Four Lines Modernisation

Last updated

The Four Lines Modernisation (4LM) is a series of projects by Transport for London (TfL) to modernise and upgrade the sub-surface lines of the London Underground: the Circle, District, Hammersmith & City and Metropolitan lines. The upgrades entail new rolling stock, new signalling and new track and drainage. [1] [2]

Contents

History

Following the implementation of the London Underground Public Private Partnership (PPP) in 2003, the Metronet consortium became responsible for the infrastructure on the District, Circle, Hammersmith & City and Metropolitan lines. [3] As part of the PPP, Metronet would deliver 190 new trains built by Bombardier Transportation and install new automatic signalling from Westinghouse Rail Systems. The first train was planned to enter service on the Metropolitan line by 2009, with all trains in service by 2015. [3] All the trains would be built to the same design, saving on parts and maintenance costs for Metronet.

In July 2007, Metronet, the private consortium responsible for the infrastructure for the sub-surfaces lines, collapsed due to financial difficulties. [4] TfL subsequently took over the contract for the new trains, and organised a new contract for the replacement of signalling.

In 2011, a £350m contract was awarded to Bombardier to replace the signals on the four lines with their Cityflo 650 system. [5] This work would be completed by 2018. [5] However the contract was terminated by TfL in 2014 due to delays, cost overruns and the complexity of the task. [6] [7] The decision by TfL to pay Bombardier £80m to end the contract was subsequently criticised by the London Assembly. [8]

In 2015, the contract was awarded to Thales, with the replacement of signalling now costing £760m. [6] [9] It would also be delivered four years later than originally planned, in 2023. [6] [10]

Rolling stock

D78 Stock on its last day in service (right), next to its replacement, an S S7 Stock unit (left). S7 Stock 21347+48 and D78 Stock 7007+7032.jpg
D78 Stock on its last day in service (right), next to its replacement, an S S7 Stock unit (left).

As part of the upgrade, the entire sub-surface fleet was to be replaced. S7 and S8 Stock manufactured by Bombardier Transportation's Derby Litchurch Lane Works were ordered to replace the A60/62 Stock on the Metropolitan line, the C69/77 Stock on the Circle, District (Edgware Road to Wimbledon section) and Hammersmith & City lines, and the D78 Stock on the rest of the District line, all of which dated from the 1960s and 1970s.

The order was for a total of 192 trains (1,403 cars), and formed of two types, S7 Stock for the Circle, District and Hammersmith & City lines and S8 Stock for the Metropolitan line. The main differences are the train lengths and seating arrangements, where the S7 Stock consists of seven cars in a longitudinal-only layout and the S8 Stock has eight cars with a mixture of longitudinal and transverse seating. New features that were not used on the previous rolling stocks include air-conditioning, low floors to ease accessibility, and open gangways between carriages. [11] [12]

The entire fleet was introduced by April 2017.

S Stock Introduction
LineStockFirst Unit IntroducedFully Introduced
Circle S72 September 201311 February 2014
District S72 September 201321 April 2017
Hammersmith & City S76 July 201211 February 2014
Metropolitan S831 July 201026 September 2012

Signalling

Part of the modernisation includes the introduction of Communications-Based Train Control (CBTC) to allow for Automatic Train Operation (ATO) via Thales's SelTrac system. [13] In order to upgrade the signalling, Signal Migration Areas have been created to allow for the gradual installation. [14] Below is a list of the SMAs and their progress:

Signal Migration Areas
SMAFromToLine(s)StatusDate
0.5HammersmithLatimer Road Circle and Hammersmith & City CompletedMarch 2019
1Latimer RoadPaddington Circle and Hammersmith & City CompletedSeptember 2019
2Paddington & Finchley RoadEuston Square Circle, District, Hammersmith & City and Metropolitan CompletedSeptember 2019
3Euston SquareMonument & Stepney Green Circle, District, Hammersmith & City and Metropolitan CompletedMarch 2021
4MonumentSloane Square Circle & District CompletedApril 2021
5Sloane SquareBarons Court, Fulham Broadway,

