StatusOperational
Construction began2006
Commission date November 2009 (Natural Gas)
Owner(s) TANESCO
Operator(s) TANESCO
Thermal power station
Primary fuel Natural gas
Power generation
Nameplate capacity 45 MW
External links
Website www.tanesco.co.tz

Tegeta Thermal Power Station is a Tanzania Electric Supply Company owned power plant. The project began in 2006 half funded by the Tanzanian Government and the other half by The Government of the Kingdom of the Netherlands under ORET/MILIEV program. [1]

Contents

The power-plant is located in Tegeta, Dar es Salaam and has an installed capacity of 45 megawatts (60,000 hp) using Natural Gas as fuel. [2] The power plant obtains Natural gas from the existing dar-es-salaam gas pipeline. [3]

Operations

The Power plant operates on Natural gas bought from the national pipeline. ORCA Exploration Group Inc. was assigned the contract to provide the natural gas. [4] Currently the government does not plan to expand this power plant due to limitations in the gas pipeline however TANESCO is expanding their gas generation capacity with their new Kinyerezi Power Plant. [5]

Confusion

In 2014 there was a Tegeta escrow scandal, that involved the embezzlement of around $250 million and $400 million. However, this was not the power station that was involved in the scandal, it was the power plant operated by Independent Power Tanzania Limited.

See also

Related Research Articles

Economy of Tanzania National economy

The economy of Tanzania is a lower-middle income economy that is overwhelmingly dependent on agriculture. Tanzania's economy has been transitioning from a command economy to a market economy since 1985. Although total GDP has increased since these reforms began, GDP per capita dropped sharply at first, and only exceeded the pre-transition figure in around 2007.

TANESCO

The Tanzania Electric Supply Company Limited (TANESCO) is a Tanzanian parastatal organisation established in 1964. It is wholly owned by the government of Tanzania. The Ministry of Energy and Minerals regulates the operations of TANESCO.

Kidatu Dam, also Kidadu Hydroelectric Power Station, is a 204 megawatts (274,000 hp) hydroelectric dam in Tanzania.

Tanzania has a wide range of energy resources in abundance, which are not yet fully exploited. These include; wood fuel, other biomass fuels, hydropower, natural gas, coal, wind, geothermal, uranium and solar.

Ubungo I Thermal Power Station

Ubungo I Thermal Power Station also known as the Ubungo Power Plant began commercial operations on 30 July 2008 with its Gas turbines. The power-plant is located in Ubungo, Dar es Salaam and has an installed capacity of 110 megawatts (150,000 hp).

Ubungo II Thermal Power Station

Ubungo II Thermal Power Station was an extension to the Ubungo I Power Station and began commercial operations in 2012. The power-plant is located in Ubungo, Dar-es-salaam and has an installed capacity of 100 megawatts (130,000 hp).

Mtwara Thermal Power Station is a power plant owned by the Tanzania Electric Supply Company. The station has a capacity of 18 MW (24,000 hp) and uses natural gas from the Mnazi Bay gas wells in Mtwara. The station is not connected to the national grid but is instead connected to the Mtwara/Lindi mini-grid.

The Tanzania Liquefied Natural Gas Project (TLNGP), also Likong’o-Mchinga Liquefied Natural Gas Project (LMLNGP), is a planned liquefied natural gas processing plant in Tanzania.

The Mtwara–Dar es Salaam Natural Gas Pipeline (MDNGP), is a pipeline that transports natural gas from Tanzania's natural gas fields in Mnazi Bay, Mtwara Region to Dar es Salaam.

Somanga Thermal Power Station is a 7.5 MW (10,100 hp), natural gas powered, electricity generating power station in Tanzania.

Tanzania Mbolea and Petrochemical Company (TMPC), a Tanzanian company that was specifically formed to design, build and operate a fertilizer-manufacturing factory in the Mtwara Region of Tanzania, using natural gas as raw material.

Julius Nyerere Hydropower Station is a hydroelectric dam under construction across the Rufiji River in eastern Tanzania. Although controversial, the government approved the plans in 2018. The power station is expected to have an installed capacity of 2,115 megawatts (2,836,000 hp) and to produce 5,920GWh of power annually. The project, power station and dam are owned by and will be managed by the government owned Tanzania Electric Supply Company (TANESCO). Construction began in 2019 and is expected to be completed in 2022.

Kinyerezi II Thermal Power Station is a 240 MW (320,000 hp), natural gas powered, electricity generating power station in Tanzania.

Kinyerezi I Thermal Power Station, also Kinyerezi 1 Thermal Power Station or Kinyerezi 1 Gas Plant, is a 150 MW (200,000 hp), natural gas powered, electricity generating power station in Tanzania.

The Kishapu Solar Power Station is a proposed 50 MW (67,000 hp) solar power plant in Tanzania. The power station is under development by Tanzania Electric Supply Company Limited (TANESCO), the national electricity monopoly utility company. The energy will be integrated into the national grid, also operated by TANESCO. The solar farm will be developed in phases to capacity of 150 megawatts. When completed and commissioned, it will be the largest, grid-ready solar power station in the country.

Zanzibar Utilities Regulatory Authority Multisectoral regulator of the Government of Zanzibar

The Zanzibar Utilities Regulatory Authority (ZURA) is a multisectoral government agency established under Act No. 7/2013 of the Laws of Zanzibar to provide technical and economic regulation in both electricity, petroleum and water sectors in Zanzibar, autonomous part of Zanzibar Archipelago, Tanzania, East Africa.

Ruhudji Hydroelectric Power Station is a planned 358 megawatts hydroelectric power station in Tanzania. The lead developer of this renewable energy project is Tanzania Electric Supply Company Limited (TANESCO), the government-owned electricity utility company. TANESCO plans to develop the power station, as a public private partnership (PPP) project. Work is contemporaneously ongoing, along with the development of the 222 megawatts Rumakali Hydroelectric Power Station, also located in Njombe Region.

Rumakali Hydroelectric Power Station is a 222 megawatts hydroelectric power station under construction in Tanzania. The power station is under development by a consortium comprising Tanzania Electric Supply Company Limited (TANESCO), the government-owned electricity utility company and the China Gezhouba Group. The power generated at this power station will be sold to TANESCO, for integration into the national electric grid.

References

  1. "Generating Power and Controversy: Understanding Tanzania's Independent Power Projects" (PDF). University of Cape Town, Graduate school of business. Retrieved 12 August 2015.
  2. Msuya, Poline. "Overview of Tanzania Gas Market and Role of EWURA" (PDF). naruc.org. RWURA. Retrieved 12 August 2015.
  3. Shana, Sebastian John. "Investment Opportunities in the gas sector in Tanzania" (PDF). sanec.org. Tanzania Petroleum Development Corporation. Retrieved 12 August 2015.
  4. "Orca Exploration announces commencement of gas sales to a new power plant in Tanzania". ORCA. 16 December 2009. Retrieved 12 August 2015.
  5. "Challenges of Unreliable Electricity Supply to Manufacturers in Tanzania" (PDF). cti.co.tz. Confederation of Tanzania Industries. Retrieved 12 August 2015.