Central Electricity Generating Board

Last updated

Central Electricity Generating Board
Company typeState owned government body and regulator
IndustryEnergy: electricity
Predecessor Central Electricity Authority (1955–1957), British Electricity Authority (1948–1955)
Founded1 January 1958
Defunct9 November 2001
FatePrivatised throughout the 1990s
Successors
HeadquartersLondon, United Kingdom
Area served
England and Wales
ProductsElectricity generation, transmission and bulk sales
Revenue0.4264 p/kWh sold (1957–1958), 3.0371 p/kWh sold (1981–1982)
£340.3 million (1957–1958), £6,363.6 million (1981–1982)
Net earnings £48.3 million (1957–1958), £295.7 million (1981–1982)
Number of employees
65,410 (1972), 55,487 (1982)

The Central Electricity Generating Board (CEGB) was responsible for electricity generation, transmission and bulk sales in England and Wales from 1958 until privatisation of the electricity industry in the 1990s. [1]

Contents

It was established on 1 January 1958 to assume the functions of the Central Electricity Authority (1955–1957), which had in turn replaced the British Electricity Authority (1948–1955). The Electricity Council was also established in January 1958, as the coordinating and policy-making body for the British electricity supply industry.

Responsibilities

The CEGB was responsible for electricity generation, transmission and bulk sales in England and Wales, whilst in Scotland electricity generation was carried out by the South of Scotland Electricity Board and the North of Scotland Hydro-Electric Board.

The CEGB's duty was to develop and maintain an efficient, coordinated and economical system of supply of electricity in bulk for England and Wales, and for that purpose to generate or acquire supplies of electricity and to provide bulk supplies of electricity for the area electricity boards for distribution. It also had power to supply bulk electricity to the Scottish boards or electricity undertakings outside Great Britain.

The organisation was unusual in that most of its senior staff were professional engineers, supported in financial and risk-management areas. [2]

Corporate structure

Background

In 1954, six years after nationalisation, the Government appointed the Herbert Committee to examine the efficiency and organisation of the electricity industry. The committee found that the British Electricity Authority's dual roles of electricity generation and supervision had led to central concentration of responsibility and to duplication between headquarters and divisional staff which led to delays in the commissioning of new stations. The Committee's recommendations were enacted by the Electricity Act 1957 which established the Electricity Council to oversee the industry and the CEGB with responsibility for generation and transmission. [3]

Constitution

Power in Trust (1961) by Norman Sillman, at Staythorpe Power Station Power In Trust sculpture (geograph 4882572).jpg
Power in Trust (1961) by Norman Sillman, at Staythorpe Power Station

The CEGB was established by section 2 of the Electricity Act 1957. [4] It consisted of a Generating Board comprising a chairman and seven to nine full-time or part-time members, appointed by the Minister of Power, who had experience or capacity in "the generation or supply of electricity, industrial, commercial or financial matters, applied science, administration, or the organisation of workers". The power of appointment later devolved to the Minister of Technology, then to the Secretary of State for Trade and Industry.

There were six chairmen of the CEGB:

The executive comprised the chairman and the full-time board members. The Headquarters Operations Department provided a service to the board and executive and could supply specialist staff. [2]

The chairman and two other members of the board plus the chairmen of the area boards were members of the Electricity Council. [2]

Organisation

The design, construction and development functions associated with power stations and transmission was undertaken by two divisions: the Generation Development and Construction Division based in Cheltenham and then Barnwood Gloucester, and the Transmission Development and Construction Division based in Guildford. [2] In 1979 the Transmission Division had been restructured as the Transmission and Technical Services Division based in Guildford, and a Technology Planning and Research Division based in London, the latter was formed from the Research Division System Technical and Generation Studies Branches. [6] [7]

A Corporate Strategy Department was formed in 1981 from some of the Planning Department. A Nuclear Operations Support Group was also formed in 1981 to provide expert support. [7]

The sculpture "Power in Trust" from the CEGB logo was made by Norman Sillman to represent a hand made from boiler pipes and a turbine, it was commissioned in the 1961 for the opening of Staythorpe B Power Station. [8]

When first constituted the CEGB's London headquarters was at the former Central Electricity Authority's building in Winsley Street W1, there were also offices in Buchanan House, 24/30 Holborn, London, EC1. [9]

