Long Beach International Gateway | |
---|---|
Coordinates | 33°45′54″N118°13′17″W / 33.76488°N 118.22130°W |
Carries | 6 lanes of I-710, pedestrians and bicycles |
Crosses | Back Channel |
Locale | Terminal Island and Long Beach, California |
Website | newgdbridge |
Preceded by | Gerald Desmond Bridge |
Characteristics | |
Design | Cable-stayed bridge |
Total length | 8,800 ft (2,682 m) |
Height | 515 ft (157 m) |
Longest span | 1,000 ft (305 m) |
Clearance below | 205 ft (62 m) |
History | |
Architect | Brownlie Ernst and Marks |
Designer | Arup |
Engineering design by | Arup |
Constructed by | Shimmick/FCC/Impreglio (SFI) Joint Venture |
Construction start | January 8, 2013 |
Construction end | October 2, 2020 |
Construction cost | est. US$1,500,000,000(equivalent to $1,928,120,000 in 2023) |
Opened | October 5, 2020 |
Location | |
The Long Beach International Gateway, originally known as the Gerald DesmondBridge Replacement, is a cable-stayed bridge that carries six lanes of Interstate 710 and a bicycle/pedestrian path in Long Beach, California, west across the Back Channel to Terminal Island. The bridge replaced the Gerald Desmond Bridge, which was completed in 1968 and named after Gerald Desmond, a prominent civic leader and a former city attorney for the City of Long Beach.
The 1968 steel arch bridge developed numerous issues, and the Port of Long Beach decided it would be best, from an economical perspective, that the bridge be replaced. After several years of studies, a cable-stayed bridge with 205 feet (62 m) of vertical clearance to be built north of the existing bridge was identified as the preferred alternative in the final environmental impact report (2010 FEIR). [1]
The new bridge allows access to the port for the tallest container ships after the older bridge is demolished. It is the first long-span cable-stayed bridge in California and the first and only cable-stayed bridge in the Los Angeles metropolitan area. [2] For the bridge to be so tall, long approaches were required to allow trucks to cross. [3] A joint venture of Parsons Transportation Group and HNTB performed preliminary engineering for the main span and the approaches. Earlier reports had studied and discarded various alternatives, including an alternative alignment with a new bridge south of the existing bridge, rehabilitation of the existing bridge, and a tunnel instead of an elevated bridge. [1]
The 1968 roadway was four lanes (two in each direction) with a fifth climbing lane on each end. The replacement bridge carries a six-lane roadway with emergency lanes on each side, and the grade has been decreased by building a longer approach, despite the higher vertical clearance over the Back Channel; the planned improvements brought the bridge up to current freeway standards. [4] The replacement bridge also carries the Mark Bixby Memorial Bicycle-Pedestrian Path and observation decks over the water along the south side of the bridge. The path is named for Mark Bixby, a longtime proponent of adding bike lanes to the new Gerald Desmond Bridge replacement [5] [6] and a descendant of one of the original founders of Long Beach. Mark Bixby died in a March 2011 plane crash at the Long Beach Airport. [7]
The 1968 bridge was designated as a portion of Ocean Boulevard and was therefore operated by the City of Long Beach. When it opened to traffic on October 5, 2020, the replacement bridge was redesignated as the western (southern) extension of I-710 (extending its terminus to its intersection with State Route 47) and is now the responsibility of Caltrans, District 7. [4]
From west to east, the new bridge spans a total of 8,800 feet (2,700 m), consisting of: [8]
By extending the approach structures, approach grades are reduced to no more than 5 percent. [1]
As the tallest structure in the area, the 2020 cable-stayed bridge is a prominent addition to the Long Beach skyline. [9]
The replacement bridge was unanimously approved by the City of Long Beach in late September 2010. [10] A project launch meeting was held at the Port of Long Beach on November 22, 2010, attended by Long Beach Mayor Bob Foster, U.S. Representatives Dana Rohrabacher and Laura Richardson, Senator Alan Lowenthal and Caltrans Director Cindy McKim. [4]
Caltrans, Port of Long Beach, and Metro officials reviewed seven potential engineering and construction firms, selecting four as qualified final lead bidders: [11]
Three of the pre-qualified bidders submitted proposals by March 2012, with Kiewit dropping out at the bid stage. [12] In May 2012, the Long Beach Board of Harbor Commissioners approved Port of Long Beach staff’s recommendation that the “best value” design-build proposal to replace the Gerald Desmond Bridge was submitted by the SFI joint venture team, comprising Shimmick Construction Company Inc., FCC Construction S.A. and Impregilo S.p.A., [13] and the contract was awarded to the SFI JV in July 2012. [14] Major participants in the joint venture also include Arup North America Ltd. and Biggs Cardosa Associates Inc. [15]
