Tsankov Kamak Hydro Power Plant

Last updated
Tsankov Kamak Hydroelectric Power Plant
Tsankov kamak Dam.jpg
Tsankov Kamak Dam
Relief Map of Bulgaria.jpg
Red pog.svg
Location of Tsankov Kamak Hydro Power Plant in Bulgaria
LocationTsankov Kamak downstream of Devin
Coordinates 41°49′56″N24°25′18″E / 41.83222°N 24.42167°E / 41.83222; 24.42167
Construction began2004
Opening date2011
Construction cost Euro 500 Million
Owner(s) NEK EAD
Dam and spillways
Type of dam Double curvature arch concrete dam
Impounds Vacha River
Height130.5 m (428 ft)
Length486 m (1,594 ft)
Spillway capacity1,450 m3/s (51,000 cu ft/s)
Reservoir
CreatesTsankov Kamak reservoir
Total capacity111,000,000 m3 (90,000 acre⋅ft)
Catchment area 1,214 km2 (469 sq mi)
Surface area3.27 km2 (810 acres)
Power Station
Operator(s) NEK EAD
Commission date2011
Hydraulic head 150 m (490 ft) (Gross head)
Turbines 2 x 40  MW
Installed capacity 80  MW
Annual generation 185 GWh

The Tsankov Kamak Hydroelectric Power Plant, also Tsankov Kamak HPP, [1] comprises an arch dam and hydroelectric power plant (HPP) on the territory of the village of Mihalkovo, southwestern Bulgaria. It is situated on the Vacha River in Smolyan Province, on the borders of Pazardzhik Province and Plovdiv Province, roughly 40 kilometres (25 mi) southwest of Plovdiv and downstream (north) of the town of Devin. It is a part of the Dospat–Vacha Hydropower Cascade (500.2 MW) development of the Vacha River involving five dams and seven power stations in the provinces of Smolyan, Plovdiv and Pazardzhik, 250 kilometres (160 mi) southeast of the capital Sofia. The other four dams are Dospat, Teshel, Vacha and Krichim.

Contents

The Tsankov Kamak dam is the first double curvature arch dam [2] in cupola shape in Bulgaria. [3] It has a maximum dam height of 130.5 metres (428 ft). It is the second in the cascade series from the upstream end, and the last to be developed. Apart from power generation, the other objectives of the five projects are use of water resources for irrigation, drinking and household water supply. While the cascade development started in 1958, construction of the Kamak power plant started on 29 April 2004 and was completed in 2011. [4] [5] [6] Initial estimated cost of the project was Euro 220 million financed by many banks and equipment manufacturers, including VA TECH Finance, Bank Austria Creditanstalt, BNP Paribas Fortis, Raiffeisen Zentralbank, Société Générale, and Credit Suisse First Boston. [4] However, the final cost of the project has far outstripped the original estimates due to topography, geology and also possible corruption, which were not assessed at the investigation stage of the project. [4]

The carbon emission reduction due to building the Tsankov Kamak HPP is assessed at about 200,000 t CO2 (228,000 tons of СО2 including the four rehabilitation projects of the cascade). This credit is transferred to the Austrian carbon-credit program under the Joint Implementation Project mechanism which was agreed for the project within the framework of the Kyoto Protocol to partially meet the project costs. For the reduced emissions, Austria compensates Bulgaria at the rate US$10 per ton of carbon emissions. [4] [7] [8] The Joint Implementation Project has two components, one is the Implementation of the Tsankov Kamak HPP and the other is the rehabilitation of the electro-mechanical components of the other four projects in the cascade development. [6] Two more HPPs, the Vacha I and the Vacha II, with total installed capacity of 20.6 MW, are located in the lower part of the cascade. [6]

Natural landscape

The Tsankov Kamak arch dam, associated works and the HPP station are located on the Vacha River, which is the second longest river in Bulgaria. It raises in the Rhodope hill ranges which borders Greece. [2] It is situated on the borders of Smolyan Province, Pazardzhik Province and Plovdiv Province, roughly 40 kilometres (25 mi) southwest of Plovdiv and downstream (north) of the town of Devin. The dam site is located about 400 metres (1,300 ft) downstream of the confluence of the Vacha River and the Gashnya River, in the valley known as Gashnya Valley. The catchment area at the dam site is 1,214 square metres (13,070 sq ft) and the annual flow is assessed to be approximately 650 million cubic metres with an average inflow of 69.5 cubic metres (2,450 cu ft) per second. The dam has been designed for a gross storage of 111 million cubic metres. [2]