Employees

There were a total of 131,178 employees in the electricity supply industry 1989, composed as follows: [10]

Electricity supply industry employees 1989
Electricity CouncilCEGBArea boardsTotal
Managerial1227805351,437
Technical and scientific44413,0988,47322,015
Administrative and Sales5667,14230,14637,854
Industrial12526,61141,14267,878
Trainees and apprentices0In Industrial1,9851,985
Total1,25747,63182,291131,178

Infrastructure

The CEGB spent more on industrial construction than any other organisation in the UK. In 1958 about 40 power stations were being planned or constructed at a capital cost of £800 million. [3]

Power stations

Those public supply power stations that were in operation at any time between 1958 and 1990 were owned and operated by the CEGB. In 1971–1972 there were 183 power stations on 156 sites, with an installed capacity of 58,880.051 MW, and supplied 190,525 GWh. [2] By 1981–1982 there were 108 power stations with a capacity of 55,185 MW and supplied 210,289 GWh. [6]

National Grid

At its inception the CEGB operated 2,763 circuit km of high-tension 275 kV supergrid. The growth of the high voltage National Grid over the lifetime of the CEGB is demonstrated in the following table. [3]

Length in circuit km of 275 kV and 400 kV transmission system
Year1958196319681973197819831988
275 kV, km2,7635,9235,4034,4714,4424,3034,069
400 kV, km0854,9277,9059,3199,5319,822

Substations

In 1981–2 there was a total of 203 substations operating at 275/400 kV, these sub-stations included 570 transformers operating at 275/400 kV. [6]

Operations

Control of generation and the National Grid

At the centre of operations was the National Control Centre of the National Grid in London, which was part of the control hierarchy for the system. The National Control Centre was based in Bankside House from 1962. [7] There were also both area and district Grid Control Areas, which were originally at Newcastle upon Tyne, Leeds, Manchester, Nottingham, Birmingham, St Albans, East Grinstead and Bristol. The shift control engineers who worked in these control centres would cost, schedule and load-dispatch an economic commitment of generation to the main interconnected system (the 400/275/132kV network) at an adequate level of security. They also had information about the running costs and availability of every power producing plant in England and Wales. They constantly anticipated demand, monitored and instructed power stations to increase, reduce or stop electricity production. They used the "merit order", a ranking of each generator in power stations based upon how much they cost to produce electricity. The objective was to ensure that electricity production and transmission was achieved at the lowest possible cost.

In 1981 the three-tier corporate transmission structure: National Control, area control rooms in the regions, and district control rooms (areas) was changed to a two-tier structure by merging the area and district control rooms. [7]

Electricity supplies and sales

The electricity generated, supplied and sold by the CEGB, in GWh, was as follows: [10]

CEGB electricity supplies and sales
Numbers in GWhYear
1958/91963/41968/91973/41978/91983/41988/9
Electricity generated91,753141,655187,064217,542238,148229,379250,699
Electricity supplied86,233132,091173,418201,763222,091212,728231,909
Imports5002,0162,9913,5213,2535,21416,416
Exports5981,0542,0465517361763
Total supplies on system86,135133,053174,363204,733224,608217,766248,322
Used in transmission2,1743,7195,2164,1034,9615,2005,619
Sales to direct customers3,0251,8903,0054,9375,6683,9444,260
Sales to area boards80,936127,444166,142195,688213,979208,623238,443
Generated by area boards1456642106
Purchases by area boards from private sources3811382103343745712,010
Used in distribution6,2457,9509,09311,41014,77813,66614,338
Sales by area boards75,073119,634157,264184,618199,581195,570226,221

Note: imports are bulk supplies from the South of Scotland and France and from private sources, exports are bulk supplies to the South of Scotland and France.

