Sleipner A

Last updated

Sleipner A is a combined accommodations, production and processing offshore platform at the Sleipner East gas field in the Norwegian sector of the North Sea. It is a Condeep-type oil platform, built in Norway by the company Norwegian Contractors for Equinor.

Contents

It is known for its catastrophic failure on 23 August 1991, due to a design flaw, that resulted from an error caused by unconservative concrete codes [1] and inaccurate finite element analysis modelling of the tricell, which formed part of the ballasting/flotation system. [2]

Location

Sleipner A is located on the Sleipner East gas field on the North Sea. Also six satellite fields–Gungne, Loke, Alpha North, Sigyn, Volve and Volve South–are tied-back to Sleipner A. [3] In addition to its own operations, the platform is used as a remote operation center for the Sleipner B wellhead platform. The Sleipner B is operated from the Sleipner A via an umbilical cable. In addition, the Sleipner T carbon dioxide treatment platform is linked physically to the Sleipner A platform by a bridge. [4]

Design

The platform is designed to accommodate roughly 160 people. The platform deck is 60 by 140 meters (197 by 459 ft) with a height of 210 meters (689 ft). [5]

The original hull was a gravity base made up of support pilings and concrete ballast chambers from which three or four shafts rise and upon which the deck sits. Once fully ballasted, the hull was to sit on the sea floor. There were 24 chambers, of which four formed the 'legs' supporting the facility on top in the case of the Sleipner A oil rig.

The hull was redesigned after the accident and the Sleipner A Platform was successfully completed in June 1993.

1991 accident

Collapse

The original hull collapsed during the final construction because of a design flaw. [5] It was towed into Gandsfjord where it was to be lowered in the water in a controlled ballasting operation at a rate of 1 meter per 20 minutes. This was necessary for the fitment of the deck platform to the hull. As the hull was lowered to the 65-meter (213 ft) mark, [6] rumbling noises were heard followed by the sound of water pouring into the unit. A cell wall had failed and a serious crack had developed, and sea water poured in at a rate that was too great for the deballasting pumps to deal with. Within a few minutes the hull began sinking at a rate of 1 meter per minute. As the structure sank deeper into the 210-meter (690 ft) fjord, the buoyancy chambers imploded and the rubble struck the floor of the fjord, creating a Richter magnitude scale 3 earthquake.

Later analysis showed that the failure would occur at 62 meters (203 feet). [6]

No one was injured during the accident. [5]

Investigation

The post-accident investigation by SINTEF in Norway discovered that the root cause of the failure resulted from inaccurate NASTRAN calculations [7] in the design of the structure. Stresses on the ballast chambers were underestimated by 47% and some concrete walls were designed too thin to resist foreseeable hydrostatic pressure when submerged. As the pressure increased, the walls failed and cracked, allowing sea water to enter the tank at an uncontrolled rate, eventually sinking the hull.

After the accident, the project leaders from Norwegian Contractors were brought before the Statoil board, and were expecting severe repercussions. But the director instead asked the famous question "Can you make a new one before schedule?"[ citation needed ] to which the contractors replied "Yes we can". The new hull was completed before schedule.

Computer-Aided Catastrophes

Computer-Aided Catastrophes, or CAC for short, such as the Sleipner Incident presented in this article, provide extremely valuable lessons for practising engineers working with numerical simulation tools such as the finite element method. The reason for the poor finite element result that led to the Sleipner Incident have been studied in more detail in NAFEMS Benchmark Challenge Number 6. [8]

Related Research Articles

<span class="mw-page-title-main">Oil platform</span> Offshore ocean structure with oil drilling and related facilities

An oil platform is a large structure with facilities to extract and process petroleum and natural gas that lie in rock formations beneath the seabed. Many oil platforms will also have facilities to accommodate the workers, although it is also common to have a separate accommodation platform linked by bridge to the production platform. Most commonly, oil platforms engage in activities on the continental shelf, though they can also be used in lakes, inshore waters, and inland seas. Depending on the circumstances, the platform may be fixed to the ocean floor, consist of an artificial island, or float. In some arrangements the main facility may have storage facilities for the processed oil. Remote subsea wells may also be connected to a platform by flow lines and by umbilical connections. These sub-sea facilities may include one or more subsea wells or manifold centres for multiple wells.

