Worcester Power Stations

Last updated

The Worcester Power Stations were a series of hydro-electric and coal-fired generating stations providing electricity to the City of Worcester.

Contents

Worcester Power Stations
Worcester Power Stations
CountryEngland
LocationWorcester Worcestershire
Coordinates 52°11′30″N02°13′43″W / 52.19167°N 2.22861°W / 52.19167; -2.22861 Coordinates: 52°11′30″N02°13′43″W / 52.19167°N 2.22861°W / 52.19167; -2.22861
StatusDecommissioned
Construction began1894, 1901, 1943
Commission date 1894, 1902, 1945
Decommission date1930s, 1943, 25 October 1976
Owner(s)Corporation of Worcester
(1894–1948)
British Electricity Authority
(1948–1955)
Central Electricity Authority
(1955–1957)
Central Electricity Generating Board
(1958–1979)
Operator(s)As operator
Thermal power station
Primary fuelCoal
Secondary fuelHydroelectric
Turbine technologySteam turbine
Chimneys1 (1902–43), 3 (1945–76)
Cooling towersNone
Cooling sourceRiver water
Power generation
Units operational4 × 100 kW (hydro), 37.5 MW (steam)
Make and modelBrush, Mordley-Victoria
Units decommissionedAll
Nameplate capacity 400 kW, 37.5 MW
Annual net output 105.309 GWh (1972)

History

There were three electricity generating stations in Worcester. The steam and hydro-electric plant at Powick Mills commissioned in 1894 has a claim to be the first such municipal plant in the world. [1] The two later power stations were conventional steam thermal plants.

Hydro-electricity and steam 1894–1930s

The Corporation of Worcester obtained legal powers under the Worcester Electric Lighting Order (confirmed by the Electric Lighting Orders Confirmation Act 1890) to generate and supply electricity throughout the city. The Corporation opened the Worcester Electricity Works on 11 October 1894 at Powick Mills, south west of the city beside the River Teme (52°10’15"N 2°14’33"W). The buildings had an L-shaped plan and were in orange and yellow brick with a tall brick chimney. [2] The prime movers in the works comprised three Brush compound vertical engines; two ‘Victor’ 54 inch (1.37 m) diameter water turbines producing 211 horsepower (155 kW) from a water head of 12 ft (3.65 m); and a 30 inch (0.76 m) and a 48 inch (1.22 m) water turbine intended for use at times of low water flow. Two of the Brush engines worked in tandem with the water turbines and one was solely steam driven. The engines and water turbines drove four Mordey-Victoria alternators each capable of generating 100 kW, giving a total station output of 400 kW. [3] The Corporation of Worcester charged customers 5d. per kWh for lighting and 3½d. per kWh for motive power.

In 1897 the plant had a generating capacity of 800 kW and the maximum load was 336 kW. A total of 325.13 MWh of electricity was sold to 291 customers and which powered 24,712 lamps, this provided an income to the corporation of £5,948-8-2. [4]

In 1905 the Corporation decided to reconstruct the Powick Mills plant. [5] The water driven plant was effective but the steam driven plant was unused for most of the year and it was decided to scrap the steam plant as obsolete and concentrate all the steam driven plant at the Hylton Road station. [5]

By 1923 there was a single 250 kW water turbine generating an AC supply and a 70 kW water turbine generating a DC supply. [6]

Powick Mills continued to generate electricity into the 1940s although by 1925 it generated less than seven per cent of the city’s electricity demand. [1] In 1946 it generated 529,306 kWh with a load factor of 59.4 per cent. [7] The buildings are extant and have been converted to residential use, they are Grade II* listed. [2]  

Steam station 1902–1943

In 1902, to meet increasing electricity demand, the Corporation of Worcester built a steam driven generating station on Hylton Road. [1] The advantages of generating electricity closer to the City included fewer transmission losses, saving of coal transportation and saving in management and working expenses. [5] The plant included triple expansion engines with a total output capacity of 1200 kW. [5] The power station had a tall brick chimney. [8] Until 1913 the output from the stations was Direct Current. Alternating current equipment was installed in 1913. [9] This comprised a British Thomson-Houston 1500 kW turbo-alternator and associated equipment for a two-phase supply. The capital cost of this equipment was £5431. [9]