Financial statistics

A summary of the income and expenditure of the CEGB (in £ million) is as follows: [10] [11]

CEGB financial summary
Numbers in £ millionYear
1958/91963/41968/91973/41978/91983/41988/9
Income from electricity sales505.8821.51,278.41,783.55,093.09,026.311,467.8
Other income14.120.325.422.830.4535.7906.0
Total income519.9841.81,303.81,806.35,123.49,562.012,373.8
Expenditure429.6657.5980.81,652.94,448.2
Operating Profit90.3184.3323.8153.4675.2917.7777.2
Interest62.5113.9222.4339.0423.8450.3159.3
Profit after interest27.370.4100.6-185.6251.4464.1607.2
Revenue account expenditure
Fuel284.1384.7707.72,379.44,008.44,268.5
Salaries143.3200.9313.4750.11,454.41,992.0
Depreciation138.3250.9328.0582.21,295.11,765.0
Interest113.922.4339.0423.8450.3159.3
Rates24.138.164.2167.5322.5496.0
Other costs67.7106.2246.6568.91,563.92,715.0
Total costs71.41,203.21,991.94,871.99,097.911,766.6
Capital expenditure
Generation142.3229.9207.6222.2433.4766.1431.8
Main transmission30.877.1118.033.761.6150.976.2
Other0.93.14.210.819.421.896.6
Total CEGB174.0310.1329.8266.7514.4938.8604.6
Area boards83.4159.1139.1140.9198.1393.5854.5
Total capital expenditure257.4469.5469.3408.2714.71,605.21,471.8

Regions

Detailed control of operational matters such planning, electricity generation, transmission and maintenance were delegated to five geographical regions. From January 1971 each region had a director-general, a director of generation, a director of operational planning, a director of transmission, a financial controller, a controller of scientific services and a personnel manager. [2]

Midlands Region

Regional headquarters: Haslucks Green Road, Shirley, Solihull, West Midlands.

The Midlands Region was responsible for the operation of 38 power stations, over 170 sub-stations and nearly 2,000 miles of grid transmission line in an area that covered 11,000 square miles. The region produced more than a quarter of the electricity used in England and Wales and had a major share of the industrial construction programme mounted by the CEGB during the 1960s.

In 1948 the total generating capacity of all the power stations in the region was 2,016 MW only a little more than a modern 2,000 MW station. By 1957 the region's capacity was up to 4,000 MW, doubling to 8,000 MW by 1966 and rising to 14,000 MW in 1969 and 16,000 MW by 1971.

Previous chairmen of the Midlands Region were Arthur Hawkins, Gilbert Blackman, and R. L. Batley. [12] [13]

Prior to 1968 the Midlands Region was divided into the West Midlands Division and the East Midlands Division. The number of power stations, installed capacity and electricity supplied in the Midlands Region was: [2] [6]

Midlands Region
YearNo. of power stationsNo. of sitesInstalled capacity of generators, MWElectricity supplied, GWh
1971–1972362616,256.054,509.849
1980–1981261915,619.070,586.354
1981–1982221714,655.571,455.615

North Eastern Region

Regional Headquarters: Merrion Centre, Leeds (1971). Beckwith Knowle, Otley Road, Harrogate.

Extending through Northumberland, Durham, Yorkshire and North Lincolnshire the North Eastern Region was responsible for the operation of 32 power stations capable of producing 8,000 MW of electricity. 108 substations and over 1,200 route miles of overhead lines transmitted the electricity to the Yorkshire Electricity Board and the North Eastern Electricity Board for passing onto the customer.

A previous chairman of the North Eastern Region was P.J. Squire. [13]

Prior to 1968 the North Eastern Region was divided into the Northern Division and the Yorkshire Division.The number of power stations, installed capacity and electricity supplied in the North Eastern Region was: [2] [6]

North Eastern Region
YearNo. of power stationsNo. of sitesInstalled capacity of generators, MWElectricity supplied, GWh
1971–1972302611,568.541,380.793
1981–1982181511,702.050,020.604

North Western Region

Regional Headquarters: 825 Wilmslow Road, Manchester, M20 (1971). Europa House, Bird Hall Lane, Cheadle Heath, Stockport.

Previous chairman of the North Western Region were J.L. Ashworth and G.B. Jackson. [13]

The number of power stations, installed capacity and electricity supplied in the North Western Region was: [2] [6]

North Western Region
YearNo. of power stationsNo. of sitesInstalled capacity of generators, MWElectricity supplied, GWh
1971–197237367,248.66219,859.890
1981–198219196,532.22526,007.229

South Eastern Region

Regional Headquarters: Bankside House, Summer Street, London.

