AQUIND Interconnector [1] | |
---|---|
Location | |
Country | France, United Kingdom |
General direction | North-south |
From | Le Havre, France |
Passes through | English Channel |
To | Portsmouth, England |
Construction information | |
Construction started | Refused permission by UK Government January 2022 [2] |
Technical information | |
Type | Submarine cable |
Type of current | HVDC |
Power rating | 2000 MW |
DC voltage | 320kV |
The AQUIND Interconnector is a proposed HVDC submarine power cable proposed to link France and England. [1] [3] [4]
Independent research carried out in Portsmouth by Savanta indicates significant public support for the project [5]
Strong public support for the project was reported in a number of Energy industry publications in 2024. [6] [7] [8]
The project has faced local opposition and attracted controversy due to claims regarding its environmental impact and links between the company's backers and the Conservative Party. [9] [10]
A decision on the project is currently awaited from the Secretary of State for Energy Security and Net Zero. Under the previous Government, the project was refused by then Business Secretary, Kwasi Kwarteng in January 2022. This decision was subsequently overturned by judicial review in the High Court and a new decision is currently awaited from the UK Government.
The cable is proposed to run between the Lovedean substation in Hampshire in England to the Barnabos substation in the Normandy region of France. [1] [3] Landfall is proposed at Eastney in Portsmouth (UK), and Pourville in Seine-Maritime (France) [11] . The route is 242 km (150 miles) long, with 187 km (116 miles) under the sea, 25 km (16 miles) on land in the UK and 30 km (19 miles) on land in France. [1]
The HVDC link would consist of four main cables, together with two much thinner fibre optic cables for operational control and communications. [1] HVDC involves lower transmission losses than the conventional alternating current (AC) technology used in most existing electricity networks. Land cables would be laid mainly under existing roads to minimize the environmental impact of the development.
The link was to be built as two separate 1,000 MW circuits, each with its own control and protection systems and auxiliary power supplies. [3] The DC circuits would run at 320 kV, and operate as symmetrical monopoles. [1] The project is expected to cost £1.1 billion. [1]
Campaigners and local MPs have urged the cancellation of the project. [12] [13] The Portsmouth South MP Stephen Morgan claims that the cable and its associated data connections pose a risk to UK national security. [14] The Guardian newspaper reported that the promoters of the project, Viktor Fedotov and Alexander Temerko, are both substantial donors to the Conservative party and MPs, and that "Three Conservative ministers have already had to recuse themselves from the decision-making process over the Aquind undersea cable because of their links to the company." Almost 10% of MPs have received donations from companies linked to Fedotov. [15] The minister and peer Martin Callanan was a former director of Aquind and another peer, James Wharton is a consultant to the company. [16]
In October 2021, AQUIND vehemently denied any wrongdoing, and stated that it would "not stand silently and accept slander based on xenophobia and the principles of guilt by association." The company stated that it was considering taking legal action against the media involved. [17]
After the development had been refused in January 2022, Temerko described Minister of State for Trade Policy Penny Mordaunt, who had represented constituents' concerns with the development, as an "absolutely uncontrollable woman" and a "threat to national security". Mordaunt subsequently said the Conservative Party’s code of conduct should apply to all members, including donors, and suggested that party colleagues should not accept funds from Temerko. Aquind and Temerko had donated £1.1 million to the Conservative Party, including to 21 MPs and ministers. [18] [19]
In spite of attracting criticism from some political figures - independent research reported in a number of Energy industry publications in 2024 indicates strong public support for the project locally. Despite the potential electric energy savings being a negligible £3.15 a year. [6] [7] [8]
When the project was announced in June 2016, the company said that the project would come online in 2021. [20]
In July 2019, Portsmouth Council formally objected to the plans, on the grounds that they would cause unacceptable disruption in a built-up area. [21] Between February and April 2019, the company undertook a statutory consultation exercise. [22] In November 2019, Aquind submitted a formal planning application for the link in the UK. [23]
