Gigafactory Mexico

Last updated

Gigafactory Mexico
Press image used to promote Tesla Gigafactory Mexico.jpg
Artist's rendering of Gigafactory Mexico
Gigafactory Mexico
Built2023–
Location Monterrey, Mexico
Coordinates 25°42′15″N100°34′20″W / 25.70417°N 100.57222°W / 25.70417; -100.57222
Industry Automotive
Area2.962 km2 (1.144 sq mi; 732 acres) [1]
Owner(s) Tesla, Inc.

Gigafactory Mexico (also known as Gigafactory 6) is a proposed manufacturing plant for Tesla, Inc. to be constructed near Monterrey, Mexico, [2] with new vehicle production expected as early as 2026. [3]

Contents

Description

The gigafactory is planned to be built near Monterrey. The factory will be an approximately US$10 billion investment by Tesla and will employ thousands of workers when fully operational, as well as employ many thousands of workers during construction. [4] [5] Including Tesla and its suppliers, the plant represents a US$15 billion investment between 2023 and 2025. [6] Production is expected to start no earlier than 2026. [3] [7]

History

The facility was officially announced by Mexican President Andrés Manuel López Obrador on 28 February 2023. [2] The following day at Tesla Investor Day, Tesla CEO Elon Musk confirmed the facility. [8] The factory was placed in Mexico in an effort to keep the cost of the vehicle low, and Tesla has encouraged suppliers to open facilities nearby. [9]

Samuel García, governor of Mexico's Nuevo León state, announced in July 2023 that the permits for the factory were nearly ready to be issued and said he expected construction would soon begin. [10] Tesla expected then that the facility would take 12 to 15 months to construct, [11] and had told suppliers to expect the plant to open in the first quarter of 2025. [9] By August 2023, preparation work had only just begun at the site to build an access road onto the property from the highway. [12] Tesla received environmental impact permits for the project in September 2023, with a requirement that construction be completed in 26 months (November 2025). [1] [13] By the end of October 2023, the government of Nuevo León said that Tesla had received all necessary permits to begin construction of the factory. [14]

In September 2023, multiple Tesla suppliers indicated that production was not expected to start until 2026 or 2027, and therefore some suppliers were delaying their own plans to build new facilities in Mexico to support the supply line for Tesla in Nuevo Leon. [3]

Tesla requested in October that the Nuevo Leon state government begin building electric, water, road and rail infrastructure to serve the Gigafactory, [15] although Tesla stated in October that they are slowing down their plans for the factory due to global concerns about the macroeconomy. [16]

As of July 2024, Tesla has placed construction of Gigafactory Mexico on hold until after the 2024 United States presidential election, because former President Trump has pledged to add tariffs on cars made in Mexico. [17]

See also

Related Research Articles

<span class="mw-page-title-main">Monterrey</span> City in Nuevo León, Mexico

Monterrey is the capital and largest city of the northeastern state of Nuevo León, Mexico, and the ninth largest city and second largest metro area in Mexico behind Greater Mexico City. Located at the foothills of the Sierra Madre Oriental, Monterrey is a major North American business and industrial hub, as well as the most populous city in Northern Mexico.

<span class="mw-page-title-main">Tesla, Inc.</span> American electric vehicle and clean energy company

Tesla, Inc. is an American multinational automotive and clean energy company. Headquartered in Austin, Texas, it designs, manufactures and sells battery electric vehicles (BEVs), stationary battery energy storage devices from home to grid-scale, solar panels and solar shingles, and related products and services.

<span class="mw-page-title-main">Tesla Fremont Factory</span> Tesla, Inc. factory

The Tesla Fremont Factory is an automobile manufacturing plant in Fremont, California, United States, operated by Tesla, Inc. The factory originally opened as General Motors' Fremont Assembly in 1962, and then was operated by New United Motor Manufacturing, Inc. (NUMMI), a joint venture of GM and Toyota from 1984. The joint venture ended when GM entered bankruptcy in 2009. In 2010, Toyota agreed to sell the plant to Tesla at a significant discount. The plant is the only production site for the Model S and Model X and also produces the Model 3, and Model Y.

<span class="mw-page-title-main">Gigafactory Nevada</span> Tesla, Inc. factory

Gigafactory Nevada is a lithium-ion battery and electric vehicle component factory in Storey County, Nevada, United States. The facility, located east of Reno, is owned and operated by Tesla, Inc. The factory supplies battery packs and drivetrain components for the company's electric vehicles, produces the Tesla Powerwall home energy storage device, and assembles the Tesla Semi. It is the largest and the first Tesla Gigafactory in the world. If fully built out, the building will have the largest footprint in the world.

Gigafactory is a generic term that refers to a manufacturing facility where components and products associated with electrification and decarbonization technologies are produced.

