The National Shipbuilding Strategy (NSS), formerly the National Shipbuilding Procurement Strategy (NSPS), is a Government of Canada program operated by the Department of Public Works and Government Services. The NSS was developed under the Stephen Harper Government in an effort to renew the fleets of the Royal Canadian Navy (RCN) and the Canadian Coast Guard (CCG). The strategy was broken into three sections; the combat package, the non-combat package and the smaller vessel package. The companies who won the bids for the larger ships were not permitted to bid on the smaller vessel package. [1] In 2019, the Trudeau Government decided to add a third shipyard to the NSS specializing in the construction of icebreakers for the Coast Guard. The agreement to incorporate Davie as a third shipyard within the NSS was finally signed in April 2023. [2]
The NSS was launched on 3 June 2010 and the results for the two larger packages were made public on 19 October 2011. [3] Contracts for smaller vessels under the NSS were announced as they were awarded. [4]
The NSS program was charged with selecting Canadian shipyards capable of rebuilding the fleets of the RCN and the CCG through two large packages of work (a combat ship package and a non-combat ship package), originally valued at about $38 billion but with that level of envisaged spending now in excess of $100 billion. Another package of work for smaller vessels was separate but part of the overall strategy.
Rising project costs have impacted every program within the strategy with the budget for the Arctic Offshore Patrol Ships having increased by more than $1.6 billion, [20] [21] that of the River-class destroyers by more than $50 billion, [22] the Joint Support Ships by $1.5 billion, [23] the Polar icebreaker by $6.5 billion (in part due to the expansion of this acquisition from one to two ships), [24] the Offshore Oceanographic Science Vessel by more than $1 billion, [25] [26] and the Offshore Fisheries Science Vessels by more than $400 million. [27]
The Department of Public Works and Government Services issued a "Solicitation of Interest and Qualification" on 20 September 2010 and closed it on 8 October 2010. Five Canadian shipyards were short-listed to build the large vessels:
Between October 2010 and January 2011, the short-listed shipyards were consulted on the content of the "Request for Proposals" (RFP), the umbrella agreements, the proposed schedule, and the evaluation methodology.
The RFP was released on 7 February 2011, and closed on 21 July 2011. Five proposals were received from three bidders:
Two of the proposals received were for the combat work package and three were for the non-combat work package.
An evaluation organization composed of Canadian Forces and Canadian Coast Guard personnel, as well as public servants from the departments involved (Public Works and Government Services Canada, Industry Canada, National Defence, and Fisheries and Oceans Canada) evaluated the proposals. An independent fairness monitor oversaw the process. The shipyards were evaluated on a combination of mandatory and rated requirements.
During the final evaluation period, one of the proponents, Davie Yards, underwent a corporate restructuring which was accepted by the NSS governance on 27 July 2011. Davie Yards Inc. was changed to 7731299 Canada Incorporated which was a consortium between Davie Yards Incorporated, Seaway Marine and Industrial and Daewoo Shipbuilding & Marine Engineering.
On 19 October 2011 the Government of Canada selected Irving Shipbuilding Inc. for the $25 billion combat work package and Seaspan Marine Corp. for the $8 billion non-combat work package. [28] [29] In 2012, the two companies negotiated the contracts for the first projects of each package. [29]
On 16 January 2015, the Government of Canada finalized the contract for the construction of the Arctic Patrol Ship Project. Initially slated to cost $3.1 billion to build eight ships, the budget was increased to $3.5 billion for five ships, possibly six if no cost overruns on the first five. [30] Construction started on the first ship in September 2015. [31]
The search for the two main subcontractors on Irving's Surface Combatant package began in June 2015. In 2017, the Government of Canada will make its choice for two main subcontractors; one for combat systems integration (gun, missile, radar, sonar, communications) and the other for the design of the ship. [32] The list of those pre-qualified candidates which applied for the Surface Combatant subcontractor positions was released on 18 November 2015. [33]
In September 2015, reports emerged that climbing costs would lead to a reduction in the number of Surface Combatants the Canadian government would receive. [6] Problems were reported to have emerged from the Seaspan-apportioned part of the contract. In order to get the contract, Seaspan's yard had to be upgraded, which was only completed in November 2014. According to the agreement signed in 2012, the yard was to be ready to build by January 2015, but missed that date. [34] Construction only started on the first Coast Guard ships in June 2015, [35] leading to fears that the Joint Support Ships could be delayed. [34] [35]
In November 2015, reports of climbing costs associated with the NSS, reportedly up to 181%, has led to possible cancellations within the program. The newly elected Canadian government is set to review the entire program, after senior officials reported that the funding estimates outlined in the original plan were too low to meet operational requirements. [36] [37] However, the new government also simultaneously committed itself to retaining the NSS.
