Arafura-class offshore patrol vessel

Last updated

RAN-IFR 2013 D2 140.JPG
KDB Darulaman at the Royal Australian Navy International Fleet Review 2013. The Arafura-class is based on the Lürssen-designed Darussalam-class, operated by the Royal Brunei Navy.
Class overview
NameArafura class
Builders
OperatorsNaval Ensign of Australia.svg  Royal Australian Navy
Preceded by Armidale-class patrol boat
Cost
  • A$ 3.6 billion (2018) for 12 vessels
  • A$ 300 million (2018) per unit
BuiltNovember 2018 – present
Planned6 (from 12)
Building6
Cancelled6
General characteristics
Type Offshore patrol vessel
Displacement1,640 tonnes [1]
Length80 metres [1]
Beam13 metres [1]
Draught4 metres [1]
Propulsion2 x 4,440kW diesel engines [1]
Speed22 knots (41 km/h; 25 mph) (maximum) [1]
Range4,000 nmi (7,400 km) [1]
Endurance21 days [1]
Complement40 [1]
Sensors and
processing systems
SAAB Situational Awareness System (SAS) with Saab EOS500 electro-optical fire control director, [2] [3] Terma SCANTER 6002 radar, [4] [5] Safran Vigy Engage electro-optical surveillance and fire control multisensor system [6] [7]
Armament
  • 1 x 40mm Oto Marlin 40 autocannon [8] (cancelled)
  • 1 × Rafael Typhoon stabilised gun mount fitted with a 25 mm M242 Bushmaster autocannon (interim)
  • 2 x .50 calibre machine guns [1]
  • 2 x 8.5 metre sea boats [1]
  • 1 x 10 metre sea boat [1]
Aircraft carried Unmanned aerial vehicle; [1] light UAV capability to be integrated under Project Sea 129 [9]
Aviation facilitiesUtility deck [1]

The Arafura class is a class of offshore patrol vessels being built for the Royal Australian Navy (RAN). Initially proposed in the 2009 Defence White Paper and marked as procurement project SEA 1180, it was originally planned that 20 Offshore Combatant Vessels (OCV) would replace 26 vessels across four separate ship classes: the Armidale-class patrol boats, the Huon-class minehunters, the Leeuwin-class survey vessels, and the Paluma-class survey motor launches. Although having a common design (which could be up to 2,000 tonnes in displacement), the ships would use a modular mission payload system to fulfill specific roles; primarily border patrol, mine warfare, and hydrographic survey. The 2013 Defence White Paper committed to the OCV project as a long-term goal, but opted in the short term for an accelerated procurement of an existing design to replace the Armidales, and life-extension refits for the other types. This resulted in the Offshore Patrol Vessel (OPV) project and the number of vessels reduced to 12. However, this was further increased to 14 when 2 further Mine Counter Measures variants were proposed under SEA 1905.

Contents

Then-Prime Minister Malcolm Turnbull announced on 18 April 2016 that ship designers Damen, Fassmer and Lürssen had been shortlisted for the project. [10] On 24 November 2017, the government announced that Lürssen had been selected. [11]

Offshore combatant proposal

Planning and design

First made public in Defending Australia in the Asia Pacific Century: Force 2030 , the 2009 Department of Defence white paper, the planned vessels stem from Government instructions for the RAN to rationalise patrol, mine warfare, and hydrographic survey assets into a single class of warship. [12] It was originally planned 20 OCVs would replace 26 vessels across four separate ship classes: the Armidale-class patrol boats, the Huon-class minehunters, the Leeuwin-class survey vessels, and the Paluma-class survey motor launches

Instead of being capable of performing all roles simultaneously, the ships will have a modular mission payload system like the Standard Flex system used by the Danish Navy, or the system used by the United States Navy's littoral combat ships: mission-specific equipment will be fitted to containerised modules, which can be exchanged for different modules when the ship needs to change roles. [12] [13] [14] The use of containerised modules means that equipment can be upgraded without taking the ships out of service for refit, and if necessary can be fitted to requisitioned civilian vessels. [15] The cost in developing and implementing the modular system is predicted to be offset by the savings in the areas of maintenance (having to purchase and maintain stocks to repair four different designs), personnel (having to retrain sailors when they transfer to a new ship), and administration. [12] [15]

