Mbarara Northern Bypass Road

Last updated

Mbarara Northern Bypass Road
Route information
Length14.5 km (9.0 mi)
HistoryDesignated in 2015
Completed in 2018 [1]
Major junctions
North end Makenke
South end Nyakayojo
Location
Country Uganda
Highway system

The Mbarara Northern Bypass Road is a road that bypasses the northern part of Mbarara City. [2]

Contents

Location

The road is located in Mbarara City, in the Western Region of Uganda. It starts from Makenke in Kakiika Division, across from the Coca-Cola plant, then it continues northwards to Rwebishuri before reaching Nkokonjeru. The road will then pass through a valley next to Ruharo hill. After crossing River Rwizi, the bypass ends at Katatumba Resort along Kabale road. [3] The road covers about 14.5 kilometres (9 mi) in length. [4] The geographical coordinates of the bypass road are 0°34'53.0"S, 30°39'30.0"E (Latitude:-0.581389; Longitude:30.658333). [5]

Overview

The road was developed and constructed to decongest the central business district of Mbarara City, by providing an alternative route for large cargo trucks destined for Tanzania, Rwanda, Burundi, or the Democratic Republic of the Congo. The construction of this road was launched by President Yoweri Museveni on 1 March 2015. [6] Original commissioning of the completed road was planned for April 2017, but additional work of 0.9 kilometres (1 mi), required a contract extension. [7]

Construction costs

The road was expected to cost about €170 million (US$210 million), of which the European Union was expected to lend about €122 million (US$144 million), with the Uganda government funding the remaining amount €45 million (US$55 million). [3] In March 2015, the China Railway Seventh Group began construction. [6] During the budget speech for the financial year 2018/2019, read on 14 June 2018, Matia Kasaija, the Uganda Minister of Finance, Planning and Economic Development announced that the road had been completed. [1]

See also

Related Research Articles

<span class="mw-page-title-main">Mbarara</span> Place in Western Region, Uganda

Mbarara City is a city in the Western Region of Uganda and the second largest city in Uganda after Kampala. The city is divided into 6 boroughs of Kakoba Division, Kamukuzi Division, Nyamitanga Division, Biharwe Division, Kakiika Division, Nyakayojo Division. It is the main commercial centre of most of south western districts of Uganda and the site of the district headquarters. In May 2019, the Uganda's cabinet granted Mbarara a city status, which started on 1 July 2020.

<span class="mw-page-title-main">National Social Security Fund (Uganda)</span> Quasi-government agency

The National Social Security Fund (NSSF) aka NSSF Uganda is a quasi-government agency responsible for the collection, safekeeping, responsible investment, and distribution of retirement funds from employees of the private sector in Uganda who are not covered by the Government Retirement Scheme. Participation for both employers and employees is compulsory. The Uganda National Social Security Fund is the largest pension fund in the countries of the East African Community, with total assets of USh18.58 trillion, as of June 2023.

<span class="mw-page-title-main">Matia Kasaija</span> Ugandan politician (born 1944)

Matia Kasaija is a Ugandan politician. He is the current Minister of Finance in Uganda's Cabinet. He was appointed to that position on 1 March 2015, replacing Maria Kiwanuka, who was appointed to Senior Presidential Advisor for Finance. From 27 May 2011 until 28 February 2015, he served as the State Minister for Finance (Planning) in the Cabinet of Uganda. He replaced Ephraim Kamuntu, who was promoted to Minister of Tourism. Before that, he served as the State Minister for Internal Affairs, from 1 June 2006 until May 2011. He is also the elected Member of Parliament for "Buyanja County", Kibaale District.

The Kampala Northern Bypass Highway, often referred to as the Northern Bypass, is a road in Uganda. It forms a semicircle across the northern suburbs of Kampala, Uganda's capital and largest city. The road was constructed to relieve traffic congestion within the city center, allowing cross-country traffic to bypass the city's downtown area.

<span class="mw-page-title-main">Source of the Nile Bridge</span> Bridge in Uganda

The Source of the Nile Bridge, also New Jinja Bridge, which was commissioned on 17 October 2018, by the President of Uganda, is a cable-stayed bridge across the Victoria Nile in Uganda. It replaced the Nalubaale Bridge, which was built in 1954.

The Entebbe–Kampala Expressway, also known as the "Kampala–Entebbe Expressway" or the "Entebbe–Kampala Highway", is a four-lane toll highway in the Central Region of Uganda. The highway links Entebbe International Airport, the country's largest civilian and military airport, to Kampala, the country's capital and largest metropolitan area. Originally, the highway was planned for commissioning in 2016, but because of the delayed works, commissioning was done on 15 June 2018 by Uganda's sitting president, Yoweri Museveni. Recently, the Uganda Minister for Works and Transport, Gen. Katumba Wamala launched the toll point at Kajjansi along Kampala–Entebbe Road.

