Karot Hydropower Project | |
---|---|
Official name | Karot Hydropower Project |
Location | Punjab, Pakistan |
Coordinates | 33°35′59.29″N073°36′4.42″E / 33.5998028°N 73.6012278°E |
Status | Operational |
Construction began | December 2016 |
Opening date | June 2022 |
Construction cost | $1.42 billion |
Owner(s) | China Three Gorges Corporation (CTG) |
Dam and spillways | |
Type of dam | Embankment, rock-fill |
Impounds | Jhelum River |
Height | 95.5 m (313 ft) |
Length | 460 m (1,510 ft) |
Reservoir | |
Total capacity | 164.5 million |
Maximum length | 27 km (17 mi) |
Normal elevation | 461 m (1,512 ft) |
Power Station | |
Commission date | June 2022 |
Turbines | 4 x 180 MW Francis-type |
Installed capacity | 720 MW |
Annual generation | 3,436 GWH |
The Karot Hydropower Project is an asphalt-core rockfill gravity dam in Pakistan, with an installed capacity of 720 MW. The project is sponsored by Chinese state-owned company China Three Gorges Corporation (CTG).
It is the first investment project of the Silk Road Fund, and is part of the much larger China–Pakistan Economic Corridor (CPEC). [1] [2] : 222
The project was successfully commissioned on June 29, 2022. [3]
The Karot Hydropower Project is located on Jhelum River near Karot village, some 1.7 kilometers upstream of Karot Bridge and 74 km upstream of Mangla Dam. The Project site is accessible through the Islamabad – Kahuta – Kotli road, approximately 29 kilometers from Kahuta, and 65 kilometers from Islamabad.
The Jhelum River is the largest river of Indus Basin River System, and its hydropower potential was identified by various studies carried out by international agencies, with the first report issued by the Canadian Consultant group MONENCO in 1983, followed by a 1994 study by the German Agency for Technical Cooperation (GTZ) that formally proposed the Karot Hydropower Project. [4]
On April 20, 2015, during a state visit by Xi Jinping to Pakistan, the investment in the project by China's Silk Road Fund was announced. [2] : 221
On September 28, 2016, the federal and Azad Jammu and Kashmir governments signed an implementation agreement with a Chinese consortium for development and operation on river Jhelum at a levelised tariff of 7.57 cents per unit for 30 years. Financial close of the project was achieved in February 2017 while land acquisition was also completed.
Groundbreaking on the project took place on January 10, 2016. [5] The project was successfully commissioned on June 29, 2022. [3]
The major project features include a 95.5 meters high asphalt-core rockfill gravity dam with a crest length of 320 meters near the village of Gohra. [6] The dam's reservoir is approximately 164.5 million cubic meters in volume, with a length of 27 kilometers. [7] [8] 72 homes and 58 businesses are relocated as a result of construction, [9] while 2.8 kilometers of the Karot-Kotli road, and 8.9 kilometers of the Azad Pattan-Kahuta road are also relocated. [10]
The power intake structure is constructed on right bank of the river immediately upstream of Dam site and diverts the water into headrace tunnels entering into Cavern Powerhouse. The water is discharged back to River Jhelum through tail-race channel located at right bank of the River Jhelum immediately downstream of Karot village. The dam generates mean annual energy 3,436 GWh, and is connected to Pakistan's national electricity grid.
SMEC International Pty Ltd is participating as Employer's Engineer, who is providing services for project management, design review and construction supervision for 720 MW Karot hydropower project.
During Xi's April 20, 2015 visit, the Silk Road Fund's management arm (the Silk Road Fund Company) signed a memorandum of understanding with the China Three Gorges Dam Corporation and the Pakistan Private Power and Infrastructure Board to finance the project. [2] : 221
Total cost for the project is estimated to be $2 billion, and is funded by International Finance Corporation, China's Silk Road Fund. [11] The Export-Import Bank of China and China Development Bank issued loans to the Karot Power Company. [12] It is built on a "Build-Own-Operate-Transfer" basis for 30 years, after which ownership will be turned over to the government of Pakistan. [13] [2] : 221
The company will run and maintain the project for 30 years at a levelised tariff of 7.57 cents per unit after which it will be transferred to the Punjab government at a notional price of Rs.1.
The Jhelum River is a river in the northern Indian subcontinent. It originates at Verinag and flows through the Indian-administered territory of Jammu and Kashmir, into Pakistan-administered Azad Kashmir, then the Pakistani province of Punjab. It is the westernmost of the five rivers of the Punjab region, and flows through the Kashmir Valley. It is a tributary of the Chenab River and has a total length of about 725 kilometres (450 mi).