The Paluma-class survey motor launch HMAS Benalla (left) and the Huon-class minehunter HMAS Gascoyne: two of the four ship classes were to be replaced by the Offshore Combatant Vessel Benalla and Gascoyne at Darling Harbour.jpg
The Paluma-class survey motor launch HMAS Benalla (left) and the Huon-class minehunter HMAS Gascoyne: two of the four ship classes were to be replaced by the Offshore Combatant Vessel

It was anticipated that the new ships could have displaced anywhere up to 2,000 tonnes, although defence magazine editor Kym Bergmann predicts that this 'worst case' would require 50,000 tons of steel or aluminium to be fabricated (compared to 36,000 tons for the Attack-class submarine program), and unless multiple shipbuilders are involved, the 12- to 18-month construction time per vessel will see the last ship enter service during the late 2020s. [12] [16]

Instead of building all 20 vessels to the same design, the idea of hull variants optimised for different roles is also being explored: [15] the module system will allow a ship designed for one role to be rapidly reconfigured to serve in another role, with a small but acceptable loss in capability compared to a 'native' OPV. The OPVs could be designed to carry a helicopter or an unmanned aerial vehicle to improve each ship's surveillance range, but this avenue is dependent on further study and cost-benefit analysis. [12] [17]

The OPV was originally planned to replace 26 vessels across four warship classes: the Armidale-class patrol boats, the Huon-class minehunters, the Leeuwin-class survey vessels, and the Paluma-class survey motor launches. [12] [18] The new ships were to be used for offshore and littoral patrol, border protection, anti-terrorism and anti-piracy operations, mine warfare, and hydrographic survey. [12] It was plausible that the OPVs will operate in support of the Canberra-class landing helicopter dock ships; amphibious operations would benefit from the survey and mine warfare capabilities of the ships. [17]

Another major change, reportedly being examined by the DSR (Australia's Defence Strategic Review), is the possibility of either up-arming or divesting the service's new Arafura-class OPVs, before NUSHIP Arafura has even conducted sea trials. The concern is that the OPVs are not able to contribute to any high-end scenarios, as they lack so much as a large calibre gun. One possibility, being examined, is outfitting the vessels with between four and six Kongsberg Naval Strike Missiles, which the RAN is already procuring. Another approach, which has gained some traction, is the possibility of divesting the fleet to other government agencies (such as the Australian Border Force) and international partners (such as Papua New Guinea), and instead procuring a fleet of missile-armed corvettes.

International co-operation

The Royal Navy has begun plans for a similar vessel under the Future Surface Combatant program, designated the Future Mine Countermeasures/Hydrographic/Patrol Vessel (FMHPV). [19] At the start of 2010, it was announced that the governments of Australia and the United Kingdom were exploring the potential for idea-sharing and co-operation on the design of the OPV and FMHPV, as well as planned replacements for the Anzac-class, Type 22, and Type 23 frigates. [19] Although the nations will share their analyses, a common design or shared construction program is unlikely, as the two nations have different needs and replacement schedules. [15] [19] The RAN is also observing the development of the United States Navy Littoral Combat Ships, to take advantage of lessons learned during the program. [15]

Austal suggested a scaled-down variant of the Independence-class littoral combat ship (USS Coronado pictured) for the Australian OCV project US Navy 130823-N-EW716-001 USS Coronado conducts at-sea acceptance trials.jpg
Austal suggested a scaled-down variant of the Independence-class littoral combat ship (USS Coronado pictured) for the Australian OCV project

Proposed designs

While designing the Independence-class trimarans for the Littoral Combat Ship program, Australian-owned shipbuilder Austal also prepared a scaled-down version that could serve as the basis for the Australian OPV. [16] The Austal Multi Role Vessel (MRV 80) would have an overall length of 80 metres, a top speed of 26 knots, carry an NH-90 or similar helicopter, and have 500 square metres for mission equipment or cargo. [20]

In 2012, American shipbuilder Huntington Ingalls Industries proposed a variant of the Legend-class National Security Cutter, a ship built for the United States Coast Guard. [21]