The project has been completed as a design-build in contrast to the traditional design-bid-build used typically in infrastructure improvement. [15]
During the groundbreaking ceremony on January 8, 2013, two helicopters hovered 515 feet (157 m) above ground level, illustrating the height of the two cable towers for the planned replacement bridge. [16]
The project was originally estimated to cost $800 million in 2008. [17] By 2010, costs had increased to $1.1 billion, [10] and funding identified in 2010 for the replacement bridge included $500 million contributed by Caltrans, $300 million contributed by the USDOT, $114 million from the Port of Long Beach, and $28 million from Metro. [4] As of 2016 [update] , the current project estimate is $1.5 billion. [2]
The new bridge was delayed shortly after breaking ground. The new piers were delayed by the relocation and/or removal of numerous old and active oil wells and utility lines, which prevented foundation work from beginning. The bridge is located in the midst of the Wilmington Oil Field, one of the most prolific oil-producing fields located in the United States. [18]
Another part of the cost increase and schedule delay is attributed to a 2013 redesign of the support towers. [19] Caltrans and the Port of Long Beach required the tower redesign, executed by the SFI joint venture, allegedly to ensure seismic safety and to preserve long term structural integrity. The redesign set the estimated completion of the bridge back by 12 to 18 months. [20] Other cost increases are attributed to extra oversight required by innovative, yet contractually compliant products and materials proposed by the designers of the replacement bridge. [2]
The roadway for the approach structures was supported during construction by an underlane self-launched movable scaffolding system (MSS), [21] and is the first project in California to use a MSS. [22] The MSS was designed to bridge the 235 ft (72 m) span between piers and to support the concrete as it was poured for each span. Once the concrete had cured, the MSS moved to the next pier and repeated the pour. The orange MSS was used on the western (Terminal Island) approach, and a similar blue MSS was used on the eastern approach. [22]
By October 2014, work had started on the pilings which would serve as foundations for the new bridge's piers. [23] The two cable-stay support towers were started in March (eastern tower) and April 2015 (western tower). [21] Approach spans were underway by April 2016. [22] By August 2016, the project had passed the halfway mark, and the two cable support towers were already more than 200 ft (61 m) high. [24] On December 5, 2017, a "topping-out" ceremony was held to celebrate the completion of the two cable support towers. [25] A virtual opening ceremony was held on October 2, 2020. Motor vehicle traffic opened in both directions on October 5, 2020, [26] although the bicycle/pedestrian path remains incomplete as of August 2024. [27]
For the first eight months after its opening, the bridge was called the Gerald Desmond Bridge Replacement. Mayor Robert Garcia and Assemblymember Patrick O'Donnell coordinated a community effort to decide if a new name was warranted. Family of Gerald Desmond and native Long Beach residents with former mayors Beverly O'Neill and Bob Foster favored keeping the original name; Foster felt a change would be disrespectful to the namesake of the original bridge, civic leader Gerald Desmond. [28]
In May 2021, Senator Lena Gonzalez and Assemblyman O'Donnell announced that the name "Long Beach International Gateway" had been chosen through a public survey [29]
A cable-stayed bridge has one or more towers, from which cables support the bridge deck. A distinctive feature are the cables or stays, which run directly from the tower to the deck, normally forming a fan-like pattern or a series of parallel lines. This is in contrast to the modern suspension bridge, where the cables supporting the deck are suspended vertically from the main cable, anchored at both ends of the bridge and running between the towers. The cable-stayed bridge is optimal for spans longer than cantilever bridges and shorter than suspension bridges. This is the range within which cantilever bridges would rapidly grow heavier, and suspension bridge cabling would be more costly.
The San Francisco–Oakland Bay Bridge, commonly referred to as the Bay Bridge, is a complex of bridges spanning San Francisco Bay in California. As part of Interstate 80 and the direct road between San Francisco and Oakland, it carries about 260,000 vehicles a day on its two decks. It includes one of the longest bridge spans in the United States.
