Estlink 1 | |
---|---|
Location | |
Country | Estonia, Finland |
General direction | south–north–south |
From | Harku converter station, Estonia 59°23′5″N24°33′37″E / 59.38472°N 24.56028°E |
Passes through | Gulf of Finland |
To | Espoo converter station, Finland 60°12′14″N24°33′06″E / 60.20389°N 24.55167°E |
Ownership information | |
Partners | Elering Fingrid |
Construction information | |
Manufacturer of conductor/cable | ABB |
Installer of conductor/cable | Global Marine Systems |
Cable layer | CS Sovereign |
Manufacturer of substations | ABB |
Installer of substations | ABB |
Construction started | 2006 |
Commissioned | 2006 |
Technical information | |
Type | Submarine power cable |
Type of current | HVDC |
Total length | 105 km (65 mi) |
Power rating | 350 MW |
AC voltage | 330 kV (Estonia), 400 kV (Finland) |
DC voltage | ±150 kV |
No. of poles | 2 |
Estlink 2 | |
---|---|
Location | |
Country | Estonia, Finland |
General direction | south–north–south |
From | Püssi converter station, Estonia 59°22′02″N27°03′50″E / 59.36722°N 27.06389°E |
Passes through | Gulf of Finland |
To | Anttila converter station, Finland 60°22′36″N25°22′01″E / 60.37667°N 25.36694°E |
Ownership information | |
Partners | Elering Fingrid |
Construction information | |
Manufacturer of conductor/cable | Nexans |
Installer of conductor/cable | Nexans |
Cable layer | C/S Nexans Skagerrak |
Manufacturer of substations | Siemens |
Installer of substations | Siemens |
Contractors | Empower Oy |
Commissioned | 2014 |
Technical information | |
Type | subsea cable, overhead line |
Type of current | HVDC |
Total length | 171 km (106 mi) |
Power rating | 650 MW |
AC voltage | 330 kV (Estonia), 400 kV (Finland) |
DC voltage | 450 kV |
No. of poles | 1 |
Estlink is a set of HVDC submarine power cables between Estonia and Finland. Estlink 1 is the first interconnection between the Baltic and Nordic electricity markets followed by Estlink 2 in 2014. The main purpose of the Estlink connection is to secure power supply in both regions to integrate the Baltic and Nordic energy markets. [1] [2] [3]
First plans for a submarine power cable between the Baltic and the Nordic regions were proposed in 1990s. Negotiations between Eesti Energia, Pohjolan Voima, Helsingin Energia, Graninge (now E.ON Sverige), Latvenergo, Statkraft and TXE Nordic Energy, a subsidiary of TXU (now Energy Future Holdings Corporation) started In 1999, and on 9 October 2001 a contract was signed in Tallinn. [4] However, only after the harsh winter of 2002–2003 which resulted in an increased demand for power, the project of the submarine cable between Estonia and Finland got a boost. [5] [6] The letter of intention for underwater sea cable was signed between Eesti Energia, Pohjolan Voima, Helsingin Energia and Latvenergo on 31 March 2003. [7] In May 2004, the Lithuanian power company Lietuvos Energija agreed to participate in the project, shortly after which the project company AS Nordic Energy Link was established. [8] [9] On 29 April 2005, the Estlink project was launched. [6] [10] Construction of Harku converter station and land cable installation begins on 5 April 2006. [11] The submarine cable was laid in September 2006. [12] [13] [14] The Estlink cable was inaugurated on 4 December 2006 and it became fully operational on 5 January 2007. [15] [16]
The Estlink 1 cable was operated by AS Nordic Energy Link company, founded by Baltic and Finnish power companies. The main shareholder was Eesti Energia with 39.9% of the shares, Latvenergo and Lietuvos Energija had 25% each, and the remaining 10.1% was divided between Pohjolan Voima and Helsingin Energia (operating through their joint project company Finestlink). On 30 December 2013 the interconnector was sold to the transmission system operators Elering and Fingrid. [17]
The 105 kilometres (65 mi) long (including 74 kilometres (46 mi) under water) +/-150 kV, 350 MW HVDC link cable is connected to the Estonian electrical system at the Harku 330 kV converter station and to the Finnish transmission network at Espoo 400 kV converter station in Järvikylä using HVDC Light transmission technology. [5] [18] [10] [19] The installation of land cable began on 4 May 2006 in Harku. The submarine cable was laid on the seabed of the Gulf of Finland in the autumn of 2006. The cable's maximum depth on the seabed is 100 metres (330 ft).
