Dar es Salaam bus rapid transit

Last updated
Dar es Salaam Bus Rapid Transit
UDART Tanzania logo.png
The Usafiri Dar-es-Salaam Rapid Transit Logo.
DarBTR.jpg
Overview
Owner Government of Tanzania
LocaleDar es Salaam, Tanzania
Transit type Bus rapid transit
Number of lines1
Number of stations29
Daily ridership179,000 (August 2017) [1]
Website Company website
Operation
Began operation10 May 2016
Operator(s)UDA-RT
Number of vehicles305
Technical
System length21.1 km (13.1 mi)
Average speed23.0 km/h (14.3 mph)

Dar es Salaam bus rapid transit is a bus rapid transit system that began operations on 10 May 2016 in Dar es Salaam, Tanzania. [2] The transit system consists of 6 phases and the construction of the first phase began in April 2012 by the Austrian construction company Strabag International GmbH. [3] Construction of the first phase was completed in December 2015 at a total cost of €134 million funded by the African Development Bank, World Bank and the Government of Tanzania. [4] The first phase of the project has a total length of 21.1 kilometers with dedicated bus lanes on three trunk routes with a total of 29 stations. [5] The entire system is operated by The Usafiri salama Dar es Salaam Rapid Transit (UDA-RT) under the surveillance of the Surface and Marine Transport regulatory authority (Sumatra) [6] Currently, the route is serviced by a fleet of 140 Chinese built Golden Dragon buses, providing express and local service for 18 hours daily from 05:00am to 11:00pm. [7] In September 2022, BRT Fleet size had increased to 305. [8] [9]

Contents

History

An aerial view of the traffic congestion in Dar es Salaam along Azikiwe avenue before the bus transit system was implemented to provide efficient commuting. Dar es Salaam traffic.jpg
An aerial view of the traffic congestion in Dar es Salaam along Azikiwe avenue before the bus transit system was implemented to provide efficient commuting.

With the rapidly growing population of the city, the government began to draw plans for a rapid transit system in 2003. The government predicted the city population to grow over 5 million by 2015 and invited the Japan International Cooperation Agency to design a master plan for transport in the city in June 2008. [10] A bus rapid transit and a metro transit system were proposed but the metro system was not approved due to the high construction and operational cost involved. The project was placed under the Prime Minister's office and a Dar Rapid Transit Agency (DART) was created through a government notice on 25 May 2007. [11] A 130 km bus rapid transit was planned to cover over 90% of the city's population and the project was split into six phases due to the large investment required. [12] The initial project cost was financed by the world bank and the bank provided $180 million for the construction of the first phase. [13]

Phases

Phase I

Phase I of the BRT system runs for 21 km from Kimara to Ubungo ending at Kivukoni/Morocco. Construction of the first phase began in April 2012 and was completed in December 2015 by Strabag international GmbH. [14] The route is designed to carry 300,000 commuters daily along 29 stations. The route consists of 21 km of trunk road, 57.9 km of feeder roads, 5 large terminals and 29 stations. [15] The route was placed under interim operations on 24 April 2015 and was fully operational on 10 May 2016, after the fares were decided. [5]

Construction costs for Phase 1 [16]
Sub-projectCost in USD
BRT roadworks237.2 million
Kivukoni terminal building and feeder station3.8 million
Utility power relocation4.2 million
Feeder stations at Shekilango, Urafiki, Magomeni, Fire, Kinondoni A, and Mwinjuma3.4 million
Ubungo depot, feeder station and up-country bus station11.0 million
Jangwani Depot15.2 million
Kariakoo terminal building and feeder station7.2 million
Improvement of the Ubungo Intersection and Complementary Road Safety Infrastructure for the BRT Phase 1 System99.9 million
Total381.9 million

Interim Operations

On 24 April 2015 the Dar Rapid Transit Agency (DART) signed a contract with UDA-RT for the provision of Interim services of the Dar es salaam Rapid Transit system. UDA-RT is a special purpose company formed by UDA and the two Daladala Associations, the Dar es Salaam Commuter Bus Owners Association (DARCOBOA) and UWADAR for the provision of interim services. The interim service was conducted to provide training to future operators and build up local capacity. During interim operations the private dala-dalas were still operational on these routes. [17]

