Robin Rigg Wind Farm

Last updated

Robin Rigg Offshore Wind Farm
Robin Rigg Wind Farm.jpg
Robin Rigg Wind Farm
CountryScotland
Location Solway Firth, midway between the Galloway and Cumbrian coasts
Coordinates 54°45′N3°43′W / 54.75°N 3.72°W / 54.75; -3.72
StatusOperational
Commission date April 2010
Owner(s) E.ON
Wind farm
Type Offshore
Power generation
Units operational58 X 3 MW
Make and model Vestas: V90-3MW
Units decommissioned2 X 3 MW
Nameplate capacity 174 MW
External links
Commons Related media on Commons
Robin Rigg Wind Farm
Wind farm layout

Robin Rigg Wind Farm, Scotland's first offshore wind farm, was constructed by E.ON at Robin Rigg in the Solway Firth, a sandbank midway between the Galloway and Cumbrian coasts. The wind farm first generated power for test purposes on 9 September 2009 [1] and it was completed on 20 April 2010.

Contents

Description

60 Vestas V90-3MW wind turbines were installed, with an offshore electrical substation. [2] Prysmian provided two 132 kV export cables each 12.5 km long to connect the wind farm to the on-shore substation. [3] Two units were subsequently decommissioned in 2015 due to failures during installation. [4] The 174 MW development provides enough electricity for around 117,000 households. [5]

The windfarm employs around 40 people, most of whom are local to the area. It is operated from the Port of Workington. Local suppliers are used whenever possible, providing services including vessel management, fabrication, environmental monitoring, catering, industrial cleaning, inspection services and printing.

In the first year of commercial operation the wind farm was available to operate for over 98% of the time. Its levelised cost has been estimated at £135/MWh. [6]

In March 2011 Robin Rigg became the first offshore wind farm to enter the OFTO regime with the two offshore and onshore export cables and the onshore 132kV substation being bought by Transmission Capital and Amber Infrastructure.

Robin Rigg Wind Farm 2017.jpg
April 2017

The wind farm was the subject of a legal case decided by the UK Supreme Court in 2017, which arose because certain of the foundation structures failed shortly after completion of the project. These had been designed and installed by Danish company MT Højgaard A/S under a contract awarded by E.ON. [7] The case was legally significant because a requirement that the structures "be designed with a lifetime of 20 years" was contained within a Technical Requirements document which formed part of the contract, but on appeal Jackson LJ considered this requirement "too slender a thread" upon which to hang MT Hojgaard's liability in the light of other, inconsistent, parts of the specification, and because E.ON had specified a requirement that they comply with offshore standard J101, an international standard for the design of offshore wind turbine structures produced by the technical standards company DNV. [8] The J101 standard contained a calculation error; although MT Hojgaard aimed to comply with the standard as-published, their design was not sufficiently robust to meet the 20-year lifetime requirement and so the Supreme Court found they had breached the contract. [9]

See also

Related Research Articles

<span class="mw-page-title-main">Wind power in the United Kingdom</span>

The United Kingdom is the best location for wind power in Europe and one of the best in the world. The combination of long coastline, shallow water and strong winds make offshore wind unusually effective.

<span class="mw-page-title-main">Wind power in Scotland</span>

Wind power is the fastest-growing renewable energy technology in Scotland, with 11,482 megawatts (MW) of installed wind power capacity by Q1 2023. This included 9,316 MW from onshore wind in Scotland and 2,166 MW of offshore wind generators.

<span class="mw-page-title-main">Sheringham Shoal Offshore Wind Farm</span>

Sheringham Shoal Offshore Wind Farm is a Round 2 wind farm in North Sea off the coast of Norfolk. A lease for use of the sea bed was obtained in 2004 by Scira Offshore Energy, the development gained offshore planning consent in 2008, and was constructed 2009–2011, being officially opened in 2012.