Olympia & Paddington

Circle and District CompletedMarch 2022
6Stepney GreenBecontree District and Hammersmith & City CompletedJanuary 2023
7BecontreeUpminster District CompletedMarch 2023
8Finchley RoadPreston Road Metropolitan Planned2024+ (TBC)
9Preston Road
  • West Harrow
  • Moor Park
Metropolitan Planned2024+ (TBC)
10†Barons Court
  • Stamford Brook
District DeferredTBD
11†Stamford BrookRichmond & Ealing Broadway District DeferredUntil further notice
12†Fulham BroadwayEast Putney District DeferredTBD
13Moor Park
  • Watford
  • Amersham
  • Chesham
Metropolitan Planned2025+ (TBC)
14West HarrowUxbridge Metropolitan Planned2025+ (TBC)

As a result of SMA 5 being installed, the Circle line began running entirely under ATO and after the completion of SMA 6 the Hammersmith & City line also now runs completely under ATO.


† For various reasons including funding and the technical difficulties with sharing tracks with National Rail & the Piccadilly line, SMAs 10-12 were scaled back until further notice.

Originally the SMAs were planned as follows: [14]

Signal Migration Areas
SMAFromToLine(s)
10Barons CourtRichmond & Chiswick Park District
11Chiswick ParkEaling Broadway District
12Fulham BroadwayWimbledon District

Related Research Articles

<span class="mw-page-title-main">London Underground</span> Rapid transit system in England

The London Underground is a rapid transit system serving Greater London and some parts of the adjacent home counties of Buckinghamshire, Essex and Hertfordshire in England.

<span class="mw-page-title-main">Metropolitan line</span> London Underground line

The Metropolitan line, colloquially known as the Met, is a London Underground line between Aldgate in the City of London and Amersham and Chesham in Buckinghamshire, with branches to Watford in Hertfordshire and Uxbridge in Hillingdon. Printed in magenta on the tube map, the line is 41.4 miles (66.7 km) in length and serves 34 stations. Between Aldgate and Finchley Road, the track is mostly in shallow "cut and cover" tunnels, apart from short sections at Barbican and Farringdon stations. The rest of the line is above ground, with a loading gauge of a similar size to those on main lines. Just under 94 million passenger journeys were made on the line in 2019.

<span class="mw-page-title-main">Circle line (London Underground)</span> London Underground line

The Circle line is a spiral-shaped London Underground line, running from Hammersmith in the west to Edgware Road and then looping around central London back to Edgware Road. The railway is below ground in the central section and on the loop east of Paddington. Unlike London's deep-level lines, the Circle line tunnels are just below the surface and are of similar size to those on British main lines. Printed in yellow on the Tube map, the 17-mile (27 km) line serves 36 stations, including most of London's main line termini. Almost all of the route, and all the stations, are shared with one or more of the three other sub-surface lines, namely the District, Hammersmith & City and Metropolitan lines. On the Circle and Hammersmith & City lines combined, over 141 million passenger journeys were recorded in 2019.

<span class="mw-page-title-main">District line</span> London Underground line

The District line is a London Underground line running from Upminster in the east and Edgware Road in the west to Earl's Court in west London, where it splits into multiple branches. One branch runs to Wimbledon in south-west London and a short branch, with a limited service, only runs for one stop to Kensington (Olympia). The main route continues west from Earl's Court to Turnham Green after which it divides again into two western branches, to Richmond and Ealing Broadway.

<span class="mw-page-title-main">Hammersmith & City line</span> London Underground line

The Hammersmith & City line is a London Underground line that runs between Hammersmith in west London and Barking in east London. Coloured pink on the Tube map, it serves 29 stations over 15.8 miles (25.5 km). Between Farringdon and Aldgate East it skirts the City of London, the capital's financial heart, hence the line's name. Its tunnels are just below the surface and are a similar size to those on British main lines. Most of the track and all stations are shared with the District, Circle or Metropolitan lines. Over 141 million passenger journeys are made each year on the Hammersmith & City and Circle lines.

<span class="mw-page-title-main">Edgware Road tube station (Circle, District and Hammersmith & City lines)</span> London Underground station on the Circle, District and Hammersmith & City lines

Edgware Road is a London Underground station on the Circle, District and Hammersmith & City lines, located on the corner of Chapel Street and Cabbell Street, within Travelcard zone 1. A separate station of the same name but served by the Bakerloo line is located about 150 metres away on the opposite side of Marylebone Road.

