elliott, Claudia (21 July 2012). "Now & Then: Remembering the quake of 1952". Tehachapi News. Retrieved 2020-05-17.
  21. United States Earthquakes. U.S. Department of the Interior, Geological Survey. 1963.
  22. 1 2 Gaillac, Loic; Fok, Kevin (April 2015). "Energy Storage: New Capabilities for the Electric Grid – The Tehachapi Energy Storage Project". Next Generation Batteries 2015.
  23. "693-2005 – IEEE Recommended Practice for Seismic Design of Substations". standards.ieee.org. Retrieved 2020-05-30.
  24. "United States Geological Survey (USGS) Earthquakes". earthquake.usgs.gov. Retrieved 2020-05-17.
  25. The Bakersfield Californian Media (16 October 2015). "Highway 58 to remain closed at least through weekend". The Bakersfield Californian. Retrieved 2020-05-17.
  26. 1 2 3 Southern California Edison. "California Public Utilities Commission: SCE Energy Storage Experience TSP & ISGD Program". California Public Utilities Commission.
  27. Irwin, Mark (June 12, 2014). "Energy Storage Demonstration Programs at Southern California Edison" (PDF). Association of Energy Engineers SoCal: Chapter Meetings.
  28. "Tehachapi Storage Project". Edison International: Newsroom.
  29. McFerron, Whitney (October 14, 2014). "Giant Battery Unit Aims at Wind Storage Holy Grail: Commodities". Bloomberg.
  30. 1 2 3 Bender, Donald; Byrne, Raymond; Borneo, Daniel (June 2015). "Sandia National Laboratories Report: ARRA Energy Storage Demonstration Projects: Lessons Learned and Recommendations" (PDF).
  31. McMahon, Richard; Infante, Lola (2017-05-22). "Harnessing the Potential of Energy Storage". Power Engineering. Retrieved 2020-05-10.; Silverstein, Ken (April 21, 2017). "Energy Storage And Demand Response Propel California Forward On Earth Day". Forbes. Retrieved 2020-05-10.
  32. Nikolewski, Rob (2016-08-29). "Energy storage is taking on a greater role in the power grid. But how big can it get?". San Diego Union-Tribune. Retrieved 2020-05-14.
  33. Magill, Bobby (January 13, 2015). "California Takes Lead In Developing Energy Storage". Climate Central.
  34. Mora, Manuel Avendaño. "Energy Storage for Enhancing Grid Reliability" (PDF). University of California, Riverside: 2019 Energy Storage Technologies and Applications Conference.
  35. Yan, Joseph (March 12, 2015). "Reliability and Affordability: Challenges and Opportunities of Integrating Renewables" (PDF). Center for Ultra-Wide-Area Resilient Electric Energy Transmission Networks (CURRENT), A National Science Foundation (NSF) Engineering Research Center: Strategic Planning Meeting, March 12–13, 2015.
  36. "California ISO: Fast Facts: Large Scale Energy Storage Pilots" (PDF). 2014.
  37. Davis, Grant (September 21–24, 2015). "Tehachapi Wind Energy Storage Project" (PDF). U.S. DOE/OE Energy Storage Program Peer Review, EESAT 2015 Technical Conference.
  38. Irwin, Mark (November 12, 2014). "The Future of Energy Storage". Kern County Energy Summit 2014.
  39. "Preliminary Monthly Electric Generator Inventory (based on Form EIA-860M as a supplement to Form EIA-860)". United States Energy Information Administration. Retrieved 2020-05-24.
  40. "Batteries perform many different functions on the power grid – Today in Energy – U.S. Energy Information Administration (EIA)". www.eia.gov. Retrieved 2020-05-24.
  41. Wu, Fu-Bao; Yang, Bo; Ye, Ji-Lei, eds. (2019-01-01), "Chapter 6 – Application of energy storage technology in grid-connected new energy power generation", Grid-scale Energy Storage Systems and Applications, Academic Press: 203–241, doi:10.1016/b978-0-12-815292-8.00006-x, ISBN   978-0-12-815292-8, S2CID   239257238 , retrieved 2020-05-10
  42. 1 2 Ifill, Gwen; O'Brien, Miles (2015-12-15). "How building a better battery would change the game for renewable energy". PBS NewsHour. Retrieved 2020-05-14.
  43. California Independent System Operator (CAISO); Renewables Grid Initiative (October 2019). "Energy Storage: Perspectives from California and Europe, Discussion Paper – October 2019" (PDF). California Independent System Operator.
  44. Rollo, Jay; Sands, Marco. "Lessons from the Energy Storage Trenches". DISTRIBUTECH International 2020. Retrieved 2020-05-10.
  45. Enslin, Johan; Fok, Kevin. "Energy Storage Experiences in California". DISTRIBUTECH International 2020. Retrieved 2020-05-12.
  46. "Resolution E-5179 Authorizing Southern California Edison's decommissioning of the Tehachapi Storage Project" (PDF). California Public Utilities Commission. Retrieved May 7, 2022.
  47. Breslau, Lindsay; Croweak, Michael; Witt, Alan (2017-10-24). "Batteries Included: Incentivizing Energy Storage". Sustainable Development Law & Policy. 17 (2).