The Roghun Dam is an embankment dam under construction on the Vakhsh River in southern Tajikistan. The dam is situated 110 km from Dushanbe. It is one of the planned hydroelectric power plants of Vakhsh Cascade.
Tarbela Dam is an earth-filled dam along the Indus River in Pakistan's Khyber Pakhtunkhwa province. It is mainly located in Haripur Tehsil. It is about 20 km (10 mi) from the city of Swabi KPK, 105 km (65 mi) northwest of Islamabad, and 125 km (80 mi) east of Peshawar. It is the largest earth-filled dam in the world. The dam is 143 metres (470 ft) high above the riverbed and its reservoir, Tarbela Lake, has a surface area of approximately 250 square kilometres (97 sq mi).
The Neelum–Jhelum Hydropower Plant is part of a run-of-the-river hydroelectric power project in Azad Kashmir (AJK) designed to divert water from the Neelum River to a power station on the Jhelum River. The power station is located 42 km (26 mi) south of Muzaffarabad, and has an installed capacity of 969 MW. Construction on the project began in 2008 after a Chinese consortium was awarded the construction contract in July 2007. After many years of delays, the first generator was commissioned in April 2018 and the entire project was completed in August 2018 when the fourth and last unit was synchronized with the national grid on 13 August and attained its maximum generation capacity of 969 MW on 14 August 2018. It will generate 5,150 GWh per year at the levelised tariff of Rs 13.50 per unit for 30 years.
China–Pakistan Economic Corridor is a 3,000 km Chinese infrastructure network project currently under construction in Pakistan. This sea-and-land-based corridor aims to secure and shorten the route for China’s energy imports from the Middle East, avoiding the existing path through the Straits of Malacca between Malaysia and Indonesia, which could be blockaded in case of war, thereby threatening China’s energy-dependent economy. Developing a deep-water port at Gwadar in the Arabian Sea and establishing a robust road and rail network from this port to the Xinjiang region in western China would serve as a shortcut, enhancing trade between Europe and China. In Pakistan, the project aims to address electricity shortages, develop infrastructure, and modernize transportation networks, while also transitioning the economy from an agriculture-based structure to an industrial one.
Patrind Hydropower Plant is a run-of-the-river, high head project of 110 metres (360 ft), located on Kunhar River near Patrind Village of Mansehra District, right on the border of Abbottabad District of Khyber Pakhtunkhwa Province and Muzaffarabad city of Azad Kashmir, Pakistan. It is approximately 138 kilometres (86 mi) from Rawalpindi and Islamabad and about 76 kilometres (47 mi) from Abbottabad city.
Jabban (Malakand-I) Hydropower Plant (MHPP-I) is a small, low-head, run-of-the-river hydroelectric power generation station having 22 megawatt generation capacity located at the Jabban area of the Malakand District in the Khyber Pakhtunkhwa province of Pakistan. It is situated on the Swat River. It is about 210 km from Pakistan's capital Islamabad, 45 km from the city of Mardan and 7 km upstream of 20 MW Dargai Hydropower Plant (Malakand-II). It is a small hydel power generating plant constructed and put in commercial operation in July, 1938, generating an average annual yield of 122 million units (GWh) of least expensive electricity.
The Dasu Dam is a large(largest run of the river dam in world) hydroelectric gravity dam currently under construction on the Indus River near Dasu in Kohistan District, Khyber Pakhtunkhwa Province, Pakistan. It is developed by Pakistan Water and Power Development Authority (Wapda), as a key component of the company's Water Vision 2025. The project was started in 2019 but faced a delay due to funds and land acquisition disputes. Work resumed in 2020 after land acquisition and arrangements of funding facility, the World Bank agreed to contribute $700 million of the $4.2 billion as the government of Imran Khan decided to proceed ahead with the construction of the project, as part of the WAPDAs vision 2025.
Gulpur Hydropower Plant (GHPP) is an operational run-of-the-river hydroelectric generation project located on Poonch River, a major tributary of Jhelum River near Gulpur in Kotli District of Azad Kashmir, Pakistan. The site is about 167 km from Federal Capital Islamabad and 285 kilometres (177 mi) from Punjab's Provincial Capital Lahore and is approachable directly from Islamabad and Lahore by a two-lane, all-weather, paved, partly mountainous road. The location of the project is about 28 km upstream of Mangla Dam Reservoir.
The Kohala Hydropower Project is a proposed run-of-the-river, high head project of 316 meters that will be located near Kohala, in Azad Kashmir. In 2020 the project's agreement was finalised later it was formally signed in a ceremony attended by the Pakistani Prime Minister Imran khan, and Chinese ambassador.
