Beles Hydroelectric Power Plant

Last updated
Beles Hydroelectric Power Plant
Beles Hydroelectric Power Plant
Country Ethiopia
Coordinates 11°49′10″N36°55′08″E / 11.81944°N 36.91889°E / 11.81944; 36.91889
StatusOperational
Commission date 2010
Owner(s) Ethiopian Electric Power
Thermal power station
Primary fuel Water
Turbine technology Run-of-the-river hydroelectric
Power generation
Units operational4 x 115 MW Francis-type
Nameplate capacity 460 MW
Annual net output 1720 GWh Est.

The Beles Hydroelectric Power Plant, sometimes referred to as Beles II or Tana Beles, is a run-of-the-river [1] hydroelectric power plant in Ethiopia near Lake Tana. The power plant receives water from the lake through the Tana-Beles interbasin transfer and after utilizing it to produce electricity, the water is then discharged into the Beles River. The plant has an installed capacity of 460 MW, making it the second largest power plant in the country. It is also expected to help provide water for the irrigation of 140,000 ha (350,000 acres). [2] It was inaugurated in May 2010 and the last generator became operational in February 2012. Its construction was negatively perceived by downstream Egypt.

Contents

Background and construction

In 1992, the first feasibility study was completed for the project, a 200 MW power station. A later study and final design was completed in 2005 by Studio Pietrangeli for the current 460 MW plant. [3] The Government of Ethiopia signed a contract with Salini Costruttori to build the plant on July 8, 2005, and construction began soon after. [4] Because of the project's remote location, transportation and manning of personnel and equipment was difficult, often taking 4–5 months for supplies to arrive. On June 2, 2007, a tunnel boring machine (TBM), operated by SELI, began boring the 7.2 km (4.5 mi) tailrace tunnel and completed it on May 31, 2008. Tunneling was carried out seven days a week in three eight-hour shifts a day. The TBM averaged 20 m (66 ft) per day while in January 2008, a maximum daily amount of 36 m (118 ft) was achieved. [5] The TBM for the 12 km (7.5 mi) headrace tunnel broke through, completing it on August 11, 2009. [6] Salini Costruttori awarded a sub contract to construct the actual power station to VA Tech Hydro. [7] On May 11, 2010, the first 115 MW generator at the power plant began operation [8] and on May 14, 2010, the plant was inaugurated. The project's cost was around $500 million USD. [9] The power plant was fully operational in February 2012. [10]

Design

The Beles Hydroelectric Power Plant receives water from Lake Tana where it is transferred to a power station and then discharged through another tunnel and into the Beles River. This is first accomplished by an inlet on Lake Tana, where the power station can utilize 9,120,000,000 m3 (7,390,000 acre⋅ft) of the lake's volume for power production. [3] The inlet channel is 43 m (141 ft) wide, 11.5 m (38 ft) high and its flow into the headrace tunnel is controlled by five floodgates. The headrace tunnel transfers the water to the southwest along its 12 km (7.5 mi) length within its diameter of 8.1 m (27 ft). At the end of the headrace tunnel, it converts into a 6.5 m (21 ft) diameter and 270 m (890 ft) long penstock before reaching the power station. [3] At the power station, water is delivered to four Francis turbines powering four 115 MW generators. [11] The power station is a cavern type and is 82 m (269 ft) long, 17.6 m (58 ft) high and 38.5 m (126 ft) wide. [3] It has a 91.2 m (299 ft) deep and 8 m (26 ft) diameter surge shaft as well. [3] Once the water is used in hydroelectric production it is then discharged from the power station to the Beles River via a 7.2 km (4.5 mi) tailrace tunnel with the same diameter as the headrace. Normal water level at the inlet is 1,800 m (5,900 ft) above sea level and the power station resides at 1,450 m (4,760 ft), allowing for 350 m (1,150 ft) of hydraulic head. [11] The project is also expected to help irrigate 140,000 ha (350,000 acres) in the future as well. [2]

Social and environmental impacts for the downstream communities

The Environmental Impact Assessment of the Beles Hydroelectric Power Plant is considered a formality and is unfindable. [12] The social impacts of the Tana-Beles water transfer have been studied and results published in the high-profile Journal of Hydrology: the dangerously high increases in discharge of Beles river have led to the drowning of 250 people between 2010 and 2018. The negative impacts on rural livelihoods are however overshadowed by national development goals (electricity production). The external costs (coping with damage) are borne by local people, who have low bargaining power. [12]