In 1923 the plant at Hylton Road comprised two 400 kW reciprocating generators and two 1500 kW turbo generators providing an AC supply. [6] There was a 250 kW and 400 kW reciprocating generators providing DC current. The total evaporative capacity of the boilers at Hylton Road was 78,000 lb/hr (9.83 kg/s). A range of electricity supplies were provided: 3 phase AC 50 Hz, 200 & 440 V; 2 phase AC 50 Hz, 200 V; DC 230 & 460 V; and 500 V DC Traction Current. [6] The amount of electricity sold, and the use, in the period 1921–3 is shown in the table, together with the revenue to the Worcester Corporation. [6]

Electricity use and revenue, 1921-3
Year192119221923
GWhGWhRevenueGWhRevenue
Domestic supply0.5890.742£17,7740.891£18,370
Public lighting0.2020.242£2,2100.249£2,257
Traction0.2810.259£2,3700.284£2,004
Power2.5913.340£22,0944.249£20,422
Total3.6634.584£44,4485.670£43,053

The 1902 station remained in operation until it was demolished in 1943 when a new larger power station was built between 1943 and 1945. [1]

Steam station 1945–1976

To meet the expected post-war increase in demand for electricity [10] the Corporation commissioned a new power station on the existing site at Hylton Road. The 1945 steel-framed station had a stepped elevation of three spaces containing the boilers, turbines and services. [11] There were three short steel chimneys on the boiler house. The open coal store was located north of the power station buildings. Coal was delivered to the site by sidings connected to the Worcester and Hereford line west of the Worcester Viaduct over the River Severn. [12] The boilers of the new station were chain grate stokers and were capable of delivering 450,000 lb/h (56.7 kg/s) of steam at 215 & 400 psi (14.8 & 27.6 bar) and 310 & 427 °C. Steam was fed to the steam turbo-alternators. These comprised: one 3 MW British Thomson-Houston turbo-alternator; one 7.5 MW British Thomson-Houston turbo-alternator; and two 15 MW Parsons turbo-alternators. [13] Steam condensing and cooling was by river water.

Upon nationalisation of the British electricity supply industry in 1948 ownership of the Worcester power station was vested in the British Electricity Authority, later the Central Electricity Authority then to the Central Electricity Generating Board (CEGB). [3] The responsibility for the distribution and sales of electricity was taken over by the Midlands Electricity Board.

The output of the station was: [13] [14] [7]

Worcester power station output (GWh)
Year1946195419551956195719581961196219631967
Output GWh118.359.4162.9066.6265.7736.5861.6737.756.09111.85

By 1972 the installed capacity of the generators was 37.5 MW. In the year ending 31 March 1972 the station delivered 105.309 GWh of electricity, its load factor (the average load as a percent of maximum output capacity) was 33.3 percent. [15] The thermal efficiency of the station (in 1972) was 20.22 per cent.

The Worcester power station closed on 25 October 1976, [16] and was demolished in 1979. [1]

Related Research Articles

Wilford power station was a coal-fired electricity generating station situated on the north bank of the River Trent, at Nottingham in the East Midlands.

Rotherham power station was a coal-fired power station sited close to the centre of Rotherham in South Yorkshire.

Stuart Street Power Station was a coal-fired power station in Bradford, Manchester, England.

Doncaster Power Station

Doncaster Power Station refers to two coal-fired electricity generating stations situated in the centre of Doncaster in South Yorkshire, England. Doncaster A provided electricity to the town from 1900 to 1958, and the B station from 1953 to 1983.