The hydropower potential in the river between Sredna and Vacha had remained unexploited under the five dams development initiative, but is now utilized through the Tsankov Kamak project. [5] The reservoir submergence is in rocky terrain, which is deforested and has unproductive vegetation. The catchment is highly rugged and mountainous with high altitudes, high watershed flats, deep ravines and large tectonic kettles. The upper and lower course of the river flows through deep cut banks. [6]

In the narrow valley stretch of the Vacha River where the project is located, the geological formation consists of sound granites and gneissic formations except for a small patch of about 7 metres (23 ft), which is the fractured zone of mylonites, which was filled up with concrete. [6] The dam’s rock foundation has seven types of rocks with elastic modules values varying from 12,000 MPa to 72,000 MPa and a Poisson’s ratio varying between 0.24 and 0.27. The damping ratio of 10% for this foundation has been adopted in the dynamic analysis. [2] The intake structure and the pressure tunnel pass through difficult geological formations. Due to this geological feature, particularly at the intake structure, an area of about 6,000 square metres (65,000 sq ft) was required to be plugged in the Gashnia Valley. [9]

Construction

Tsankov Kamak Hydro Power Plant TsankovKanakDam.jpg
Tsankov Kamak Hydro Power Plant

The Natsionalna Elektricheska Kompania EAD (NEK EAD) was awarded the contract to the project in 2001, [10] and in November 2003 they forwarded their plans to start construction of the project to the Government of Bulgaria. At the end of the year 2003, Alpine Mayreder, an Austrian company, was awarded the civil works contract of the project. The equipment supply and installations were awarded to Austrian group of suppliers, Andritz Hydro for HEM – equipment and Pöyry Energy GmbH for engineering with Energoproekt Hydropower as a Bulgarian Co-designer of the project [5] The project was financed by export and commercial credits, which were finalized in Vienna on 14 November 2003; the financial credit without any backup guarantee by the Government of Bulgaria. The total value of the financing contract was roughly €220 million (€216 million has been specifically cited [11] ), with bank security provided by the Oesterreichische Kontrolbank Aktiengellschaft. The balance amount was financed by the commercial credits provided by VA TECH Finance, Bank Austria Creditanstalt, BNP Paribas Fortis, Raiffeisen Zentralbank, Société Générale, and Credit Suisse First Boston who organized the bank credits. Insurance coverage for the export credit of €100 million was provided by Coface of France; Hermes of Germany; EKN of Sweden and Egap of the Czech Republic apart from the Oesterreichische Kontrolbank Aktiengellschaft (OeKB) which has also covered political and the commercial risks. [4] [12]

Construction of the project was considered a challenge in view of the terrain and geologically weak structural region. The building of a new road of about 22 kilometres (14 mi) in difficult terrain, with frequent landslides and rockfalls, caused problems in road construction. This significantly increased the cost of the project up to roughly €500 million. [13] Civil construction works involved six million cubic metres of excavation, two million cubic metres of filling, 850,000 cubic metres of batching and mixing of concrete and placing 100,000 anchors with a total combined length of about 400 kilometres (250 mi). Concreting was done in 3 metre lifts. A service road of 6 metres in width was built on top of the dam. Apart from the Christian Schild and 60 engineers of the Alpine Slovakia and contractors of civil engineering works of the project, some 1200 Bulgarian workers were involved in its construction at one point. [12] Work was carried out continuously, involving 535,000 cubic metres of concrete delivered by a crane of 26 tons capacity, which was erected across the river over the dam. [12] The concreting of the dam began in October 2007 and was completed in January 2010. [5]

Project features

Dam

Tsankov Kanak Dam spillway openings of 8 m x 8 m Tsankov Kamak Dam.jpg
Tsankov Kanak Dam spillway openings of 8 m x 8 m