Phase II

Funds for the Second phase were secured in October 2015. The second phase is to run for approximately 19 km from Kilwa to Kawawa south via Kivukoni and is to cost around $160 million. The African Development Bank agreed to fund $141 million for the project, while the remaining funds will come from the government. Construction for the project is due to begin in June 2019 and will take approximately 36 months to complete. [18] Construction of the road will include two flyovers as well. The 20.3 km DART project will commence at Gerezani & City Council BRT station. Which will include Kilwa Road, Chang’ombe Road, Kawawa Road, Gerezani Street, Sokoine Drive and Bandari Road. [19]

Phase III

Funding for the 3rd phase was provided by the International Development Association (IDA). The construction will take place from Gongo La Mboto to City Center, including part of Uhuru Road from Tazara all the way to Kariakoo-Gerezani. [20]

Infrastructure

Stations

There are three types of stations along the route depending on its location and utility: [15]

Mwendokasi when turning (2020)

Buses

The BRT system operates a fleet of 140 Golden Dragon buses. There are two types of buses operated along the routes, one which is 18 meters long with a carrying capacity of 150 passengers and the other which is 12 meters long with a carrying capacity of 80 passengers. [2] In January fleet size increased to 210, followed with the addition of UAE firm's 95 buses, bringing the total to 310. [21]

Routes and Stations

DART Phase I
BSicon KHSTa.svg
Kimara Terminal
BSicon HST.svg
Korogwe
BSicon HST.svg
Bucha
BSicon HST.svg
Baruti
BSicon HST.svg
Kona
BSicon HST.svg
Kibo
BSicon HST.svg
Ubungo Maji
BSicon HST.svg
Ubungo Terminal
BSicon HST.svg
Shekilango
BSicon HST.svg
Urafiki
BSicon HST.svg
Manzese Tip Top
BSicon HST.svg
Manzese
BSicon HST.svg
Manzese Argentina
BSicon HST.svg
Kagera
BSicon HST.svg
Mwembe Chai
BSicon HST.svg
Usalama
BSicon KRWgl.svg
BSicon KRW+r.svg
Magomeni Mapipa
BSicon HST.svg
BSicon HST.svg
Magomeni Hospitali
Jangwani
BSicon HST.svg
BSicon HST.svg
Kanisani
Fire
BSicon HST.svg
BSicon HST.svg
Mkwajuni
BSicon KRW+l.svg
BSicon KRWgr.svg
BSicon HST.svg
Mwanamboka
Msimbazi Police
BSicon HST.svg
BSicon STR.svg
BSicon HST.svg
Kinondoni B
Gerezani
BSicon KHSTe.svg
BSicon STR.svg
BSicon KHSTe.svg
Morocco Terminal
BSicon HST.svg
DIT
BSicon HST.svg
Kisutu
BSicon HST.svg
Nyerere Square
BSicon HST.svg
Posta ya Zamani
BSicon KHSTe.svg
Kivukoni Terminal

There are six planned phases that will serve over 90% of the city's population and currently only Phase I is operational. Phase II is on construction.

Awards

See also

Related Research Articles

<span class="mw-page-title-main">Dar es Salaam</span> Largest city in Tanzania and capital of Dar es Salaam Region

Dar es Salaam or commonly known as Dar, is the largest city and financial hub of Tanzania. It is also the capital of Dar es Salaam Region. With a population of over six million people, Dar is the largest city in East Africa and the seventh-largest in Africa. Located on the Swahili coast, Dar es Salaam is an important economic centre and is one of the fastest-growing cities in the world.