Beles River downstream of the hydropower outlet Beles downstream of Tana outlet.jpg
Beles River downstream of the hydropower outlet

Egyptian opposition

The Beles Hydroelectric Power Plant is part of a larger issue amongst the Nile River Basin countries as the Beles River is a tributary of the Blue Nile and Lake Tana supplies the basin as well. After the inauguration of the power plant, statements were released from a meeting of Egyptian officials, one of which was "Tana Beles dam aims to provoke Egypt’s anger and lead it to take swift diplomatic action which would turn the global opinion in favor of the upstream Nile countries." The officials, many involved in the Nile River Sector, stated they had no information about the project. [13] [14] The power plant was inaugurated at the same time as a Cooperative Framework Agreement over the Nile Basin was signed by upstream countries such as Uganda, Rwanda, Tanzania, and Ethiopia, but downstream countries Sudan and Egypt refused to sign. Under colonial-era accords, only Sudan and Egypt were to benefit from the Nile's flow and could reject any upstream projects that would impede it. [15] [16] [17]

See also

Related Research Articles

<span class="mw-page-title-main">Underground power station</span> Type of hydroelectric power station

An underground power station is a type of hydroelectric power station constructed by excavating the major components from rock, rather than the more common surface-based construction methods.

<span class="mw-page-title-main">Kárahnjúkar Hydropower Plant</span> Dam

Kárahnjúkar Hydropower Plant, officially called Fljótsdalur Power Station is a hydroelectric power plant in Fljótsdalshérað municipality in eastern Iceland, designed to produce 4,600 gigawatt-hours (17,000 TJ) annually for Alcoa's Fjarðaál aluminum smelter 75 kilometres (47 mi) to the east in Reyðarfjörður. With the installed capacity of 690 megawatts (930,000 hp), the plant is the largest power plant in Iceland. The project, named after the nearby Kárahnjúkar mountains, involves damming the rivers Jökulsá á Dal and Jökulsá í Fljótsdal with five dams, creating three reservoirs. Water from the reservoirs is diverted through 73 kilometres (45 mi) of underground water tunnels and down a 420-metre (1,380 ft) vertical penstock towards a single underground power station. The smelter became fully operational in 2008 and the hydropower project was completed in 2009.

<span class="mw-page-title-main">Ambuklao Dam</span> Dam in Benguet, Philippines

Ambuklao Dam is part of a hydroelectric facility in Baragay Ambuclao, Bokod, Benguet province in the Philippines. With a maximum water storage capacity of 327,170,000 cubic metres (265,240 acre⋅ft), the facility, which is located 36 km (22 mi) from Baguio city, can produce up to 105 megawatts of electricity for the Luzon grid. The main source of water is the Agno River, which originates from Mount Data. The dam is located in a conservation area known as the Upper Agno River Basin Resource Reserve.

The Ingula Pumped Storage Scheme is a pumped-storage power station in the escarpment of the Little Drakensberg range straddling the border of the KwaZulu-Natal and Free State provinces, South Africa. It is about 22 km (14 mi) North-East of Van Reenen.

The Kamburu Hydroelectric Power Station, also Kamburu Dam is a rock-filled embankment dam on the Tana River in Kenya which straddles the border of Embu and Machakos Counties in Eastern Province. The primary purpose of the dam is hydroelectric power generation and it supports a 93 MW power station. Construction on the dam began in 1971 and it was completed in 1975, with the power station getting commissioned the same year. US$23 million of the US$47 million project cost was provided by the World Bank. The power station is operated by the Kenya Electricity Generating Company and is part of the Seven Forks Scheme.

The Kiambere Hydroelectric Power Station is an earth-filled embankment dam on the Tana River near Kiambere, Kenya. It straddles the border of Embu and Kitui Counties in the former Eastern Province. The primary purpose of the dam is hydroelectric power generation and it supports a 165 MW power station. Construction on the dam began in 1983 and it was completed in 1987. The power station was commissioned in 1988. Beginning in 2008 both turbine-generators were upgraded from 72 MW to 82.5 MW. They were commissioned in 2009. US$95 million in funding for the original project was provided by the World Bank. The power station is operated by the Kenya Electricity Generating Company and is part of the Seven Forks Scheme.

<span class="mw-page-title-main">Beles River</span> River in western Ethiopia

The Beles is a river of western Ethiopia. A tributary of the Abay river, the Beles rises in Dangur woreda to flow in a south-west direction to its confluence. Its catchment area amounts to about 14,200 square kilometers.

