Sahiwal Coal Power Project

Last updated
Sahiwal Coal Power Project
Sahiwal Coal Power Project
Location of the Sahiwal Coal Power Project
Official nameSahiwal Coal Power Project
Country Pakistan
Location Sahiwal, Punjab
Coordinates 30°42′55″N73°14′20″E / 30.71528°N 73.23889°E / 30.71528; 73.23889
StatusOperational
Construction beganJuly 31, 2015
Commission date 12 May 2017
Construction cost$1.91 billion USD
Owner(s) Huaneng Shandong and Shandong Ruyi
Thermal power station
Primary fuel Bituminous coal
Power generation
Nameplate capacity 1,320 MW
External links
Website www.chng.com.cn/eng/

The Sahiwal Coal Power Project is a coal power plant project located in the province of Punjab in Pakistan by the name of Huaneng Shandong Ruyi (Pakistan) Energy (Limited). It has an installed capacity of 1320 MW. It commenced full operations on 3 July 2017. [1]

Contents

Project details

The power plant is located about (12 mi) from Sahiwal and (9.3 mi) from Okara cantonment, just north of the road which connects the two towns, in Pakistan's Punjab Province.

The power plant is Pakistan's first supercritical coal power plant, and consists of two 660-megawatt (890,000 hp) plants for a combined capacity of 1,320 MW. [2] This is the first phase, and may be followed by a possible second phase which will include two 1,000-megawatt (1,300,000 hp) plants. [3]

Though the plant is now considered to be part of the China Pakistan Economic Corridor (CPEC) which was announced in April 2015, the symbolic ground breaking for the project actually preceded the announcement of CPEC and took place in May 2014, [4] as the government of Punjab in March 2014 invited bids for the construction of two 660MW power plants in order to help alleviate Pakistan's energy shortfalls. [5]

The plant was built by a joint consortium of China's state-owned China Huaneng Group which will own 51% of shares, and the Shandong Ruyi, which will hold 49% of shares. [6] The Government of Pakistan will purchase electricity from the consortium at a tariff of 8.3601 US Cents/kWh. [7] The project was built on a build, operate, transfer basis in which the plant's ownership will be transferred to the Government of Punjab after 30 years of operation. [8]

The project site spans a total of 690 hectares (1,700 acres), [9] given by the Government of Punjab free of charge. [9] The project includes the construction of a railway siding from the village of Yusuf Wala to the site for exclusive use of the plant. [10]

The plants each consist of one boiler, steam turbine and generator, and are fueled by sub-bituminous coal which will be offloaded at the project's purpose-built rail terminus. [10] The plants generate a total of 1,320 megawatts of electricity, with a gross efficiency of 42.11% [11] by the use of a supercritical steam generator operating at temperatures of up to 580 degrees Celsius. [12]

The plant includes an air quality monitoring system(Flue Gas Desulfurization), and an electrostatic precipitator in order to reduce ash and sulfur emissions from the plant. [12] It requires 60,000 cubic meters of water daily for operation, with water being drawn from the Lower Bari Doab Canal. [12] Raw materials for the plant, including cement, sand, wood, and other buildings materials are being sourced from Pakistan, while furniture from the plants is being procured specifically from markets in nearby Sahiwal. [12]

Construction

While symbolic ground breaking for the project took place in May 2014, [4] commencement of actual civil works began on July 31, 2015. [13] The first of the two 660MW plants was put into operation on May 12, 2017, while the second 660MW plant was put into operation on May 24, 2017. [1] An estimated 350 personnel are required to operate the plant, [14] including 200 Pakistani engineers who are to undergo training in China. [12] Approximately 3000 laborers are required for construction of the plant. [12]

Boiler foundations, and the plant's turbine steel structure have been completed, while the 9-storey tall boiler structure, chimneys, and cooling towers are under construction as of May 2016. [12] In order to transport coal, a purpose-built railway line will be built from the Pakistan Railway at Yusuf Wala to the power plant itself. [10] From there, the coal is to be transported via the purpose-built railway line. In order to assist in coal transportation, Pakistan Railways has signed a $214 million contract for the purchase of 55 diesel electric locomotives from General Electric. [15] Pakistan Railways will also procure a further 20 diesel electric locomotives specifically for coal transport. [16] In January 2016, the Pakistan Railways signed a $37 million contract with Jinan Railway Vehicles Equipment Company for the supply of 800 hopper wagons which will be used to transport coal to the Sahiwal Coal Power Plant; [15] 580 of these wagons are to be constructed at the Mughalpura railway workshop. [15]

