Vijayawada Metro

Last updated

Vijayawada Metro
Vijaywada Metro Map.png
Overview
OwnerAndhra Pradesh Metro Rail Corporation Limited
Locale Andhra Pradesh Capital Region
Transit type Rapid transit
Website https://amrc.ap.gov.in/vijayawada-metro.php

Vijayawada Metro is a planned rapid transit system for the city of Vijayawada, located in the state of Andhra Pradesh, India. The approved DPR consists of 3 lines with a total length of 74.2 kilometres. [1] [2]

Contents

In December 2024, the Government of India approved the Phase-I of two metro rail projects with an estimated cost of ₹11,498 crore for the Visakhapatnam Metro and ₹11,009 crore for the Vijayawada Metro. [3]

History

Following the bifurcation of Andhra Pradesh in 2014, Andhra Pradesh Chief Minister Chandrababu Naidu announced plans to construct a brand new capital in Amaravati with Vijayawada as its gateway. [4] [5] [6] As part of this plan the government announced its plans to build a metro system in Vijayawada. Initially, the government explored ideas to link Vijaywada to nearby cities such as Tenali and Guntur using the metro system. [7] This idea was later cancelled and it was announced that the metro would stay confined to the city. [8] [9]

The Andhra Pradesh government announced that it had appointed the Delhi Metro Rail Corporation (DMRC) to prepare a Detailed Project Report (DPR) for the city. The DPR submitted by DMRC proposed two routes. [10] [11] The first corridor would run from the Pandit Nehru Bus Station (PNBS) to Penamaluru and the second corridor would run from Pandit Nehru Bus Station (PNBS) to Nidamanuru via Vijayawada Airport. The two corridors were proposed to be fully elevated and totaled to a distance of 26.03 km (16.17 mi) with an estimated cost of 6,823 crore (US$810 million). [12] [13] The project was then submitted to the ministry of urban affairs for approval. Following this, DMRC invited tenders for the construction of the two corridors on 25 September 2015. [14] [15] However, the tenders were later cancelled due to the central governments new Metro Rail policy, which increased the scrutiny regarding ridership and cost projections. [16] [17] Later DMRC ended its MoU with the Amaravati Metro Rail Corporation, which forced the AMRC to explore a PPP alternative to build the metro lines. [18] [19]

Due to the new policy, the government revised the line from a heavy-rail based mass rapid transit system to a Light Rail Transit System. The new plan involved building a 66.2 km (41.1 mi) network with a cost of 15,000 crore (US$1.8 billion). However, unlike the previous plan, the plan would see construction spread across Gannavaram – Vijayawada – Amaravati across three different phases. [20] The revised DPR was then submitted by SYSTRA – RITES – GOPA JV to the government in April 2019. [21] [22]

However, following the 2019 Andhra Pradesh elections, former chief minister, Jagan Mohan Reddy announced he was putting the project on hold. This was part of the government's broader plan to revise its plans of constructing Amaravati as the sole capital of the state. [23] [24] Later in 2020, the government announced that the Amaravati Metro Rail Corporation (AMRC) would be renamed the Andhra Pradesh Metro Rail Corporation (APMRC). [25] [26]

Once again however, following the 2024 Andhra Pradesh election Chief Minister Chandrababu Naidu announced that both the Vijayawada and Visakhapatnam Metro would be back on track. The government approved the new DPRs for Vijayawada and Visakhapatnam. [27] In March 2025, it was announced Systra would be tasked with the responsibility of updating the comprehensive mobility plans (CMP) for Visakhapatnam and Vijayawada metro. [28] Soon the government also announced that the land acquisition for the project would resume after it was put on hold in 2019. [29] [30] The revised CMP was submitted to the state government who approved it later. The state government then forwarded the updated CMP and brand new DPRs to the central government for approval. [31] [32] On 28 July 2025, the Andhra Pradesh Metro Rail Corporation invited bids for the initial civil contract of the Vijayawada Metro Rail Project, worth 4,150 crore (US$490 million). The civil contract concerns the design, construction and engineering of a 4.33 kilometres (2.69 mi) double-decker, four-lane flyover-cum-metro viaduct, one underground metro station, and thirty-two elevated metro stations. The project will be executed on an EPC basis, with an overall completion period of thirty months from the commencement date, with a dedicated period of 24 months comprising the double-decker flyover segment. [33]