Ethiopia is called the water tower of Africa due to its combination of mountainous areas with a comparatively large share of water resources in Africa. Only a fraction of this potential has been harnessed so far, 1% at the beginning of the 21st century. In order to become the powerhouse of Africa, Ethiopia is actively exploiting its water resources by building dams, reservoirs, irrigation and diversion canals and hydropower stations. The benefits of the dams are not only limited to hydropower. Many dams are multi-purpose dams that are also designed to provide water for irrigation, drinking water and flood control. However, hydropower is expected to be the main benefit of the dams.

The Gilgel Gibe II Power Station is a hydroelectric power station on the Omo River in Ethiopia. It is located about 80 km (50 mi) east of Jimma in Wolaita/Dawro Region. The power station receives water from a tunnel entrance 7°55′27″N37°23′16″E on the Gilgel Gibe River. It has an installed capacity of 420 MW and was inaugurated on January 14, 2010. Almost two weeks after inauguration, a portion of the head race tunnel collapsed, causing the station to shut down. Repairs were completed on December 26, 2010.

The Tianshengqiao-II Dam is a dam and hydroelectric power station on the Nanpan River in the Anlong and Longlin districts in China. Construction of the dam and power plant began in 1982 and was complete in 1997.

<span class="mw-page-title-main">Grand Ethiopian Renaissance Dam</span> Gravity dam in Ethiopia

The Grand Ethiopian Renaissance Dam, formerly known as the Millennium Dam and sometimes referred to as the Hidase Dam, is a gravity dam on the Blue Nile River in Ethiopia. The dam is in the Benishangul-Gumuz Region of Ethiopia, about 14 km (9 mi) east of the border with Sudan.

The Jinping-II Dam, also known as the Jinping-II Hydropower Station, is a gravity dam on the Jinping Bend of the Yalong River in Sichuan, China. Construction on the project began in 2007 and it was complete in 2014. Its hydroelectric power station has a 4,800 MW installed capacity.

The Porce III Dam is an embankment dam on the Porce River 90 kilometres (56 mi) northeast of Medellín in Antioquia Department, Colombia. The dam was constructed between 2004 and 2011 for the primary purpose of hydroelectric power generation.

<span class="mw-page-title-main">Kazunogawa Pumped Storage Power Station</span> Pumped-storage hydroelectric power station in Yamanashi Prefecture, Japan

The Kazunogawa Pumped Storage Power Station is a pumped-storage hydroelectric power station near Kōshū in Yamanashi Prefecture, Japan. The station is designed to have an installed capacity of 1,600 megawatts (2,100,000 hp) and three of the four 400 megawatts (540,000 hp) generators are currently operational, for a total operational capacity of 1200 MW. Construction on the power station began in 1993 and the first generator was commissioned on 3 December 1999. The second was commissioned on 8 June 2000. The third one became operational on 9 June 2014, six year early due to post-power demand from the Great East Japan earthquake. The fourth and final generator is slated to be commissioned by 2024. It is owned by TEPCO and was constructed at a cost of US$2.2 billion.

The Dongfeng Dam is an arch dam on the Wu River 65 km (40 mi) northwest of Qingzhen in Guizhou Province, China. The primary purpose of the dam is hydroelectric power generation and it supports a 570 MW power station. Construction on the dam began in 1989 and the first generator was operational in 1994, the last in 1995. The generators were up-rated between 2004 and 2005; bringing their capacity from 170 MW each to 190 MW.

The Upper Cisokan Pumped Storage Plant is a proposed pumped-storage hydropower facility in Indonesia, due for completion by 2025.

<span class="mw-page-title-main">Karcham Wangtoo Hydroelectric Plant</span> Dam

The Karcham Wangtoo Hydroelectric Plant is a 1,091 megawatts (1,463,000 hp) run-of-the-river hydroelectric power station on the Sutlej River in Kinnaur district of Himachal Pradesh state of India.

Masinga Hydroelectric Power Station, also Masinga Dam, is an embankment dam on the Tana River, the longest river in Kenya and straddles the border of Embu and Machakos Counties in Eastern Province and is located about 106 km. (66 mi.), by road, northeast of Nairobi, Kenya's capital and largest city. Construction of the dam began in 1978, and was completed in 1981. It is owned by Tana and Athi Rivers Development Authority (TARDA). The dam is used for power production and is part of the Seven Forks Scheme.