In order to connect the plant to the national electrical grid, a 9.5 kilometer 500 kilovolt single circuit transmission line will be constructed from the site to the Sahiwal Substation. [17]

Coal Source

As with the Pakistan Port Qasim Power Project, most of the coal used for the power plant is imported from Indonesia and South Africa, and is transported by rail from the Port of Karachi and Port Qasim in Pakistan's Sindh Province to the nearby village of Yusuf Wala on Pakistan's existing railway infrastructure. [18]

An estimated 4.48 million tons of coal will be required annually for the plant, based on a calculation of 22 hours of power generation per day. [6] Indonesia is identified as a primary source for its high quality coal, reliable production, and short transit times to Pakistan. [19] Coal from Pakistan's own Thar coalfield was found to contain excessive amounts of sulfur and lime, and was not deemed to be of high enough quality for the project. [20] The supply of reliable coal from the fields was also considered to be inadequate. [20] A mixture of Pakistani indigenous coal with imported coal was also deemed to be unsuitable as it would decrease heat production from coal, and would compromise safety of the boilers which are to be used in the project. [20]

Financing

The project is expected to cost a total of $1.8 billion. [21] Of this, the Chinese consortium bore 20% of the cost ($356.4 million) while the remaining 80% ($1.4256 billion) was be financed by a loan from the Industrial and Commercial Bank of China. [22]

Tariff

The Government of Pakistan will purchase electricity from the plant at a tariff of 8.3601 US Cents/kWh. [7]

Is Sahiwal a suitable site for this project?

Sahiwal is located in the Central Punjab, Pakistan with a very productive agrarian land of extreme fertility. This raises in the minds of people concerned, a critical question related to the site of the project and the possible risks linked with pollution and soil fertility decline.

The answers to such questions might be scientific but easily understandable.

Though thermal poweplants which involve coal as the main burning substance increase the risk factors of pollution but certain precautions can minimize the harmful effects resulting from the thermal procedures. For this purpose, modern electrostatic precipitator and desulphurization technology has been fitted in this project which will take care of the quality of air by eliminating dust particles, ash and sulphur contents from the outgoing flowing gas. An anti seepage ash yard has been built in the system to prevent ash water from entering the ground. Furthermore, the most advanced air quality monitoring system has been fitted in the site to monitor and maintain the air quality of the surroundings.

The question related to the disturbance in the balance of water supply for agriculture is answered by the logic that only 60,000 cubic metres of water per day from Lower Bari Doab is needed for complete operation of the plant which does not have any impact on the water being used for agrarian purposes of the surrounding agricultural land.

So, Sahiwal proves to be a very suitable site for Coal Power Plant despite the concerns of some people.

Related Research Articles

<span class="mw-page-title-main">Gadani</span> Town in Balochistan, Pakistan

Gadani is a coastal town of Hub District located in the southern part of Balochistan along the Arabian Sea, Pakistan. and is just a 1-hour drive away from Karachi. The population of Gadani was estimated to be around 10,000 in 2005. More than 97% of the population is Muslim with a small Hindu minority. The majority of the population speaks Balochi, Brahui languages and there is a small Lasi speaking minority. They belong to the Sanghur, Kurd, Sajdi, Muhammad Hasni, Gurginari and Bezinjo tribes.

<span class="mw-page-title-main">Hub Power Company</span> Electric power company in Pakistan

Hub Power Company Limited, colloquially known as HUBCO, is the first and largest Pakistani Independent Power Producer (IPP) with a combined installed power generation capacity of 3250 MW.

According to the United States Energy Information Administration (EIA), Pakistan may have over 9 billion barrels (1.4×109 cubic metres) of petroleum oil and 105 trillion cubic feet (3.0 trillion cubic metres) in natural gas (including shale gas) reserves.

The Huaneng Yingkou Power Station is a large thermal power station in China, with installed capacity of 1,840 MW. As of 2016, the plant is installed with two 320 MW units, and two 600 MW units, totalling to 1,840 MW.

Renewable energy in Pakistan is a relatively underdeveloped sector; however, in recent years, there has been more and more interest to explore renewable energy resources for the energy production. Around 10.57% of Pakistan’s total installed power generation capacity comes renewables. Most of Pakistan's renewable energy comes from hydroelectricity. As per the vision of the Prime Minister, there is the aim to “induct 20% of RE by the year 2025 and 30% of RE by the year 2030.”