The cable was manufactured by ABB. [10] The submarine cable was laid by Global Marine Systems using the CS Sovereign . [6] The project cost €110 million. [12]
Name | Coordinates |
---|---|
Estonia – Harku | 59°23′5″N24°33′37″E / 59.38472°N 24.56028°E |
Finland – Espoo | 60°12′14″N24°33′06″E / 60.20389°N 24.55167°E |
A preliminary agreement on EstLink 2 was signed between Elering and Fingrid on 15 February 2010 in Tallinn. [20] [21] Capital investment decision by Fingrid was made on 20 May 2010. [22] A construction agreement was signed on 1 November 2010. [23]
On 23 December 2010, the contract to manufacture and install the subsea and underground cables was awarded to Nexans, the contract to build converter stations was awarded to Siemens, the contract to build the Nikuviken cable terminal station and to expand the Anttila substation in Finland was awarded to Empower Oy, and the contract to build the transmission line between Anttila and Nikuviken was awarded to ETDE, a part of Bouygues. [1] [2] [24] [25]
Laying of the cable started on 15 October 2012 and it is laid by the cable ship Nexans Skagerrak. [26] [27] The cable testing started on 22 October 2013. [28] A trial operation started on 6 December 2013 and continued until 6 February 2014 after which it started commercial operations. [29] [30] It was officially inaugurated on 6 March 2014. [31] [32]
The cable experienced a failure on 26 January 2024 originating from the Estonian coast. After repair work was concluded, the connection resumed commercial operation on 4 September 2024. [33]
The total length of Estlink 2 would be 171 kilometres (106 mi), including a 145-kilometre (90 mi) long offshore cable, a 12-kilometre (7.5 mi) long onshore cable in Estonia, and 14 kilometres (8.7 mi) of overhead lines in Finland. [1] The 12-kilometre (7.5 mi) long underground cable starts at the Püssi substation and runs the coast of the Gulf of Finland at Aseri. From there the 145-kilometre (90 mi) long offshore cable runs to the Nikuviken cable terminal station in Finland. The Nikuviken cable terminal station will be connected with the Attila converter station by the 14-kilometre (8.7 mi) long overhead line. [24]
Estlink 2 will be a classic bidirectional monopolar high-voltage direct current connection with line-commutated converter thyristors. Its maximum transmission rate will be 650 MW and it will operate with a voltage of 450 kV. [2] Its estimated cost is about €320 million, of which converter stations cost €100 million and cable €180 million. [1] [24] The European Commission has decided to allocate €100 million to the project. [34] [35]
Name | Coordinates |
---|---|
Estonia – Püssi Static Inverter Plant | 59°22′13″N27°04′05″E / 59.37028°N 27.06806°E |
Finland – Nikuviken Cable Terminal | 60°17′34″N25°31′41″E / 60.29278°N 25.52806°E |
Finland – Anttila Static Inverter Plant | 60°22′36″N25°22′01″E / 60.37667°N 25.36694°E |
On June 28, 2022, Elering and Fingrid signed a memorandum of understanding to begin planning for a third submarine cable, EstLink3, with a capacity of up to 1000 MW, expected to be completed by 2035. [36] [37]
A high-voltage direct current (HVDC) electric power transmission system uses direct current (DC) for electric power transmission, in contrast with the more common alternating current (AC) transmission systems. Most HVDC links use voltages between 100 kV and 800 kV.
The Kontek HVDC is a 170-kilometre (110 mi) long, monopolar 400 kV high-voltage direct current cable between Germany and the Danish island Zealand. Its name comes from "continent" and the name of the former Danish power transmission company "Elkraft", which operated the power grid on the Danish islands Lolland, Falster and Zealand and had the abbreviation "ek". As of today, the cable is operated by Energinet.dk in Denmark and 50Hertz Transmission GmbH in Germany.
The Baltic Cable is a monopolar HVDC power line running beneath the Baltic Sea that interconnects the electric power grids of Germany and Sweden. Its maximum transmission power is 600 megawatts (MW).
The HVDC Cross-Channel is the 73-kilometre-long (45 mi) high-voltage direct current (HVDC) interconnector that has operated since 1986 under the English Channel between the continental European grid at Bonningues-lès-Calais and the British electricity grid at Sellindge. The cable is also known as IFA, and should not be confused with the new IFA-2, another interconnect with France that is three times as long but only half as powerful.
SwePol is a 254.05-kilometre (157.86 mi)-long monopolar high-voltage direct current (HVDC) submarine cable between the Stärnö peninsula near Karlshamn, Sweden, and Bruskowo Wielkie, near Słupsk, Poland. The link was inaugurated in 2000 and can transmit up to 600 MW power at a voltage of 450 kV.