Construction

Phase 1 network
CorridorTerminalsStationsDistance (km)Status
1 Pandit Nehru Bus Station Penamaluru1212.50 km (7.77 mi)Approved
2Pandit Nehru Bus StationNidamanuru1325.90 km (16.09 mi)Approved
NidamanuruGannavaram Bus Stand8Approved
Total3338.40 km (23.86 mi)
Phase 2 network
3Pandit Nehru Bus StationAmaravati Reservoir Station1927.80 km (17.27 mi)Proposed
Total1927.80 km (17.27 mi)

Stations

There are 3 corridors currently proposed for the metro system. The first proposed corridor runs from Pandit Nehru Bus Station to Penamaluru has 12 proposed station, all of which are elevated. The second proposed corridor runs from Pandit Nehru Bus Station to Ganavaram Bus Stand and has a total of 22 stations of which 21 are elevated and 1 is underground. The third proposed corridor runs from Pandit Nehru Bus Station to Amaravati Reservoir Station and has a total of 19 stations of which 3 are proposed to be elevated and 16 are underground.

Vijayawada Metro Stations
Corridor123
snoPNBS to Gannavaram Bus StandLayoutPNBS to PenamaluruLayoutPNBS to Amaravati Reservoir StationLayout
1PNBSElevatedPNBSElevatedPNBSElevated
2Railway Station SouthElevatedVictoria Jubilee MuseumElevatedMahanaduElevated
3Railway Station EastElevatedMunicipal StadiumElevatedKrishna Canal JunctionElevated
4Besant RoadElevatedTikkle RoadElevatedPolkampaduUnderground
5Seetharampuram SignalElevatedBenz CircleElevatedUndavalli CentreUnderground
6Machavaram DownElevatedAuto NagarElevatedUndavalliUnderground
7PadavalarevuElevatedAshok NagarElevatedVenkata Palem (East)Underground
8GunadalaElevatedKrishna NagarElevatedVenkata Palem (West)Underground
9Ramavarappadu RingElevatedKanuru CentreElevatedTallaya PalemUnderground
10PrasadampaduElevatedTadigadapaElevatedMandadamUnderground
11MBT CenterElevatedPorankiElevatedUddandrayuni PalemUnderground
12EnikepaduElevatedPenamaluruElevatedLingaya PalemUnderground
13NidamanuruElevatedThe Square StationUnderground
14Nidamanuru Railway StationElevatedCentral Park StationUnderground
15Sri Chaitanya CollegeElevatedCeremonial Space StationUnderground
16GudavaliElevatedAssembly StationUnderground
17VelpuruElevatedFG StationUnderground
18KesarapalleElevatedGH StationUnderground
19AirportUndergroundAmaravati Reservoir StationUnderground
20YogashramElevated
21GannavaramElevated
22Gannavaram Bus StandElevated