The Nandipur Power Project is a 425 MW combined cycle thermal power plant situated at Nandipur near Gujranwala in the Punjab province of Pakistan. Being constructed by the China Dongfang Electric Corporation, the project was completed in March 2015. The initial cost of the project was Rs. 27 billion, but this escalated during the revised project cycle-1 and totalled Rs. 58.42 bn at completion. The power plant faced a series of hiccups during and after launching its commercial operations. Prior and after construction, the project continued to attract a number of court cases, inquiries, investigations, audits, and political and commercial disputes. The plant collapsed after 5 days of operation, launching a series of inquiries ordered by then prime minister Nawaz Sharif.

<span class="mw-page-title-main">China–Pakistan Economic Corridor</span> Infrastructure and geostrategic project

China–Pakistan Economic Corridor (CPEC) is a 3000 km Chinese infrastructure network project undertaken in Pakistan. This sea-and-land based corridor is aimed to secure and reduce the passage for China's energy imports from the Middle East by avoiding existing route from the Straits of Malacca between Malaysia and Indonesia, which in case of a war could be blocked and thus hampering the Chinese energy dependent economic avenues. Developing a deep water port at Gwadar in Arabian Sea and a well built road and rail line from this port to Xinjiang Province in western China would be a shortcut for boosting the trade between Europe and China. In Pakistan, its aim is to overcome an electricity shortfall, infrastructural development and modernize transportation networks. Along with shifting it from an agricultural based economic structure to industrial based.

Butibori Power Project is a coal-based thermal power plant located at Butibori near Nagpur in the Indian state of Maharashtra. The power plant is operated by the Reliance Power.

The Quaid-e-Azam Solar Park is a photovoltaic power station in Bahawalpur, Punjab, Pakistan, named in honor of Quaid-e-Azam Muhammad Ali Jinnah, the Founder of Pakistan. It is a 100 MW solar plant spanning 500 acres (200 ha) and hosting 392,158 solar modules. The initial phase of the project was constructed by the Government of Punjab, Pakistan in May 2015 at a cost of $131 million.

Xi Jinping's visit to Pakistan from 20 to 21 April 2015, was the first state visit of Xi Jinping to Pakistan. Xi is the second Chinese leader to visit Pakistan in 2010s after Chinese Premier Li Keqiang's visit to Pakistan between 22 and 23 May 2013. It was also Xi's first overseas trip of 2015. The trip led to the signing accords for $46 billion of investment in Pakistan by China for the construction of roads, rails and power plants to be built on a commercial basis by Chinese companies over 15 years. Most of the 51 projects were part of the China–Pakistan Economic Corridor.

The Balloki Power Plant is a 1,223 MW natural gas power plant completed in mid 2018 in Pattoki, in the Punjab province of Pakistan. Groundbreaking was commenced on November 11, 2015, and construction was scheduled for completion by December 2017. The project utilizes regasified liquefied natural gas (RLNG) for fuel, with diesel as an alternate backup. A 40 kilometer long transmission line with a capacity of 500 kilovolts was also constructed between the new plant and a grid station in southern Lahore.

<span class="mw-page-title-main">Pakistan Port Qasim Power Project</span> Coal powered electrical generation project in Pakistan

The 1,320 megawatt Pakistan Port Qasim Power Project comprises two 660 megawatt supercritical coal power plants, one of which was inaugurated in December 2016 as part of the China–Pakistan Economic Corridor. The $2.09 billion project is located on 330.7 acres at Port Qasim, 37 kilometers east of Karachi in Sindh Province. The project is part of a group of 14 energy projects which fall under the fast-tracked "Early Harvest" program of the $46 billion China Pakistan Economic Corridor project.

The Matiari–Lahore transmission line is a privately developed $2.1 billion transmission line under construction as part of the China–Pakistan Economic Corridor (CPEC). The line will stretch 878 kilometers from Matiari, Sindh, to Nankana Sahib District near Lahore, Pakistan, of which 550.65 kilometers will be in Punjab province, and 314.9 kilometers in Sindh Province.

SK Hydro also known as Suki Kinari HPP, is an under-construction, run-of-the-river hydropower project located on the Kunhar river in the Kaghan valley of Mansehra District Khyber Pakhtunkhwa, which has an installed generation capacity of 874 MW.

The Karot Hydropower Project is an under-construction concrete-core rockfill gravity large dam in Pakistan, with a planned installed capacity of 720 MW. The project is sponsored by Chinese state-owned company China Three Gorges Corporation (CTG).