Transport in Tanzania includes road, rail, air and maritime networks. The road network is 86,472 kilometres (53,731 mi) long, of which 12,786 kilometres (7,945 mi) is classified as trunk road and 21,105 kilometres (13,114 mi) as regional road. The rail network consists of 3,682 kilometres (2,288 mi) of track. Commuter rail service is in Dar es Salaam only. There are 28 airports, with Julius Nyerere International being the largest and the busiest. Ferries connect Mainland Tanzania with the islands of Zanzibar. Several other ferries are active on the countries' rivers and lakes.

Dart or DART may refer to:

<span class="mw-page-title-main">Bus rapid transit</span> Public transport system

Bus rapid transit (BRT), also called a busway or transitway, is a bus-based public transport system designed to have much more capacity, reliability and other quality features than a conventional bus system. Typically, a BRT system includes roadways that are dedicated to buses, and gives priority to buses at intersections where buses may interact with other traffic; alongside design features to reduce delays caused by passengers boarding or leaving buses, or paying fares. BRT aims to combine the capacity and speed of a light rail or metro system with the flexibility, lower cost and simplicity of a bus system.

<span class="mw-page-title-main">TransMilenio</span>

TransMilenio is a bus rapid transit (BRT) system that serves Bogotá, the capital of Colombia, and Soacha. The system opened to the public in December 2000, covering Caracas Avenue and 80 street. Other lines were added gradually over the next several years, and as of 2022, 12 lines totalling 114.4 km (71 mi) run throughout the city. It is part of the city's Integrated Public Transport System, along with the urban, complementary and special bus services operating on neighbourhoods and main streets.

STRABAG SE is an Austrian construction company based in Spittal an der Drau, Austria, with its headquarters in Vienna. It is the largest construction company in Austria and one of the largest construction companies in Europe. The company is active in its home markets Austria and Germany and in all countries of Central, Eastern and South-East Europe, in selected markets in Western Europe, on the Arabian Peninsula, as well as in Canada, Chile, China and India. In these markets STRABAG has subsidiaries or operates on a project-basis.

<span class="mw-page-title-main">Kivukoni</span> Ward of Ilala District, Dar es Salaam

Kivukoni is an administrative ward located in Ilala District, Dar es Salaam Region of Tanzania. Kivikoni's name come from the Swahili word meaning "a crossing place". The ward is bordered by Upanga East ward to the west, Kisutu ward to the southwest, and Kigamboni ward across the Kivukoni channel. The ward covers an area of 2.387 km2 (0.922 sq mi). Kivukoni ward is one of the most important wards in the country, as it is home to the Ikulu, which is the home of the president of Tanzania. Kivukoni ward is also home to the National Museum of Tanzania. According to the 2012 census, the ward had a total population of 6,742.

<span class="mw-page-title-main">Kilwa Masoko</span> Ward in Kilwa District, Lindi Region

Kilwa Masoko or Masoko is an administrative ward in Kilwa District of Lindi Region in Tanzania. The ward covers an area of 200 km2 (77 sq mi), and has an average elevation of 11 m (36 ft). The ward is also the capital of Kilwa District. According to the 2012 census, the ward has a total population of 13,601.

<span class="mw-page-title-main">Iskandar Malaysia Bus Rapid Transit</span> Proposed BRT system in Johor, Malaysia

The Iskandar Malaysia Bus Rapid Transit (IMBRT) is a proposed bus rapid transit system to be built in and around Iskandar Malaysia, Johor, Malaysia. It will consist of trunk, direct, and feeder bus rapid transit corridors.

<span class="mw-page-title-main">Tanzania Ports Authority</span> Public corporation in Tanzania

Tanzania Ports Authority (TPA) is a parastatal public corporation acting under the aegis of the Ministry of Infrastructure Development, that has the responsibility "to manage and operate" the ocean ports and lake ports of the country of Tanzania. The Tanzania Ports Authrorty headquarters are located in Kurasini Dar es Salaam. It is a member of the Port Management Association of Eastern and Southern Africa.

<span class="mw-page-title-main">MyCiTi</span>

MyCiti is a bus rapid transit service with feeders, which forms part of a greater Integrated Public Transport driven economic development strategy of the City of Cape Town Municipality (CoCT) in South Africa. The service is being rolled out across the Cape Metropole, and provides a significantly enhanced public transport system in about 10% of the City. The service commenced in 2010 with Phase 1, which features buses running north to south along the west coastline of the City.