The double curved arch dam is 130.3 metres (427 ft) in height with a reservoir water spread area of 3.27 square kilometres (1.26 sq mi). It has four spillway blocks designed for a maximum flood discharge of 1,425 cubic metres (50,300 cu ft)/sec, each provided with radial gates, and has a pressure shaft of 4.4 metres (14 ft) in width and 600 metres (2,000 ft) in length which is steel lined and bifurcated at the lower end to feed the turbines from the intake on the upstream on the left bank of the dam. It feeds two units of 40 MW capacity turbine generators (Francis Turbines) housed in a surface powerhouse, a tailrace channel of 700 metres (2,300 ft) length, and a balancing channel of 1,300 metres (4,300 ft) length. These features are elaborated further with relevant design details. [2] [6] [12] It has gross storage capacity of 111 million cubic metres.

The Tsankov Kamak dam has a total length of 459.4 m and crest level of EL 688.50 m, with 22 cantilever blocks which are "interconnected by a system of shear boxes", [5] which are tangential to the axis at the crest, and the gravity blocks abut on the left and right banks. Horizontal sections of the arch dam are of parabolic shape with fixed thickness. [5] A series of 10 centimetres (3.9 in) thick shear key locks on both surfaces of each cantilever block are provided to achieve uniform distribution of shear force between the blocks. The dam width at the top is 8.8 metres and at the foundation the base is 26.36 metres (86.5 ft). The curved part of the arch dam is 340 metres in length and its chord length is 345 metres (1,132 ft) . The maximum reservoir water level is EL 685.00 m and the minimum draw down level is EL 670.00 m with a storage capacity of 41 million cubic metres. [2]

The spillway has four bays located in the middle section of the dam controlled by radial gates of 8 m x 8 m size each designed to pass a 1 in 1000 year frequency flood of 1,425 cubic metres (50,300 cu ft)/sec, which raises the water level to EL 687.42 m (all gates open condition) thus allowing for a free board of 1.42 metres (4.7 ft) to top of the dam. [5] The spillway energy dissipation chute has aeration baffle blocks. Over the dam height of 130.5 metres, five galleries are provided in the body of the dam; the gallery at the bottom has been used initially for grouting of the foundation and for drainage and four horizontal inspection galleries at different elevations (at 30 metres (98 ft) interval). [2]

The reservoir stretches over a surface area of 3.27 square kilometres (810 acres) and a length of 22 kilometres (14 mi). The filling of the reservoir was started in June 2010 and completed over roughly 15 weeks. [2] A reservoir management plan envisages fish farming and reservoir operation and maintenance along the periphery of the reservoir and its tributaries. [6] Two bottom outlets in the form of steel pipes of 1.3 metres (4.3 ft) diameter, each of 28.3 metres (93 ft) length have been provided in the body of the dam which facilitates emptying of the reservoir in any emergency; it takes about 11–12 hours to empty the reservoir. The outlets have been provided with slide gate controls on the downstream end. The stilling basin of the spillway is also used for energy dissipation of the outflows from the bottom outlets. [5] [6] The penstock/pressure shaft is in the form of a steel lined pressure shaft which is 4.4 metres (14 ft) diameter to carry a discharge of 69.5 cubic metres (2,450 cu ft)/sec for power generation. It is 609 metres (1,998 ft) in length (with 10% slope). [9] ) and bifurcates into two at the bottom end to feed two turbines, each of 40 MW capacity. [5] Slope protection in the 22 kilometres (14 mi) long stretch of the reservoir spread (up to a surface area of 3.24 square kilometres (1.25 sq mi)) also involved concreting to the extent of 40,000 cubic metres (1,400,000 cu ft) to take care of draw down condition for operating the power stations of the cascade under two daily peaks in the morning and evening. [12]