The Norwich power stations were a sequence of electricity generating stations that provided electric power to the City of Norwich and the wider area between 1893 and 1986. The first station in Duke Street began operating in 1893, a new power station at Thorpe was in service from 1926 to 1967, this was supplemented with a 'high pressure' station, 1937–1975, and finally a gas turbine station operated from 1964–1986.

Ribble Power Station was a coal-fired electricity generating station on the River Ribble in Penwortham near Preston, Lancashire, England. The station was built by the Corporation of Preston to replace a small privately-run generating station in the town. It supplied electricity to Preston and the surrounding area from 1923 until 1976. The station was expanded with new equipment in 1943–47 which remained in operation until the power station was closed in 1976 and was subsequently demolished.

Blackburn power stations are a series of electricity generating stations that have provided electric power to the town of Blackburn and the wider area from 1895 to the present. The first station in Jubilee Street, Blackburn began operating in 1895. A new larger station known as Blackburn East or Whitebirk power station was commissioned in 1921 and was rebuilt in stages over the period 1942 to 1955. Whitebirk station closed in 1976. The 60 MW Blackburn Mill Combined Cycle Gas Turbine (CCGT) power station has generated electricity since 2002. The Blackburn energy from waste (EfW) plant is currently (2020) being planned.

Leicester power station

Leicester power stations are a series of electricity generating stations that have provided electric power to the City of Leicester and the wider area from 1894. The first station, located within Aylestone gas works, supplied electricity for street lighting. The city’s new electric tram system was supplied from 1904 by a station at Lero which operated until 1930. A large coal-fired power station was constructed at Freemans Meadow in 1922 and was operational until 1976. Finally a gas turbine power plant was commissioned in 1976.

Stourport power stations were two electricity generating stations that supplied electricity to Stourport-on-Severn Worcestershire and to the wider West Midlands area from 1927 to 1984. The two stations, A (1927–78) and B (1950–84), were collocated on a joint site adjacent to the River Severn south of Stourport-on-Severn.

The Lancaster power stations provided electricity to the Lancashire town and city of Lancaster and the surrounding area from 1894 to 1976. The first power station was built and operated by Lancaster Corporation and started generating electricity in April 1894. The second power station was built during the First World War near the Lune Aqueduct to provide electric power for a munitions factory. When the factory closed after the war the power station was purchased by the corporation to provide electric power throughout its supply area.

Derby power station Former coal-fired power station in England

Derby power station supplied electricity to the town of Derby and the surrounding area from 1893 to 1969. The power station was built and operated by Derby Corporation and started generating electricity in October 1893. It was located in Silkmill Lane in the town centre adjacent to the River Derwent from which it drew its cooling water. The power station was extended in the 1920s and 1940s. It was closed in 1969 and was subsequently demolished.

Huddersfield power station supplied electricity to the town of Huddersfield and the wider area from 1893 to 1981. It was owned and operated by Huddersfield Corporation until the nationalisation of the electricity supply industry in 1948. The power station was redeveloped several times: including the incorporation of new plant in the 1910s, and in the 1930s to 1950s. The station was decommissioned in October 1981.

Lombard Road power station supplied electricity to the Battersea area of South-East London from 1901 to 1972. It was owned and operated by the Borough of Battersea until the nationalisation of the electricity supply industry in 1948. The power station was redeveloped several times: including the incorporation of new plant in the 1910s and the 1930s. The station was decommissioned in 1972.

The Thornhill power station generated and supplied electricity to the town of Dewsbury and the wider regional area from 1902 to 1982, and again from 1998. The first generating station on the site was owned and operated by the Yorkshire Electric Power Company. Following nationalisation of the British electricity supply industry in 1948 Thornhill power station was operated by a succession of state owned bodies. The power station was redeveloped with new plant in 1915, 1925, 1932–37 and 1950–54. The coal-fired steam station was decommissioned in 1982, and was subsequently demolished. A gas turbine power station on the site was commissioned in 1998.

Burton upon Trent power station supplied electricity to the town of Burton upon Trent and the wider area from 1894 to 1976. It was owned and operated by Burton upon Trent Corporation until the nationalisation of the British electricity supply industry in 1948. The power station was redeveloped several times: including the incorporation of new plant in the 1910s, in 1924–28 and 1941–43. The station was decommissioned in October 1976.

