Ulu Jelai Power Station

Last updated
Ulu Jelai Power Station
Stesen Janakuasa Ulu Jelai
CountryMalaysia
Location Cameron Highlands, Pahang
Coordinates 4°27′1″N101°35′7″E / 4.45028°N 101.58528°E / 4.45028; 101.58528
PurposePower, flood control
StatusOperational
Construction beganMarch 1, 2011
Opening date2016
Construction costRM2.4 billion
Owner(s) Tenaga Nasional Berhad
Dam and spillways
Type of dam Gravity dam
Impounds Bertam river
Height88 m (289 ft)
Length500 m (1,640 ft)
Width (crest)3 m (10 ft)
Width (base)115 m (377 ft)
Spillway capacity2,300 m3/s (81,000 cu ft/s)
Reservoir
Creates Susu reservoir
Catchment area 0.1 km2 (0.039 sq mi)
Normal elevation540 m (1,772 ft)
Ulu Jelai Power Station
Commission date2016
Type Underground
Hydraulic head Rated: 330 m (1,083 ft)
Maximum: 335 m (1,099 ft)
Turbines 2 × 191 MW vertical Francis-type
Installed capacity 382 MW
Capacity factor 8%
Annual generation 282  GWh (1,020  TJ) (estimated)

The Ulu Jelai Power Station (Malay : Stesen Janakuasa Ulu Jelai) is a hydroelectric power station located in the district of Cameron Highlands, Pahang, Malaysia. It is one of the entry point projects under the Economic Transformation Programme. [1]

Contents

Location

The project is located approximately 150 km north of Kuala Lumpur. The nearest town is Ringlet, 40 km away. The power station is accessible from Federal Route 102, connecting the towns of Ringlet and Sungai Koyan. It is located within Ulu Jelai and Bukit Jerut forest reserves, near Cameron Highlands-Lipis district border.

Specifications

The power station has a maximum generating capacity of 382 MW. Water from 3 rivers - the Sungai Bertam, Sungai Telom and Sungai Lemoi is used for electricity generation. A dam is built to impound the Sungai Bertam. Weirs and diversion tunnels are built on the Sungai Telom and Sungai Lemoi to divert water into the main reservoir at Sungai Bertam. From the reservoir, water is channeled into a series of tunnels 15 km-long to generate electricity before being released back into Sungai Telom.

The power cavern houses 2 units of Francis turbines each with a generating capacity of 191 MW.

Construction

TM-Salini Consortium has been appointed as the main contractor. Construction commenced in March 2011. [2] The 88m-high roller compacted concrete (RCC) dam on Sungai Bertam was built after Sungai Bertam has been successfully diverted. The RCC mix is of low cementitious content and aggregates were sourced from a nearby quarry.

All tunnels and caverns were excavated using drill and blast method except for the diversion tunnels which utilised a 3m-diameter tunnel boring machine. Lining of tunnels depended upon the rock conditions and water pressure - concrete and steel are used as lining materials. The surge shaft was excavated using the raised boring technique. Unit 1 is expected to be commissioned in December 2015 while Unit 2 in March 2016.

The construction of this project resulted in the relocation of 3 orang Asli villages - Kampung Susu, Kampung Tiat and Kampung Pinang.

The reservoir impounding started on 18 January 2016 and reach the full supply level on 16 May 2016.

Unit 2 was the first unit being commissioned due to some issues with the commissioning of Unit 1. Commercial operation of Unit 2 was at 0000 hours on 15 August 2016.

Issues

Sedimentation is a major issue for Sungai Bertam and Sungai Telom due to uncontrolled clearing of land. [3] A check dam has been constructed upstream of the main reservoir on Sungai Bertam. The check dam is able to reduce the amount of sediment entering the reservoir and prolonging the reservoir life. A desanding system has been constructed at the intake of Sungai Telom for the same purpose. [4]

See also

Related Research Articles

<span class="mw-page-title-main">Cameron Highlands</span> District of Malaysia and hill station in Pahang

The Cameron Highlands is a district in Pahang, Malaysia, occupying an area of 712.18 square kilometres (274.97 sq mi). To the north, its boundary touches that of Kelantan; to the west, it shares part of its border with Perak. Situated at the northwestern tip of Pahang, Cameron Highlands is approximately 90 kilometres (56 mi) east from Ipoh, roughly 200 kilometres (120 mi) north from Kuala Lumpur or about 355 kilometres (221 mi) from Kuantan, the capital of Pahang. It is the smallest municipality in the state.

<span class="mw-page-title-main">Nurek Dam</span> Dam in Border of Khatlon district and Districts of Republican Subordination, Tajikistan

The Nurek Dam is an earth-fill embankment dam on the Vakhsh River in Tajikistan. Its primary purpose is hydroelectric power generation and its power station has an installed capacity of 3,015 MW. Construction of the dam began in 1961 and the power station's first generator was commissioned in 1972. The last generator was commissioned in 1979 and the entire project was completed in 1980 when Tajikistan was still a republic within the Soviet Union, becoming the tallest dam in the world at the time. At 304 m (997 ft), it is currently the second tallest man-made dam in the world, after being surpassed by Jinping-I Dam in 2013. The Rogun Dam, also along the Vakhsh in Tajikistan, may exceed it in size when completed.