Past chairman of the South Eastern Region were G.N. Stone, H.J. Bennett and F.W. Skelcher. [14] [13]

Prior to 1968 the South Eastern Region was divided into the North Thames Division and the South Thames Division. The number of power stations, installed capacity and electricity supplied in the South Eastern Region was: [2] [6]

South Eastern Region
YearNo. of power stationsNo. of sitesInstalled capacity of generators, MWElectricity supplied, GWh
1963–196473599,957.17130,355.353
1971–1972463713,114.80442,005.335
1980–1981353312,556.90422,764.492
1981–1982282812,758.40423,637.504
1983–1984202010,628.26,519.474

South Western Region

Regional Headquarters: 15–23 Oakfield Grove, Clifton, Bristol (1971). Bedminster Down, Bridgwater Road, Bristol.

Previous chairman of the South Western Region were Douglas Pask, Roy Beatt, A.C. Thirtle and R.H. Coates. [14]

Prior to 1968 the South Western Region was divided into the Southern Division, the Western Division and the South Wales Division. The number of power stations, installed capacity and electricity supplied in the South Western Region was: [2] [6]

South Western Region
YearNo. of power stationsNo. of sitesInstalled capacity of generators, MWElectricity supplied, GWh
1971–1972343110,692.08532,769.175
1980–1981222013,423.45040,925.009
1981–1982211912,988.95039,167.919
1983–1984181610,83938,956.301

Supplies to area boards

The supplies of electricity from the CEGB Regions to the area electricity boards in 1971–2 and 1981–2 were as follows. [6] [2] The average charge in 1971–2 was 0.6519 pence/kWh, in 1981–2 the charge was 3.0615 pence/kWh.

Electricity supplies to area boards
Area boardElectricity sold 1971–1972, GWhElectricity sold 1981–1982, GWh
London 14,47216,173
South Eastern 12,58614,730
Southern 17,74421,073
South Western 9,03010,817
Eastern 20,46923,661
East Midlands 16,43918,596
Midlands 19,58720,209
South Wales 9,63810,470
Merseyside and North Wales 13,67214,783
Yorkshire 19,64021,420
North Eastern 11,29613,272
North Western 18,61418,988
Total183,187204,192

During the lifetime of the CEGB peak demand had more than doubled from 19,311 MW in 1958 to 47,925 MW in 1987. Sales of electricity had increased from 79.7 TWh in 1958 to 240 TWh in 1988. [3]

Research and development

The CEGB had an extensive R&D section with its three principal laboratories at Leatherhead (Central Electricity Research Laboratories, CERL) (opened by the Minister of Power in May 1962), [7] Marchwood Engineering Laboratory (MEL), and Berkeley Nuclear Laboratories (BNL). There were also five regional facilities and four project groups, North, South, Midlands and the Transmission Project Group. These scientific service departments (SSD) had a base in each region. A major SSD role was solving engineering problems with the several designs of 500 MW units. These were a significant increase in unit size and had many teething problems, most of which were solved to result in reliable service and gave good experience towards the design of the 660 MW units.

In the 1970s and 1980s, for the real-time control of power stations the R&D team developed the Cutlass programming language and application system. After privatisation, CUTLASS systems in National Power were phased out and replaced largely with Advanced Plant Management System (APMS) – a SCADA solution developed in partnership by RWE npower (a descendant company of CEGB) and Thales UK. [15] APMS itself has since become obsolete. However, Eggborough was the last station, particularly unit 2; fully operated using APMS until its decommissioning in 2017.

In contrast, PowerGen, later taken over by E.ON (which further split to form Uniper), undertook a programme to port the entire system to current hardware. The most current version of Cutlass, 'PT-Cutlass Kit 9', runs on Motorola PPC-based hardware, with the engineering workstation and administrative functions provided by a standard Microsoft Windows PC. It is fully compatible (with a few minor exceptions) with the DEC PDP-11 version (kit 1) released by PowerGen and has a high level of compatibility with the final version of kit 1 formerly used at National Power. [16] It is used at three UK power stations: Ratcliffe-on-Soar, Cottam, and Fiddlers Ferry.

Policies and strategies

The CEGB was subject to examination from external bodies and formed policies and strategies to meet its responsibilities.