<span class="mw-page-title-main">London Underground rolling stock</span> Passenger trains that run on the London Underground

London Underground rolling stock includes the electric multiple-unit trains used on the London Underground. These come in two sizes, smaller deep-level tube trains and larger sub-surface trains of a similar size to those on British main lines, both running on standard gauge tracks. New trains are designed for the maximum number of standing passengers and for speed of access to the cars.

<span class="mw-page-title-main">London Underground 1992 Stock</span> Electric multiple unit used on the Central and Waterloo & City lines of the London Underground

The London Underground 1992 Stock is a type of rolling stock used on the Central and Waterloo & City lines of the London Underground. A total of 85 eight-car trains were built for the Central line and 5 four-car trains were built for the Waterloo & City line.

<span class="mw-page-title-main">History of the London Underground</span>

The history of the London Underground began in the 19th century with the construction of the Metropolitan Railway, the world's first underground railway. The Metropolitan Railway, which opened in 1863 using gas-lit wooden carriages hauled by steam locomotives, worked with the District Railway to complete London's Circle line in 1884. Both railways expanded, the Metropolitan eventually extending as far as Verney Junction in Buckinghamshire, more than 50 miles (80 km) from Baker Street and the centre of London. The first deep-level tube line, the City and South London Railway, opened in 1890 with electric trains. This was followed by the Waterloo & City Railway in 1898, the Central London Railway in 1900, and the Great Northern and City Railway in 1904. The Underground Electric Railways Company of London (UERL) was established in 1902 to fund the electrification of the District Railway and to complete and operate three tube lines, the Baker Street and Waterloo Railway, the Charing Cross, Euston and Hampstead Railway and the Great Northern, Piccadilly and Brompton Railway, which opened during 1906–1907. By 1907, the District and Metropolitan Railways had electrified the underground sections of their lines.

<span class="mw-page-title-main">Metronet (British infrastructure company)</span>

Metronet Rail was an asset-management company responsible for the maintenance, renewal and upgrade of the infrastructure, including track, trains, signals, civils work and stations, on several London Underground lines. It was one of two infrastructure companies in a public-private partnership (PPP) with the Underground.

<span class="mw-page-title-main">Tube Lines</span> British infrastructure company

Tube Lines Limited, initially known as Infraco JNP, was an asset-management company responsible for the maintenance, renewal and upgrade of the infrastructure, including track, trains, signals, civils work and stations, of three London Underground lines.

<span class="mw-page-title-main">London Underground 1972 Stock</span> Type of rolling stock used on the Bakerloo line of the London Underground

The London Underground 1972 Stock is a type of rolling stock used on the London Underground. The 1972 Stock was originally ordered to make up the shortfall in trains on the Northern line's 1959 Tube Stock fleet, but is currently used on the Bakerloo line. Following the withdrawal of the British Rail Class 483 EMUs in 2021, the 1972 Stock are now the oldest EMUs in passenger service in the United Kingdom. A total of 63 seven-car trains were built in two separate batches.

<span class="mw-page-title-main">London Underground C69 and C77 Stock</span> Type of sub-surface railway vehicle

The London Underground C69 and C77 Stock, commonly referred to as the C Stock, was a type of sub-surface rolling stock used on the Circle, District and Hammersmith & City lines of the London Underground between 1970 and 2014. They were replaced by the S7 Stock.

<span class="mw-page-title-main">London Underground 2009 Stock</span> An electric multiple unit used on the Victoria line of the London Underground

The London Underground 2009 Stock is a type of London Underground train built by Bombardier as part of its Movia family at its Derby Litchurch Lane Works, England. A total of 47 eight-car trains have been built for the Victoria line. They entered service between July 2009 and June 2011 and replaced the 1967 Tube Stock. It is the first new deep level tube stock on the Underground network since the 1996 Stock entered service on the Jubilee line in 1997.

<span class="mw-page-title-main">London Underground 1996 Stock</span> Electric multiple unit used on the Jubilee line of the London Underground

The London Underground 1996 Stock is a type of rolling stock used on the Jubilee line of the London Underground. The trains were built by GEC Alsthom-Metro-Cammell and entered service in 1997. They are externally similar to the 1995 Stock used on the Northern line.