<span class="mw-page-title-main">Bus rapid transit in Brazil</span>

The first bus rapid transit in Brazil (BRT) was built in 1974 in the city of Curitiba by the then mayor, architect Jaime Lerner, and became the second BRT in the world. The goal of the system is to provide high quality rail transit service to customers and at a comparable cost to that of a bus transit. Curitiba's success inspired the implementation of similar plans in more than 100 cities around the world, including the Brazilian cities of São Paulo, Rio de Janeiro, Belo Horizonte, Porto Alegre, Manaus, Goiânia, Aracaju, Salvador, Recife, and Brasília.

<span class="mw-page-title-main">Cebu Bus Rapid Transit System</span>

The Cebu Bus Rapid Transit System is a planned mass transit system for Cebu City located within the greater Cebu Metropolitan Area. It is expected to become the first operational bus rapid transit project in the Philippines. Only one line has been planned in detail so far, but scheme developers note the potential to develop a larger network comprising the adjacent cities Lapu-Lapu, Mandaue and Talisay. Leadership in both Lapu-Lapu and Mandaue have shown interest in the network. This will be constructed at the end or last quarter of 2017 and the first route could be operational by the end of 2019.

<span class="mw-page-title-main">Nyerere Bridge</span> Monument and Bridge in Dar es Salaam Region, Tanzania

Nyerere Bridge is a 680-meter-long bridge in Tanzania that connects the Dar es Salaam ward of Kurasini from the east to the west of Kigamboni district across the Kurasini estuary. Construction work began in February 2012 and completed in April 2016. The completion of the bridge has offered an alternative transport link to the new district of Kigamboni. Previously, the Kivukoni ferry provided a quick transport link between south east of the Dar es Salaam Central Business District specifically from south east of Kivukoni to north west of Kigamboni. The bridge has six lanes and two pedestrians/cyclists lanes with width of 2.5 meters. Construction of 2.5 km approach roads were completed with 1 km on the Kurasini side and 1.5 km on the Kigamboni side. The road joins the Nelson Mandela expressway through elevated free interchange to separate traffic approaching and leaving the junction. There is a toll plaza for controlling and charging of vehicles passing through the bridge. A total of 14 controlled lanes are going to be in this area.

<span class="mw-page-title-main">Dar es Salaam commuter rail</span> Public transit system in Tanzania

The Dar es Salaam commuter rail, informally known as Treni ya Mwakyembe, is an urban and suburban commuter rail network serving the Tanzanian commercial city of Dar es Salaam. It is one of the two initiatives taken by the government to ease travel within the congested city; the other being the Dar es Salaam bus rapid transit system. Services are provided by the Tanzania-Zambia Railway Authority (TAZARA) and Tanzania Railways Limited (TRL).

<span class="mw-page-title-main">Dar Rapid Transit Agency</span>

The Dar Rapid Transit Agency (DART) is an executive agency of Tanzania with the mandate to establish and operate a bus rapid transit system in Dar es Salaam.

<span class="mw-page-title-main">Rainbow Bus Rapid Transit System</span>

Rainbow BRTS is a bus rapid transit system in the city of Pune. The system is operated by the Pune Mahanagar Parivahan Mahamandal Limited (PMPML). The infrastructure has been developed by the Pune Municipal Corporation & Pimpri Chinchwad Municipal Corporation, Pune. The project currently envisages 113 km of dedicated bus corridors along with buses, bus stations, terminals and intelligent transit management system.

<span class="mw-page-title-main">Zhengzhou BRT</span>

Zhengzhou Bus Rapid Transit is a bus rapid transit system in Zhengzhou, the capital of Henan Province in the People's Republic of China. The system has 5 main trunk routes with dedicated bus lanes along with a number of feeder routes that run for a portion of the corridor and serves other areas.

