South London Route Utilisation Strategy

Last updated

Network Rail's (NR) South London Route Utilisation Strategy (SLRUS), published in March 2008 [1] [2] [3] (SLRUS) was the eighth Route Utilisation Strategy to be produced. By default, RUSs are established by the Office of Rail Regulation (ORR) unless the latter objects within 60 days. The RUS is included in NR's map as established. [4]

Contents

The scope includes the London suburban lines of Strategic Route 1 - Kent, [5] including lines as far as Hayes, Sevenoaks and Rochester (but excluding the Swanley-Rochester line) and those of Route 2 - Brighton Main Line and Sussex, [6] including lines as far as Horsham (via Dorking), Epsom Downs, Purley (plus the branches to Tattenham Corner and Caterham), East Grinstead and Uckfield. Where routes are four-tracked the fast lines are generally excluded. As such the routes are heavily short/medium distance commuter routes into London, but there are some freight services as well. The lines excluded from Routes 1 and 2 are to be covered in the Kent RUS [7] and the Sussex RUS. [8]

As with other RUSs, the SLRUS took into account a number of responses, [9] [10] [11] including the Office of Rail Regulation (ORR). [12]

Some issues are closely related to other published RUSs: South West Main Line RUS, Cross London RUS; Freight RUS; East Coast Main Line RUS. The Strategic Rail Authority's (SRA) Brighton Main Line (BML) RUS, [13] published February 2006, as superseded by the Department for Transport's (DfT) consultation [14] and briefing, [15] led to changes in the December 2008 timetable; the most important of these is the change to the Gatwick Express service in the morning peak. The Kent, Sussex and East Midlands [16] RUSs will have some interfaces with the SLRUS.

The RUS needs to be seen against existing contingent and prospective schemes, most notably the Thameslink project and the East London Line (ELL) extension (ELLx). Thameslink will see a step-change in services continuing through central London onto the network north of London, which are currently limited to 15 trains per hour in each direction (tph) at 8-car length; many interventions identified in the SLRUS are interdependent with certain works in this programme. Phase 1 of the ELL extension (ELLx1), already authorised at time of SLRUS publication, will incorporate new services on the lines from West Croydon and Crystal Palace to New Cross Gate; Phase 2 (authorised in February 2009) will incorporate new services on a route from Clapham Junction to Surrey Quays via a currently freight-only line, the South London Line, and a reinstated disused alignment. In addition Crossrail would interact with the RUS area at Abbey Wood from 2017 (at the earliest). Another project that does not directly form part of the RUS area but has a knock-on effect certainly to passenger services and possibly to freight services is High Speed One (HS1).

Largely because of these interdependencies the timescale of the SLRUS, while divided into a short, medium and long term, does not coincide with NR's Control Periods (CP) as is usual with RUSs. The short term is up to 2010 to coincide with the introduction of the December 2009 timetable. There are really three medium term timescales

A longer term timescale corresponding approximately with the remainder of CP4 and CP5 (commencing April 2019) and beyond is examined.

Apart from the prerequisites to train lengthening, mainly platform lengthening, increased depot capacity and power upgrades, the medium term interventions involve little infrastructure apart from the heavy undertakings within the contingent projects described above.

Short term

Three major projects affect the situation in the short term:

  1. the reconstruction of Blackfriars Thameslink station
  2. the starting of domestic passenger services on High Speed 1, scheduled for December 2009
  3. the re-opening of the extended ELL, scheduled for June 2010

The reconstruction of Blackfriars The commencement of works (in March 2009) results in the closure of the south-facing terminating platforms, 1 to 3, on the east side of the station. Consequently, all services need to continue north through Blackfriars. A recasting of services is necessary and, as this location is the boundary between the overhead-line and third-rail electrification area, additional dual-voltage stock is required.

High Speed One Originally, with the prospect of re-routing services from east Kent to London to use High Speed One, some service frequencies elsewhere on the Southeastern franchise were to be reduced. The RUS recommends retaining approximate the previous service levels on the classic lines.

The southern extension of ELL The East London Line Phase 1 extension (ELLx1) south of New Cross Gate will use the slow lines to serve all stations through Norwood Junction, where there is a branch to Crystal Palace, to West Croydon. This requires a major recasting of the South Central franchise timetables.