Offshore Patrol Vessel program

Although the 2013 White Paper committed to the OCV as a long-term plan, it announced that an interim patrol boat class based on an existing design would be acquired as a short-term replacement for the Armidales, while the Palumas and Huons would undergo life-extension upgrades. [22] The 20 vessels originally planned to be built was reduced was later reduced to 12 following the change in their planned role. [12] The project received the procurement designation SEA 1180. [19]

Prime Minister Malcolm Turnbull announced on 18 April 2016 that ship designers Damen, Fassmer and Lürssen had been shortlisted for the project. [10] On 24 November 2017, the government announced that Lürssen had been selected. [11]

In October 2017, the Australian government announced that the vessels would use an Australian-designed SAAB tactical combat management system. [23]

Under SEA 1905 a further two ships are to be built by Civmec for the mine countermeasures role. A third vessel may be procured under SEA 2400 to fulfill the survey role although this is unlikely. [24] This was expanded in the 2020 Defence Strategic Update and 2020 Force Structure Plan released on 30 June 2020 for up to 8 vessels optimised for mine countermeasures and hydrographic survey roles potentially based on the Arafura design, possibly bringing the total number of vessels back up to the original 20. [25] [26]

Design

The Arafura-class is based on the Lürssen-designed Darussalam-class, operated by the Royal Brunei Navy. [1] Each vessel has a gross displacement of 1,640 tonnes, and measures 80 metres long, with a beam of 13 metres and a draft of 4 metres. [1] Propulsion power is from two MTU 16V diesel engines rated at 4440kW each, which drive variable pitch propellers and give a top speed of 22 knots, and shipboard electrical power is generated by MAN diesel engines. [1] The ship's range is about 4,000 nautical miles (7,400 km), with an endurance of 21 days. [1] The standard crew complement is 40 sailors, though up to 20 more can be berthed if required. [1] The ships will be deployed with empty space available to install container-mounted systems such as aircraft support and sensors; if fully utilized, the gross displacement could increase to 1,800 tonnes. [1]

Shipboard armament was originally intended to be a single 40 mm gun and two 12.7 mm guns. [1] The 40 mm gun was cancelled in 2021 due to a combination of technical problems and a re-assessment of the threats the ships would face. The ships will instead be armed with a Typhoon Weapon Station on an interim basis until a replacement weapon is identified and then acquired. [27] In May 2023 it was reported that the RAN was considering purchasing a containerised variant of the C-Dome surface-to-air missile system to improve the Arafura-class's armament. [28]

Each vessel carries two 8.5 metre rigid inflatable boats and a single 10 metre boat, which are intended as the primary means of deploying offensive force in the ships' border patrol role. [1] A single unmanned aerial vehicle is carried and deployed from an open utility deck. [1] Two separate electro-optic targeting systems and three radars are installed and managed by the Saab 9LV system. [1] In order to allow the ships to operate in conjunction with allied international forces, each ship is equipped with a unique electronic identifier transponder that allows for communication via the Link 16 network. [1]

According to the Department of the Defence, while the flight deck will not land helicopters, it can carry weights of up to 11 tonnes. [29]

Construction

The class of ships will be based on Lürssen's OPV80, similar to the Darussalam-class offshore patrol vessel of the Royal Brunei Navy. [30] [31] The first two vessels will be built by ASC Shipbuilding in Adelaide, South Australia before production is transferred to the shipyard of Forgacs Marine & Defence, a subsidiary of Civmec, in Henderson, Western Australia. [11] [32]

Construction of the first ship began on 15 November 2018. On that day, it was also announced that the vessel would be named HMAS Arafura, and the class the Arafura-class patrol vessels. [33]

On 9 April 2020 the second ship in the class, HMAS Eyre, was laid down at ASC's shipyard. The names of the following four ships were also announced at this time: HMA Ships Pilbara, Gippsland, Illawarra and Carpentaria. [34]

The first three ships amongst the then new names, HMAS Pilbara, HMAS Gippsland and HMAS Illawarra were laid down at the shipyard of Civmec in Henderson on 11 September 2020, [35] 30 July 2021 [36] and 27 September 2022, [37] respectively.