Xi Jinping's visit to Pakistan from 20 to 21 April 2015, was the first state visit of CCP General Secretary Xi Jinping to Pakistan. Xi is the second Chinese leader to visit Pakistan in the 2010s after Chinese Premier Li Keqiang's visit to Pakistan between 22 and 23 May 2013. It was also Xi's first overseas trip of 2015. The trip led to the signing of accords for $46 billion of investment in Pakistan by China for the construction of roads, rails, and power plants to be built on a commercial basis by Chinese companies over 15 years. Most of the 51 projects were part of the China–Pakistan Economic Corridor.
The Silk Road Fund is a China Government Guidance Fund to foster increased investment in countries along the Belt and Road Initiative, an economic development initiative primarily covering Eurasia. The Chinese government pledged US$40 billion for the creation of the investment fund, established on 29 December 2014.
The New Bong Escape Hydropower Project is a privately owned 84 MW run-of-the-river project located on Jhelum River 7.5 km downstream of the 1,070 MW Mangla Dam, a major multi-purpose water storage project commissioned. It is about 120 km from Islamabad, the capital city of Pakistan. The project commenced commercial operations on 23 March, 2013 and has the distinction of being Pakistan and AJ&K’s first hydropower IPP. By developing a bankable framework this trendsetting project has paved the way for rapid and full scale development of Pakistan and AJ&K’s hydropower potential.
The Azad Pattan Hydropower Project is a 700.7 MW hydroelectric power station on the Jhelum River roughly 7 km upstream of Azad Pattan Bridge in the Sudhanoti District, Azad Jammu and Kashmir, Pakistan and 90 km from Islamabad, the capital city of Pakistan. The project is scheduled for completion by 2026. In July 2020, the project's $1.5 billion investment agreement was signed between Chinese state-owned China Gezhouba Group and Pakistan, in a ceremony attended by Prime Minister Imran Khan and senior government ministers.
SK Hydro also known as Suki Kinari HPP, is a run-of-the-river hydropower project located on the Kunhar River at Balakot Tehsil in District Mansehra, Khyber Pakhtunkhwa, which has an installed generation capacity of 884 MW.
As part of the China–Pakistan Economic Corridor, reconstruction and upgrade works are underway on the 887-kilometre-long (551 mi) National Highway 35 (N-35), which forms the Pakistani portion of the Karakoram Highway (KKH).
The Pakistan-China Fiber Optic Project is an 820 kilometer long optical fiber cable laid down between the Khunjerab Pass on the China-Pakistan border and the city of Rawalpindi. It has been constructed as part of the China–Pakistan Economic Corridor at an estimated cost of $44 million. Groundbreaking on the project took place on 19 May 2016, in the city of Gilgit. The line was first envisaged in 2009, with Pakistan and China signing an agreement in 2013 to implement the project. However the project was not implemented until being included as part of the China Pakistan Economic Corridor. Placement of the line will take an estimated 2 years, and will bring 3G and 4G connectivity to the Gilgit-Baltistan region.
Karachi–Peshawar Railway Line is one of four main railway lines in Pakistan, operated and maintained by Pakistan Railways. The line starts from Kiamari station in the province of Sindh and ends at Peshawar Cantonment Station in Khyber Pakhtunkhwa province. The railway track is dual between Keamari and Shahdara Bagh, Chaklala and Golra Sharif. The total length of the line is 1,687 kilometers (1,048 mi), with 176 railway stations in between. The line serves as the country's main passenger and freight line with 75% of the country's cargo and passenger traffic.
Nenskra Hydro Power Plant is a proposed hydroelectric power station to be located on the southern slopes of the Central Caucasus mountains in Svaneti, Georgia.
The Nam Ou cascade hydropower project is a series of seven hydroelectric dams along the Nam Ou river which are located in the provinces of Phongsaly and Luang Prabang in northern Laos. The project is managed by the Power Construction Corporation of China (PowerChina) and the Lao government. The project is the series of dams include seven levels of reservoirs in an attempt to mitigate ecological deterioration. The construction of the hydropower project is being completed in two phases. Phase I of the dams, including Nam Ou 2, Nam Ou 5, and Nam Ou 6 began operating on May 12, 2016. Phase II of the dams, including Nam Ou 1, 3, 4, and 7 is expected to be completed in 2020.
January 2015
{{cite web}}
: Missing or empty |title=
(help)January 2015
{{cite web}}
: Missing or empty |title=
(help)January 2015
{{cite web}}
: Missing or empty |title=
(help)