Two Creeks Solar Park

Last updated
Two Creeks Solar Park
Two Creeks Solar Park.jpg
Two Creeks Solar Park
CountryUnited States
LocationTown of Two Creeks & Town of Two Rivers
Coordinates 44°14′52″N87°32′36″W / 44.24778°N 87.54333°W / 44.24778; -87.54333
StatusCommissioned
Construction beganQ4 2019
Commission date Nov 2020
Construction cost$195 Million
Owner(s)WPS & MG&E
Employees3
Solar farm
Type Flat-panel PV
Solar trackerSingle-Axis
Power generation
Nameplate capacity 150 MW
Capacity factor 14.6% (2023)
Annual net output 192 GWh (2023)

The Two Creeks Solar Park is a 150 MW solar photovoltaic energy station in Manitowoc County, Wisconsin. Ownership is shared between Wisconsin Public Service Corporation (WPS) and Madison Gas and Electric (MG&E), at 100 MW and 50MW, respectively. [1] It was the first utility-scale solar plant approved and constructed in Wisconsin.

Contents

The facility consists of approximately 533,000 PV panels on single-axis tracking systems. PV panels are Jinko Eagle HC mono-crystalline measuring approximately 2 meters by 1 meter and rated at 400 watts (i.e. maximum output). The total DC output rating of the facility is 213 MW. [2] The facility covers approximately 800 acres within the towns of Two Creeks and Two Rivers, southwest of the nearby Point Beach Nuclear Plant.

Construction for the plant was completed in November 2020 at a cost of $195 million. [3] As part of project application materials, the facility was expected to require three full-time staff once constructed. [4] The facility is eligible for the Federal Solar Investment Tax Credit (ITC). The ITC is normalized over the 30 year life of the project as required by the IRS. [5]

History

Two Creeks Solar, LLC submitted an engineering plan to the Public Services Commission of Wisconsin (PSC) on March 20, 2018, and an application for a Certificate of Public Convenience and Necessity (CPCN) on May 31, 2018. On May 31, 2019, the CPCN application to construct the facility was approved by the PSC. In its approval ruling, the PSC found that the project satisfied the requirements of Wisconsin Statute § 1.12 and 196.025(1), known as the Energy Priorities Law. [2] [6]

A groundbreaking ceremony was held in late August 2019 featuring Governor Tony Evers and senior executives from MG&E, WPS, WEC, and Next Era Energy Resources LCC. At the time, a spokesperson for WPS stated that the Two Creeks plant, along with the Badger Hollow Solar Farm in southwestern Wisconsin, would save $100 million over its lifetime. [7] Construction formally started later in 2019 and by July 2020 half of the panels had been installed. [4] [8] An estimated 300 people were required to construct the facility, mostly in the form of installing support posts and racking the panels. The facility started generating electricity in November 2020. [9]

The PSC approved MG&E and WPS's purchase and acquisition of the solar park from Two Creeks Solar (an entity of NextEra Energy Resources, LCC) for approximately $1,299 per kW for a total project cost of $195 million. The PSC denied MGE and WPS's request for authorization to acquire Two Creeks at a cost of up to 110 percent of the $195 million cost, which would have covered allowance for funds used during construction (AFUDC). [2]

Electricity Production

In 2023 Two Creeks generated 193 GWh, approximately 0.3% of the total electric power generated in Wisconsin (63,216 GWh) for that year. [10] The facility had an approximate annual capacity factor of 14.6% in 2023. A capacity factor of 24% was used during the economic analysis during the transfer of ownership stage. [5]

Generation ( MWh ) Two Creeks Solar Park [11]
YearJanFebMarAprMayJunJulAugSepOctNovDecAnnual (Total)
2020--------------------8,8374,56813,405
20215,50815,42817,51419,01722,33925,73627,08723,88419,2539,8658,0673,120196,818
20227,5839,86115,13615,31223,38025,56326,58323,21017,86214,0157,8763,423186,381
20234,45011,56516,70717,22024,60625,74427,61024,13716,24110,6999,4544,467192,900
20244,84611,800

Repower Cost Analysis

As part of their application to purchase the facility, MG&E and WPS conducted an economic feasibility analysis. The analysis indicated it would cost between $90 million to $180 million (2018 dollars) to repower the facility, that is to replace the existing solar panels with new solar panels. [5] Solar panels experience degradation over time due to ultraviolet light and weather, reducing the efficiency and electrical output of the panel. Repowering aims to increase the output efficiency of a solar facility by replacing some or all of the photovoltaic panels.

Related Research Articles

<span class="mw-page-title-main">Solar Energy Generating Systems</span> Concentrated solar thermal power station in the Mojave Desert of California

Solar Energy Generating Systems (SEGS) is a concentrated solar power plant in California, United States. With the combined capacity from three separate locations at 354 megawatt (MW), it was once the world's second largest solar thermal energy generating facility, until the commissioning of the even larger Ivanpah facility in 2014. It consisted of nine solar power plants in California's Mojave Desert, where insolation is among the best available in the United States.

<span class="mw-page-title-main">Point Beach Nuclear Plant</span> Nuclear power plant in Two Creeks, Wisconsin, U.S.