<span class="mw-page-title-main">Troll A platform</span> Natural gas rig off the coast of Norway

The Troll A platform is a Condeep gravity-based structure offshore natural gas platform in the Troll gas field off the west coast of Norway. Built from reinforced concrete, as of 2014, it was the tallest structure that has ever been moved to another position, relative to the surface of the Earth, and is among the largest and most complex engineering projects in history. The platform was a televised sensation when it was towed into the North Sea in 1995, where it is now operated by Equinor. It is also the heaviest object moved and the object with the second highest displacement at 1.2 million tons(the object with the highest displacement is the Gullfaks C, which had a displacement approaching 1.5 million tons in comparison with Troll A's 1.2 million). Troll A was towed from the afternoon 10 May 1995 until the platform was in place 17 May 1995. It was lowered to the seabed in 303 meters of water, and had penetrated 36 meters into the soil by 19 May 1995. It was self-supporting with no further mooring required.

<span class="mw-page-title-main">Semi-submersible platform</span> Marine vessel used in offshore roles with good stability and seakeeping

A semi-submersible platform is a specialised marine vessel used in offshore roles including as offshore drilling rigs, safety vessels, oil production platforms, and heavy lift cranes. They have good ship stability and seakeeping, better than drillships.

<span class="mw-page-title-main">Ormen Lange (gas field)</span> Large fossil fuel deposit off the coast of Norway

Ormen Lange is a natural gas field on the Norwegian continental shelf. It is situated 120 kilometres (75 mi) northwest of Kristiansund, where seabed depths vary between 800 and 1,100 metres. The field is named after the famous longship Ormen Lange of Olaf Tryggvason, a 10th-century Viking king of Norway.

<span class="mw-page-title-main">Troll gas field</span>

Troll is a natural gas and oil field in the Norwegian sector of the North Sea, one of the biggest in the North Sea, holding 40% of Norway’s gas – it also possesses significant quantities of oil, in thin zones under the gas cap, to the west of the field. The field as a whole consists of the main Troll East and Troll West structures in blocks 31/2, 31/3, 31/5 and 31/6, about 65 kilometres (40 mi) west of Kollsnes, near Bergen. Most of the gas lies in Troll East.

<span class="mw-page-title-main">Condeep</span> Make of gravity based oil platform structure

Condeep is a make of gravity-based structure for oil platforms invented and patented by engineer Olav Mo in 1972, which were fabricated by Norwegian Contractors in Stavanger, Norway. Condeep is an abbreviation for concrete deep water structure. A Condeep usually consists of a base of concrete oil storage tanks from which one, three or four concrete shafts rise. The Condeep base always rests on the sea floor, and the shafts rise to about 30 meters above the sea level. The platform deck itself is not a part of the construction.

<i>Byford Dolphin</i> Semi-submersible offshore drilling rig

Byford Dolphin was a semi-submersible, column-stabilised drilling rig operated by Dolphin Drilling, a Fred Olsen Energy subsidiary. It drilled seasonally for various companies in the British, Danish, and Norwegian sectors of the North Sea. It was registered in Hamilton, Bermuda. In 2019, Dolphin scrapped the rig.

Saipem 7000 Semi-submersible crane vessel

The Saipem 7000 is the world's third largest semi-submersible crane vessel, after the SSCV Sleipnir and the SSCV Thialf. It is owned by the oil and gas industry contractor Saipem S.p.A.

SSCV <i>Thialf</i> Semi-submersible crane vessel

The SSCV Thialf is a huge semi-submersible crane vessel operated by Heerema Marine Contractors; it was the largest crane vessel in the world until the SSCV Sleipnir became the largest in 2019.

This is an overview of Equinor's operations in various countries. Equinor is a Norwegian petroleum company.

<span class="mw-page-title-main">Equinor</span> Norwegian energy company

Equinor ASA is a Norwegian state-owned multinational energy company headquartered in Stavanger, Norway. It is primarily a petroleum company operating in 36 countries with additional investments in renewable energy. In the 2020 Forbes Global 2000, Equinor was ranked as the 169th-largest public company in the world. In 2023, the company was ranked 52nd in the same list. As of 2021, the company has 21,126 employees.

<span class="mw-page-title-main">Sleipner gas field</span> North Sea off Norway

The Sleipner gas field is a natural gas field in the block 15/9 of the North Sea, about 250 kilometres (160 mi) west of Stavanger, Norway. Two parts of the field are in production, Sleipner West, and Sleipner East (1981). The field produces natural gas and light oil condensates from sandstone structures about 2,500 metres (8,200 ft) below sea level. It is operated by Equinor. The field is named after the eight-legged steed Sleipnir of Odin a widely revered god in Norse mythology.