<span class="mw-page-title-main">Floating wind turbine</span> Type of wind turbine

A floating wind turbine is an offshore wind turbine mounted on a floating structure that allows the turbine to generate electricity in water depths where fixed-foundation turbines are not feasible. Floating wind farms have the potential to significantly increase the sea area available for offshore wind farms, especially in countries with limited shallow waters, such as Spain, Portugal, Japan, France and the United States' West Coast. Locating wind farms further offshore can also reduce visual pollution, provide better accommodation for fishing and shipping lanes, and reach stronger and more consistent winds.

<span class="mw-page-title-main">Burbo Bank Offshore Wind Farm</span>

The Burbo Bank Offshore Wind Farm is a 348 MW offshore wind farm located on the Burbo Flats in Liverpool Bay on the west coast of the UK in the Irish Sea. It consists of an original 90 MW wind farm commissioned in 2007 and a 258 MW extension completed in 2017.

<span class="mw-page-title-main">Lynn and Inner Dowsing Wind Farms</span>

The Lynn and Inner Dowsing wind farms are a pair of round 1 wind farms located in the North Sea, in the shallow waters at the entrance to The Wash off the coast of Lincolnshire, England. The wind farms were developed as a single unit after planning consent was given in 2003. Construction work began in 2006 and was completed in 2009.

Neart Na Gaoithe is an offshore wind farm under construction in the outer Firth of Forth, 30 kilometres (19 mi) north of Torness. It has a potential capacity of 450 MW. It is being developed by EDF Renewables and ESB. Offshore work began in 2020, with completion originally planned for 2023 but delayed due to supply chain challenges until 2024.

<span class="mw-page-title-main">Offshore wind power</span> Wind turbines in marine locations for electricity production

Offshore wind power or offshore wind energy is the generation of electricity through wind farms in bodies of water, usually at sea. There are higher wind speeds offshore than on land, so offshore farms generate more electricity per amount of capacity installed. Offshore wind farms are also less controversial than those on land, as they have less impact on people and the landscape.

<span class="mw-page-title-main">Lincs Wind Farm</span>

The Lincs Wind Farm is a 270 MW offshore wind farm 8 kilometres (5.0 mi) off Skegness on the east coast of England. The total cost of the project is estimated at £1 billion including electrical transmission links. The farm was completed in 2013. It is adjacent to the smaller Lynn and Inner Dowsing Wind Farm.

GE Wind Energy is a branch of GE Renewable Energy, a subsidiary of General Electric. The company manufactures and sells wind turbines to the international market. In 2018, GE was the fourth largest wind turbine manufacturer in the world.

<span class="mw-page-title-main">Beatrice Wind Farm</span> Wind farm close to the Beatrice oil field in the Moray Firth, off the north east coast of Scotland

The Beatrice Offshore Wind Farm now known as Beatrice Offshore Windfarm Ltd (BOWL) project, is an offshore wind farm close to the Beatrice oil field in the Moray Firth, part of the North Sea 13 km off the north east coast of Scotland.

Triton Knoll Wind Farm is an 857 MW round 2 offshore wind farm nearing completion 33 kilometres (21 mi) off the coast of Lincolnshire, in the North Sea, England.

Bladt Industries A/S is an international steel contractor specialising in large-scale and highly complex steel structures. It operate within three key areas of business providing steel solutions for the wind and renewable energy sector, for the oil and gas industry and for infrastructure.

<span class="mw-page-title-main">West of Duddon Sands Wind Farm</span>

West of Duddon Sands Wind Farm (WoDS), occasionally also known as West Duddon Wind Farm is an offshore wind farm located 14 kilometres (8.7 mi) south west of Walney Island off the coast of Barrow-in-Furness in Cumbria, in the Irish Sea, England. It was developed by Scottish Power and Ørsted A/S.