Route 710, consisting of the non-contiguous segments of State Route 710 (SR 710) and Interstate 710 (I-710), is a major north–south state highway and auxiliary Interstate Highway in the Los Angeles metropolitan area of the U.S. state of California. Also called the Los Angeles River Freeway prior to November 18, 1954, the highway was initially planned to connect Long Beach and Pasadena, but a gap in the route exists from Alhambra to Pasadena through South Pasadena due to community opposition to its construction.
The Blue Water Bridge is a twin-span international bridge across the St. Clair River that links Port Huron, Michigan, United States, and Point Edward, Ontario, Canada. The Blue Water Bridge connects Highway 402 in Ontario with both Interstate 69 (I-69) and Interstate 94 (I-94) in Michigan.
The Alex Fraser Bridge is a cable-stayed bridge over the Fraser River that connects Richmond and New Westminster with North Delta in Greater Vancouver, British Columbia. The bridge is named for Alex Fraser, a former British Columbia Minister of Transportation. The bridge was the longest cable-stayed bridge in the world when it opened on September 22, 1986, and was the longest in North America until the Arthur Ravenel Jr. Bridge, in the U.S. state of South Carolina opened in 2005.
Ting Kau Bridge is a 1,177-metre (3,862 ft) long cable-stayed bridge in Hong Kong that spans from the northwest of Tsing Yi Island and Tuen Mun Road. It is near the Tsing Ma Bridge which also serves as a major connector between the Hong Kong International Airport on Lantau Island and the rest of Hong Kong. It was completed on 5 May 1998. The bridge is toll-free.
The Carquinez Bridge is a pair of parallel bridges spanning the Carquinez Strait at the northeastern end of San Francisco Bay. They form the part of Interstate 80 between Crockett and Vallejo, California, United States.
The Vincent Thomas Bridge is a 1,500-foot-long (460 m) suspension bridge, crossing Los Angeles Harbor in Los Angeles, California, linking San Pedro with Terminal Island. It is the only suspension bridge in the Greater Los Angeles area. The bridge is part of State Route 47, which is also known as the Seaside Freeway. The bridge opened in 1963 and is named for California Assemblyman Vincent Thomas of San Pedro, who championed its construction. Its chief engineer was William (Jim) Jurkovich who was instrumental in bringing pre-stress concrete bridge design to California. It was the first welded suspension bridge in the United States and is now the fourth-longest suspension bridge in California and the 76th-longest span in the world. The clear height of the navigation channel is approximately 185 feet (56 m); it is the only suspension bridge in the world supported entirely on piles.
The eastern span replacement of the San Francisco–Oakland Bay Bridge was a construction project to replace a seismically unsound portion of the Bay Bridge with a new self-anchored suspension bridge (SAS) and a pair of viaducts. The bridge is in the U.S. state of California and crosses the San Francisco Bay between Yerba Buena Island and Oakland. The span replacement took place between 2002 and 2013, and is the most expensive public works project in California history, with a final price tag of $6.5 billion, a 2,500% increase from the original estimate of $250 million, which was an initial estimate for a seismic retrofit of the span, not the full span replacement ultimately completed. Originally scheduled to open in 2007, several problems delayed the opening until September 2, 2013. With a width of 258.33 ft (78.74 m), comprising 10 general-purpose lanes, it is the world's widest bridge according to Guinness World Records.
Stonecutters Bridge is a high level cable-stayed bridge spanning the Rambler Channel in Hong Kong, connecting Nam Wan Kok, Tsing Yi to Stonecutters Island. The bridge deck was completed on 7 April 2009, and opened to traffic on 20 December that year. The bridge was the second-longest cable-stayed span in the world at the time of its completion.
The Port Mann Bridge is a 10-lane cable-stayed bridge, 90 km/h speed limit, in British Columbia, Canada, that opened to traffic in 2012. It carries 10 lanes of traffic with space reserved for a light rail line.
An extradosed bridge employs a structure that combines the main elements of both a prestressed box girder bridge and a cable-stayed bridge. The name comes from the word extrados, the exterior or upper curve of an arch, and refers to how the "stay cables" on an extradosed bridge are not considered as such in the design, but are instead treated as external prestressing tendons deviating upward from the deck. In this concept, they remain part of the main bridge superstructure.
The Greenville Bridge, or the Jesse Brent Memorial Bridge, is a cable-stayed bridge over the Mississippi River, in the United States, carrying US 82 and US 278 between Refuge, Mississippi, and Shives, Arkansas. When it opened in 2010, it was the fourth-longest cable-stayed bridge in North America.