Southern Central franchise area

At the time of SLRUS publication, the preparation for the process of refranchising of services on the South Central area was well underway. The DfT would take the recommendations of the RUS into account when specifying the franchise. Off-peak services were not a priority for the RUS, but the franchising process would carefully consider these services. The DfT subsequently (in May 2008) issued a briefing document in respect of the process, and identified service level commitments (SLC) which closely corresponded with the schedule highlighted in the RUS as follows:

As SLC2 had to include provision for ELLx1, that in turn would have extensive impact on other aspects of the timetable, which need to be consistent with the following service levels and outline timetable:

SLC3 is dealt with below as part of the medium term.

Southeastern

At the time of the awarding of the Integrated Kent franchise, Southeastern undertook to provide services according to two phases of service level commitments (SLC): SLC1, the immediate level of services; SLC2, the mix of services to be provided once high-speed domestic services began over HS1, scheduled for December 2009. In the latter service mix, a net reduction of services over the 'classic' (i.e. non-HS1) routes was envisaged. However the SLRUS concluded that, owing mainly to the growth in traffic, the overall level of services over the classic routes be broadly retained. By the time of RUS publication, this had been agreed by DfT and Southeastern as regards the Hayes, Sidcup, Bexleyheath, Greenwich and Chislehurst slow lines. The timetable will still need to be revamped to accommodate the HS1 services from Medway and east Kent.

The RUS recommends 14tph through Blackfriars towards Farringdon:

Because of scarcity of dual-voltage rolling stock, some shoulder peak trains may run at less than 8-car formation.

Medium term

In the medium term the RUS recommends widespread train and platform lengthening, combined with station improvements to relieve congestion, all concentrated particularly into the near-medium term. The withdrawal of the South London line Victoria-London Bridge local service is recommended, to be replaced by the East London Line Phase 2 Extension (ELLx2) and a Victoria-Bellingham service. Other services patterns will change a number of times in the period according to the availability of infrastructure.

Medium term, 2010-12

The main recommendation in this period is for train and consequent platform lengthening, to 10 cars on most Southern Central suburban routes and 12 cars on most Southeastern suburban routes into London Bridge. The lengthening works are required before reconstruction works begin at London Bridge. These in turn have implications for power supply and deporting.

This period also corresponds with the delivery to completion of Thameslink Key Output 1, which will facilitate 16tph at maximum 12-car length. This will include an expanded interchange with the London Underground and a new entrance on the south bank of the River Thames.

Brighton Main Line (BML) services to Thameslink will all run via Herne Hill (not London Bridge) with peak direction services as follows:

East London Line Phase 2 Extension (ELLx2)

The SLRUS recommends early implementation of the ELL branch from Surrey Quays to Clapham Junction. It would serve the South London Line (SLL) stations of Wandsworth Road, Clapham High Street (both with increased frequency of 4tph), Denmark Hill, Peckham Rye and Queens Road Peckham; this would mitigate the effects of withdrawal of the SLL route from Victoria to London Bridge, which the RUS states is inevitable for a number of reasons, including its unsustainability into London Bridge during the latter's redevelopment (starting in 2012). ELLx2 would also provide access from Clapham Junction and the above SLL stations to destinations east of London Bridge on both sides of the river, potentially relieving pressure on London Bridge for significant numbers of passengers.

Medium term, 2012-15

This period corresponds with the commencement of the process of delivery of Thameslink Key Output 2, mainly the redevelopment of London Bridge station and directly related works on both east and west approaches.

This will reduce capacity in and through London Bridge station. During the works capacity into the terminating platforms will be 20tph. A number of interventions are required, including diversion of services to the Thameslink route via Herne Hill, and encouraging passengers to travel to Victoria.

Medium term, to immediately beyond 2015

The completion of Thameslink Key Output 2 will facilitate 24tph at maximum 12-car length. The full north–south routing and timetabling need to be developed. All principal stations served should have 4tph.

The capacity into and through London Bridge is estimated as a total of 86tph broken down as follows:

All London Bridge trains will need to be run at their full possible length to maintain capacity. East Grinstead and Uckfield trains should split and joining at Oxted, served by diesel trains. Frequency will need to be reduced on services via Sydenham and via Tulse Hill.

The service via Thameslink towards the south is foreseen to be as follows:

via London Bridge

via Elephant & Castle

The RUS did not specify the northern terminating points from Thameslink.

An indicative schedule of the services into the terminating platforms at London Bridge was given.

The total service level into Charing Cross will be roughly as today, but with modified individual routes, though all services will be able to call at London Bridge. The total service level into Cannon Street will be somewhat reduced.

Even with all these interventions, some peak crowding will remain. Some train lengthening beyond that provided 2010-1015 is likely to be required.