External

A 1978 government white paper Re-organisation of the Electricity Supply in England and Wales proposed the creation of an Electricity Corporation to unify the fragmented structure of the industry. Parliamentary constraints prevented its enactment. [7]

A report by the Monopolies and Mergers Commission, Central Electricity Generating Board: a Report on the Operation by the Board of its system for the generation and supply of Electricity in bulk was published in 1981. The report found that the CEGB's operations were efficient but that their investment appraisal operated against the public interest. [7]

Internal

In 1964 the CEGB chose the Advanced Gas-cooled Reactor, developed by the United Kingdom Atomic Energy Authority, for a programme of new station construction. The five stations were: Dungeness B, Hinkley Point B, Hartlepool, Heysham and Hunterston B. [7]

In 1976 the CEGB introduced an accelerated power station closure programme. On 25 October 23 power stations were closed and 18 partly closed, with a combined capacity of 2,884 MW. Six further stations with a capacity of 649 MW were closed in March 1977. [7] [17]

In 1979 the CEGB and the National Coal Board entered a joint understanding that the CEGB would endeavour to take 75 million tonnes of coal per year to 1985 provided the pithead price did not increase above the rate of inflation. [7]

In 1981 the CEGB applied for planning consent to build a 1,200 MW pressurized water reactor at Sizewell. There was a lengthy public inquiry. [7]

In 1981 the CEGB introduced another accelerated power station closure programme. On 26 October 16 power stations were closed with a combined capacity of 3,402 MW. A further 1,320 MW of capacity was maintained unmanned in reserve. [7] [17]

Privatisation

The electricity market in the UK was built upon the break-up of the CEGB into four companies in the 1990s. Its generation (or upstream) activities were transferred to three generating companies, 'PowerGen', 'National Power', and 'Nuclear Electric' (later 'British Energy', eventually 'EDF Energy'); and its transmission (or downstream) activities to the 'National Grid Company'. [18] [19]

The shares in National Grid were distributed to the regional electricity companies prior to their own privatisation in 1990. PowerGen and National Power were privatised in 1991, with 60% stakes in each company sold to investors, the remaining 40% being held by the UK government. The privatisation process was initially delayed as it was concluded that the 'earlier decided nuclear power plant assets in National Power' would not be included in the private National Power. A new company was formed, Nuclear Electric, which would eventually own and operate the nuclear power assets, and the nuclear power stations were held in public ownership for a number of years. [20]

In 1995, the government sold its 40% stakes, and the assets of Nuclear Electric and Scottish Nuclear were both combined and split. The combination process merged operations of UK's eight most advanced nuclear plants – seven Advanced Gas Cooled Reactor (AGR) and one Pressurised Water Reactor (PWR) – into a new private company founded in 1996, 'British Energy' (now 'EDF Energy'). [21] [22] The splitting process created a separate company in 1996 called 'Magnox Electric' to hold the older Magnox reactors, later combined with BNFL.

Although electricity privatisation began in 1990, the CEGB continued to exist until the Central Electricity Generating Board (Dissolution) Order 2001, a statutory instrument, came into force on 9 November 2001. [23]

Powergen is now E.ON UK, owned by the German utility company E.ON, who then further split to form Uniper, who own the majority of the former E.On conventional power generation. National Power split into a UK business, 'Innogy', now 'RWE npower', owned by the German utility company RWE, and an international business, 'International Power', now Engie Energy International and owned by the French company Engie.

Arms

Coat of arms of Central Electricity Generating Board
Central Electricity Generating Board Escutcheon.png
Notes
Granted 6 November 1958 [24]
Crest
On a wreath Or Gules and Sable a male griffin segreant Gules armed langued and rayed Or behind the head a sun in splendour Gold.
Escutcheon
Paly gules and Or two bars dancetty the upper per pale Sable and Argent the lower per pale Argent and Sable.
Supporters
On the dexter side a lion guardant Or winged Gules and on the sinister side a dragon Gules winged Or.
Motto
Power In Trust

Publications

See also

Related Research Articles

<span class="mw-page-title-main">Christopher Hinton, Baron Hinton of Bankside</span> British nuclear engineer (1901–1983)

Christopher Hinton, Baron Hinton of Bankside was a British nuclear engineer, and supervisor of the construction of Calder Hall, the world's first large-scale commercial nuclear power station.

<span class="mw-page-title-main">National Power</span>

National Power was an energy company based in the United Kingdom.