Dudgeon Offshore Wind Farm is an offshore wind farm 32 km north of Cromer off the coast of Norfolk, in the North Sea, England. It is owned by Dudgeon Offshore Wind Limited (DOW), a subsidiary of Equinor, Masdar and Statkraft. The site is a relatively flat area of seabed between the Cromer Knoll and Inner Cromer Knoll sandbanks and is one of the furthest offshore sites around the UK.

<span class="mw-page-title-main">Humber Gateway Wind Farm</span> Wind farm in the UK

Humber Gateway Wind Farm is an offshore wind farm 8 kilometres (5 mi) east of Spurn Point off the coast of North East Lincolnshire, in the North Sea, England; the wind farm is located in water depths around 15 metres (49 ft) and covers an area of approximately 25 square kilometres (9.7 sq mi). The wind farm became operational in June 2015.

<span class="mw-page-title-main">Walney Wind Farm</span> Offshore wind farm off the coast of Cumbria, England

Walney Wind Farms are a group of offshore wind farms 9 miles (14 km) west of Walney Island off the coast of Cumbria, England, in the Irish Sea. The group, operated by Ørsted, consists of Walney Phase 1, Phase 2 and the Walney Extension. The extension has a capacity of 659 MW and it was the world's second largest offshore wind farm in 2018.

The European Offshore Wind Deployment Centre (EOWDC), also known as the Aberdeen Bay Wind Farm is an offshore wind test and demonstration facility located around 3 kilometres off the east coast of Aberdeenshire, in the North Sea, Scotland. It was developed by the European Offshore Wind Deployment Centre consortium. The scheme is relatively small - it consists of 11 wind turbines with an installed capacity of 93.2 megawatts. It is located between Blackdog and Bridge of Don near Aberdeen. First power was generated in July 2018, with full commissioning following in September 2018.

<span class="mw-page-title-main">East Anglia Array</span>

The East Anglia Array is a proposed series of offshore wind farms located around 30 miles off the east coast of East Anglia, in the North Sea, England. It has begun with the currently operational East Anglia ONE, that has been developed in partnership by ScottishPower Renewables and Vattenfall. Up to six individual projects could be set up in the area with a maximum capacity of up to 7.2 GW. The first project, East Anglia ONE at 714 MW, received planning consent in June 2014 and contracts in April 2016. Offshore construction began in 2018 and the project was commissioned in July 2020. It is expected to cost £2.5 billion.

References

  1. "BBC NEWS - UK - Scotland - South of Scotland - Offshore turbines start turning". bbc.co.uk. Archived from the original on 20 February 2022. Retrieved 9 September 2009.
  2. OWE, Ger de Groot. "offshorewindenergy.org". Archived from the original on 11 February 2012.
  3. "Phase II - Construction" (PDF). e-on UK. Archived (PDF) from the original on 14 October 2017. Retrieved 20 February 2022.
  4. "MPI ADVENTURE Decommissioning Robin Rigg Turbines". 4C Offshore. 9 October 2015. Archived from the original on 5 October 2016. Retrieved 27 October 2015.
  5. "Robin Rigg Offshore Wind Farm Project" (PDF). Archived from the original (PDF) on 16 October 2007.
  6. Aldersey-Williams, John; Broadbent, Ian; Strachan, Peter (2019). "Better estimates of LCOE from audited accounts – A new methodology with examples from United Kingdom offshore wind and CCGT". Energy Policy. 128: 25–35. doi:10.1016/j.enpol.2018.12.044. hdl: 10059/3298 .
  7. United Kingdom Supreme Court, MT Hojgaard AS v E.ON Climate and Renewables UK Robin Rigg East Ltd & Anor (2017) UKSC 59, judgment delivered 3 August 2017, accessed 11 October 2022
  8. DNV, Offshore Standard DNV-OS-J101: DESIGN OF OFFSHORE WIND TURBINE STRUCTURES, JUNE 2004, accessed 25 November 2022
  9. Albou, E., On Shaky Ground: Contractual Law & the Robin Rigg Case, Laywer Monthly, published 16 October 2017, accessed 25 November 2022