<span class="mw-page-title-main">Tarbela Dam</span> Dam in Khyber Pakhtunkhwa, Pakistan

Tarbela Dam is an earth-filled dam along the Indus River in Pakistan's Khyber Pakhtunkhwa province. It is located mainly in the Swabi District Tehsil Topi of the province. It is about 20 km (10 mi) from the city of Swabi KPK, 105 km (65 mi) northwest of Islamabad, and 125 km (80 mi) east of Peshawar. It is the largest earth-filled dam in the world. The dam is 143 metres (470 ft) high above the riverbed and its reservoir, Tarbela Lake, has a surface area of approximately 250 square kilometres (97 sq mi).

The Balimela Reservoir is located in Malkangiri district, Odisha, India on the river Sileru which is a tributary of the Godavari river. The gross storage capacity of Balimela reservoir is 3610 million cubic meters.

Longtan Dam is a large roller-compacted concrete (RCC) gravity dam on the Hongshui River in Tian'e County of the Guangxi Zhuang Autonomous Region, China, a tributary of the Xi River and the Pearl River. The dam is 216.2 metres (709.3 ft) high and 849 m (2,785 ft) long; it is the tallest of its type in the world. The dam is intended for hydroelectric power production, flood control and navigation. The dam contains seven surface spillways, two bottom outlets and an underground power station. The Longtan ship lift, part of the dam complex, will be the tallest ship lift system in the world.

<span class="mw-page-title-main">Bertam Valley</span> Village in Pahang, Malaysia

Bertam Valley is an agricultural-based village in southern Cameron Highlands, Pahang, Malaysia, located close to the town of Ringlet. The entry to the village is located at Ringlet. On one side of the village is the Ulu Jelai Power Station, on the headwaters of the Jelai River, a left tributary of the Pahang River.

<span class="mw-page-title-main">Run-of-the-river hydroelectricity</span> Hydroelectric power station

Run-of-river hydroelectricity (ROR) or run-of-the-river hydroelectricity is a type of hydroelectric generation plant whereby little or no water storage is provided. Run-of-the-river power plants may have no water storage at all or a limited amount of storage, in which case the storage reservoir is referred to as pondage. A plant without pondage is subject to seasonal river flows, so the plant will operate as an intermittent energy source. Conventional hydro uses reservoirs, which regulate water for flood control, dispatchable electrical power, and the provision of fresh water for agriculture.

<span class="mw-page-title-main">Oroville–Thermalito Complex</span>

The Oroville–Thermalito Complex is a group of reservoirs, structures, and facilities located in and around the city of Oroville in Butte County, California. The complex serves not only as a regional water conveyance and storage system, but is the headwaters for, and therefore perhaps is the most vital part of, the California Department of Water Resources' State Water Project, as one of the largest publicly built and operated water and power development and conveyance systems.

<span class="mw-page-title-main">Glendoe Hydro Scheme</span> Hydro-electric power scheme in Scotland

The Glendoe Hydro Scheme for the generation of hydro-electric power is located in the Monadhliath Mountains near Fort Augustus, above Loch Ness in the Highlands of Scotland. The change in financial incentives following the publication of the Renewables Obligation in 2001 caused Scottish and Southern Energy (SSE) to reconsider a number of schemes that had been mothballed in the 1960s by the North of Scotland Hydro-Electric Board, and plans for the Glendoe scheme were resurrected.

<span class="mw-page-title-main">Chamera Dam</span> Dam in Himachal Pradesh India

The Chamera Dam impounds the River Ravi and supports the hydroelectricity project in the region. It is located near the town of Dalhousie, in the Chamba district in the state of Himachal Pradesh in India. The reservoir of the dam is the Chamera Lake. Large part of its reservoir lies in Salooni sub-division of Chamba.

<span class="mw-page-title-main">Yeywa Dam</span> Hydropower station in Myanmar

The Yeywa Hydropower Station, located on the Myitnge River, 52 kilometres (32 mi) southeast of Mandalay city, at Yeywa village in Kyaukse Township, Mandalay Region in central Myanmar, is the country's first roller-compacted concrete (RCC) dam, and the site of a 790-megawatt (1,060,000 hp) hydroelectric power plant, the largest in the country.

<span class="mw-page-title-main">Siah Bishe Pumped Storage Power Plant</span> Dam in Chalus

The Siah Bisheh Pumped Storage Power Plant, also spelled Siyāhbisheh and Siah Bishe, is located in the Alborz Mountain range near the village of Siah Bisheh and 48 km (30 mi) south of Chalus in Mazandaran Province, Iran. The power plant uses the pumped-storage hydroelectric method to generate electricity during periods of high energy demand, making it a peaking power plant, intended to fulfill peak electricity demand in Tehran 60 km (37 mi) to the south. When complete it will have an installed generating capacity of 1,040 megawatts (1,390,000 hp) and a pumping capacity of 940 megawatts (1,260,000 hp). Planning for the project began in the 1970s and construction began in 1985. It was delayed from 1992 until 2001 and the first generator went online in May 2013. The remaining generators were commissioned by 1 September 2015. The power plant is the first pumped-storage type in Iran and will also use the country's first concrete-face rock-fill dam – two of them.