Power station

The surface power station at the end of pressure shafts has two units, each of 40 MW capacity (Francis turbines) operating under a gross head of 150 metres (490 ft) and an average net head is 133.7 metres (439 ft). The annual energy generation is about 185 GWh. This also has beneficial impact on other cascade development projects in the basin as the energy generation gets enhanced by a 48% increase. [2] [5] [6] The power station is run as a peaking station with two peaks, one in the morning and the other in the evening. [12] With the completion of the Tsankov Kamak HPP, and the rehabilitation of the other HPPs, and all stations connected to a common grid, the efficiency of the whole cascade is improved and energy production rose by a further 16 GWh per annum for the cascade. [7]

The design output of Francis turbines is 41,171 kW each, the turbine speed is 428.6 r.p.m., the generator rating is 46 MVA, and generation voltage is 10.5 kV. An outdoor switch yard is provided next to the surface powerhouse with main two step up transformers of 50 MVA rating and voltage ratio is 10.5/240 kV. The powerhouse is operated both under the remote control mode from the south regional dispatching control and automatically under the local control mode. [6]

Related Research Articles

<span class="mw-page-title-main">Dospat Reservoir</span> Reservoir in Bulgaria

Dospat Reservoir is situated in the western part of the Rhodope Mountains, Bulgaria. The reservoir stretches nearly 19 km (12 mi) northwest to the city of Sarnitsa. At 1,200 m (3,900 ft) above the sea level, it is one of the highest dams in Bulgaria in terms of altitude, and, with its 22 km2 (8.5 sq mi) of water area, the second largest in capacity. It is fed by the Dospat River.

<span class="mw-page-title-main">Vacha (river)</span> River in Bulgaria

The Vacha is a river in southern Bulgaria, a right tributary of the river Maritsa. Reaching length of 112 km, it is the 23rd longest river of Bulgaria and the second longest in the Rhodope Mountains, following the Arda (272 km), another major Maritsa tributary. The Vacha drains significant area of the western Rhodope Mountains, including the ridges Batak Mountain, Veliyshko–Videnishki, Pereliksko–Prespanski and Chernatitsa.

The Hàm Thuận – Đa Mi Hydroelectric Power Complex is a cascade of two hydroelectric power stations in Hàm Thuận Bắc District of the central region of Vietnam. It is operated by Da Nhim – Ham Thuan – Da Mi Hydropower Joint Stock Co., a subsidiary of Vietnam Electricity. The same company also operates the older Đa Nhim Hydroelectric Power Station.

<span class="mw-page-title-main">Rana Pratap Sagar Dam</span> Dam in Chittorgarh District, Rajasthan

The Rana Pratap Sagar Dam is a gravity masonry dam of 53.8 metres (177 ft) height built on the Chambal River at Rawatbhata in Rajasthan in India. It is part of integrated scheme of a cascade development of the river involving four projects starting with the Gandhi Sagar Dam in the upstream reach in Madhya Pradesh and the Jawahar Sagar Dam on the downstream with a terminal structure of the Kota Barrage in Rajasthan for irrigation.

<span class="mw-page-title-main">Mingachevir Dam</span> Dam in Mingachevir

The Mingachevir Dam is an earth-fill embankment dam on the Kura River just north of Mingachevir in Azerbaijan. It serves several purposes to include hydroelectric power production and water storage for irrigation. The Mingachevir reservoir, behind the dam, supplies water to the Upper Qarabag and Upper Sirvan Channels which help irrigate about 1,000,000 ha of farmland in the country. Its six Francis turbine-generators were overhauled or replaced with 70 megawatts (94,000 hp) sets in 2000. Mingachevir reservoir has a storage capacity of 15.730 cubic kilometres (12,753,000 acre⋅ft), covering 605 km2 (234 sq mi). The length of the dam is 1,550 metres (5,090 ft), its width is 16 metres (52 ft) and height is 80 m (260 ft). It is the largest hydroelectric power station in the South Caucasus, is located over Kur river and not far from Mingachevir city.

<span class="mw-page-title-main">Teshel Hydro Power Plant</span> Hydroelectric power plant in Bulgaria

The Teshel Hydro Power Plant is an active hydro power project near Teshel, Smolyan Province, southern Bulgaria. It is situated along the river Vacha in the Rhodope Mountains. It has 2 individual Francis turbines which deliver up to 60 MW of power. The Teshel HPP forms part of the Dospat–Vacha Hydropower Cascade (500.2 MW).

