Leicester power stations | |
---|---|
Country | United Kingdom |
Location | Leicester |
Coordinates | 52°37′11″N01°08′36″W / 52.61972°N 1.14333°W |
Status | Decommissioned and demolished |
Construction began | 1893 |
Commission date | 1894, 1904, 1922, 1976 |
Decommission date | 1928, 1930, 1976, 1990 |
Owner(s) | Leicester Corporation (1894-1948) British Electricity Authority (1948–1955) Central Electricity Authority (1955–1957) Central Electricity Generating Board (1958–1989) |
Operator(s) | As owner |
Thermal power station | |
Primary fuel | Coal |
Secondary fuel | Fuel oil (gas turbines) |
Turbine technology | Steam turbines |
Chimneys | 3 (Freemans Meadow), 2 (gas turbine) |
Cooling towers | 6 |
Cooling source | River or canal water plus cooling towers |
Power generation | |
Make and model | see text |
Nameplate capacity | 131 MW (steam), 102 MW (gas turbine) |
Annual net output | 561 GWh (1955) |
External links | |
Commons | Related media on Commons |
Leicester power stations are a series of electricity generating stations that have provided electric power to the City of Leicester and the wider area from 1894. The first station, located within Aylestone gas works, supplied electricity for street lighting. The city's new electric tram system was supplied from 1904 by a station at Lero which operated until 1930. A large coal-fired power station was constructed at Freemans Meadow in 1922 and was operational until 1976. Finally a gas turbine power plant was commissioned in 1976.
Leicester was one of first nine municipalities to obtain legal powers to provide street lighting in the city. The authority to do this was provided for under the Leicester (Further Powers to Corporation) Act 1879 (42 & 43 Vict. c. cc). [1] However, little progress was made with the new technology. The Corporation of Leicester obtained, from the Board of Trade, a Provisional Electric Lighting Order in 1890 permitting it to generate electricity and supply electric lighting for the city. This Provisional Order was confirmed by Parliament by the Electric Lighting Order Confirmation (No. 7) Act 1890 (53 & 54 Vict. c. cxcii). [2]
The first power station in Leicester was built in 1894 within the gas works site on Aylestone Road (52°37'00.1"N 1°08'32.0"W). [3] It first provided electricity on 19 December 1894. In 1897 the plant had a generating capacity of 675 kW and the maximum load was 515 kW. A total of 262.179 MWh of electricity was sold to 331 customers which powered 26,512 lamps, this provided an income to the corporation of £6,056-12-9. [4]
By 1923 the station comprised three 1 MW reciprocating engines and a 5 MW turbo-alternator. [5] These machines were powered by total of up to 181,000 pounds per hour (22.8 kg/s) of steam from coal-fired boilers. The machines generated alternating current (AC) supplied at 240 & 415 V and 100 & 200 V. The electricity works were decommissioned in 1928 after the new power station at Freemans Meadow had been built. [3]
In 1894 the Midland Railway Company installed a gas-fired power station in Leicester. [6] This used two Dowson gas producers working on anthracite, the gas produced operated six single cylinder Crossley engines with porcelain tube ignition. Three machines drove 60-lamp Brush arc lighting generators and the other three drove 110 Volt direct current dynamos for incandescent lights. The total output of the station was 274 MWh per year. The Midland railway station and the goods yards were lit by 141 arc lights and 288 incandescent lamps. The system was reported to have run for many years. [6]
Leicester's tram system was first built in 1874 using horse drawn cars. [7] The Corporation of Leicester took over the system in 1901 and converted it to electric power in 1904. To meet this demand a new generating station was constructed on Painter Street [8] (52°38'42.0"N 1°07'47.2"W) the station buildings, comprising a boiler house and an engine room, were known as the Lero building. [3] It was located next to the Grand Union Canal to facilitate the supply of coal by barge and for the availability of cooling water. The power station was officially opened on 18 May 1904. The boiler house was 108 ft long and 77 ft wide (32.9 m by 23.5 m). [3] In 1904 there were four Yates and Thom Lancashire type boilers, these were 33 ft long and 8 ft 5 inches diameter (10 m by 2.5 m). The tapered octagonal brick chimney was 186 ft high (56.7 m). [3]
The engine room adjoining the boiler house was 118 ft long, 60 ft wide and 40 ft high (36 m by 18.2 m, by 12.2 m). There were three 500 kW steam generating sets. The engines were Yates and Thom vertical cross-compound Corliss condensing type. [9] The principal specifications of the engines were: [3]
There was a separate battery room which supplied additional current when the demand on the system was high. [3]
In 1906 additional plant was added raising the capacity to 3 × 500 kW and 1 × 1,000 kW generators. [3] There was sufficient generating capacity to allow up to 20 percent of the electricity produced to be sold to industry throughout Leicester. [3] Electricity was delivered to consumer's premises by overhead wires and the return current through the tram track completed the circuit. In 1910 the engine room was extended by 54 ft (11 m) and a Willans & Robinson turbine and a Siemens 1,000 kW DC generator were commissioned. To meet the demand for alternating current (AC), a 750 kW alternator driven by a direct current (DC) motor was also installed. [3]
The Lero and the Aylestone generating sites were electrically coupled in 1914, and were managed by the Tramways and Electricity Committee of the Corporation. [3] As Leicester expanded so did the demand for electricity.