Point Beach Nuclear Plant is a nuclear power plant located on Lake Michigan in the town of Two Creeks, Wisconsin, United States. The plant was built by Wisconsin Electric Power Company, and previously operated by the Nuclear Management Company. The plant is currently owned and operated by NextEra Energy Resources, of Juno Beach, Florida.

<span class="mw-page-title-main">Nellis Solar Power Plant</span> Solar park in Nevada, US

The Nellis Solar Power Plant is a 14-megawatt (MW) photovoltaic power station located within Nellis Air Force Base in Clark County, Nevada, northeast of Las Vegas. The power plant was inaugurated in a ceremony on December 17, 2007, with Nevada Governor Jim Gibbons activating its full operation. On average, it has since generated 32 gigawatt-hours of electricity annually and supplied more than 25% of the power used at the base.

<span class="mw-page-title-main">Columbia Energy Center</span> Electrical power station in Pacific, Columbia County, Wisconsin

Columbia Energy Center is a base load, sub-bituminous coal-fired, electrical power station located south of Portage in the Town of Pacific, Columbia County, Wisconsin. Ownership is 46.2% Wisconsin Power and Light Company, 31.8% Wisconsin Public Service, and 22% Madison Gas and Electric (MGE).

<span class="mw-page-title-main">Solar power in the United States</span>

Solar power includes solar farms as well as local distributed generation, mostly on rooftops and increasingly from community solar arrays. In 2023, utility-scale solar power generated 164.5 terawatt-hours (TWh), or 3.9% of electricity in the United States. Total solar generation that year, including estimated small-scale photovoltaic generation, was 238 TWh.

<span class="mw-page-title-main">Forward Wind Energy Center</span> Wind farm in Wisconsin, USA

The Forward Wind Energy Center is a 137.85 megawatt (MW) wind farm in Dodge and Fond du Lac County, Wisconsin near the village of Brownsville. The wind farm sits on approximately 4,000 acres of land. "Forward" is the state's motto. The facility is sited in close proximity to the Horicon National Wildlife Refuge and the Horicon Marsh State Wildlife Area which provide nesting areas for waterfowl and a resting area for large numbers of migratory birds.

<span class="mw-page-title-main">Solar power in California</span>

Solar power has been growing rapidly in the U.S. state of California because of high insolation, community support, declining solar costs, and a renewable portfolio standard which requires that 60% of California's electricity come from renewable resources by 2030, with 100% by 2045. Much of this is expected to come from solar power via photovoltaic facilities or concentrated solar power facilities.

<span class="mw-page-title-main">Solar power in Florida</span> Overview of solar power in Florida, United States

Solar power in Florida has been increasing, as the cost of solar power systems using photovoltaics (PV) has decreased in recent years. Florida has low electricity costs compared with other states, which makes individual solar investment less attractive. Florida ranks ninth nationally in solar resource strength according to the National Renewable Energy Laboratory and tenth in solar generation by the Solar Energy Industries Association.

<span class="mw-page-title-main">Badger Hollow Solar Farm</span> Solar photovoltaic energy station

The Badger Hollow Solar Farm is a 300 MW solar photovoltaic energy station currently in construction in Iowa County in southwestern, Wisconsin. Ownership is shared between Wisconsin Public Service Corporation (WPS), Madison Gas and Electric (MG&E), and Wisconsin Electric Power Company, with each utility owning 100 MW. It was the second utility-scale solar plant approved and constructed in Wisconsin.

References

  1. Group, WEC Energy. "WEC Clean Energy". WEC Energy Group. Retrieved 2023-01-08.
  2. 1 2 3 "FINAL DECISION". April 18, 2019. Retrieved 2023-01-08.
  3. Journal, Chris Hubbuch | Wisconsin State. "Wisconsin's first large-scale solar plant enters service; Two Creeks plant to power 33,000 homes". Wisconsin State Journal. Retrieved 2023-01-08.
  4. 1 2 "Two Creeks Solar, LLC Solar CPCN Application Manitowoc and Kewaunee Counties, Wisconsin PSC Docket No. 9696-CE-100". May 31, 2018. Retrieved January 8, 2021.
  5. 1 2 3 "Re: Docket 5-BS-228: Joint Application of Wisconsin Public Service Corporation and Madison Gas and Electric Company for Approval to Acquire Ownership of Solar Generating Facilities". January 8, 2023. May 31, 2018.
  6. "Wisconsin Legislature: 1.12". docs.legis.wisconsin.gov. Retrieved 2023-01-09.
  7. Edquist, Kaitlin. "Wisconsin's first large-scale solar project breaks ground in Two Rivers". Green Bay Press-Gazette. Retrieved 2023-01-08.
  8. "Construction at halfway mark for Wisconsin's first large-scale solar farm". madison.com. Retrieved 2023-01-08.
  9. "Electricity Data Browser". www.eia.gov. Retrieved 2023-01-08.
  10. "Electricity Data Browser". www.eia.gov. Retrieved 2024-05-14.
  11. "Electricity Data Browser". www.eia.gov. Retrieved 2024-05-14.