<span class="mw-page-title-main">Ministry of Works and Transport (Uganda)</span>

The Ministry of Works and Transport is a Cabinet level government ministry of Uganda, that is mandated to plan, develop and maintain an economic, efficient and effective transport infrastructure, and transport services by road, rail, water, and air. The ministry is also mandated to manage public works including government structures and promote standards in the construction industry. The ministry is headed by a Cabinet Minister. The current Minister of Works and Transport is Katumba Wamala.

The Uganda National Roads Authority (UNRA) is a government agency mandated to develop and maintain the national roads network, advise the government on general roads policy, contribute to the addressing of national transport concerns, and perform certain other functions. UNRA is charged with, among other things, the selection of contractors, the supervision of construction, the scheduling of maintenance, and the prioritization of national road works.

The Kampala–Jinja Expressway, also known as the Jinja–Kampala Expressway, is a proposed four-lane toll highway in Uganda, linking Kampala, the capital and largest city of Uganda, with the city of Jinja in the Eastern Region of Uganda.

The Osukuru Industrial Complex sometimes referred to as Sukulu Industrial Complex, is a set of related industries, in the mining and manufacturing sectors, under construction in Uganda, the third-largest economy in the East African Community.

Makenke is a neighborhood within Mbarara City, in the Western Region of Uganda.

The Ntungamo–Mirama Hills Road is a road in the Western Region of Uganda, connecting the towns of Ntungamo and Mirama Hills, both in Ntungamo District.

Mbarara–Ntungamo–Kabale–Katuna Road is a road in the Western Uganda, connecting the city of Mbarara, in Mbarara District, with the towns of Ntungamo, Kabale and Katuna at the international border with the Republic of Rwanda.

The Kampala–Mpigi Expressway, also Busega–Mpigi Expressway, is a four-lane, dual carriage highway under construction in the Central Region of Uganda, connecting, Kampala, the capital city, and Mpigi, the headquarters of Mpigi District.

Pearl Dairy Farms Limited, often referred to as Pearl Dairy, is a dairy processing company in Uganda.

Mbarara Regional Cancer Centre (MRCC) is a public, specialized, tertiary care medical facility owned by the Uganda Ministry of Health. The facility is located along the Mbarara-Kabale Road, in the central business district of the city of Mbarara, on the campus of Mbarara Regional Referral Hospital. The coordinates of the centre are: 0°37'03.0"S, 30°39'17.0"E (Latitude:0.617500S, Longitude:30.654720E).

Katosi Water Works (KWW), also Katosi Water Treatment Plant is a water purification and distribution project in Uganda.

The Uganda National Medical Stores, commonly referred to as National Medical Stores (NMS), is a government-owned organisation in Uganda, mandated to procure, store and distribute human medication and health-related consumable items to government-owned health units in all districts of Uganda.

The Mbarara–Nkenda High Voltage Power Line is a high voltage electricity power line, connecting the high voltage substation in the city of Mbarara, in the Western Region to another high voltage substation at Nkenda, also in the Western Region of Uganda.

References

  1. 1 2 Matia Kasaija (Uganda Minister of Finance) (14 June 2018). "Uganda Budget Speech for Fiscal Year 2018/2019" (PDF). Kampala: Daily Monitor . Retrieved 14 June 2018.
  2. Arinaitwe, Solomon (26 September 2013). "Government gets Shs38 billion grant for Northern Bypass upgrade". Daily Monitor . Kampala. Retrieved 14 June 2018.
  3. 1 2 Aidah Nanyonjo (26 May 2010). "Mbarara Gets Sh459 Billion Bypass". New Vision . Kampala. Retrieved 14 June 2018.
  4. Colleb, Mugume (4 March 2015). "Those buying mailo land are getting air - Museveni". Daily Monitor . Kampala. Retrieved 14 June 2018.
  5. Google (14 June 2018). "Location of Mbarara Northern Bypass Road" (Map). Google Maps . Google. Retrieved 14 June 2018.
  6. 1 2 Nahamya, Joshua (1 March 2015). "Mbarara Bypass Construction Underway". Kampala: Chimpreports.com. Retrieved 14 June 2018.
  7. Nahamya, Joshua (28 September 2017). "Minister Impressed by Mbarara Bypass Progress". Kampala: Chimpreports Uganda. Retrieved 17 June 2017.

00°34′53″S30°39′30″E / 0.58139°S 30.65833°E / -0.58139; 30.65833