Longer term (2019 and beyond)

In the longer term further peak train lengthening of up to 12 cars on certain routes may become highly desirable, though technically difficult. Another strategy could be to increase peak service level frequencies, though the RUS highlights the difficulties and even drawbacks of the interventions required to support that. Developments away from the existing heavy rail network are discussed such as:

Certain key stations may require significant redevelopment, and a few new stations, including Brixton High Level, have been mooted and should be explored further at a later date.

Subsequent developments

Eastfields station on the Wimbledon loop opened in June 2008.

In February 2008 [17] an announcement of the approval and funding package for the East London London Phase 2 extension (from Surrey Quays to Clapham Junction) was made by Transport for London (TfL). However, the associated (as mitigation for the withdrawal of the South London Line service) Victoria-Bellingham service has not been confirmed. In early 2010 TfL is studying various alternatives to fill the gap. [18]

The bay platforms at Blackfriars were closed in March 2009, pending reconstruction of the station.

In March 2009 Network Rail published its CP4 Delivery Plan 2009, including Enhancements programme: statement of scope, outputs and milestones, [19] confirming most of the recommended interventions.

As at early May 2009 there are about 12tph through Blackfriars in the peak three hours.

In December 2010 completion of the Thameslink Programme was deferred to 2018.

In December 2011 platform lengthening was complemented on the Sydenham Line (to 10-car), the East Grinstead line (to 12-car) and the Bedford - Brighton route (to 12-car). The latter included the opening of a new station entrance at Blackfriars (South Bank) and a new station concourse at Farringdon.

Related Research Articles

Thameslink Main-line route in the British railway system

Thameslink is a 24-hour, 115-station main-line route in the British railway system, running from Bedford, Luton, St Albans City, Peterborough and Cambridge via central London to Sutton, Orpington, Sevenoaks, Rainham, Horsham and Brighton. The network opened as a through service in 1988, with severe overcrowding by 1998, carrying more than 28,000 passengers in the morning peak. All the services are currently operated by Govia Thameslink Railway.

London Bridge station London Underground and mainline railway station

London Bridge is a central London railway terminus and connected London Underground station in Southwark, south-east London. It occupies a large area on three levels immediately south-east of London Bridge, from which it takes its name. The main line station is the oldest railway station in London fare zone 1 and one of the oldest in the world having opened in 1836. It is one of two main line termini in London to the south of the River Thames and is the fourth-busiest station in London, handling over 50 million passengers a year.

Blackfriars station London Underground and railway station

Blackfriars, also known as London Blackfriars, is a central London railway station and connected London Underground station in the City of London. It provides Thameslink services: local, and regional and limited Southeastern commuter services to South East London and Kent. Its platforms span the River Thames, the only one in London to do so, along the length of Blackfriars Railway Bridge, a short distance downstream from Blackfriars Bridge. There are two station entrances either side of the Thames, along with a connection to the London Underground District and Circle lines.

Farringdon station Railway and London Underground station

Farringdon is a London Underground and connected main line National Rail station in Clerkenwell, central London. The station is in the London Borough of Islington, just outside the boundary of the City of London. Opened in 1863 as the terminus of the Metropolitan Railway, the world's first underground passenger railway, Farringdon is one of the oldest surviving underground railway stations in the world.

City Thameslink railway station Central London railway station

City Thameslink is a central London railway station within the City of London, with entrances on Ludgate Hill and Holborn Viaduct. The station is on the Thameslink route between Blackfriars to the south and Farringdon to the north.

Herne Hill railway station Railway station in Lambeth, South London, England

Herne Hill railway station is in the London Borough of Lambeth, South London, England, on the boundary between London fare zones 2 and 3. Train services are provided by Thameslink to London Blackfriars, Farringdon, St Pancras International and St Albans on the Thameslink route and by Southeastern to London Victoria and Orpington on the Chatham Main Line. It is 3 miles 76 chains (6.4 km) down the line from Victoria.

East Croydon station National rail station and Tramlink tram stop in London

East Croydon is a railway station and tram stop in the town of Croydon, Greater London, England, and is located in Travelcard Zone 5. At 10 miles 28 chains from London Bridge, it is one of the busiest non-terminal stations in London, and in the United Kingdom as a whole. It is one of three railway stations in the London Borough of Croydon with Croydon in their name, the others being West Croydon and South Croydon. A Tramlink tram stop is located immediately outside the main station entrance.