In October 2022 it was reported that Arafura did not meet civilian safety standards and the Albanese government was concerned that the ships were too lightly armed to meet the Navy's needs. The government was considering reducing the number of ships to be built, with those completed possibly being transferred to the Australian Border Force. [38] The delays to completing the Arafura-class ships led the project to be added to the Defence 'projects of concern' list in April 2023. [39] As of November 2023, Arafura had been launched but not commenced sea trials, and her commissioning date had been delayed until 2024 potentially due to the ship not meeting safety standards. [40] [41]

Criticism

With the cancellation of the main gun and the lack of any other major weaponry, the class has been criticised for being unable to operate in medium to high-end warfighting and resulting in calls to either up-arm the class or transfer the ships to the Australian Border Force Marine Unit in favour of a fleet of corvettes. [42] [43] [44] The class has also faced criticism for schedule delays and being over budget. [44] [43]

Cancellation

Following the Defence Strategic Review 2023 and the Independence Surface Combatant Fleet Review 2024 and the release of the Enhanced Lethality Surface Combatant Fleet 2024 by the Albanese government in February 2024, the final 6 vessels were cancelled due to the vessels being deemed as an inefficient use of resources for civil maritime security operations and does not possess the survivability and self-defence systems to contribute to a surface combatant mission. Instead, further investigation will be taken to determine how these vessels can contribute to other mission sets. [45]

Ships

Dates in Italics indicate estimates

NamePennant numberBuilderLaid downLaunchedCommissionedStatusNamed for
Arafura OPV 203 ASC Shipbuilding,
Osborne
10 May 201916 December 20212024 [40] Fitting out Arafura Sea
Eyre OPV 2049 April 202022 November 2023 [46] Fitting Out Eyre Peninsula, South Australia
Pilbara OPV 205 Forgacs Marine & Defence,
Henderson
11 September 2020Under construction Pilbara, Western Australia
Gippsland OPV 20630 July 2021Under construction Gippsland, Victoria
Illawarra OPV 20727 September 2022Under construction Illawarra, New South Wales
Carpentaria OPV 208Under construction; steel cut August 2022 [47] Gulf of Carpentaria
Source: [34] [48] [49]