Fenno–Skan is the designation of the high voltage direct current transmission between Dannebo in Sweden and Rauma in Finland.
NorNed is a 580-kilometre (360 mi) long high-voltage direct current submarine power cable between Feda, Norway and the seaport of Eemshaven in the Netherlands, which interconnects both countries' electrical grids. It was once the longest submarine power cable in the world. Budgeted at €550 million, and completed at a cost of €600m, the NorNed cable is a bipolar HVDC link with a voltage of ±450 kV and a capacity of 700 MW. NorNed is a joint project of the Norwegian transmission system operator Statnett and its Dutch counterpart TenneT. The cable system itself and the two converter stations were produced by ABB.
The HVDC Russia–Finland was a project to build a HVDC submarine power cable between Kernovo, Leningrad Oblast (Russia) and Mussalo, Kotka (Finland). The main purpose of this project was to export Russian nuclear energy to Sweden and Finland.
NordBalt is a submarine power cable between Klaipėda in Lithuania and Nybro in Sweden. The purpose of the cable is to facilitate the trading of power between the Baltic and Nordic electricity markets, and to increase the supply and energy security in both markets.
Eesti Energia AS is a public limited energy company in Estonia with its headquarters in Tallinn. It is the world's biggest oil shale to energy company. The company was founded in 1939. As of 2014, it operates in Estonia, Latvia, Lithuania, Finland, Jordan and Utah, United States. In Estonia, the company operates under the name Eesti Energia, while using the brand name Enefit for international operations. The main raw material for energy production – oil shale – is extracted from mines located in Eastern-Estonia and owned by the company. The group of Eesti Energia has three main operation areas: electricity generation, shale oil production, and sale and distribution of electricity. Its shares are owned by the Government of Estonia.
LitPol Link is an electricity link between Poland and Lithuania which connects the Baltic transmission system to the synchronous grid of Continental Europe. It has a capacity of 500 MW and since 2021 it can operate in a synchronous regime.
The Vyborg HVDC scheme is a system of electricity transmission from the Russian power system to Finland, using high-voltage direct current. It consists of four 355 MVA (250 MW) back-to-back converter blocks, the first three of which were completed in the early 1980s and the last in January 2001. Much of the original converter equipment has been refurbished or modernised.
The Great Belt power link, also known as the Great Belt electricity link, is a high-voltage direct-current interconnection across the Great Belt between Funen and Zealand connecting two power transmission systems in Denmark.
Nord Pool AS is a pan-European power exchange. Nord Pool has a main office in Oslo and further offices in Stockholm, Helsinki, Tallinn and London. The company is owned by the European exchange operator Euronext as well as TSO Holding, which represents the continental Nordic and Baltic countries' transmission system operators. Nord Pool has two subsidiaries, Nord Pool AB and Nord Pool Finland Oy.
Elering AS is a national transmission system operator for electricity and natural gas with headquarters in Tallinn, Estonia. The managing director of Elering is Taavi Veskimägi.
The electricity sector in Finland relies on nuclear power, renewable energy, cogeneration and electricity import from neighboring countries. Finland has the highest per-capita electricity consumption in the EU. Co-generation of heat and electricity for industry process heat and district heating is common. Finland is one of the last countries in the world still burning peat.
The Kiisa Power Plant is an emergency reserve power plant, based on the engine power plant technology, located in Kiisa, Estonia, about 25 kilometres (16 mi) from Tallinn. As an emergency plant, it operates only in the case of a network failure or capacity shortfall, and it does not participate in the everyday electricity market. The power plant is owned and operated by the Estonian transmission system operator Elering.
Nemo Link is a 1,000 MegaWatt HVDC submarine power cable between Richborough Energy Park in Kent, the United Kingdom and Zeebrugge, Belgium. The project is a joint venture between British National Grid and Belgian Elia. The 400 kV electrical interconnector is the first between the two countries, with an annual transmission capacity of 8.76 TWh. The link has been fully operational since 31 January 2019, and has transported 29 TWh during its first 5 years; 24.75 TWh to the UK and 4.25 to Belgium with an availability above 99%.
The Nordic regional group of ENTSO-E is a synchronous electrical grid composed of the electricity grids of Norway, Sweden, Finland and the eastern part of electricity sector in Denmark. The grid is not synchronized with the synchronous grid of Continental Europe, but has a number of non-synchronous DC connections with that as well as other synchronous grids. Gotland is not synchronized with the Swedish mainland either, as it is connected by HVDC.