By 1923 the plant at the Lero station had been increased to 2 × 3 MW turbo-alternators generating AC; 3 × 0.5 MW and 1 × 1 MW reciprocating engines plus 1 × 0.75 MW steam turbine all generating direct current (DC). [5] The machines at Lero were supplied with up to 164,000 pounds per hour (20.7 kg/s) of steam from the coal-fired boilers. [5]
The Lero station was closed on 30 June 1930, when electricity generation was centralised at Freemans Meadow power station. [3] The buildings were used from 1946 as an extension for the Leicester College of Technology; they were eventually demolished in 2010. [3]
Following the First World War, and in anticipation of a post-war increase in demand for electricity, the Corporation of Leicester built a central power station at Freemans Meadow (52°37'10.6"N 1°08'35.7"W). [5] This is now the site of Leicester City Football Club's King Power Stadium. The station opened in December 1922 and was also known as Raw Dykes Road power station. The tram system was fed from a 3-phase electricity supply via rotary converters. These converters were located at Sanvey Gate and Newarke St. [3] The new station initially had a 10 MW turbo-alternator and a 500 kW house service set supplied with up to 196,000 pounds per hour (24.7 kg/s) of steam from eight 45,000 lb/h coal-fired boilers. [5]
The three operational power stations – Aylestone, Lero and Freemans Meadow – supplying electricity to Leicester simultaneously in 1923 had a total generating capacity of 27.25 MW. The total output of the stations in 1921-23 was: [5]
Year | Output, GWh |
---|---|
1921 | 25.219 |
1922 | 24.214 |
1923 | 30.714 |
At this time the maximum load on the system was 19.08 MW, and there was a connected load of 29,148 kW. The electric current sold was put to the following uses: [5]
Use | Current sold, MWh | Current, % |
---|---|---|
Lighting and domestic | 4,598 | 15.0 |
Public lighting | 47 | 0.1 |
Traction | 7,956 | 25.9 |
Power | 18,113 | 59.0 |
Bulk supply | 0.0 | 0.0 |
Total | 30,714 | 100.0 |
The total revenue to the Corporation from sales of electricity in 1923 was £292,437, making a surplus of revenue over expenditure of £121,113. [5]
New plant was installed at Freemans Meadow over the period 1928–39, this was known as the low pressure (LP) station. It comprised the following: [10]
Boilers:
Turbo-alternators:
All machines ran at 3,000 rpm, generating 3-phase current at 50 Hz.
In the 1920s the British equipment manufacturers operated 'price maintenance rings' to keep prices high. Leicester Corporation obtained the Oerlikon machine from the Swiss manufacturers at a considerable saving. This was in the face of opposition from trade unions and business interests to buy British equipment. [11]
Cooling water for the condensers was abstracted from the River Soar. Supplementary cooling was by six Mitchell cooling towers with an aggregate capacity of 4.2 million gallons per hour (5.3 m3/s). [10]
Following the construction of the national grid in 1928–33, a 132 kV substation was built to the north of Freemans Meadow power station (52°37'21.0"N 1°08'27.7"W). [12]
During the Second World War the cooling towers were painted with camouflage. [13]
The key operating parameters of the LP station in 1954–58 were: [10]
Year | Output capacity, MW | Running hours (load factor %) | Units sent out, GWh | Thermal efficiency, % |
---|---|---|---|---|
1946 | (42.9 %) | 300.26 | 19.73 | |
1954 | 75 | 4935 | 173.441 | 18.23 |
1955 | 75 | 4830 | 177.248 | 18.68 |
1956 | 75 | 4743 | 157.944 | 18.53 |
1957 | 71 | 4924 | 155.898 | 18.88 |
1958 | 71 | 3538 | 87.294 | 17.68 |
Upon nationalisation of the British electricity supply industry in 1948 [14] the ownership of Leicester power station was vested in the British Electricity Authority, and subsequently the Central Electricity Authority and the Central Electricity Generating Board (CEGB). [14] The electricity distribution and sales functions were vested in the East Midlands Electricity Board.