<span class="mw-page-title-main">Jackup rig</span> Type of mobile platform

A jackup rig or a self-elevating unit is a type of mobile platform that consists of a buoyant hull fitted with a number of movable legs, capable of raising its hull over the surface of the sea. The buoyant hull enables transportation of the unit and all attached machinery to a desired location. Once on location the hull is raised to the required elevation above the sea surface supported by the sea bed. The legs of such units may be designed to penetrate the sea bed, may be fitted with enlarged sections or footings, or may be attached to a bottom mat. Generally jackup rigs are not self-propelled and rely on tugs or heavy lift ships for transportation.

<span class="mw-page-title-main">Spar (platform)</span> Marine structure used for floating oil/gas platforms

A spar is a marine structure, used for floating oil/gas platforms. Named after navigation channel Spar buoys, spar platforms were developed as an extreme deepwater alternative to conventional platforms. The deep draft design of spars makes them less affected by wind, wave, and currents and allows for both dry tree and subsea production.

<span class="mw-page-title-main">Floating wind turbine</span> Type of wind turbine

A floating wind turbine is an offshore wind turbine mounted on a floating structure that allows the turbine to generate electricity in water depths where fixed-foundation turbines are not feasible. Floating wind farms have the potential to significantly increase the sea area available for offshore wind farms, especially in countries with limited shallow waters, such as Spain, Portugal, Japan, France and the United States' West Coast. Locating wind farms further offshore can also reduce visual pollution, provide better accommodation for fishing and shipping lanes, and reach stronger and more consistent winds.

Offshore concrete structures, or concrete offshore structures, are structures built from reinforced concrete for use in the offshore marine environment. They serve the same purpose as their steel counterparts in oil and gas production and storage. The first concrete oil platform was installed in the North Sea in the Ekofisk oil field in 1973 by Phillips Petroleum, and they have become a significant part of the marine construction industry. Since then at least 47 major concrete offshore structures have been built.

Oseberg Øst is an offshore oil field in the North Sea, located east of Oseberg Oil Field. The field was developed with a fixed production, drilling and quarters (PDQ) facility and is operated by Statoil. The first stage phase processing is done at the Oseberg Øst platform. The second and third phase processing of oil is done at the Oseberg Field Center and it is then transported to Sture terminal in Norway through the Oseberg Transport System.

Heimdal is an offshore natural gas field in the North Sea located 212 kilometres (132 mi) northwest of Stavanger, Norway. Heimdal serves as a connection hub for processing and distribution of natural gas from satellite fields.

The Johan Sverdrup oil field is an oil field in the North Sea, about 140 kilometres (87 mi) west of Stavanger, Norway. The field lies in two different production licenses and consists of two different discoveries called Avaldsnes and Aldous Major South. When it was revealed that these discoveries constituted one single field, it was renamed Johan Sverdrup after the father of Norwegian parliamentarism. The field has not yet been unitized between production licenses 501, 501B, and 265. Johan Sverdrup is expected to hold 1.9–3.0 billion barrels of oil. According to Statoil, the field is in 110 to 120 metres water depth, and the reservoir is at 1900 meters depth.

<i>Scarabeo 8</i>

Scarabeo 8 is an ultra deepwater 6th generation semi-submersible drilling rig. It is owned and operated by Saipem. The vessel is registered in Nassau, Bahamas.

References

  1. Selby RG, Vecchio FJ, Collins MP (1997). "The Failure of an Offshore Platform". Concrete International. 19 (8): 28–35. Archived from the original on 2011-07-23. Retrieved 2008-06-28.
  2. Arnold DN. The sinking of the Sleipner A offshore platform. URL: http://www.ima.umn.edu/~arnold/disasters/sleipner.html Archived 2008-09-19 at the Wayback Machine . Accessed on: June 27, 2008.
  3. "Sleipner Area". SubseaIQ. Bishop Interactive. Retrieved 2009-12-26.
  4. "Statoil shuts Sleipner B, transit intact". Reuters. 2009-12-18. Archived from the original on February 1, 2013. Retrieved 2009-12-26.
  5. 1 2 3 Doug Mellgren (2003-11-08). "North Sea oil platforms: Hard work, strict safety and inventive fun". The Associated Press . Alexander's Gas & Oil Connections. Retrieved 2009-12-26.
  6. 1 2 "Sleipner A". Oil Rig Disasters. Archived from the original on 2010-12-04. Retrieved 2010-06-30.
  7. Soereide, T.H., Jersin, E. (1997). Sleipner A GBS Loss, Report 16, Quality Assurance. SINTEF. p. 24. ISBN   82-14-00444-6.{{cite book}}: CS1 maint: multiple names: authors list (link)
  8. Ramsay, Angus. "NBC Number 6". www.ramsay-maunder.co.uk. Ramsay Maunder Associates. Retrieved 25 March 2017.