Barrow-in-Furness power station supplied electricity to the town of Barrow-in-Furness and the wider area of Lancashire, England from 1899 to about 1960. It was owned and operated by Barrow-in-Furness Corporation until the nationalisation of the UK electricity supply industry in 1948. The power station was redeveloped throughout its operational life. Barrow-in-Furness Corporation also operated Coniston hydro-electric power station.

Salisbury power station supplied electricity to the English city of Salisbury and the surrounding area from 1898 to c. 1970. It was owned and operated by Salisbury Electric Light and Supply Company Limited prior to the nationalisation of the British electricity supply industry in 1948. The power station was redeveloped several times to incorporate new plant to replace retired equipment. The facilities included a water driven turbine.

Wolverhampton power station, also known as Commercial Road power station, supplied electricity to the Borough of Wolverhampton, England and the surrounding area from 1895 to 1976. It was redeveloped in several stages to meet growing demand for electricity: including the addition of new plant in 1902 to 1908, 1925 and 1942. The power station was initially owned and operated by Wolverhampton Corporation, but was transferred to the West Midlands Joint Electricity Authority in 1928. The British Electricity Authority assumed ownership at nationalisation in 1948. Wolverhampton power station was decommissioned in 1976.

Trafford power station supplied electricity to the Trafford and Stretford areas of Greater Manchester, and to the national grid, from 1929 to 1976. The generating station was built by the Stretford and District Electricity Board which it operated until the nationalisation of the British electricity supply industry in 1948. The 60 megawatt coal-fired station was supplemented in 1952 with an experimental 15 megawatt gas turbine generating set.

Luton power station supplied electricity to the Borough of Luton and the surrounding area from 1901 to 1969. The power station was operated by the Luton Corporation until the nationalisation of the British electricity industry in 1948. It was redeveloped after the First World War to meet the increased demand for electricity.

References

  1. 1 2 3 4 5 "When Worcester supplied its own power". Explore the Past. 19 March 2019. Retrieved 17 February 2020.
  2. 1 2 "Former hydro electricity works". Historic England. Retrieved 17 February 2020.
  3. 1 2 The Electricity Council (1987). Electricity Supply in the United Kingdom: a Chronology. London: The Electricity Council. pp. 32, 60. ISBN   085188105X.
  4. Garcke, Emile (1898). Manual of Electrical Undertakings vol. 3. London: P. S. King & son.
  5. 1 2 3 4 "The reconstruction of an electric lighting scheme". The Times. 8 July 1908.
  6. 1 2 3 4 Electricity Commission (1925). Electricity Supply - 1920-1923. London: HMSO. pp. 106–9, 332–7.
  7. 1 2 Electricity Commission, Generation of Electricity in Great Britain year ended 31st December 1946. London: HMSO, 1947.
  8. "Power station Hylton Road". The Changing Face of Worcester. 12 October 2015. Retrieved 17 February 2020.
  9. 1 2 "Worcester Electricity". The Times. 15 January 1913.
  10. Hannah, Leslie (1979). Electricity before Nationalisation. London: Macmillan. pp. 308–10.
  11. "Worcester Bridge and Power Station 1970". The Changing Face of Worcester. 1 January 1970. Retrieved 17 February 2020.
  12. "CEGB Worcester Power Station". Railways in Worcestershire. Retrieved 19 February 2020.
  13. 1 2 Garrett, Fredrick C, ed. (1959). Garcke's Manual of Electricity Supply (vol. 56). London: Electrical Press. pp. A-110, A-139.
  14. GEGB Annual report and accounts, various years
  15. CEGB (1972). CEGB Statistical Yearbook 1972. London: CEGB. p. 13.
  16. "Coal-fired Power Stations (closures 1974-83)". Hansard. 16 January 1984. Retrieved 17 February 2020.