Public electricity suppliers (PES) were the fourteen electricity companies created in Great Britain when the electricity market in the United Kingdom was privatised following the Electricity Act 1989. The Utilities Act 2000 subsequently split these companies between distribution network operators and separate supply companies.

Wilford power station was a coal-fired electricity generating station situated on the north bank of the River Trent, at Nottingham in the East Midlands.

<span class="mw-page-title-main">Aberthaw power stations</span> Two decommissioned power stations in Wales

Aberthaw Power Station refers to two decommissioned coal-fired and co-fired biomass power stations on the coast of South Wales, near Barry in the Vale of Glamorgan. They were located at Limpert Bay, near the villages of Gileston and West Aberthaw. The most recent power station on the site, Aberthaw B Power Station, co-fired biomass and as of 2008 had a generating capacity of 1,560 megawatts (MW). The power station closed on 31 March 2020.

Nuclear Electric was a nuclear power generation company in the United Kingdom. It was formed in 1990 as part of the privatisation process of the UK Electricity Supply Industry.

<span class="mw-page-title-main">Cwm Dyli</span> Dam in Cwm Dyli, Wales

Cwm Dyli is the location of a hydro-electric power station on the southern flank of the Snowdon range in North Wales. At the time it was built, it was the largest hydro-electric power station in the United Kingdom. It is Britain's oldest power station, and is believed to be one of the oldest Grid-connected hydro-electric stations in the world.

<span class="mw-page-title-main">Portishead power station</span> Series of two coal and oil-fired power stations

Portishead Power Station refers to a series of two coal and oil-fired power stations which operated in the dock area of Portishead in Somerset, South West England, between 1929 and 1982.

<span class="mw-page-title-main">Littlebrook Power Station</span> Series of four oil and coal-fired power stations in Dartford, Kent

The Littlebrook Power Station were a series of four oil and coal-fired power stations situated on the south bank of the River Thames, next to the Queen Elizabeth 2 Bridge and the Dartford Tunnel in Dartford, Kent. The final power station, Littlebrook D, ceased operating in March 2015, and has now been demolished.

<span class="mw-page-title-main">Little Barford Power Station</span>

Little Barford Power Station is a gas-fired power station just north of the village of Little Barford in Bedfordshire, England. It lies just south of the A428 St Neots bypass and east of the Wyboston Leisure Park. The River Great Ouse runs alongside. It was formerly the site of two coal-fired power stations, now demolished. The station is operated by RWE.

<span class="mw-page-title-main">Staythorpe Power Station</span> Gas-fired power station in Nottinghamshire, England

Staythorpe C Power Station is a 1,735 MWe gas-fired power station at Staythorpe between Southwell and Newark-on-Trent in Nottinghamshire, England, between the River Trent and Nottingham to Lincoln railway line. The station was handed over to the owner RWE from Alstom Power with full commercial operation being achieved in December 2010. The official opening ceremony attended by Charles Hendry, Minister of State took place on 9 May 2011.

<span class="mw-page-title-main">Tilbury power stations</span> Thermal power stations in Essex, England

The Tilbury power stations were two thermal power stations on the north bank of the River Thames at Tilbury in Essex. The 360 MW dual coal- and oil-fired Tilbury A Power Station operated from 1956 until 1981 when it was mothballed, prior to demolition in 1999. The 1,428 MW Tilbury B Power Station operated between 1968 and 2013 and was fueled by coal, as well as co-firing with oil and, from 2011, biomass. Tilbury B was demolished in 2016–19. Since 2013 three other power stations have been proposed or constructed in Tilbury.

<span class="mw-page-title-main">North Tees Power Station</span>

North Tees Power Station refers to a series of three coal-fired power stations on the River Tees at Billingham in County Durham. Overall, they operated from 1921 until 1983, and the C station, the last on the site, was demolished in 1987. Billingham Biomass Power Station is to be built on their site.

Birchills power station and Walsall power station are a series of three coal-fired power stations in, or near, Walsall in the West Midlands, England.

<span class="mw-page-title-main">Ince Power Station</span> Two demolished power stations in England

Ince Power Station refers to two demolished power stations near Ellesmere Port in Cheshire, North West England.

<span class="mw-page-title-main">Doncaster Power Station</span>

Doncaster Power Station refers to two coal-fired electricity generating stations situated in the centre of Doncaster in South Yorkshire, England. Doncaster A provided electricity to the town from 1900 to 1958, and the B station from 1953 to 1983.