<span class="mw-page-title-main">Nemak</span>

Nemak, S.A.B. de C.V., known as Nemak, is a global automotive parts manufacturing company headquartered in García, Nuevo León, a municipality next to the City of Monterrey, Nuevo León, México. The company manufactures a wide range of automotive parts and systems with primary focus on aluminum auto parts, mainly engine blocks, cylinder heads, and transmission components. It is a Tier 1 supplier to major OEMs and is among the 60 largest auto industry suppliers worldwide.

<span class="mw-page-title-main">Tesla Model Y</span> Electric mid-size crossover SUV

The Tesla Model Y is a battery electric mid-size crossover SUV produced by Tesla, Inc. since 2020. The vehicle was presented in March 2019 as the company's fifth production model since its inception after the Roadster, Model S, Model X and Model 3.

<span class="mw-page-title-main">Lucid Motors</span> American automotive company

Lucid Group, Inc. is an American automotive and technology company that manufactures electric vehicles and supplies advanced electric vehicle powertrain systems. The company is headquartered in Newark, California. In September 2021, the company began producing the Lucid Air sedan at its factory in Casa Grande, Arizona. The company expects to begin production of its second model, the Lucid Gravity SUV, in late 2024. Lucid also supplies and develops powertrain technology to other automakers, including Aston Martin.

<span class="mw-page-title-main">Gigafactory Berlin-Brandenburg</span> Tesla, Inc. factory

Gigafactory Berlin-Brandenburg is a manufacturing plant for Tesla, Inc. in the municipality of Grünheide (Mark) in the Brandenburg state of Germany. The campus is located 35 kilometres (20 mi) south-east of central Berlin and some 8 kilometres (5 mi) southeast of the Berlin state boundary at Erkner and Rahnsdorf. Proximity to Berlin Brandenburg Airport was explicitly cited as a factor in choosing the site. It is Tesla's first manufacturing location in Europe.

<span class="mw-page-title-main">Gigafactory New York</span> Tesla, Inc. factory in Buffalo, New York

Gigafactory New York is factory leased by Tesla, Inc. in the Riverbend section of Buffalo, New York. The factory, owned by the State of New York, was built on brownfield land remediated from a former steel mill. Construction of the factory started in 2014 and was completed in 2017. It produces the Tesla Solar Roof and Tesla Superchargers. Additionally, Tesla employs data analysts for its Autopilot software at the site.

<span class="mw-page-title-main">Gigafactory Shanghai</span> Tesla, Inc. factory

Gigafactory Shanghai is an automobile manufacturing plant in Shanghai, China, operated by Tesla, Inc. Construction of the plant began in January 2019, initial production started in October, and the first production vehicles rolled out of the factory in December 2019, less than one year after groundbreaking. The main plant currently manufactures the Model 3 and Model Y. As of July 2023, Tesla says the factory has the capacity to build over 750,000 vehicles per year and is the primary production site for Tesla vehicles exported to regions without a Gigafactory.

<span class="mw-page-title-main">Giga Press</span> Series of aluminium die casting machines

The Giga Press program is a series of aluminium die casting machines manufactured for Tesla, initially by Idra Group in Italy. Idra presses were the largest high-pressure die casting machines in production as of 2020, with a clamping force of 55,000 to 61,000 kilonewtons. Each machine weighs 410–430 tonnes (900,000–950,000 lb).

<span class="mw-page-title-main">Gigafactory Texas</span> Tesla, Inc. factory

Gigafactory Texas is an automotive manufacturing facility in Austin, Texas built by Tesla, Inc. Construction began in July 2020, limited production of Model Y began before the end of 2021, and initial deliveries of vehicles built at the factory took place at an opening party called “Cyber Rodeo” on April 7, 2022.

Northvolt AB is a Swedish battery developer and manufacturer, specialising in lithium-ion technology for electric vehicles. Founded in 2015 by two former Tesla executives, it commissioned its first manufacturing plant in Skellefteå, Sweden in 2021 and has announced plans for five others in Europe and North America.

<span class="mw-page-title-main">Samuel García (politician)</span> Mexican politician (born 1987)

Samuel Alejandro García Sepúlveda is a Mexican lawyer and politician serving as the Governor of Nuevo León. A member of the Citizens' Movement party, he served as a local deputy in the Congress of Nuevo León from 2015 to 2018 and represented Nuevo León in the Senate from 2018 to 2020.

The Tesla next-generation vehicle is an electric car platform under development by Tesla. The next-generation vehicle will be the third mainstream platform for the company, and it is expected that production volumes will greatly surpass those of the Model 3/Y platform. Although the vehicle has not been given an official name, the moniker Model 2 has been used to refer to the vehicle in the media. The car will be manufactured at Gigafactory Texas, Gigafactory Berlin-Brandenburg, and the planned Gigafactory Mexico.