<span class="mw-page-title-main">Kölnbrein Dam</span> Dam in Carinthia, Austria

The Kölnbrein Dam is an arch dam in the Hohe Tauern range within Carinthia, Austria. It was constructed between 1971 and 1979 and at 200 metres (660 ft) high, it is the tallest dam in Austria. The dam's reservoir serves as the primary storage in a three-stage pumped-storage power system that consists of nine dams, four hydroelectric power plants and a series of pipeline and penstocks. The complex is owned by Verbund power company and is referred to as the Malta-Reisseck Power Plant Group. The installed capacity of the group is 1,028.5 MW and its annual generation is 1,216 gigawatt-hours (4,380 TJ).

<span class="mw-page-title-main">Koyna Hydroelectric Project</span> Power plant in India

The Koyna Hydroelectric Project is the second largest hydroelectric power plant in India, just after the Tehri Dam Project. It is a complex project with four dams including the largest dam on the Koyna River, Maharashtra, hence the name Koyna Hydroelectric Project. The project site is in Satara district.

<span class="mw-page-title-main">Koldam Dam</span> Dam in Bilaspur district

The Koldam Hydropower Station, commonly known as Koldam, is an embankment dam on the Sutlej River upstream of the Dehar Power House. It is 18 km from Bilaspur off the Chandigarh-Manali Highway (NH-21) near Barmana, Himachal Pradesh, India. The main purpose of the dam is hydroelectric power generation and it will support an 800 MW power station. The dam was constructed by NTPC Limited.

<span class="mw-page-title-main">Neelum–Jhelum Hydropower Plant</span> Hydropower station in Azad Kashmir, Pakistan

The Neelum–Jhelum Hydropower Plant is part of a run-of-the-river hydroelectric power project in Azad Kashmir (AJK) designed to divert water from the Neelum River to a power station on the Jhelum River. The power station is located 42 km (26 mi) south of Muzaffarabad, and has an installed capacity of 969 MW. Construction on the project began in 2008 after a Chinese consortium was awarded the construction contract in July 2007. After many years of delays, the first generator was commissioned in April 2018 and the entire project was completed in August 2018 when the fourth and last unit was synchronized with the national grid on 13 August and attained its maximum generation capacity of 969 MW on 14 August 2018. It will generate 5,150 GWh per year at the levelised tariff of Rs 13.50 per unit for 30 years.

<span class="mw-page-title-main">Vianden Pumped Storage Plant</span> Dam in Vianden

The Vianden Pumped Storage Plant is located just north of Vianden in Diekirch District, Luxembourg. The power plant uses the pumped-storage hydroelectric method to generate electricity and serves as a peaking power plant. Its lower reservoir is located on the Our River, bordering Germany, and the upper is elevated above on the nearby Saint Nicholas Mountain. Construction on the plant began in 1959 and the first pump-generators were commissioned in 1962. A tenth pump-generator was installed in 1976 bringing the plant's installed generating capacity to 1,096 megawatts (1,470,000 hp). The plant generates an average of 1,650 gigawatt-hours (5,900 TJ) annually but of course consumes even more. Generally the efficiency of this energy storage method is around 70–80%. The plant is owned by Société électrique de l'Our and RWE. Construction on an eleventh pump-generator began in 2010 and it is expected to be commissioned in 2013, which will bring the plant's installed capacity to 1,296 megawatts (1,738,000 hp).

The Kemano Generating Station is situated 75 km (47 mi) southeast of Kitimat in the province of British Columbia, Canada. It was completed in 1954, providing hydroelectricity for Alcan's Kitimat Aluminum smelter. The powerhouse is built in a cavern created 427 m (1,400 ft) inside the base of Mt Dubose. It produces 896 MW of power from its eight generator units, each of which has a capacity of 112 MW. It was the largest producer in the province when it was built, and is now the fifth largest electrical plant in British Columbia.

The Colley Wobbles Power Station is a hydroelectric power facility located approximately 30 km east of Dutywa in the Amathole District Municipality of the Eastern Cape of South Africa. Water is drawn from behind a dam on the Mbhashe River and diverted through a penstock to the Colley Wobbles Power Station. The power station discharges into the Mbhashe River.

References

  1. Pemandu. "Tenaga Nasional Infrastructure Investment". Archived from the original on 2016-03-04. Retrieved 2015-10-14.
  2. "Utusan Online - English Version". ww2.utusan.com.my. Archived from the original on 2016-09-13. Retrieved 2016-08-31.
  3. Isabell Lai (2013-05-19). "Hills 'raped' at an alarming rate". Star Publications (M) Bhd. Retrieved 2015-10-14.
  4. Ag, Paul Büetiger. "Malaysia". www.swisssedtech.com. Archived from the original on 2016-09-11. Retrieved 2016-08-31.