<span class="mw-page-title-main">Rangit Dam</span> Dam in India

Rangit Dam, which forms the headworks of the Rangit Hydroelectric Power Project Stage III, is a run-of-the-river hydroelectric power project on the Ranjit River, a major tributary of the Teesta River in the South Sikkim district of the Northeastern Indian state of Sikkim. The project's construction was completed in 1999. The project is fully functional since 2000. The project was built at a cost of Rs 4922.6 million. The average annual power generation from the 60 MW project is 340 GWh with firm power of 39 MW.

<span class="mw-page-title-main">Farkhad Dam</span> Dam in Spitamen, Sughd Province

The Farkhad Dam is a hydroelectric and irrigation dam on the Spitamen in Sughd Province, Tajikistan. It is a part of the Naryn-Syr Darya Cascade. The dam is located on the territory of Tajikistan and controlled by Tajikistan, while the Farkhad hydropower station, operated by Uzbekenergo.

The Baishan Dam is an arch-gravity dam on the Second Songhua River near the town of Baishanzhen, Huadian, Jilin Province, China. The purpose of the dam is hydroelectric power generation and flood control. The dam supplies water to five turbine-generators in two different powerhouses for an installed capacity of 1,500 megawatts (2,000,000 hp) while it can also control a design 19,100 cubic metres per second (670,000 cu ft/s) flood. Additionally, it has a 300 megawatts (400,000 hp) pumped-storage hydroelectric generation capacity. It is named after Baekdu Mountain, near the city of Baishan.

<span class="mw-page-title-main">Lake Cachí</span> Artificial reservoir in Costa Rica

Lake Cachi is an artificial lake in central Costa Rica created by the Cachí Dam, an arch dam north of Tapantí National Park, to the east-southeast of Cartago in Cartago Province. The main town is Cachí, away from the east bank of the lake. Built in the 1970s, it was one of the first hydroelectric projects in Costa Rica. It has an installed capacity of 102 MW with three units of 34 MW capacity each.

Tsankov Dam is a dam on the Vacha River, Bulgaria. It is part of the Vacha Cascade Joint Implementation Project involving three more dams and four power stations. The two other existing dams on the Vacha River are the Vacha Dam and the Kamak Dam.

<span class="mw-page-title-main">Krichim Reservoir</span> Reservoir in Bulgaria

Krichim Dam is a dam on the Vacha River, Bulgaria. It is part of the Dospat–Vacha Hydropower Cascade (500.2 MW) involving four more dams and seven power stations. The three existing dams on the Vacha River are the Vacha Dam, Tsankov Dam, and the Kamak Dam. The 144.5 metres (474 ft) concrete dam was in its implementation stage as of 2011.

<span class="mw-page-title-main">Vacha Reservoir</span> Reservoir in Devin Municipality, Bulgaria

Vacha Reservoir is a body of water associated with a dam in Devin Municipality, south Bulgaria. It is part of the Dospat–Vacha Hydropower Cascade (500.2 MW) involving four more dams and seven power stations. The three other existing dams on the Vacha River are the Krichim Dam, the Tsankov Kamak Dam and the Teshel Dam.

The Trung Sơn Dam is a hydroelectric power station on the Ma River in northwestern Vietnam. Located in the Trung Sơn commune, Quan Hóa District, Thanh Hóa Province, it is approximately 95 kilometres (59 mi) southwest of Hòa Bình city, and 195 kilometres (121 mi) northwest of Thanh Hóa city. The dam created a reservoir which covers a large area of the Mường Lát and Quan Hóa Districts in the Thanh Hoa province as well as part of the Mộc Châu District in Sơn La Province. It is approximately 9.5 kilometres (5.9 mi) from the Vietnam–Laos border. The 260 MW associated power plant became fully operational in September 2017.

<span class="mw-page-title-main">Vorotan Cascade</span> Dam in Syunik Province

The Vorotan Cascade, or the ContourGlobal Hydro Cascade, is a cascade on the Vorotan River in Syunik Province, Armenia. It was built to produce hydroelectric power and provide irrigation water. The Vorotan Cascade consists of three hydroelectric power plants and five reservoirs with a combined installed capacity of 404.2 MW. It is one of the main power generation complexes in Armenia.