See also

References

  1. Raghavendra, V. (30 January 2025). "Vijayawada, Visakhapatnam metrorails: Andhra Pradesh Government gives nod for land acquisition". The Hindu. ISSN   0971-751X . Retrieved 7 February 2025.
  2. "Andhra Metro Rail News: Andhra Pradesh govt approves double-decker metro rail for Vijayawada, Visakhapatnam". Deccan Herald. Retrieved 7 February 2025.
  3. Raghavendra, V. (30 January 2025). "Vijayawada, Visakhapatnam metrorails: Andhra Pradesh Government gives nod for land acquisition". The Hindu. ISSN   0971-751X . Retrieved 21 August 2025.
  4. P. Pavan (7 June 2015). "Naidu performs Bhoomi pooja for AP capital". Bangalore Mirror. Retrieved 14 June 2025.
  5. "PM Modi to lay foundation stone of new Andhra Pradesh capital on October 22". India Today. 30 November 1999. Retrieved 14 June 2025.
  6. "Vijayawada will become Gateway of Amaravati, says Andhra MP Kesineni". The New Indian Express. Express News Service. 25 April 2025. Retrieved 14 June 2025.
  7. "Metro rail project plans gain momentum". The Hindu. 18 June 2014. ISSN   0971-751X . Retrieved 14 June 2025.
  8. "Metro rail will be confined to Vijayawada: Sreedharan". The Times of India. 21 September 2014. ISSN   0971-8257 . Retrieved 14 June 2025.
  9. "Metro rail projects for Vizag, Vijayawada approved". The Hindu. 1 August 2014. ISSN   0971-751X . Retrieved 14 June 2025.
  10. "Govt. wants Amaravati metro integrated with Thullur on priority". The Hindu. 23 November 2015. ISSN   0971-751X . Retrieved 14 June 2025.
  11. "Metro rail authority to tie up with DMRC". The Hindu. 13 May 2016. ISSN   0971-751X . Retrieved 14 June 2025.
  12. "DPR on Vijayawada Metro Rail submitted to Chief Minister". The Hindu. 27 April 2015. ISSN   0971-751X . Retrieved 14 June 2025.
  13. Raj, R. Prithvi (2 April 2015). "Chandrababu Naidu May Clear Vijayawada Metro Rail DPR by April 20". The New Indian Express. Retrieved 14 June 2025.
  14. "Tenders invited for metro rail corridor". The Hindu. 25 September 2015. ISSN   0971-751X . Retrieved 14 June 2025.
  15. "Delhi Metro Rail floats tenders for Vijayawada metro". BusinessLine. 25 September 2015. Retrieved 14 June 2025.
  16. "Vijayawada metro rail project in limbo as DMRC suspends tender process". The Times of India. 1 June 2017. ISSN   0971-8257 . Retrieved 14 June 2025.
  17. Raghavendra, V. (4 June 2017). "Fresh tenders not yet invited for metro corridor". The Hindu. ISSN   0971-751X . Retrieved 14 June 2025.
  18. "Delhi Metro ends MoU with Amaravati Rail". Deccan Chronicle. 16 October 2017. Retrieved 14 June 2025.
  19. "Google Search". Google. Retrieved 14 June 2025.
  20. "A White Paper" (PDF). Department of Municipal Administration& Urban Development. December 2018.
  21. "Systra-RITES JV submits revised DPR of Vijayawada Metro to AMRC". Urban Transport News. Retrieved 14 June 2025.
  22. Shah, Narendra (20 April 2019). "Systra Submit Vijayawada Metro DPR - Metro Rail News". Metrorail News. Retrieved 14 June 2025.
  23. "Concept of 3 capitals to be considered in Andhra Pradesh: Chief Minister YS Jagan Mohan Reddy". India Today. 17 December 2019. Retrieved 14 June 2025.
  24. "Andhra Pradesh to have three capitals, says YS Jaganmohan Reddy". The Times of India. 17 December 2019. ISSN   0971-8257 . Retrieved 14 June 2025.
  25. "Amaravati Metro is now AP Metro Rail". The Times of India. 29 April 2020. ISSN   0971-8257 . Retrieved 14 June 2025.
  26. "Amaravati Metro Rail Corporation rechristened AP Metro Rail Corporation Limited". The New Indian Express. 28 April 2020. Retrieved 14 June 2025.
  27. "Andhra Pradesh govt approves DPR for Vijayawada and Visakhapatnam metro rail projects". The New Indian Express. Express News Service. 3 December 2024. Retrieved 14 June 2025.
  28. Raghavendra, V. (19 March 2025). "Vijayawada and Vizag metro rails: Centre approves appointment of SYSTRA MVA Consulting for preparing mobility plans". The Hindu. ISSN   0971-751X . Retrieved 14 June 2025.
  29. Raghavendra, V. (4 March 2025). "Govt. authorises APMRCL to acquire land for Vizag and Vijayawada metro rail projects". The Hindu. ISSN   0971-751X . Retrieved 14 June 2025.
  30. "Officials to take up land acquistion [sic] for phase-1 of Vijayawada metro". The Times of India. 8 March 2025. ISSN   0971-8257 . Retrieved 14 June 2025.
  31. "విజయవాడ మెట్రో రైలు ప్రాజెక్ట్‌లో మరో ముందడుగు.. CMP పక్రియ పూర్తి, కొత్త బస్టాప్‌లు". Samayam Telugu (in Telugu). Retrieved 14 June 2025.
  32. "Metro rail will transform Vijaywada: NTR District Collector Lakshmisha". The New Indian Express. Express News Service. 14 June 2025. Retrieved 14 June 2025.
  33. "APMRCL Issues Bids For ₹4150 Cr Civil Contract Of Vijayawada Metro Project". Metro Rail News. 28 July 2025. Retrieved 4 August 2025.