The Uma Oya Hydropower Complex (also internally called Uma Oya Multipurpose Development Project or UOMDP) is an irrigation and hydroelectric complex in the Badulla District of Sri Lanka. Early assessments of the project date back to 1989, when the first studies was conducted by the country's Central Engineering and Consultancy Bureau. The complex involves building a dam across Dalgolla Oya, and channelling water over a 3,975 m (13,041 ft) tunnel to Mathatilla Oya, both of which are tributaries of the Uma Oya. At Mathatilla Oya, another dam is constructed to channel 145,000,000 m3 (5.1×109 cu ft) of water per annum, via a 15,290 m (50,160 ft) headrace tunnel to the Uma Oya Power Station, where water then discharged to the Alikota Aru via a 3,335 m (10,942 ft) tailrace tunnel.

<span class="mw-page-title-main">Tana-Beles interbasin water transfer</span>

The Tana-Beles interbasin water transfer takes water from Lake Tana in Ethiopia and delivers it to the Beles River via the Tana Beles hydroelectric power plant. The water downstream is also used for irrigation.

References

  1. 1Q. Goor; C. Halleux; Y. Mohamed; A. Tilmant (July 6, 2010). "Optimal operation of a multipurpose multireservoir system in the Eastern Nile River Basin" (PDF). Copernicus Publications. p. 4356 (10). Retrieved 30 November 2013.{{cite web}}: CS1 maint: numeric names: authors list (link)
  2. 1 2 "Ethiopia's Beles Power Plant Inaugrated[sic]". Ezega. May 14, 2010. Retrieved 13 October 2010.
  3. 1 2 3 4 5 "Beles MPP" (PDF). Studio Pietrangeli. Archived from the original (PDF) on 13 March 2012. Retrieved 13 October 2010.
  4. "Report on Operations". Salini Construtorri. Retrieved 13 October 2010.
  5. Francesco Bartimoccia, Antonio Raschillà. "- Case History - 8 M Diameter 7 Km Long Beles Tailrace Tunnel (Ethiopia) Bored And Lined In Basaltic Formations In Less Than 12 Months" (PDF). SELI Tunnel. Retrieved 13 October 2010.
  6. "News - Ethiopia - Beles Headrace Breakthrough". SELI. Retrieved 13 October 2010.
  7. "Beles supply contract signed". International Power Technology and Dam Construction. May 18, 2006. Archived from the original on 14 June 2011. Retrieved 13 October 2010.
  8. "Beles operates in trial test". International Water Power and Dam Construction Magazine. May 11, 2010. Archived from the original on 14 June 2011. Retrieved 13 October 2010.
  9. Sisay, Andualem (May 14, 2010). "AfricaNews - Ethiopia inaugurates third hydro power plant in a year". AfricaNews. Archived from the original on March 29, 2012. Retrieved 13 October 2010.
  10. "Ethiopia Tana Beles Hydroelectric power at full capacity". WN.com. 10 February 2012. Retrieved 28 February 2014.
  11. 1 2 "Works in progress - Beles". Salini Costruttori. Archived from the original on 13 March 2012. Retrieved 13 October 2010.
  12. 1 2 Annys, S. and colleagues (2019). "Impacts of the hydropower-controlled Tana-Beles interbasin water transfer on downstream rural livelihoods (northwest Ethiopia)". Journal of Hydrology. 569: 436–448. Bibcode:2019JHyd..569..436A. doi:10.1016/j.jhydrol.2018.12.012. hdl: 1942/28548 . S2CID   135072795.
  13. "Ethiopian dam 'funded by Italy,' say govt sources". Al-Masry Al-Youm. May 18, 2010. Retrieved 13 October 2010.
  14. "Egypt discuss response to Ethiopian dam". Egypt News. May 17, 2010. Archived from the original on February 2, 2011. Retrieved 13 October 2010.
  15. Sintayehu, Zekarias (May 22, 2010). "Ethiopia can build any infrastructure and dams it wants on the Nile River". Ethiopia Journal. Archived from the original on 3 March 2016. Retrieved 13 October 2010.
  16. "East Africa seeks more Nile water from Egypt". BBC News. May 14, 2010. Retrieved 13 October 2010.
  17. Kate Linthicum, Jeffrey Fleishman (September 13, 2010). "On the Nile, Egypt cuts water use as Ethiopia dams for power". Los Angeles Times. Archived from the original on 18 September 2010. Retrieved 13 October 2010.