Catford railway station National Rail station in London, England

Catford railway station is one of two stations serving the London suburb of Catford. Mainly used by commuters, it is in Travelcard Zone 3 and is on the Catford Loop Line, between Crofton Park and Bellingham. It is served mainly by Thameslink trains between West Hampstead Thameslink, London Blackfriars and Sevenoaks. Connections to London Victoria are available at Peckham Rye. Catford is 8 miles 3 chains (12.9 km) measured from Victoria.

Sydenham railway station (London) National rail station in London, England

Sydenham (London) is a railway station in Sydenham in the London Borough of Lewisham, South London. Originally opened in 1839, the station is located on the former Croydon Canal, which is now a branch of the Brighton Main Line, often known as the Sydenham Corridor. Sydenham falls within Travelcard Zone 3 and is served by London Overground and Southern. The station is 6 miles 32 chains (10.30 km) down the line from London Bridge.

Norwood Junction railway station National rail station in London, England

Norwood Junction railway station is a National Rail station in South Norwood in the London Borough of Croydon, south London and is in Travelcard Zone 4. It is 8 miles 55 chains (13.98 km) down the line from London Bridge.

Bickley railway station National Rail station in London, England

Bickley railway station is on the Chatham Main Line in England, serving the town of Bickley in the London Borough of Bromley, south-east London. It is 11 miles 76 chains (19.2 km) down the line from London Victoria and is situated between Bromley South and St Mary Cray on the main line. Southeastern trains branch from the main line south of Bickley and run to Orpington via Petts Wood. Thameslink services run either via Petts Wood or St Mary Cray on the main line.

St Mary Cray railway station National Rail station in London, England

St Mary Cray railway station is in St Mary Cray, South East London within the London Borough of Bromley. It is 14 miles 57 chains (23.7 km) down the line from London Victoria. Train services are operated by Southeastern, who manage the station, and Thameslink.

South Croydon railway station National Rail station in London, England

South Croydon railway station is in the London Borough of Croydon in south London, in Travelcard Zone 5. It is on the Brighton Line at its junction with the Oxted Line, 11 miles 21 chains (18.1 km) measured from London Bridge.

Woodmansterne railway station National Rail station in London, England

Woodmansterne railway station is a railway station which primarily serves the western areas of Coulsdon in the London Borough of Croydon, England. Situated on the Tattenham Corner line, it is 17 miles 40 chains (28.2 km) from London Charing Cross. For ticketing purposes the station is in London Travelcard Zone 6. The station has a single island platform, which can be reached by a footbridge, and there is a ticket office on the platform.

Chatham railway station Railway station in Chatham, Kent, England

Chatham railway station is on the Chatham Main Line in England, serving the town of Chatham, Kent. It is 34 miles 25 chains (55.2 km) down the line from London Victoria and is situated between Rochester and Gillingham.

Eynsford railway station Railway station in Kent, England

Eynsford railway station serves Eynsford in Kent, England. It is 20 miles 32 chains (32.8 km) down the line from London Victoria and is situated between Swanley and Shoreham. Train services are provided by Thameslink.

Portslade railway station

Portslade railway station is a railway station serving the town of Portslade-by-Sea in East Sussex, England, but located on the western fringes of the village of Aldrington. It is 2 miles 73 chains (4.7 km) down the line from Brighton.

Thameslink Programme

The Thameslink Programme, originally Thameslink 2000, is a £6 billion project in south-east England to upgrade and expand the Thameslink rail network to provide new and longer trains between a wider range of stations to the north and to the south of London. The development facilitates cross-London journeys, which means that passengers no longer have to change trains in London. Work includes platform lengthening, station remodelling, new railway infrastructure, and new rolling stock. The project was originally proposed in 1991 following the successful introduction of the initial Thameslink service in 1988. After many delays, planning permission was granted in 2006 and funding was approved in October 2007. Work started in 2009 and, was completed on September 18th, 2020.

The Kent Route Utilisation Strategy (KRUS) is a Route Utilisation Strategy (RUS), published by Network Rail (NR) in January 2010. it was the thirteenth RUS to be completed, not counting the partially completed Network RUS. By default, RUSs are established by the Office of Rail Regulation (ORR) unless the latter objects within 60 days; and the ORR have confirmed no objection to the establishment of the Kent RUS.

The Sussex Route Utilisation Strategy is a Route Utilisation Strategy (RUS), published by Network Rail (NR) in January 2010. It was the fourteenth RUS to be completed, not counting the partially completed Network RUS. By default, RUSs are established by the Office of Rail Regulation (ORR) unless the latter objects within 60 days, and the ORR have confirmed no objection to the establishment of the Sussex RUS.

References