The first vessel constructed under the NSS, CCGS Sir John Franklin, was launched at Seaspan's shipyard in North Vancouver on 8 December 2017. [38] On 5 February 2019, the Canadian government changed the build order of ships at the Seaspan yard, placing the construction of one of the planned naval replenishment ships ahead of the Coast Guard's oceanographic science vessel. The second supply vessel will still be constructed after the oceanographic science vessel is completed. [39] In February 2021, a contract for the construction of Offshore Oceanographic Science Vessel was finally awarded. However, the total costs were reported to be nearly $1 billion, a figure attracting considerable criticism. [40]
On 8 February 2019, Canada signed an agreement with Lockheed Martin Canada, BAE Systems, Inc. and Irving Shipbuilding to design and construct the $60 billion Canadian Surface Combatant (River-class destroyer) project. [41]
In 2019, the Government of Canada decided to initiate a competition to add a third yard to the NSS. Widely rumored to end up being Davie Yards of Quebec, the yard appeared likely to specialize in medium, and possibly Polar, icebreakers for the Coast Guard. [19] [42]
In December 2019 it was announced that only Davie Yards had qualified for the icebreaker work. The next step was to negotiate an umbrella agreement between the federal government and Davie Yards by the end of 2020. The umbrella agreement would formally add Davie as a third yard under the NSS. [43] However, by the end of 2020 no progress had yet been reported.
In May 2021, the Government announced that the conclusion of the envisaged umbrella agreement was now "expected to be in place in late 2021". It was also announced that, pending the conclusion of that agreement, Davie would build one polar icebreaker for the Coast Guard while the Seaspan yard would build another one. [14] As of the end of 2021, further progress on the conclusion of the umbrella agreement had not yet been reported.
In June 2022 the Government again indicated that negotiations had been initiated to conclude an agreement by the end of the year. [44] However, as of early January 2023 and consistent with the pattern of previous years, no further progress had been reported. The agreement to incorporate Davie as a third shipyard within the NSS was finally signed in April 2023. [45]
CCGS Louis S. St-Laurent is a Canadian Coast Guard (CCG) heavy icebreaker. Louis S. St-Laurent's home port is St. John's, Newfoundland and Labrador. She is the largest icebreaker and flagship of the CCG.
Seaspan ULC provides marine-related services to the Pacific Northwest. Within the Group are three (3) shipyards, an intermodal ferry and car float business, along with a tug and barge transportation company that serves both domestic and international markets. Seaspan, is part of the Washington Companies that are owned by Dennis Washington. Kyle Washington, is the Executive Chairman of Seaspan, who has become a Canadian citizen.
The Protecteur class of naval auxiliaries for the Royal Canadian Navy (RCN) began as the Joint Support Ship Project, a Government of Canada procurement project for the RCN that is part of the National Shipbuilding Procurement Strategy. It will see the RCN acquire two multi-role vessels to replace the earlier Protecteur-class auxiliary oiler replenishment vessels.
Davie Shipbuilding is a shipbuilding company located in Lauzon, Quebec, Canada. The facility is now operating as Chantier Davie Canada Inc. and is the oldest continually operating shipbuilder in North America.
The Halifax Shipyard Limited is a Canadian shipbuilding company located in Halifax, Nova Scotia.
CCGS Arpatuuq is a future Canadian Coast Guard icebreaker that will be built under the Polar Icebreaker Project as part of the National Shipbuilding Strategy. The ship was initially expected to join the fleet by 2017 but has been significantly delayed and is now expected by 2030.
Polar Class (PC) refers to the ice class assigned to a ship by a classification society based on the Unified Requirements for Polar Class Ships developed by the International Association of Classification Societies (IACS). Seven Polar Classes are defined in the rules, ranging from PC 1 for year-round operation in all polar waters to PC 7 for summer and autumn operation in thin first-year ice.
CCGS Captain Molly Kool is a Canadian Coast Guard converted medium class icebreaker. She was originally built as an icebreaking anchor handling tug Vidar Viking for Trans Viking Icebreaking & Offshore in 2001. The vessel was acquired by the Canadian Coast Guard in August 2018 and was commissioned in May of the next year after refit. She is named after the Canadian sailor, Molly Kool.