  48. Byrne, Raymond H.; Nguyen, Tu A.; Copp, David A.; Chalamala, Babu R.; Gyuk, Imre (2018). "Energy Management and Optimization Methods for Grid Energy Storage Systems". IEEE Access. 6: 13231–13260. Bibcode:2018IEEEA...613231B. doi: 10.1109/ACCESS.2017.2741578 . ISSN   2169-3536.
  49. Yu, Nanpeng (May 3–5, 2016). "Stochastic Valuation of Energy Storage Systems" (PDF). IEEE/PES Transmission and Distribution Conference and Exposition.
  50. Yu, Nanpeng; Foggo, Brandon (March 18, 2017). "Stochastic valuation of energy storage in wholesale power markets" (PDF). Energy Economics. 64 (2017): 177–185. doi:10.1016/j.eneco.2017.03.010. S2CID   38838653.
  51. 1 2 Mohsenian-Rad, Hamed (January 2016). "Optimal Bidding, Scheduling, and Deployment of Battery Systems in California Day-Ahead Energy Market". IEEE Transactions on Power Systems. 31 (1): 442–453. Bibcode:2016ITPSy..31..442M. doi: 10.1109/TPWRS.2015.2394355 . ISSN   0885-8950. S2CID   17315858.
  52. 1 2 Mohsenian-Rad, Hamed (January 2016). "Coordinated Price-Maker Operation of Large Energy Storage Units in Nodal Energy Markets". IEEE Transactions on Power Systems. 31 (1): 786–797. Bibcode:2016ITPSy..31..786M. doi: 10.1109/TPWRS.2015.2411556 . ISSN   0885-8950. S2CID   12636318.
  53. 1 2 3 4 "IEEE Power & Energy Magazine - September/October 2017 - 56". www.nxtbook.com. Retrieved 2021-04-05.
  54. 1 2 Edison Electric Institute (October 2018). "U.S. Electric Company Investment and Innovation in Energy Storage" (PDF). Edison Electric Institute. Archived from the original (PDF) on 2021-04-28. Retrieved 2020-05-10.
  55. 1 2 3 4 Schledde, Dominik (August 15, 2018). "Support to R&D Strategy for battery based energy storage: Technical analysis of ongoing projects (D12)" (PDF). European Commission Directorate General Energy.
  56. 1 2 3 "Battery storage as peaking capacity: How Alamitos changed the game for California". Energy Storage News. 7 June 2021. Retrieved 2021-07-02.
  57. 1 2 Smirnoff, Nick. "Grand Opening of the Tehachapi Energy Storage Project". The Loop Newspaper. Retrieved 2020-05-12.
  58. 1 2 3 "Ribbon-Cutting for Southern California Edison Tehachapi Energy Storage Project". From Edison International: Energy Storage. September 24, 2014.
  59. Energy Storage North America (ESNA) (Aug 18, 2014). "Energy Storage North America Names Top Nine Energy Storage Project Finalists". PR Newswire. Retrieved 2020-05-29.
  60. "Energy Storage North America Hall of Fame". Energy Storage North America. Retrieved 2020-05-27.
  61. 1 2 Edison Foundation Institute for Electric Innovation (2014). Volume II: Innovations Across the Grid. The Edison Foundation.
  62. "Gamechangers: How Energy Storage Transforms the Power System". Energy Storage North America. February 22, 2016.
  63. Milbourn, Mary Ann. "SCE's Leadership in Grid of the Future Recognized". Energized by Edison. Retrieved 2021-04-05.
  64. "LG Chem scores prestigious energy storage award from ESA". Electrical Business. 2017-05-07. Retrieved 2021-04-05.
  65. "2019 ESA Award Winners". Energy Storage Association. 2019-04-19. Retrieved 2021-04-05.
  66. Kaushik, Vibhu, Vibhu Kaushik - Southern California Edison's Recent Energy Storage Projects , retrieved 2022-05-08
  67. 1 2 "Search for the Super Battery". www.pbs.org. February 2017. Retrieved 2021-05-29.
  68. "2018 Economic Round Table Report". Greater Antelope Valley Economic Alliance. 2018.; "2019 Economic Round Table Report". Greater Antelope Valley Economic Alliance. 2019.
  69. Meredith, Kasey (12 February 2018). "KEDC's Economic Summit highlights Kern's best assets". The Bakersfield Californian. Retrieved 2020-05-14.
  70. "Market Overview" (PDF). Kern Economic Development Corporation. 2019–2020. Retrieved 2020-05-10.
  71. Jackson, Cara (3 October 2019). "What's up in town? Art, hospital news and economic growth tackled at EDC meeting". Tehachapi News. Retrieved 2020-05-23.
  72. "Edwards Air Force Base harnessing the sun to bring more energy storage to the state". KERO 23 ABC News Bakersfield. 2 February 2023.
  73. 1 2 3 4 5 6 7 8 9 10 U.S. Department of Energy Office of Technology Transitions (July 2019). "Solving Challenges in Energy Storage" (PDF).
  74. 1 2 Silverstein, Ken (March 8, 2021). "Utilities Are The Focus Of Electrification And Decarbonization, But Can They Deliver?". Forbes. Retrieved 2021-04-03.

Bibliography

Listen to this article (31 minutes)
Sound-icon.svg
This audio file was created from a revision of this article dated 23 November 2021 (2021-11-23), and does not reflect subsequent edits.