The Commodore Schuyler F. Heim Bridge was a vertical-lift bridge in the Port of Los Angeles. Dedicated on January 10, 1948, the bridge allowed State Route 47 to cross over the Cerritos Channel. Named after Schuyler F. Heim, who was in command of the Naval Air Station on Terminal Island in 1942, the bridge was one of the largest vertical-lift bridges on the West Coast. At the time of its opening, it was the highest in the country with the deck weighing about 820 short tons. Its towers are 186 feet (57 m) tall above the roadway deck and about 236 feet (72 m) tall when measured from the water level at high water. The bridge was decommissioned on October 12, 2015 and replaced by a new, six-lane fixed-span bridge in order to meet current safety and earthquake standards. A replacement bridge, tentatively titled State Route 47 Schuyler Heim Bridge Replacement, was completed in September 2020.
The Gerald Desmond Bridge was a 1968 through arch bridge that carried five lanes of Ocean Boulevard from Interstate 710 in Long Beach, California, west across the Back Channel to Terminal Island. The bridge was named after Gerald Desmond, a prominent civic leader and former city attorney for the City of Long Beach. In October 2020, a new cable-stayed bridge named Long Beach International Gateway replaced the old Gerald Desmond Bridge to allow taller container ships to access the ports. Demolition of the old bridge began in July 2022 and was completed in August 2023.
Perai River Bridge is a dual-three lane cable stayed bridge that straddles the Perai River in Seberang Perai, Penang, Malaysia. It is part of the Butterworth Outer Ring Road (BORR).
The Incheon Bridge is a reinforced concrete cable-stayed bridge in South Korea. At its opening in October 2009, it became the second bridge connection between Yeongjong Island and the mainland of Incheon. The Incheon Bridge is South Korea's longest spanning cable-stayed bridge. In comparison, it is the world's sixteenth longest cable-stayed bridge as of January 2019.
The Queensferry Crossing is a road bridge in Scotland. It was built alongside the existing Forth Road Bridge and the Forth Bridge. It carries the M90 motorway across the Firth of Forth between Edinburgh, at South Queensferry, and Fife, at North Queensferry.
Vidyasagar Setu, also known as the Second Hooghly Bridge, is a 822.96 meter long cable-stayed 6 laned toll bridge over the Hooghly River in West Bengal, India, linking the cities of Kolkata and Howrah.
A movable scaffolding system (MSS) is a special-purpose self-launching form used in bridge construction, specifically prestressed concrete bridges with segments or spans that are cast in place. The movable scaffolding system is used to support a form while the concrete is cured; once the segment is complete, the scaffold and forms are moved to the end of the new segment and another segment is poured.
Mark Bixby Memorial Bicycle Pedestrian Path
Note 1: WEST APPROACH: The 2,800-ft. west approach will be on Terminal Island.[ permanent dead link ]
Note 7: TOWERS: At 515 feet tall, the bridges two towers will be the second-tallest of any cable-stayed bridge in the U.S. The steel-reinforced concrete towers will be supported by massive foundations. The tower design – unique to this bridge – transitions from an octagon shape at the base to diamond shape at the top.
Note 8: CABLE-STAYED BRIDGE: The new bridge is a cable-stayed design, in which cables directly connect the towers to the road deck (unlike a traditional suspension bridge, which uses cables draped over towers). The entire length of the bridge – main span and approaches – will be 8,800 feet.
Note 9: SPAN: The main span and back spans of the bridge will be 2,000 feet long and 205 feet above the water. It will be the highest deck of any cable-stayed bridge in the U.S.
Note 10: EAST APPROACH: The 3,600-ft. east approach will connect the bridge to both the Long Beach (710) Freeway and east Ocean Boulevard toward downtown Long Beach.
PROJECT DESCRIPTION
This project consists of replacement of the aging Gerald Desmond Drive. The project location is in the Back Channel area of the Port of Long Beach, centered along Ocean Blvd. From the intersection of the Terminal Island Freeway (SR-47) at the western end to its terminus at the westerly end of the bridge over the Los Angeles River. The total project cost is estimated to be $721,400,000 subject to escalation from a base November 2005 dollar. Project cost will be revised at environmental certification scheduled for third quarter of 2008. Caltrans fact sheet for project shows construction costs of $800,500,000 with $65,000,000 support costs.