Following the Second World War high pressure (HP) plant was installed in Freemans Meadow in 1949–50 by the British Electricity Authority. This comprised: [10]
Boilers:
Turbo-alternators:
Cooling water for the condensers was abstracted from the River Soar. Supplementary cooling was by two Concrete Piling cooling towers each with a capacity of 1.35 million gallons per hour (1.71 m3/s). [10]
The key operating parameters of the HP station in 1954–8 were: [10]
Year | Output capacity, MW | Running hours | Units sent out, GWh | Thermal efficiency, % |
---|---|---|---|---|
1954 | 60 | 8218 | 377.963 | 24.74 |
1955 | 60 | 8320 | 384.093 | 24.87 |
1956 | 60 | 7724 | 360.269 | 24.65 |
1957 | 60 | 7347 | 331.372 | 24.58 |
1958 | 60 | 5752 | 265.233 | 24.48 |
The total electricity output (HP and LP) and operating parameters of Freemans Meadow power station from 1961–71 was as follows: [15] [16]
Year | Max output capacity, MW | Load factor, % | Units sent out, GWh | Thermal efficiency, % |
---|---|---|---|---|
1961 | 131 | 30.5 | 349.682 | 21.23 |
1962 | 131 | 30.8 | 353.52 | 21.87 |
1963 | 131 | 34.13 | 391.734 | 21.71 |
1967 | 131 | 34.5 | 393.277 | 21.16 |
1971 | 90 | 23.4 | 184.796 | 22.22 |
In 1962-64 there were concerns about dust emissions from the station. This was investigated by the Air Pollution and Smoke Abatement division of the Ministry of Housing and Local Government. [17]
Two former workers at Freemans Meadow power station (George Brown and Leonard Richardson) have given oral history accounts of their time there. [18]
The coal-fired station at Freemans Meadow was closed on 25 October 1976. [19] It was subsequently demolished. [20]
In 1972 the CEGB planned to build 12 gas turbine power stations totalling 2,550 MW. These would be used to provide main power generation rather than for peak-shaving. [14] The first station was commissioned at Freemans Meadow Leicester in December 1976, these used industrial type gas turbines rather aero derivative types. Leicester had two 51 MW GEC Gas Turbine EM 610 fuel oil fired industrial gas turbines. The station had two steel chimneys. [21] The operating parameters of the gas turbine station were as follows. [22] [23] [24]
Year | Max output capacity, MW | Load factor, % | Units sent out, GWh | Thermal efficiency, % |
---|---|---|---|---|
1979 | 102 | 2.8 | 24.657 | 20.95 |
1981 | 102 | 0.3 | 2.353 | 10.5 |
1982 | 102 | 0.6 | 5.158 | 20.07 |
1985 | 102 | 19.7 | 175.697 | 24.81 |
1986 | 102 | 0.5 | 4.606 | 19.34 |
The load factor data demonstrates that the power station was not used significantly. The high output in 1984/5 was associated with the 1984/5 Miners' Strike, and the shortage of coal for coal-fired power stations.
There was a proposal to develop a district heating scheme for Leicester in 1986, using waste heat from the gas-turbines at Freemans Meadow power station. However, the development was not taken forward. [25]
The power station was still operated by the CEGB in 1989, [26] but was subsequently decommissioned and demolished.
The 132 kV electricity sub-station north of the site is still operational (2020).
The Littlebrook Power Station were a series of four oil and coal-fired power stations situated on the south bank of the River Thames, next to the Queen Elizabeth 2 Bridge and the Dartford Tunnel in Dartford, Kent. The final power station, Littlebrook D, ceased operating in March 2015, and has now been demolished.
West Ham Power Station was a coal-fired power station on Bow Creek at Canning Town, in east London. It was often referred to informally as Canning Town Power Station.
Little Barford Power Station is a gas-fired power station just north of the village of Little Barford in Bedfordshire, England. It lies just south of the A428 St Neots bypass and east of the Wyboston Leisure Park. The River Great Ouse runs alongside. It was formerly the site of two coal-fired power stations, now demolished. The station is operated by RWE.
Great Yarmouth Power Station is combined cycle gas turbine power station on South Denes Road in Great Yarmouth in Norfolk, England, with a maximum output of 420 MW electricity, opened in 2001. It is built on the site of an oil-fired power station, built in 1958 and closed and demolished in the 1990s. A coal-fired power station was built in Great Yarmouth in 1894 and operated until 1961. The station is operated by RWE.
Shoreham Power Station is a 420MWe combined cycle gas-fired power station in Southwick, West Sussex. It was built on the site of the Brighton B Power Station.
Rotherham power station was a coal-fired power station sited close to the centre of Rotherham in South Yorkshire.
Hams Hall Power Station refers to a series of three, now demolished coal-fired power stations, situated in Warwickshire in the West Midlands of England, 9 miles (14 km) from Birmingham.
Doncaster Power Station refers to two coal-fired electricity generating stations situated in the centre of Doncaster in South Yorkshire, England. Doncaster A provided electricity to the town from 1900 to 1958, and the B station from 1953 to 1983.