Citations

  1. 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 "Arafura ahead of schedule". Australian Defence Magazine. 11 April 2019. Retrieved 11 July 2020.
  2. "SAAB Receives Order for Australian OPV Situational Awareness System". Saab Press Release. 20 April 2018.
  3. "Saab sensor system for OPVs". Australian Defence Magazine. 23 April 2018.
  4. "SCANTER 6002 radar selected for SEA 1180 OPVs". Defence Connect. 7 August 2018.
  5. "Australian SEA1180 OPVs to feature Terma's air and surface surveillance radars". Naval Today. 31 July 2018.
  6. Scott, Richard. "Vigy Engage selected for Project SEA 1180 OPVs". Jane's Navy International.
  7. "Safran Vigy Engage Selected for Australia's SEA 1180 OPVS". Monash Publishing Group. 5 September 2018.
  8. "Navy Outlook 2020". Faircount Media Group. Retrieved 6 March 2021.
  9. "Shortlist announced for Sea 129 Phase 5 - Australian Defence Magazine".
  10. 1 2 Anderson, Stephanie (18 April 2016). "Malcolm Turnbull says 12 offshore patrol vessels to be built in Adelaide". ABC News. Retrieved 18 April 2016.
  11. 1 2 3 "Hundreds of Australian Jobs Created in Offshore Patrol Vessel Project". Christopher Pyne. Federal Member for Sturt, Minister for Defence Industry. 24 November 2017. Retrieved 24 November 2017.
  12. 1 2 3 4 5 6 7 8 Department of Defence, Defending Australia in the Asia Pacific Century, pp. 72–3
  13. Thornton, The Rationale for the RAN Offshore Combatant Vessel, pp. 6, 8
  14. Boettger, The Offshore Combatant Vessel, p. 31
  15. 1 2 3 4 5 Australian Offshore Combatant Vessels, p. 1
  16. 1 2 Bergmann, Buzz around all-in-one combatant vessels
  17. 1 2 Australian Offshore Combatant Vessels, p. 2
  18. Thornton, The Rationale for the RAN Offshore Combatant Vessel, p. 6
  19. 1 2 3 4 Scott, UK, Australia begin talks on future ship projects
  20. "Multi Role Vessel MRV80" (PDF). Austal. 2010. Archived from the original (PDF) on 5 March 2012. Retrieved 18 January 2013.
  21. HII Targets RAN SEA1180 Project, in The Navy
  22. Department of Defence (3 May 2013). Defence White Paper 2013. Commonwealth of Australia. p. 84. ISBN   978-0-9874958-0-8.
  23. "Joint Media Release – Prime Minister, Minister for Defence and Minister for Defence Industry – New Approach to Naval Combat Systems". Department of Defence. 3 October 2017. Retrieved 3 October 2017.
  24. "Draft: Strategic infrastructure and land use plan" (PDF). Western Australian Government. 18 June 2020. Archived (PDF) from the original on 2 July 2020.
  25. "Factsheet: Naval Shipbuilding" (PDF). Department of Defence. Retrieved 6 March 2021.
  26. McLaughlin, Andrew (30 June 2020). "Govt outlines expansion of Australian Defence Firepower". ADBR. Retrieved 6 March 2021.
  27. Tillett, Andrew (14 December 2021). "Defence quietly cancels another navy contract – after denying problems". Australian Financial Review. Retrieved 17 December 2021.
  28. Felton, Ben (5 May 2023). "Australia Considering Modular C-Dome For Arafura OPVs". Naval News. Retrieved 6 August 2023.
  29. Department of Defence, Department of Defence (14 February 2024). "ANSWERS TO QUESTIONS ON NOTICE".
  30. "ASC Shipbuilding welcomes OPV bid partners Lürssen and Forgacs to Techport for the first time". www.asc.com.au. Retrieved 3 April 2018.
  31. '"Aussie Navy Renewal", Ships Monthly , March 2018, page 14
  32. Bell, Frances (24 November 2017). "Navy Offshore Patrol Vessels to be built in WA and SA by German company Luerssen". ABC News . Retrieved 24 November 2017.
  33. Zerbe, Ryan (15 November 2018). "Construction begins on Arafura Class patrol vessels". Navy Daily. Royal Australian Navy. Retrieved 15 November 2018.
  34. 1 2 "Major milestone for Navy's multibillion-dollar OPV program". Defence Connect. 9 April 2020. Retrieved 9 April 2020.
  35. "Keel Laid for Australia's third Arafura-class OPV". Naval News. 11 September 2020. Retrieved 11 September 2020.
  36. "2020–21 Major Projects Report" (PDF). Australian National Audit Office. 13 December 2021. p. 173. Retrieved 23 March 2022.
  37. "Keel laid for fifth Arafura OPV". Defence Connect. 27 September 2022. Retrieved 27 September 2022.
  38. Greene, Andrew (9 October 2022). "'97 years late': Expensive problems on major defence projects concern federal government". ABC News. Retrieved 15 April 2023.
  39. "Defence updates 'projects of concern' list". www.defenceconnect.com.au. 27 October 2022. Retrieved 15 April 2023.
  40. 1 2 "Australia Lists Arafura-class OPV as 'Project of Concern'". Naval News. 21 October 2023. Retrieved 29 October 2023.
  41. Felton, Ben (23 November 2023). "Luerssen Australia Launches Second Arafura Class OPV". Naval News. Retrieved 13 December 2023.
  42. Felton, Benjamin (20 December 2022). "What does Australia's Strategic Review hold for the RAN?". Naval News. Retrieved 9 January 2023.
  43. 1 2 Bergmann, Kym. "Arafura class OPVs late, over budget and underequipped". The Australian. News Corp. Retrieved 9 January 2023.
  44. 1 2 Greene, Andrew (9 October 2022). "'97 years late': Expensive problems on major defence projects concern federal government". ABC News. ABC. Retrieved 9 January 2023.
  45. https://www.defence.gov.au/sites/default/files/2024-02/Enhanced_Lethality_Surface_Combatant_Fleet_web.pdf
  46. Defence Media (22 November 2023). "Second Arafura class offshore patrol vessel launches in South Australia".
  47. "Luerssen starts construction of the sixth Arafura class OPV Carpentaria".
  48. "Arafura Class OPV". Royal Australian Navy. Retrieved 13 November 2021.
  49. "RAN's second Arafura class patrol vessel to be delayed by six months". Baird Maritime. 28 July 2021. Retrieved 13 November 2021.