<span class="mw-page-title-main">London Underground 1995 Stock</span> Type of rolling stock used on the London Underground

The London Underground 1995 Stock is a type of rolling stock used on the Northern line of the London Underground. A total of 106 six-car trains were built, entering service between June 1998 and April 2001, replacing the 1959 Stock, 1962 Stock and 1972 Stock. They are externally similar to the 1996 Stock used on the Jubilee line.

<span class="mw-page-title-main">London Underground S7 and S8 Stock</span> Rolling stock in use on the London Underground

The London Underground S7 and S8 Stock, commonly referred to as S Stock, is a type of passenger train running on the London Underground's subsurface lines since 2010. Manufactured by Bombardier Transportation's Derby Litchurch Lane Works, the S Stock was ordered to replace the A60, A62, C69, C77 and D78 stock on the Metropolitan, District, Hammersmith & City, and Circle lines, which all dated from the 1960s and 1970s.

The railway infrastructure of the London Underground includes 11 lines, with 272 stations. There are two types of line on the London Underground: services that run on the sub-surface network just below the surface using larger trains, and the deep-level tube lines, that are mostly self-contained and use smaller trains. Most of the lines emerge on the surface outside the Central London area.

<span class="mw-page-title-main">History of the District line</span>

The history of the District line started in 1864 when the Metropolitan District Railway was created to create an underground 'inner circle' connecting London's railway termini. The first part of the line opened using Metropolitan Railway gas-lit wooden carriages hauled by steam locomotives. The District introduced its own trains in 1871 and was soon extended westwards through Earl's Court to Fulham, Richmond, Ealing and Hounslow. After completing the 'inner circle' and reaching Whitechapel in 1884, it was extended to Upminster in East London in 1902. To finance electrification at the beginning of the 20th century, American financier Charles Yerkes took it over and made it part of his Underground Electric Railways Company of London (UERL) group. Electric propulsion was introduced in 1905, and by the end of the year electric multiple units operated all of the services.

<span class="mw-page-title-main">London Underground 2024 Stock</span> New type of London Underground rolling stock

The London Underground 2024 Stock, known as the New Tube for London (NTfL) during development, is a London Underground train being built by Siemens Mobility at its facilities in Goole, United Kingdom and Vienna, Austria. It is part of the Siemens Inspiro family of metro and rapid-transport trains.

References

  1. "Four Lines Modernisation". Transport for London. Retrieved 2022-05-11.
  2. "THIRD TIME LUCKY FOR SUB-SURFACE RESIGNALLING". www.modernrailways.com. 1 December 2022. Retrieved 2023-04-30.
  3. 1 2 "Metronet Brochure 2005" (PDF). Metronet. 2005. Archived from the original (PDF) on 31 October 2006. Retrieved 7 March 2021.
  4. "Metronet calls in administrators". BBC News. 18 July 2007. Retrieved 7 March 2021.
  5. 1 2 "Bombardier wins major Underground signalling project". Rail News. 15 June 2011. Retrieved 2023-04-30.
  6. 1 2 3 "Plans to modernise four London Underground lines 'double' in cost". BBC News. 2015-08-03. Retrieved 2023-04-30.
  7. "Bombardier loses sub-surface lines signalling contract". www.railtechnologymagazine.com. 2 January 2014. Retrieved 2023-04-30.
  8. "Transport for London criticised over £80m payout". BBC News. 2014-10-23. Retrieved 2023-04-30.
  9. "Thales wins one billion euro contract to upgrade London underground lines". Reuters. 2015-08-03. Retrieved 2023-04-30.
  10. "THIRD TIME LUCKY FOR SUB-SURFACE RESIGNALLING". www.modernrailways.com. 1 December 2022. Retrieved 2023-04-30.
  11. "SQUAREWHEELS.org.uk – S stock". www.squarewheels.org.uk. Retrieved 2022-05-11.
  12. "S7/8 stock - Tube History". tube-history.uk. Retrieved 2022-05-11.
  13. Kessell, Clive. "Progress with the Four Lines Modernisation project". RailEngineer. Retrieved 10 January 2024.
  14. 1 2 "Programmes and Investment Committee - Four Lines Modernisation Update" (PDF). Transport for London. 13 October 2017. Retrieved 24 July 2022.