TransPeshawar or Peshawar BRT is a bus rapid transit system in Peshawar, capital of Pakistan's Khyber Pakhtunkhwa (KP) province. TransPeshawar BRT system consists of two parts: the first encompasses an east–west corridor served by 32 stations on a dedicated lane for exclusive use by buses, while the second part consists of a network of feeder routes in which buses can enter and exit the system to travel on city streets. The system was inaugurated on August 13, 2020, and is the fourth BRT system in Pakistan.

References

  1. http://wedocs.unep.org/xmlui/bitstream/handle/20.500.11822/25448/1917_2018_te_unenvironment_gef_global_cc_msp_spcc_darcart_bus_rapid_transit.pdf?sequence=1&isAllowed=y [ bare URL PDF ]
  2. 1 2 "Tanzania: Dar Es Salaam Gets New Fast Shuttle Bus Service". allAfrica.com. Retrieved 2016-06-11.
  3. "Bus Rapid Transit (BRT) Infrastructure Package 1" (PDF). Strabag-international.com. Retrieved 2015-10-19.
  4. "Dar es Salaam Bus Rapid Transit: Environmental and Social Impact" (PDF). afdb.org. African Development Bank. March 2015. Retrieved 11 June 2016.
  5. 1 2 "Tanzania sets the pace for East Africa with rapid bus transit system - Asoko Insight". Asoko Insight. Retrieved 2016-06-11.
  6. "Home". sumatra.go.tz.
  7. "Dar sets the pace for East Africa with rapid bus transit system". www.theeastafrican.co.ke. Retrieved 2016-06-11.
  8. "Rapid bus service provider's fleet jumps to 210 vehicles". The Citizen. January 9, 2022.
  9. "Dart to furnish 95 new buses for BRT". The Citizen. March 9, 2022.
  10. "Dar es Salaam Transport Policy and System Development Master Plan" (PDF). JAPAN INTERNATIONAL COOPERATION AGENCY. June 2008. Retrieved 11 June 2016.
  11. "Chief Executive Officer's welcoming statement". dart.go.tz. dart. Retrieved 11 June 2016.
  12. "Section 1: "Why the Bus Rapid Transport"" (PDF). tanzania.go.tz. Government of Tanzania. Retrieved 11 June 2016.
  13. "Additional Financing for Tanzania's Bus Rapid Transit System to benefit 300,000 Commuters and Create 80,000 Jobs". World Bank. Retrieved 2016-06-11.
  14. "Bus Rapid Transit (BRT) Infrastructure, Dar Es Salaam, Tanzania". strabag-international.com. Strabag International GmbH. Retrieved 11 June 2016.
  15. 1 2 "DART Phase I" (PDF). dart.go.tz. Dar Rapid Transit Agency. October 2015. Retrieved 11 June 2016.
  16. World Bank (February 14, 2017). INTERNATIONAL DEVELOPMENT ASSOCIATION PROJECT APPRAISAL DOCUMENT ON A PROPOSED CREDIT IN THE AMOUNT OF SDR 316.2 MILLION (US$425 MILLION EQUIVALENT) UNITED REPUBLIC OF TANZANIA FOR A DAR ES SALAAM URBAN TRANSPORT IMPROVEMENT PROJECT (Report). World Bank. pp. 41–42. Retrieved May 25, 2021.
  17. "Dart Interim Bus Services Set for Take Off". AllAfrica. Tanzania Daily News. 10 May 2015. Retrieved 21 December 2015.
  18. "Tanzania: Chinese Firm Wins U.S.$160m Tender for Phase 2 of BRT". All Africa. September 4, 2018.
  19. "Tanzania to begin phase two construction of Dar Bus Rapid Transit (Dart". The TNews Times. February 12, 2019.
  20. "government releases Sh5.7 billion for 3rd phase BRT payout". The Citizen. April 13, 2020.
  21. "UAE firm set to commence transport services in Dar next week". The Citizen. September 2, 2022.
  22. 1 2 "Tanzania's Dar wins global award for Bus Rapid Transit system". Daily Nation . July 7, 2017.