<span class="mw-page-title-main">Metrorrey Line 4</span> Monorail line in Nuevo León, Mexico

Metrorrey Line 4 is an under-construction Metrorrey line that will municipalities of Monterrey and San Pedro Garza García. It will have an extension of approximately 7.5 kilometers. It will connect with lines 3, 5 and 6 at the Saint Lucia station.

<span class="mw-page-title-main">Metrorrey Line 6</span> Metro line in Monterrey, Mexico

Metrorrey Line 6 is one of the three lines currently planned by Metrorrey, which will connect the municipalities of Monterrey, Guadalupe, San Nicolás de los Garza and Apodaca. It will have an extension of approximately 17.6 kilometers. It will connect with lines 3, 4 and 5 at the Saint Lucia station, in front of the High Specialty Medical Unit No. 33 of the Mexican Social Security Institute (IMSS). It connects to line 1 at the Y.A. station. Officially it does not have a distinctive color, but on the map, it is shown as purple.

The Tren Suburbano de Monterrey is a future commuter rail line in Monterrey, Nuevo León, Mexico. The cost of the project will be 12 billion pesos, Phase 1, of which 3 billion come from the federal government of Mexico, via Fonadin, another 3 billion via Banobras and 6 billion from the private initiative, under a private-public association scheme. Samuel García clarified that in 2022 they intend to start with the technical studies of the project themselves that will cost up to 500 million pesos.

References

  1. 1 2 Garza, Víctor González (21 September 2023). "Nuevo León aprueba permisos ambientales para Tesla" [Nuevo Leon Approves Environmental Impact Permits for Tesla Factory]. Telediario (in Mexican Spanish). Retrieved 25 September 2023.
  2. 1 2 Graham, Dave; Solomon, Daina Beth (28 February 2023). "Tesla plant gets green light in northern Mexico". Reuters . Retrieved 3 March 2023.
  3. 1 2 3 Olvera, Silvia (6 September 2023). "Avisan a proveedores de Tesla: 'no hay prisa'" [Tesla suppliers warned: 'no hurry']. El Norte (in Mexican Spanish). Retrieved 25 September 2023.
  4. Spinetto, Juan Pablo (7 March 2023). "New Tesla Gigafactory Marks Mexico's Manufacturing Golden Moment". Bloomberg News . Retrieved 8 March 2023.
  5. Averbuch, Maya (3 March 2023). "Tesla Mexico Plant Means $10 Billion Investment, Garcia Says". Bloomberg News . Retrieved 25 September 2023.
  6. Pulice, Carolina; Soloman, Daina Beth (12 September 2023). Garcia, David Alire; Fahmy, Miral (eds.). "Tesla, suppliers to invest $15 billion in Mexico factory, local governor says". Reuters . Retrieved 25 September 2023.
  7. Lambert, Fred (7 September 2023). "Tesla Gigafactory Mexico might be coming online way later than expected". Electrek . Retrieved 7 September 2023.
  8. Shakir, Umar (1 March 2023). "Tesla confirms its next Gigafactory will be in Mexico". The Verge . Retrieved 3 March 2023.
  9. 1 2 Alvarez, Simon (29 June 2023). "Tesla Gigafactory Mexico production set at Q1 2025: report". Teslarati. Retrieved 4 August 2023.
  10. Cubero, César (7 July 2023). "Samuel García asegura que en "cualquier momento" pondrán la primera piedra para Gigafactory de Tesla" [Samuel García assures that at "any time" they will lay the first stone for Tesla's Gigafactory]. Milenio (in Mexican Spanish). Retrieved 26 August 2023.
  11. Merano, Maria (17 April 2023). "Tesla Giga Mexico building 'new production line' for $25k compact car". teslarati.com. Retrieved 4 August 2023.
  12. Delgado, Pedro (9 August 2023). "Llega maquinaria a terrenos donde construirán Gigafactory de Tesla en Santa Catarina" [Machinery arrives at land where Tesla's Gigafactory will be built in Santa Catarina]. Milenio (in Mexican Spanish). Retrieved 26 August 2023.
  13. John, Darryn (22 September 2023). "Tesla's environmental impact permits for Giga Mexico approved". Drive Tesla Canada. Retrieved 25 September 2023.
  14. Cubero, César (30 October 2023). "Tesla viene a Nuevo León, ya tiene todos sus permisos: Iván Rivas" [Tesla is coming to Nuevo León, it already has all its permits: Iván Rivas]. Grupo Milenio (in Mexican Spanish). Retrieved 7 November 2023.
  15. Bravo, Tomas; Madry, Kylie (5 October 2023). "Tesla requests infrastructure ahead of Mexico factory construction, state government says". Reuters. Retrieved 5 October 2023.
  16. Lambert, Fred (19 October 2023). "Tesla pumps the brakes on Gigafactory Mexico" . Retrieved 29 October 2023.
  17. Revell, Eric (23 July 2024). "Musk says Tesla's Mexico factory on pause over Trump's tariff pledge". Fox Business . Retrieved 25 July 2024.