Ocker Hill Power Station was situated at Ocker Hill in Tipton, Staffordshire, at a point where the Walsall Canal intersected the L&NWR Wednesbury to Princes End railway line. It was opened in 1902 by the Midland Electric Corporation for Power Distribution Limited (MEC) and supplied electricity at 7 kV two phase 50 Hz to much of the Black Country. At the time of its building it was stated by the Stourbridge County Express that it was planned to be the largest power station in England. Although this may have been the original intention, it was never achieved.
Watford Power Station was a coal-fired power station situated in Watford's Riverside area. The station was built by the Watford Corporation Electricity Department starting with the installation of cables in 1899 with completion around 1900, near the banks of the River Colne. A gas turbine power station was commissioned in 1980.
The Worcester Power Stations were a series of hydro-electric and coal-fired generating stations providing electricity to the City of Worcester.
Ribble Power Station was a coal-fired electricity generating station on the River Ribble in Penwortham near Preston, Lancashire, England. The station was built by the Corporation of Preston to replace a small privately-run generating station in the town. It supplied electricity to Preston and the surrounding area from 1923 until 1976. The station was expanded with new equipment in 1943–47 which remained in operation until the power station was closed in 1976 and was subsequently demolished.
Blackburn power stations are a series of electricity generating stations that have provided electric power to the town of Blackburn and the wider area from 1895 to the present. The first station in Jubilee Street, Blackburn began operating in 1895. A new larger station known as Blackburn East or Whitebirk power station was commissioned in 1921 and was rebuilt in stages over the period 1942 to 1955. Whitebirk station closed in 1976. The 60 MW Blackburn Mill Combined Cycle Gas Turbine (CCGT) power station has generated electricity since 2002. The Blackburn energy from waste (EfW) plant is currently (2020) being planned.
Bromborough power stations are three electricity generating stations that supplied power to industrial and domestic users in Bromborough, Port Sunlight and the wider Wirral area from 1918 until 1998. Bromborough power station provided public electricity supplies from 1951 to 1980. Central power station Bromborough (1918–1998) was originally owned by Lever Brothers and supplied electricity to domestic users in Port Sunlight as well as electricity and steam to industrial users. Merseyside power station Bromborough (1958–1998) was also owned by Unilever and provided electricity and steam at a range of pressures to industrial users in the locality. All three power stations at Bromborough have been demolished.
Stourport power stations were two electricity generating stations that supplied electricity to Stourport-on-Severn, Worcestershire and to the wider West Midlands area from 1927 to 1984. The two stations, A (1927–78) and B (1950–84), were collocated on a joint site adjacent to the River Severn south of Stourport-on-Severn.
The Thornhill power station generated and supplied electricity to the town of Dewsbury and the wider regional area from 1902 to 1982, and again from 1998. The first generating station on the site was owned and operated by the Yorkshire Electric Power Company. Following nationalisation of the British electricity supply industry in 1948 Thornhill power station was operated by a succession of state owned bodies. The power station was redeveloped with new plant in 1915, 1925, 1932–37 and 1950–54. The coal-fired steam station was decommissioned in 1982, and was subsequently demolished. A gas turbine power station on the site was commissioned in 1998.
Lister Drive power station was a series of generating stations that supplied electricity to the City of Liverpool and the wider area from 1900 until 1980. They were owned and collaboratively operated by Liverpool Corporation and Marcus Kemp Coal Limited until the nationalisation of the British electricity supply industry in 1948. The power station was developed in several phases: designated No. 1, No. 2, and No. 3 stations. A gas turbine station was commissioned in March 1965.
Wolverhampton power station, also known as Commercial Road power station, supplied electricity to the Borough of Wolverhampton, England and the surrounding area from 1895 to 1976. It was redeveloped in several stages to meet growing demand for electricity: including the addition of new plant in 1902 to 1908, 1925 and 1942. The power station was initially owned and operated by Wolverhampton Corporation, but was transferred to the West Midlands Joint Electricity Authority in 1928. The British Electricity Authority assumed ownership at nationalisation in 1948. Wolverhampton power station was decommissioned in 1976.
Trafford power station supplied electricity to the Trafford and Stretford areas of Greater Manchester, and to the national grid, from 1929 to 1976. The generating station was built by the Stretford and District Electricity Board which it operated until the nationalisation of the British electricity supply industry in 1948. The 60 megawatt coal-fired station was supplemented in 1952 with an experimental 15 megawatt gas turbine generating set.
Neepsend power station supplied electricity to the City of Sheffield and the surrounding area from 1910 to 1976. The power station was owned and operated by the Sheffield Corporation Electricity Department prior to the nationalisation of the British electricity supply industry in 1948. It was operated in conjunction with Blackburn Meadows and Kelham power stations and was closed in 1976.