In June 2020, Aquind submitted to Ofgem and the Commission de Régulation de l'Energie (CRE) a request for partial exemption from Articles 19(2) and 19(3) of Regulation (EU) 2019/943 concerning Use of Revenues obligations, for a period of 25 years from the start of commercial operations. In December 2020, Ofgem and CRE published a joint consultation document; this consultation was intended to close on 29 January 2021. In January 2021, the CRE and Ofgem announced that they had discontinued a public consultation for the AQUIND Interconnector, as this exemption request process is only available to interconnector projects developed between EU member states, the UK ceased to be a member state and the Brexit transition period had ended. [24]
In October 2020, there was a protest against the project in Portsmouth. [25]
In November 2020, Aquind won an appeal in the General Court of the European Union against the Agency for the Cooperation of Energy Regulators' (ACER) decision to reject an application for exemption pursuant to Article 17 of Regulation (EC) No 714/2009. [26]
On 26 January 2021, the French authorities in Normandy refused to give the project the green light. [27]
In March 2021, the examination by Portsmouth City Council closed. [28]
In May 2021, there was another protest in Portsmouth. The Conservative MP for Portsmouth North, Penny Mordaunt, called the proposals "sinister". The Labour MP for Portsmouth South, Stephen Morgan, also voiced his opposition. [29] The following month, Mordaunt handed in a petition against the project. Another protest was planned for July 2021. [30]
A final decision by the British government on whether to permit construction was postponed several times. On 21 October 2021, the business secretary Kwasi Kwarteng set a new deadline of 21 January 2022 for deciding on the planning application. [31] [32]
After the decision in January 2021 by the French regional government in Normandy to refuse permission, [27] the company stated that this "does not prevent AQUIND from securing the relevant French planning consents required to construct and operate AQUIND Interconnector". [33]
In October 2021, after growing criticism, the company vowed to "continue the development of the AQUIND Interconnector project". [17]
On 20 January 2022, Business Secretary Kwasi Kwarteng refused permission for the project, stating that he was not satisfied that "more appropriate alternatives to the proposed route" had been fully considered. [2] In November 2022, that ruling by the Business Secretary was the subject of a judicial review at the High Court brought by Aquind Ltd. Justice Lieven has reserved her decision. [34]
In January 2023, the decision by Kwasi Kwarteng to block the cable was overturned by judicial review. [35]
Whilst some local MPs and the local campaign group Stop AQUIND reasserted their opposition to the plans, [36] public support for the project has since been reported in a number of industry publications. [6] [7] [8]
Akwasi Addo Alfred Kwarteng is a British politician who served as the Chancellor of the Exchequer from 6 September to 14 October 2022 under Liz Truss and the Secretary of State for Business, Energy and Industrial Strategy from 2021 to 2022 under Boris Johnson. A member of the Conservative Party, he was the Member of Parliament (MP) for Spelthorne from 2010 to 2024.
The North Sea Link is a 1,400 MW high-voltage direct current submarine power cable between Norway and the United Kingdom.
Alexander Viktorovich Temerko is a Ukrainian businessman in the energy sector, currently a director of the British company Aquind Limited. Previously, he was director and deputy chairman of the British company OGN Group. While in Russia, he held senior posts in the Russian Defence Ministry in the 1990s and, from 1999, was a senior executive and director at the Russian oil and gas company Yukos. He has resided in the United Kingdom since 2004. He became a British citizen in 2011.
The NorthConnect was a proposed 650 km (400-mile) 1,400 MW HVDC interconnector over the floor of the North Sea.
Viking Wind Farm is a large on-shore wind farm in the Shetland Islands which was developed by Viking Energy, a partnership between Shetland Islands Council and SSE plc. It has a generation capacity of 443 MW.
Shetland HVDC Connection is a high-voltage direct current submarine power cable connecting Shetland to the British mainland.
The Western HVDC Link is a high-voltage direct current (HVDC) undersea electrical link in the United Kingdom, between Hunterston in Western Scotland and Flintshire Bridge in North Wales, routed to the west of the Isle of Man. It has a transmission capacity of 2,250 MW and became fully operational in 2019.