Related Research Articles

<span class="mw-page-title-main">Royal Australian Navy</span> Naval warfare branch of the Australian Defence Force

The Royal Australian Navy (RAN) is the naval force of the Australian Defence Force (ADF). The professional head of the RAN is Chief of Navy (CN) Vice Admiral Mark Hammond AM, RAN. CN is also jointly responsible to the Minister of Defence (MINDEF) and the Chief of Defence Force (CDF). The Department of Defence as part of the Australian Public Service administers the ADF.

<span class="mw-page-title-main">Patrol boat</span> Small naval vessel

A patrol boat is a relatively small naval vessel generally designed for coastal defence, border security, or law enforcement. There are many designs for patrol boats, and they generally range in size. They may be operated by a nation's navy, coast guard, police, or customs, and may be intended for marine, estuarine, or river environments.

<i>Anzac</i>-class frigate Australian military ship class

The Anzac class is a ship class of ten frigates; eight operated by the Royal Australian Navy (RAN) and two operated by the Royal New Zealand Navy (RNZN). During the 1980s, the RAN began plans to replace the River-class destroyer escorts with a mid-capability patrol frigate and settled on the idea of modifying a proven German design for Australian conditions. Around the same time, the RNZN was seeking to replace their Leander-class frigates while maintaining blue-water capabilities. A souring of relations between New Zealand and the United States of America in relation to New Zealand's nuclear-free zone and the ANZUS security treaty prompted New Zealand to seek improved ties with other nations, particularly Australia. As both nations were seeking warships of similar capabilities, the decision was made in 1987 to collaborate on their acquisition. The project name is taken from the Australian and New Zealand Army Corps of the First World War.

<i>Armidale</i>-class patrol boat Class of patrol boats built for the Royal Australian Navy

The Armidale class is a class of patrol boats built for the Royal Australian Navy (RAN). Planning for a class of vessels to replace the fifteen Fremantle-class patrol boats began in 1993 as a joint project with the Royal Malaysian Navy, but was cancelled when Malaysia pulled out of the process. The project was reopened in 1999 under the designation SEA 1444, with the RAN as the sole participant. Of the seven proposals tendered, the Austal/Defence Maritime Services (DMS) proposal for twelve vessels based on an enlarged Bay-class patrol boat was selected. Two additional boats were ordered in 2005 to provide a dedicated patrol force for the North West Shelf Venture.

<span class="mw-page-title-main">Lürssen</span> German shipbuilding company

Lürssen is a German shipyard with headquarters in Bremen-Vegesack and shipbuilding facilities in Lemwerder, Berne and Bremen-Fähr-Lobbendorf.

The Royal Australian Navy, although a significant force in the Asia-Pacific region, is nonetheless classed as a medium-sized navy. Its fleet is based around two main types of surface combatant, with limited global deployment and air power capability. However, in 2009, a white paper, Defending Australia in the Asia Pacific Century: Force 2030, was produced by the Australian government which set out a programme of defence spending that will see significant improvements to the RAN's fleet and capabilities.

HMAS <i>Coonawarra</i> Royal Australian Navy base in the Northern Territory

HMAS Coonawarra is a Royal Australian Navy (RAN) base located in Darwin, Northern Territory, and is home to seven fleet units of the RAN. The current commander is Captain Moses Raudino, ADC, RAN.

<i>Huon</i>-class minehunter Class of Royal Australian Navy minehunters

The Huon-class minehunter coastal (MHC) ships are a group of minehunters built for the Royal Australian Navy (RAN). Following problems with the Bay-class minehunters, a request for tender was issued in 1993 for a class of six coastal minehunters under the project designation SEA 1555. The tender was awarded in 1994 to the partnership of Australian Defence Industries (ADI) and Intermarine SpA, which was offering a variant of the Italian Gaeta-class minehunter.