<span class="mw-page-title-main">Darlington Power Station</span> British coal-fired power station

Darlington power station refers to a series of two coal-fired power stations situated in Darlington in County Durham, North East England.

Meaford Power Station was a coal-fired power station situated on the River Trent at Meaford near Stone in Staffordshire.

<span class="mw-page-title-main">Skelton Grange power station</span>

Skelton Grange Power Station refers to two now-demolished coal fired power stations that served the city of Leeds and surrounding areas. They were located in the Stourton area of the city. The power stations were built in the early 1950s and early 1960s, taken out of use in 1983 and 1994 and subsequently dismantled but the associated 275 kV switching substation was retained and remains in use.

Maentwrog power station was built by the North Wales Power Company and supplied electricity to North Wales, Deeside and Cheshire. It exploits the water resources of the Snowdonia mountains, using water turbines to drive electricity alternators. The 24 MW station has been owned by several organisations; since 2004 it has been owned by the Nuclear Decommissioning Authority. It generates an annual electricity output of 60.6 GWh.

References

  1. The CEGB Story Archived 9 December 2012 at archive.today by Rob Cochrane (with additional research by Maryanna Schaefer) (1990)
  2. 1 2 3 4 5 6 7 8 9 10 11 12 CEGB (1972). CEGB Statistical Yearbook 1972. London: CEGB. pp. 2–3, 31.
  3. 1 2 3 4 Sheail, John (1991). Power in Trust: The Environmental History of the Central Electricity Generating Board. Oxford: Oxford Scientific. pp. 101, 104, 117, 280. ISBN   0198546734.
  4. "Electricity Act 1957". www.legislation.gov.uk.
  5. Cochrane, Robert (30 March 1990). "The CEGB Story" (PDF): 34. Retrieved 1 February 2019.{{cite journal}}: Cite journal requires |journal= (help)
  6. 1 2 3 4 5 6 7 8 9 CEGB (1982). CEGB Statistical Yearbook 1981-2. London: CEGB. pp. 20, 17. ISBN   0902543695.
  7. 1 2 3 4 5 6 7 8 9 10 11 12 The Electricity Council (1987). Electricity Supply in the United Kingdom: a Chronology. London: The Engineering Council. pp. 88, 120, 126, 131, 132, 137, 142. ISBN   085188105X.
  8. "RWE npower – who we are" (PDF). npower . Retrieved 18 February 2020.
  9. Trade Directory Greater London (1959)
  10. 1 2 3 Electricity Council (1989). Handbook of Electricity Supply Statistics 1989. London: Electricity Council. pp. 20–21, 33, 36–7, 42–3, 98–9. ISBN   085188122X.
  11. Electricity Council (1979). Handbook of Electricity Supply Statistics 1979. London: Electricity Council. pp. 35, 38–40, 50–1. ISBN   0851880762.
  12. Gilbert, Blackman. "The London Gazette" (PDF). The Gazette. Retrieved 15 June 2018.
  13. 1 2 3 4 CEGB Publicity Brochure dated March 1964 and January 1967
  14. 1 2 Ledger, Frank (8 September 2017). Crisis Management in the Power Industry: An Inside Story. Routledge. ISBN   978-1351394291 . Retrieved 15 June 2018.
  15. Farewell to CUTLASS Archived 5 May 2013 at archive.today
  16. http://esolangs.org/wiki/CUTLASS CUTLASS on Esolangs.org
  17. 1 2 "Coal-fired Power Station Closures". Hansard. Retrieved 20 February 2020.
  18. Page 68 "Lessons from Liberalised Electricity Markets" IEA / OECD (2005)
  19. "Funding Universe – History of BNFL" . Retrieved 11 July 2012.
  20. "International Power PLC History" . Retrieved 11 July 2012.
  21. "EDF agrees to pay $23 billion for British Energy". The New York Times. 24 September 2008. Retrieved 11 July 2012.
  22. "The sale of the Government's interest in British Energy" . Retrieved 11 July 2012.
  23. The Central Electricity Generating Board (Dissolution) Order 2001 full text
  24. "Central Electricity Generating Board". Heraldry of the World. Retrieved 5 February 2021.