Harry DeWolf-class offshore patrol vessels are warships of the Royal Canadian Navy (RCN) built within the Government of Canada Arctic and Offshore Patrol Ship (AOPS) procurement project, part of the National Shipbuilding Strategy. In July 2007 the federal government announced plans for acquiring six to eight icebreaking warships for the RCN.
CCGS Earl Grey is a Samuel Risley-class light icebreaker and buoy tender in the Canadian Coast Guard. Constructed in 1986, the vessel serves a variety of roles, including light ice-breaking and buoy tending, as well as being strengthened for navigation in ice to perform tasking along the shores off the Atlantic coast of Canada. Like her sister ship, CCGS Samuel Risley, she carries a large and powerful crane on her long low afterdeck for manipulating buoys. Earl Grey is the second icebreaker in Canadian service to carry the name.
CCGS Jean Goodwill is an icebreaking anchor handling tug supply vessel (AHTS) converted to a medium class icebreaker for the Canadian Coast Guard. She was originally built as Balder Viking for Trans Viking Icebreaking & Offshore AS in 2000. The vessel was sold to Canada in 2018 and was initially expected to enter service in late 2019 following a refit. However, due to delays the conversion of the vessel was not completed until November 2020.
CCGS Vincent Massey is an icebreaking anchor handling tug supply vessel (AHTS) converted to a medium class icebreaker for the Canadian Coast Guard. She was originally built as Tor Viking for Trans Viking Icebreaking & Offshore AS in 2000 and has also traded under the name Tor Viking II. The vessel was sold to Canada in 2018 and was initially expected to enter service in summer 2020 following a refit. However, the conversion work was delayed and the vessel was delivered to the Canadian Coast Guard in October 2022 and dedicated to service in September 2023.
Irving Shipbuilding Inc. is a Canadian shipbuilder and in-service support provider.
The Samuel Risley-class icebreakers are a class of two icebreakers and buoy tenders constructed for and operated by the Canadian Coast Guard. The two ships are based on offshore supply tugboat design and entered service in the 1980s. Samuel Risley is deployed to the Central Region, operating mainly on the Great Lakes of North America, while Earl Grey is posted to Atlantic Canada, working off the east coast of Canada.
CCGS Sir John Franklin is an offshore fisheries research ship of the Canadian Coast Guard. The ship was ordered in 2011 as part of the Canadian National Shipbuilding Procurement Strategy (NSPS) as a replacement for aging Canadian Coast Guard vessels. The ship was launched on 8 December 2017, named for Sir John Franklin, an arctic explorer who led two Royal Navy expeditions in search of the Northwest Passage, the second ending with the death of all his crew around 1848. The first of three vessels, Sir John Franklin is the sister ship of CCGS Capt. Jacques Cartier and CCGS John Cabot.
CCGS Capt. Jacques Cartier is an offshore fisheries research ship of the Canadian Coast Guard. The ship was ordered in 2011 as part of the Canadian National Shipbuilding Procurement Strategy (NSPS) as a replacement for aging Canadian Coast Guard vessels. Capt. Jacques Cartier is the sister ship of CCGS Sir John Franklin and CCGS John Cabot. The ship was constructed at Seaspan Shipyard, Vancouver, British Columbia and launched on 5 June 2019.
CCGS Judy LaMarsh is a Canadian Coast Guard light icebreaker. Built in 2010 as a shallow-draught icebreaking tug Mangystau-2 for the Caspian Sea oil fields, the vessel was acquired by Canada as an interim solution while the existing fleet undergoes service life extension and maintenance.
CCGS John Cabot is a Canadian Coast Guard offshore fisheries research ship. The vessel was constructed in 2020 by Vancouver Shipyards, operated by Seaspan Shipyards, in North Vancouver, British Columbia. It is named after John Cabot, an Italian explorer. John Cabot's home port is St. John's, Newfoundland and Labrador.
The Polar Icebreaker Project is an ongoing Canadian shipbuilding program under the National Shipbuilding Strategy. Announced in 2008 with an intention to replace the ageing CCGS Louis S. St-Laurent with a new polar icebreaker by 2017, the program has faced multiple delays and changes, and as of 2024 consists of two planned icebreakers, CCGS Arpatuuq and CCGS Imnaryuaq, with the first vessel expected to enter service in 2030.