HMAS <i>Cairns</i> (naval base) Australian naval base

HMAS Cairns is a Royal Australian Navy (RAN) base located adjacent to the Trinity Inlet on the shore of Trinity Bay in Cairns, Queensland, Australia. Although used regularly as a port-of-call since before World War II, a permanent RAN presence was not established until 1971, when a maintenance and support base for patrol boats was set up. The base was formally commissioned in 1971 as a minor war vessel base. The current commander of the base is Commander David Hannah, RAN.

HMAS <i>Waterhen</i> (naval base) Australian naval base

HMAS Waterhen is a Royal Australian Navy (RAN) base located in Waverton on Sydney's lower north shore, within Sydney Harbour, in New South Wales, Australia. Constructed on the site of a quarry used to expand Garden Island in the 1930s, the location was used during World War II as a boom net maintenance and storage area. In 1962, the area was commissioned as a base of the RAN, and became home to the RAN's mine warfare forces. Waterhen was the first small-ship base established by the RAN, and from 1969 to 1979 was also responsible for the RAN's patrol boat forces.

HMAS <i>Armidale</i> (ACPB 83)

HMAS Armidale, named for the city of Armidale, New South Wales, is the lead ship of the Armidale class of patrol boats serving in the Royal Australian Navy (RAN). It was commissioned in June 2005 and decommissioned in March 2023.

The Australian Patrol Boat Group is a Force Element Group (FEG) of the Royal Australian Navy. It manages the Navy's patrol boats.

Protector-class offshore patrol vessel Ship class of patrol vessels

The Protector-class offshore patrol vessel is a ship class of two offshore patrol vessel (OPVs) operated by the Royal New Zealand Navy (RNZN) since 2010. The ships are named HMNZS Otago and HMNZS Wellington.

<span class="mw-page-title-main">Marine Unit (Australian Border Force)</span> Division of the Australian Border Force which acts as a Coast Guard

The Marine Unit, formerly the Australian Customs Service National Marine Unit, is a division of the Australian Border Force which acts as a Coast Guard in guarding Australia's coast. The Marine Unit focuses on surveillance and response activities within the Australian Economic Exclusion Zone, and the operation and training of ships and crews to do so.

<i>Paluma</i>-class motor launch

The Paluma-class motor launch was a class of four hydrographic survey motor launches operated by the Royal Australian Navy (RAN). Built in Port Adelaide between 1988 and 1990, the four catamarans were primarily based at HMAS Cairns in Cairns, Queensland, and operated in pairs to survey the waters of northern Australia.

<i>Darussalam</i>-class offshore patrol vessel

The Darussalam-class offshore patrol vessel is a class of four offshore patrol vessels in Brunei Darussalam constructed for the Royal Brunei Navy. They are the largest and most capable ships of the Royal Brunei Navy, and often participate in international naval exercises. The lead ship in the class is KDB Darussalam (06).

ASC Shipbuilding, formerly the shipbuilding division of ASC Pty Ltd, is a subsidiary of BAE Systems Australia and will remain a subsidiary for the duration of the contract to build the Hunter class frigates. It was structurally separated from ASC Pty Ltd in December 2018 and became a subsidiary of BAE Systems Australia. In 2021 it was renamed as BAE Systems Maritime Australia.

HMAS <i>Arafura</i> Patrol vessel of RAN

NUSHIP Arafura, named to represent Australia's interests in the Arafura Sea, is the lead ship of the Arafura-class offshore patrol vessels currently under construction for the Royal Australian Navy. The ship is based on the Lürssen OPV80 design, and is being constructed by ASC Pty Ltd at the Osborne Naval Shipyard in Osborne, South Australia. It was planned that the ship would enter service in 2022. However, as of March 2023, it is yet to be commissioned. The ship was launched at the Osborne Naval Shipyard on 16 December 2021.

NUSHIP Eyre ,, is the second ship of the Arafura-class offshore patrol vessels currently under construction for the Royal Australian Navy. The ship is based on the Lürssen OPV80 design, and is being constructed by ASC Pty Ltd at the Osborne Naval Shipyard in Osborne, South Australia.

References