An interconnector is a structure which enables high voltage DC electricity to flow between electrical grids. An electrical interconnector allows electricity to flow between separate AC networks, or to link synchronous grids. They can be formed of submarine power cables or underground power cables or overhead power lines.
Anne-Marie Belinda Trevelyan is a British politician who served as Minister of State for Indo-Pacific under Rishi Sunak between October 2022 to July 2024. A member of the Conservative Party, she was the Member of Parliament (MP) for Berwick-upon-Tweed from 2015 until 2024, when she lost her seat in the 2024 General Election by Labour's David Smith. She previously served in the Cabinets of Boris Johnson and Liz Truss.
FAB Link is a proposed HVDC Interconnector, spanning the 220 kilometres (140 mi) between France and Great Britain, running close to the island of Alderney.
ElecLink is a 1,000 MW high-voltage direct current (HVDC) electrical interconnector between the United Kingdom and France, passing through the Channel Tunnel. ElecLink commenced operations on 25 May 2022.
Greenlink is a 190 km high-voltage direct current (HVDC) submarine power cable under construction between County Wexford in Ireland and Pembrokeshire in Wales.
NeuConnect is an high-voltage direct current submarine power cable under construction since 2023 between the Isle of Grain, England and Wilhelmshaven Germany, expected to operate in 2028. The cost of £2.4 billion is financed by Meridiam from France and German Allianz Capital Partners.
Gridlink Interconnector is a proposed submarine power cable between England and France. The 1,400 MW high-voltage direct current connector would link Kingsnorth National Grid substation in north Kent, England, with Réseau de Transport d'Électricité Warande substation in Bourbourg (Nord) near Dunkirk in northern France.
Starting from August 2021, high European wholesale natural gas prices started severely impacting the United Kingdom. Due to a combination of unfavourable circumstances, including soaring demand of gas in Asia, diminished gas supply from Russia to the European markets, low gas stockpiles, and a series of breakdowns at various electrical facilities, consumers in the United Kingdom faced steep increases in gas prices.
Viktor Fedotov is a Russian-British businessman. He was a vice-president of Lukoil in 1990-1998 and headed a number of other companies in the Russian oil industry, including the Caspian Pipeline Consortium. He is now the majority owner of Aquind, a company that plans to build a HVDC submarine power cable that would link France and England.
Liz Truss's tenure as Prime Minister of the United Kingdom began on 6 September 2022 when she accepted an invitation of Elizabeth II to form a government, succeeding Boris Johnson, and ended 49 days later on 25 October upon her resignation. As prime minister, she served simultaneously as First Lord of the Treasury, Minister for the Civil Service, Minister for the Union and Leader of the Conservative Party.
On 23 September 2022, the Chancellor of the Exchequer, Kwasi Kwarteng, delivered a Ministerial Statement entitled "The Growth Plan" to the House of Commons. Widely referred to in the media as a mini-budget, it contained a set of economic policies and tax cuts such as bringing forward the planned cut in the basic rate of income tax from 20% to 19%; abolishing the highest (45%) rate of income tax in England, Wales and Northern Ireland; reversing a plan announced in March 2021 to increase corporation tax from 19% to 25% from April 2023; reversing the April 2022 increase in National Insurance; and cancelling the proposed Health and Social Care Levy. Following widespread negative response to the mini-budget, the planned abolition of the 45% tax rate was reversed 10 days later, while plans to cancel the increase in corporation tax were reversed 21 days later.
The October 2022 Conservative Party leadership election was triggered by Liz Truss's announcement that she would resign as Leader of the Conservative Party and Prime Minister of the United Kingdom, amid an economic and political crisis.
In September and October 2022, the Conservative Party government led by newly appointed prime minister Liz Truss faced a credibility crisis. It was caused by the September 2022 mini-budget and a disorganised vote in the House of Commons over a parliamentary vote to ban fracking, ultimately resulting in the loss of support of Conservative members of parliament (MPs).
a controversial energy project
Aquind's project has already been mired in controversy