The Engro Thar Coal Power Project (Thar-ll) is a coal-fired power plant developed as part of the China–Pakistan Economic Corridor by Sindh Engro Coal Mining Company and China Machinery Engineering Corporation in the Thar Block-II of the Thar Coalfield, Tharparkar District, Sindh, Pakistan 25 kilometers from the town of Islamkot near the village of Singharo-Bitra.

<span class="mw-page-title-main">Karachi–Peshawar Line</span> Main railway line in Pakistan

Karachi–Peshawar Railway Line is one of four main railway lines in Pakistan, operated and maintained by Pakistan Railways. The line begins from Karachi City station or Kiamari station and ends at Peshawar Cantonment Station. The total length of this railway line is 1,687 kilometers (1,048 mi). There are 184 railway stations from Kiamari to Peshawar Cantonment on this line. The line serves as the main passenger and freight line of the country. 75% of the country's cargo and passenger traffic uses the line. The line is currently undergoing a six-year Rs. 1286.68 billion (US$4.5 billion) upgrade and renovation as part of the China Pakistan Economic Corridor, with average rail speeds expected be doubled to 160 kilometers per hour upon completion.

<span class="mw-page-title-main">Chief Ministership of Shehbaz Sharif</span>

Shehbaz Sharif served the longest tenure in history as chief minister of Punjab spanning over 11 years of rule. His tenures involved the 1997 Nawaz Government, the 2008 Pakistan Peoples Party's regime and the 2013 PML-N's rule. His prominent contribution involves infrastructure development, transit projects and power plants. He has developed flyovers, road infrastructures, transit services and power projects. He is best known for his dedication, working speed, ability to execute mega projects and quick actions. However, he is also criticised over lack of priorities, spending development funds mostly in Lahore and large cities, keeping major power and assignments within himself, nepotism, conflict of interests, and misuse of authority by opposition parties.

References

  1. 1 2 "Second unit of Sahiwal power plant being inaugurated today". The Nation. 3 July 2017. Retrieved 6 July 2017.
  2. "Sahiwal coal power project will be functional by 2017: CM". Daily Times. 30 September 2015. Retrieved 17 December 2015.
  3. Liu, Youliang (9 March 2015). "APPLICATION FOR A GENERATION LICENSE OF HUANENG SHANDONG RUYI (PAKISTAN) ENERGY (PRIVATE) LIMITED FOR ITS 2 X 660 MW IMPORTED COAL FIRED POWER PROJECT AT SAHIWAL, PAKISTAN" (PDF). NEPRA. p. 109. Retrieved 17 December 2015.
  4. 1 2 "PM performs ground breaking of Punjab's first coal power plant". Dawn. 30 May 2014. Retrieved 17 December 2015.
  5. Liu 2015, p. 90
  6. 1 2 Liu 2015, p. 235
  7. 1 2 Huaneng Shandong Ruyi (Pakistan) Energy (Pvt.) Limited. "LAG-292 Huaneng Shandong Generation License" (PDF). NEPRA. p. 18. Retrieved 17 December 2015.
  8. "Sahiwal coal power project: power to people". The News. 19 March 2016. Retrieved 1 April 2017.
  9. 1 2 Liu 2015, p. 236
  10. 1 2 3 Liu 2015, p. 117
  11. Liu 2015, p. 111
  12. 1 2 3 4 5 6 7 Abrar, Mian (7 May 2016). "Sahiwal Coal Power Project set to become first CPEC project to be completed". Pakistan Today. Retrieved 8 May 2016.
  13. Liu 2015, p. 91
  14. Liu 2015, p. 342
  15. 1 2 3 Ahmed, Amin (14 January 2016). "Deal signed with China for 800 hopper wagons". Dawn. Retrieved 14 January 2016.
  16. "SAHIWAL, JAMSHORO POWER PLANTS: RAILWAYS TO PROCURE 20 DE LOCOMOTIVES FOR COAL FREIGHT". Business Recorder. 4 August 2015. Retrieved 18 December 2015.
  17. Liu 2015, p. 138
  18. Liu 2015, p. 92
  19. Zhong, Haixang (13 August 2014). "General Licence Application of Port Qasim" (PDF). NEPRA. NEPRA. p. 152. Retrieved 17 December 2015.
  20. 1 2 3 Zhong 2014, p. 156-157.
  21. Liu 2015, p. 94
  22. Liu 2015, p. 175.