The Ngoulmendjim Power Station is a planned hydroelectric power station across the Komo River in Gabon. The power station is under development, by a consortium comprising the French conglomerate Eranove Group and Gabonese Fund for Strategic Investments (FGIS). As of November 2021, the development was in the "financial mobilization phase".

The Batak Hydroelectric Cascade is situated in the Pazardzhik Province, southern Bulgaria and is among the first hydroelectric cascades in the country. Inaugurated on 6 September 1959, it includes seven reservoirs and three underground hydro power plants — Batak, Peshtera and Aleko with a combined installed capacity of 254.2 MW, producing an average of 796 GWh annually.

The Gashnya is a 20 km long river in southern Bulgaria, flowing through Pazardzhik and Smolyan Provinces. It is a left tributary of the Vacha, itself a right tributary of the Maritsa. There are no settlements along its course.

Batak Hydro Power Plant is an active underground hydro power plant located in Batak, Bulgaria, which is a part of the Batak Hydropower Cascade.

The Dospat–Vacha Hydroelectric Cascade is situated in the western Rhodope Mountains of southern Bulgaria, on the territory of the Smolyan, Pazardzhik and Plovdiv Provinces. It is owned by the National Electricity Company. The cascade was constructed between 1963 and 2010 by "Hydrostroy".

References

  1. Energy and Good Governance in Bulgaria: Trends and Policy Options. CSD. 2011. p. 61. ISBN   978-954-477-167-6 . Retrieved 25 September 2012.
  2. 1 2 3 4 5 6 7 8 9 K. Apostolov, A. Andonov, & A. Iliev Risk Engineering LTD, Sofia, and M. Kostov, G. Varbanov, D. Stefanov, A. Kaneva & N. Koleva, Central Laboratory for Seismic Mechanics and Earthquake Engineering, BAS. "Seismic Safety Assessment of "Tsankov Kamak" Arch Dam Part I – Response to MCE" (PDF). andonov.bg. Retrieved 20 September 2012.{{cite web}}: CS1 maint: multiple names: authors list (link)
  3. "Hydroelectric Power Plants in Bulgaria". Induscards.com. Retrieved 20 September 2012.
  4. 1 2 3 4 5 "Hydro power project Tsankov Kamak". Minstroy. Retrieved 19 September 2012.
  5. 1 2 3 4 5 6 7 8 9 10 R. Kohler & G. Zenz. "Analysis and Monitoring of Tsankov Kamak Arch Dam" (PDF). lamp3.tu-graz.ac.at. pp. 205–210. Retrieved 20 September 2012.
  6. 1 2 3 4 5 6 7 8 9 10 "Joint Implementation and Clean Mechanism Project, Project Design Documents" (PDF). dnv.com. July 2003. p. 8,9,17,22,29,30–34. Retrieved 21 September 2012.
  7. 1 2 "Hydropower project as part of the Vacha Cascade" (PDF). alpine.at. Retrieved 21 September 2012.
  8. "Reservoir Storage Scheme, Tsankov Kamak, Natsionalna Elektricheska Kompania (NEK), Bulgaria" (PDF). Pöyry Energy GmbH. Retrieved 21 September 2012.
  9. 1 2 "Hydropower Station Tsankov Kamak". alpine.pl. Retrieved 21 September 2012.
  10. International Conference on Engineering of Dams and Appurtenance Works including Power Houses and Transmission Systems, 29-31 January 2003, Hotel Hyatt Regency, New Delhi, India. Council of Power Utilities. 2003. p. 180. Retrieved 25 September 2012.
  11. Profil. Wirtschafts-trend Zeitschriftenverlag. 2006. p. 73. Retrieved 25 September 2012.
  12. 1 2 3 4 5 6 "Dam Impressive, The Tsankov Kamak Challenge" (PDF). AlpinesLovakia, Company Magazine. February 2010. Retrieved 20 September 2012.
  13. "Oettinger tells Sofia to be 'wiser' with energy projects". EurActiv.com PLC. 2010-04-06. Retrieved 19 September 2012.